© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 1 NOP, 38x E-126 7,5MW Bram van Noort Country Manager Enercon Netherlands Grid Integration Shaping the future
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 1
NOP, 38x E-126 7,5MW
Bram van Noort
Country Manager Enercon Netherlands
Grid Integration Shaping the future
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 2
AGENDA
1 Introductie
2 Net integratie
3 Technology van vandaag en voor morgen
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 3
Bron: ENERCON GmbH – Dutch Branch | November 2016
Overijssel 42,5 MW - 17
Flevoland 478 MW - 129
Zeeland 60 MW - 26
Groningen 270 MW - 98
Gelderland 30 MW - 15
Friesland 30,5 MW - 17
Drenthe 1 MW - 1
N-Holland 100 MW - 79
Z-Holland 98 MW - 37
N-Brabant 23 MW - 6
Limburg 12 MW - 5
1145 MW, 430 WECs
39 130 19 182 58 13 42 73 76 92 216 125 0
8 127
119
249 267
449 507 520
562 635
711
803
1020
1152
1279
0
200
400
600
800
1000
1200
1400
0
50
100
150
200
250
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Cu
mu
lati
ve (
MW
)
An
nu
al (
MW
)
Annual Planned Cumulative
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 4
1 2 3 4 9 10 11 17 27
44 56 55 75
96
165
244
285 290
30
1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
Employees ENERCONNetherlandsTo be expected current year
FTE NL
Source: ENERCON Benelux BV | October 2016
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 5
Trainingscentrum Emmeloord: van nationaal naar internationaal
• 11 -15 verschillende technische trainingen
• 2015: 234 dagen
• 2016: ca 470 dagen
• 2017: ca 900 dagen
• 130 dagen per trainer
• Ca 8 per groep
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 6
Testfield Lelystad (TLF)
6
2x E-115 3.0MW 135m
W06274-V01(loc11), We4S
W06274-V02(loc12), Flevoland BV
1x E-101 3.05MW 99m
W08790-V01(loc2), TFL 2 BV
1x E-101 E2 3.5MW 99m
W10980-V01(loc6), TFL 6 BV
1x E-126 EP4 4.2MW 135m
W10663-V01(loc7), TFL 7 BV
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 7
Ervaring in en op dijken – totaal 370 MW out of 1.150 MW
WP Noord Oost Polder – 285
MW
WP Hartelbrug – 12 MW
WP Suurhoffbrug – 9.2 MW
WP XL Wind– 24 MW
WP Enkhuizen– 3.2 MW
WP Roggeplaat– 12 MW
WP Battenoert– 12 MW
WP Vlissingen– 12 MW
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 8
AGENDA
1 Introductie
2 Net integratie
3 Technology van vandaag en voor morgen
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 9
Centraal opgesteld: 17.300 MW (55%) Decentraal 14.200 MW (45%)
)
kWh 63% kWh 37%
Het Nederlandse Energie-systeem (2016) : 31,5 GW
Bron: CBS | Oktober 2016 (cijfers 2015); Tennet | Oktober 2016; eigen berekening
WKK 7.600 MW
Wind 3.390 MW
Zon 1.485 MW
Biomassa/overig 1.725 MW
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 10
Totale elektriciteitsgebruik in Nederland in PJ (2015)
Verbruik:
80% Zakelijk
20% Huishoudelijk
Totaal:
426 PJ = 118 TWh
396 PJ =110 TWh
Eigen productie
+30 PJ = 8 TWh
Import
Totaal fossiel input 768 PJ
Omzetting 42% rendement
Bron: CBS | Oktober 2016 (cijfers 2015)
Geproduceerde Elektrische Energie
Fossiel 320 PJ
Duurzaam 48 PJ
Kernenergie 15 PJ
Andere bronnen 43 PJ
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 11
Het Nederlandse Energie-systeem (2015) Totale energieverbuik in Nederland in PJ
Totaal:
3040 PJ
36% Gebouwde omgeving (woningen / bedrijven /
winkels / andere gebouwen)
27% Mobiliteit: Wegverkeer / Treinverkeer /
Binnenlandse Scheepvaart & Luchtvaart
27% Industrie, Opwek, Zuivering, Winning
7% Landbouw, Bosbouw en Visserij
2% Warmte voor Industrie / Landbouw
1012 PJ
Voor omzetting naar
Elektra/WKK
Bron: CBS | November 2016 (cijfers 2015)
Aardgas 1200 PJ
Aardolie 1129 PJ
Steenkool 462 PJ
Duurzaam 137 PJ
Andere
bronnen
70 PJ
Totaal 3040 PJ
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 12
Het Nederlandse Energie-systeem (2015)
Totale elektriciteitsgebruik in Nederland in PJ
*data inaccuraat
Wind Vermogen vs. opbrengst
land (89%) produceert 85% elektriciteit
6.45 TWh Gem. 2127 vollast uren
Zee (11%) produceert 15% elektriciteit =
1.13 TWh
Gem. 3165 vollast uren
Totaal Wind in NL ca. 7,6 TWh
Ca. 7% totale gebruik
Bron: CBS | Oktober 2016 (cijfers 2015)
Geproduceerde Elektrische
Energie
Wind 25 PJ
Biomassa* 8.5 PJ
Warmtepompen 6 PJ
Photovoltaic (PV) 6 PJ
Aardwarmte 2 PJ
Waterkracht 0.5 PJ
48 PJ = 13.2 TWh
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 13
INTRODUCTION SECURITY OF ENERGY SUPPLY IN GERMANY
System Average Interruption Duration Index (SAIDI) value for Germany
21.53
19.25
16.89
14.63 14.9 15.31 15.91
15.32
12.28
0
5
10
15
20
25
2006 2007 2008 2009 2010 2011 2012 2013 2014
ATOMAUSSTIEG
Source: Energy Brainpool/BNetzA 2015
SA
IDI
in m
inu
tes
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 14
INTRODUCTION SECURITY OF ENERGY SUPPLY IN DIFFERENT COUNTRIES
Annual comparison of System Average Interruption Duration Index (SAIDI) for Europe (2015)
Source: Energy Brainpool/CEER 2015
SA
IDI
in m
inu
tes
11.25 15 15.32 23
42.27 54.9
67.21 68
254.9
0
50
100
150
200
250
300
DK CH DE NL IT GB HU FR PL
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 15
INTRODUCTION SECURITY OF ENERGY SUPPLY IN DIFFERENT COUNTRIES
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 16
Net transformatie
vandaag: sterk-net met wind turbines en windparken morgen: Net structuur met renewables op alle net grid niveaus
~ EXTRA HIGH VOLTAGE
HIGH VOLTAGE
MEDIUM VOLTAGE
~ ~ EXTRA HIGH VOLTAGE
HIGH VOLTAGE
MEDIUM VOLTAGE
~
• Energie leverings systeem zal veranderen van centraal naar meer decentrale strukturen
• Bidirectional power flow
• Wind parken worden wind power plants
• Specifieke hoge eisen voor de net aansluiting
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 17
REQUIREMENTS
ENERGY SUPPLY SYSTEMS ARE SHIFTING. AIM: 100% SUPPLY WITH RENEWABLE ENERGIES
YESTERDAY TODAY TOMORROW
Conventional wind
energy converter
• Negative load
• 100ms disconnecting time
< 10 % RE
APPROACH: Modular multi-functional technology platform
Grid-supportive
wind farm
• FRT
• Basic system services (Q, U, f)
• Weak grids
~ 50 % RE
System relevant
wind power plant
• Pure inverter grids
• Advanced system services
• Smart contribution to system
blackstart
• ???
100 % RE
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 18
PENETRATION
AIM: cost minimised energy supply system with maximum RE-integration
ENERCON TECHNOLOGY PLATFORM Wind Turbine + Wind Power Plant Control
Virtual
Power
Plant Smart
Grid
Grid Integration &
Grid-Supportive
Power Plant
STORAGE
FLEXIBLE GENERATION
GRID EXPANSION /
STRENGTHENING
CONTROLLABLE LOAD (VIRTUAL STORAGE)
LE
VE
L O
F IN
TE
GR
AT
ION
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 19
GRID INTEGRATION ANCILLARY SERVICES
CLASSIFICATION OF ANCILLARY SERVICES
FREQUENCY STABILITY
TODAY
Primary, secundary,
tertiär reserve power
TOMORROW
Inertia, damping control
VOLTAGE STABILITY
TODAY
Reactive power
TOMORROW
weak grid stability control
OPERATION MANAGEMENT
TODAY
Setpoint operation
TOMORROW
smart grid, sector coupling,
virtual power plants
BLACK START PROCEDURES
TODAY
Not smart, passiv
TOMORROW
smart contribution to
system blackstart
DENA*-Study on ancillary services 2030 applied to
ENERCON technology developments
* Deutsche Energie Agentur
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 20
GRID INTEGRATION ANCILLARY SERVICES - FREQUENCY STABILITY
TODAY: Primary, secundary, tertiär reserve power
50,0
Hz
NORMALBETRIEB
GENERATION LOAD
activation of
negative reserve power
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 21
GRID INTEGRATION ANCILLARY SERVICES - FACTS* Control
• Requirements from most diverse
Grid Codes implementable
• Constant development of
operational strategies
WIND
POWER
PLANT
CONTROL +
FACTS Control Software
* Flexible AC Transmission Systems
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 22
AGENDA
1 Introductie
2 Net integratie
3 Technologie van vandaag en voor morgen
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 23
GRID INTEGRATION WIND POWER PLANT Control
SCADA and wind park control at the point of connection
ENERCON FCU Farm Control Unit
ENERCON RTU Remote Terminal Unit
ENERCON PDI-OPC Process Data Interface
ENERCON MCU Master Control Unit
ENERCON METEO
SCADA PC
Interface wind
measuring masts
Online signal exchange
(grid operator)
Main control and communication
acc. to MV-Directive etc.
Efficient control for
wind power plants
Integrated remote control
of multiple wind parks
POINT OF
CONNECTION
FCU BUS
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 24
GRID INTEGRATION ENERCON EXPERIENCE RETROFIT FOR SDLWindV 2009
• Retrofit of existing WECs to get the ancillary services bonus
• ENERCON received the first unit certificate for existing and new plants
NUMBER OF WECS TOTAL CAPACITY (MW) RETROFIT PERIOD
3.416 6.709 09/2009–06/2011
ANCILLARY SERVICE
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 25
TECHNOLOGY TOOLBOX SPEICHER FELDHEIM PRIMARY RESERVE
• 10 MW / 10MWh
• 3400 Battery modules
• 120-150T€ / MW
and year
frequency
battery power
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 26
SMART CONTAINER APPLICATIONS
CHARGING STATION BATTERY STORAGE HYDROGEN STORAGE DESALINATION
ENERCON TECHNOLOGY PLATFORM
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 27
Battery FELDHEIM PRIMARY RESERVE
• 10 MW / 10MWh
• 3400 Battery modules
• 120-150T€ / MW
and year
frequency
battery power
© Copyright ENERCON GmbH. All rights reserved. Stefan Lütkemeyer – Sales Director 28
RAGLAN, CANADA FALKLAND
BONAIRE, NETHERLANDS ANTILLES
ANTARCTICA
EL HIERRO, SPAIN HUSAHAGI, FAROE ISLAND
TECHNOLOGIES FOR HIGH WIND PENETRATION ARE AVAILABLE:
inverter-based generation, technology platform, storage systems, …
Hartelijk dank voor uw aandacht