8/12/2019 Bil 1 Jun Klcc
1/35
A STUDY ON THE INTELLEGENCE CRITERIA
ON PETRONAS TOWERS BUILDING.
POLYTECHNIC SULTAN AZLAN SHAH
DEPARTMENT OF CIVIL ENGINEERING
Prepared by:
NORHAYATI BINTI JAMIL
ANIZA BINTI TAHIR
LALITHAMBIGAI A/P SIVANGANAM
8/12/2019 Bil 1 Jun Klcc
2/35
TABLE OF CONTENTS
CONTENTS PAGE
Terms of Reference i
Acknowledgements ii
Table of Contents iii
List of illustrations iv
I INTRODUCTION 1
A. Background 2B. Objectives 3C. Literature Review
(i) What Technology ? 4
(ii) Effect of Technology 5
(iii) Intelligence Township 5
(iv) Intelligence Buildings 6
(v) System Interoperability 7
D. Methodology(i) Methodology Flow Chart 9
II FINDINGS 10A. Questionnaire 27
III CONCLUSIONS 28
IV RECCOMMENDATIONS 29
Appendixes
iii
8/12/2019 Bil 1 Jun Klcc
3/35
8/12/2019 Bil 1 Jun Klcc
4/35
ii
I A. BACKGROUND
As long as Petronas Towers are well known as one of the intelligencebuilding in this country, this study was carried out to gathered information and to
find out what are the intelligence facilities or criteria, that the Petronas Towers has.
The information was gathered through an interview with Ass. Prof. Ir. Dr. Khafilah
bt. Din, a skybridge project coordinator, who is at present a lecturer in Faculty of
Civil Engineering, UiTM. In addition an interview with Petronas Officer, Mr.
Zulkarnain Abdullah was also held for the same purpose. Some information was
also gathered from Internet.
The intelligence criteria and facilities that has been discovered in this study could be
summarised as follows:
i) The conceptcity-within-a-city.ii) Building structure and materials used.iii) Building control system.iv) Telecommunication system.v) Energy saving system.vi) Elevator system.vii) Public parkdesign concept and facilities.viii) Infrastructure.
8/12/2019 Bil 1 Jun Klcc
5/35
2
I INTRODUCTION
Petronas Towers (Kuala Lumpur, Malaysia)
452 meters high
The worl d's tall est reinf orced concrete off ice bui lding,
a symbol of the new Asia
Malaysia is a nation on the rise. In its energetic capital Kuala Lumpur a
gigantic project is under way that symbolizes the emerging of the new Asia. The
Kuala Lumpur City Center (KLCC) project is a complex of office buildings, hotels
and an industrial center. At its heart is the Petronas Twin Towers intelligent office
building, which began construction in 1994.
The 88-floor Petronas Twin Towers have stood 452 meters tall, surpassing
the 443-meter Sears Tower in Chicago to become the world's tallest building.
Among reinforced concrete buildings this stunning architectural triumph will also
far exceed the 295 meters of Chicago's 311 South Wacker Drive. Soon Asia will be
home to the world's tallest building.
The soaring twin cylindrical towers appear to embrace their smaller
adjoining wings, and are connected by a sky bridge at the -meter level. The metal
curtain wall adopted for the exterior design reflects Islamic architecture, blending
tradition with a futuristic image and achieving a rich beauty that sets this building
apart from earlier skyscrapers.
Nowadays this intelligent building is applying the latest in architectural
engineering technology to create the world's tallest building.
Petronas Towers is raising the curtain on the new Asia, and adding a bright
page to architectural history.
8/12/2019 Bil 1 Jun Klcc
6/35
8/12/2019 Bil 1 Jun Klcc
7/35
3
I C. LITERATURE REVIEW
1.1 WHAT TECHNOLOGY ?
The new technology era that we shall be witnessing in the next
millennium will focus more on technologies that encapsulate knowledge-
based systems. We shall be talking about intelligent systems that react
dynamically on data input. Theses knowledge based systems will almost
always rely on high technology information technology equipment. Most
people may think that such technology is better discussed in other forums
such as electronics, computing, electrical or mechatronics but the painful
part about technology is the indirect impact that it may have on all other
aspect of our lives. It should not be taken for granted that such technology
will not affect Civil Engineering work, as technology itself is currently
being used in most civil engineering design systems. It becomes more
complex when human needs on housing and infrastructure facilities
change with the coming of new technology. It therefore becomes
important for civil engineers and anybody dealing with civil engineering
work to acknowledge the technologies concerned.
The technology incumbent in the millennium would be technologies
related to the use of up-to-date information on all aspect of design and
operation. It can be coined simply as Information Technology (IT). This is
clearly manifested in the vision of Malaysia to implement the Multimedia
Super Corridor, which shall focus on the efficient use of information
technology in all its development and functions. Town and regional
planners need to think about regional development with infrastructure to
support the efficient use of information technology. Building architecture
and design need to cater for information technology device to be
introduced within buildings. Structural members designed by civil
engineers must incorporate possible fluctuation of loads due to the
presence of IT driven parts such as mobile roof that react to the position of
the sun and others.
8/12/2019 Bil 1 Jun Klcc
8/35
4
1.2 EFFECT OF TECHNOLOGY
The advent of new IT equipment for measurements as well as design
changes the way an engineer would work in the design office. New
surveying instruments that incorporate IT concepts allows surveyors and
civil technician to conduct better and faster site investigation. Construction
control has been made accurate through the use of such equipment.
It is through the availability of these devices that we may have to
change some of the way we work and perhaps some of the design criteria in
our architectural and engineering design. Building services thus become one
of the important design aspects to be taken into consideration in civil
engineering construction work. Building structures need also take into
account that part of the structure that may need to host special IT devices to
monitor structural behavior and even perhaps control some of the dynamic
movement of the structural member.
These technology also affects other periphery activities such as
highways, wastewater treatment plants, bridges and dams may require some
review as to the additional high technology design tools that are available
now and the provisions such design need to consider to include IT related
devices in their structures.
1.3 INTELLIGENT TOWNSHIP
The development of the Multimedia Super Corridor (MSC) between
Kuala Lumpur City Center to the new Kuala Lumpur International Airport is
an example of an Intelligent Township. The whole development incorporate
construction techniques that take into account the preservation of the
ecology around the development area as well as ensuring that the various IT
infrastructure is blended carefully within the built structure. All structure has
provisions to include IT services that is built within its central building
services ducting and external infrastructure had to be built in tandem with
5
8/12/2019 Bil 1 Jun Klcc
9/35
the development of the cables required for the information superhighway. It
is envisioned that all building and structures within the MSC are wired to
have IT services available upon completion of the project.
1.4 INTELLIGENT BUILDINGS
The process of designing, constructing, starting up, controlling and
maintaining an intelligent building is very complex. The construction of
such building requires the engineer to understand the various devices require
to be installed within the structures. Such devices require an intelligent
system to be developed to manage interactively the environment within the
building. If done properly, the final product delivers comfort, safety, and a
healthy environment and operates efficiently at reasonable cost. The key to
managing this complex process of designing and operating buildings
efficiently lies in the ability to manage information, deliver it efficiently to
the proper controlling equipment and devices, and to use it effectively for
the control of the building environment.
Among the type of intelligent buildings are designed to be energy
conscious yet environmentally comfortable to its occupants. This would
usually be building that stores solar energy for its energy supply and
maintains its comfort through having properly designed windows and
opening within its structure. There might be a need to allow certain parts of
the building to be mobile.
Special system need to be developed an in corporate within the
building services control system to manage and monitor the environment of
the building.
6
8/12/2019 Bil 1 Jun Klcc
10/35
1.5 SYSTEM INTEROPERABILITY AND CONTROL
The trend in equipment design and control systems is to embed
greater intelligence in individual components. This distributed
intelligence present new opportunities to optimise dynamic building
systems resulting in lower energy use, energy cost and maintenance costs
while maximizing building performance environmental quality and comfort.
Tomorrows control system will be networked to operate as
integrated systems. The system will include a robust performance tracking
database technology to monitor and archive information on a broad spectrum
of building systems and their real time attributes including HVAC, lighting
and shell component s. Integrated building systems and their control
technology will be linked to software modules that compare actual
performance to original design objectives, metrics and functional intent.
Some specific control developments will include:
Adaptive/optimized/self-generating control algorithms:
Development of techniques whereby control algorithms adapt
to changing building or system conditions adjust, set points
and eventually algorithms themselves to be optimal and
eventually support automatic generation of control strategies
based on the equipment and systems present
Advanced control technique: Development of control
techniques based on artificial neural networks, fuzzy logic
and genetic algorithms.
7
8/12/2019 Bil 1 Jun Klcc
11/35
The following elements of interoperable and integrated information
across the building life cycle:
Formats for data exchange between design tools, commissioningtools, controls and sensor suites, facilities maintenance management
systems and related software.
Standardized schema for archiving building simulation,
commissioning, control and operational data sets.
Process and workflow management techniques in the use ofinteroperable and integrated systems to ensure that data required as
input to software modules are supplied by the database archive or
related software module.
A user interface or browser that can interact with the data archive to
obtain a global view of the data for a building project.
8
8/12/2019 Bil 1 Jun Klcc
12/35
I D. METHODOLOGY
METHODOLOGY FLOW CHART
9
1. LITERATURE
REVIEW
2. INTERVIEW WITH
PROF.MADYA DR KHAFILAH
BINTI DIN
3. ANALYSE INFORMATION
GATHER FOR FURTHER
INVESTIGATION
4. SITE VISIT AND
INTERVIEW WITH
OFFICER IN
CHARGE
5. COMPILE ALL THE
INFORMATION
GATHERED
6. IDENTIFY THE
INTELLIGENCE
CRITERIA OF KLCC
7. PREPARE THE
REPORT
8/12/2019 Bil 1 Jun Klcc
13/35
II FINDINGS
2.1 CONCEPTS
The concept of KLCC is a self-contained, city-within-a-city.
The integrated mixed-use development provides more than 1.67 million sq.
meters (18 million sq. feet) of:
commercialretailhotelresidentialentertainment facilities
The winning Master plan submitted by Klages, Carter, Vail & Partners
delineated the site into 22 freehold lots located around a 20-hectare (50-acre)
park.
The KLCC project is being implemented in phases. Phase One was launched in
1992 comprising:
the 88-storey PETRONAS Twin Towers; Suria KLCC - the six-level, 1.5 million sq. feet shopping centre; the 49-storey Menara Maxis; the 30-storey Menara Esso; the 32-storey Mandarin Oriental Kuala Lumpur Hotel; a 20-hectare (50-acre) Public Park; two District Cooling Centres; a Mosque
10
8/12/2019 Bil 1 Jun Klcc
14/35
2.2 KLCC Logo:
The logo is derived from a "Dualism Theme"; the twinning of KLCC with
the city itself. The corporate colours are in blue and green. Blue for the highrise
with the blue sky and waterscape, green for the park and the landscape.
Architect
The 88-storey PETRONAS Twin Towers are designed by Cesar
Pelli, the award winning, world renowned architect and founder of the firm
of Cesar Pelli and Associates. Other prominent works of the former dean of
Yale University's School of Architecture include:
Canary Wharf, London World Financial Centre, Manhattan Crile Clinic Building, Cleveland Rice University's Herring Hall, Houston Carnegie Hall Tower, New York City Owens-Corning World Headquarters, Toledo
11
8/12/2019 Bil 1 Jun Klcc
15/35
2.3 BUILDING STRUCTURE & MATERIALS USED
2.3.1 PETRONAS Twin Towers At A Glance
Number of storeys = 88
Height = 452 meters above street level
Total built-up area = 341,760 sq.meters (3.7 million sq. feet)
Design/Architecture = Cesar Pelli & Associates [U.S.] in association
with KLCC architects.
Location of skybridge = Levels 41 and 42
Length of skybridge = 58.4 meters
Height of skybridge = 170 metres above street levelVertical transportation = 29 double-deck high speed passenger
lifts in each tower
Number of escalators = 10 in each tower
Stainless steel cladding = 65,000 sq. metres
Vision glass = 77,000 sq. metres
Concrete [various strengths up to grade 80] = 160,000 cubic metres
in the superstructures [see also foundation description below]
Steel = 36,910 tonnes of beams, trusses and reinforcement
Foundation = 4.5 metre [15 feet] thick raft containing 13,200 cubic
meters of grade 60 reinforced concrete, weighing approximately
32,550 tonnes under each Tower, supported by 104 barrette piles
varying from 60 to 115 metres in length.
The floor-plate of the Tower is designed based on geometric
patterns common in architecture of Islamic heritage. It is composed of two
rotated and superimposed squares with small circular infills. These
geometric figures have been described by architects as symbolising unity,
harmony, stability and rationality - all important principles of Islam.
Like the exterior design, the Towers' entrance design was also
inspired by the country's cultural heritage, incorporating contemporary
Malaysian motifs adapted from traditional handicrafts such as songket and
12
8/12/2019 Bil 1 Jun Klcc
16/35
timber carvings. The overall character of the building is high-tech and
international but distinctively Malaysian.
At the podium level, the PETRONAS Twin Towers feature the following :
The 864-seat Dewan Filharmonik PETRONAS, a venue of architecturaland acoustic distinction. It is also home to the Malaysian Philharmonic
Orchestra.
A reference library on energy, petroleum, petrochemical and relatedindustries.
The Towers were topped-out in March 1996 and occupation began
in early 1997. Tower One is currently being occupied by PETRONAS, the
state-owned petroleum corporation. Tower Two is being occupied by
PETRONASassociate companies while the remaining space is being leased
out to multinationals.
The PETRONAS Twin Towers are located on the northern boundary
of the Multimedia Super Corridor (MSC) and has state-of-the-art
communication facilities. MSC is the launching pad to propel Malaysia into
the frontline of the information age.
2.3.2 SkybridgeThe skybridge is an essential functional component linking the Twin
Towers to facilitate movement between the two towers.
The 58.4 meters double-decked skybridge is located at levels 41 and
42 joining the sky lobbies situated in both towers.
Engineering Design Assembly of Skybridge Lifting of Skybridge
13
8/12/2019 Bil 1 Jun Klcc
17/35
Engineering Design
The structural system selected utilises a 'two-hinge arch' springing
from supports at level 29 and rising at 63 degrees to support a pair of parallel
two-span continuous bridge girders at Level 41.
The structure of the two-level bridge is conventional framing
constructed of structural steel with beams moment-connected to columns
which bear on the level 41 continuous girders. The bridge is 58.4 m long and
weighs about 750 tonnes.
The two-hinge arch supporting the bridge has rotational pins
(spherical bearings) at the end of each leg or 'spring point' and at the top or
'crown' of the arch (bearings). The main bridge girders have a rotational
(centering) pin directly over the arch crown to permit the crown to rise and
fall as the Towers move closer or further apart.
The arch is a centering device, equalising joint movement at both
Towers. As the Towers move together or apart, the legs change slope, the
spherical bearings rotate at spring points and the legs flex at their top end.
The bridge mid-point sinks or rises, flexing the two main girders.
The girders are pinned on the arch crown, which stays centered
between the Towers, while both girder and blocks slide on pads. The mid-
span centering pin and two girder slip pads accommodate this movement.
Continuous expansion joints provided through the level 42 and 43
structure, facade and roof to each side of the bridge mid point. Providing
14
8/12/2019 Bil 1 Jun Klcc
18/35
expansion joints at mid-point reduces the effect of girder flexure on bridge
glazing, as window panel movement is then limited to each half-span rather
than cumulating over the whole girder length.
When the Towers move side-to-side in opposite directions, or when
they 'twist', the arch spring points twist on the spherical bearings and bridge
end bearings slide in opposing directions guided by 'sliding keeper' blocks
on bridge centreline.
In the event that it loses its arch support, the bridge structure would
not collapse but deflect and stay in position.
Lifting of Skybridge
VSL Heavy Lifting, a specialist in this field, was appointed for the
lifting of the skybridge studies and preparation for the lifting was carried out
for more than a year in several countries including the United States and
South Korea, simulating various wind and weather conditions including
those based on actual load data over the past 50 years.
There are nine main steps in the lifting of the skybridge.
STEP ONE
The skybridge's legs are lifted up one at a time by tower cranes. Once
they are in position, control cables are used to lower them over their
permanent bearings at level 29.
STEP TWO
The two end block girder frames of the skybridge are lifted
individually. The blocks are installed about 100mm above their final
position at level 41. They are also retracted about 100mm into the tower to
provide sufficient clearance for the skybridge centre section during lifting.
15
8/12/2019 Bil 1 Jun Klcc
19/35
STEP THREE
The four lifting jacks located at level 50 of both towers are connected
on the bridge centre. The other four lifting jacks located on level 48 of both
towers are connected to the bridge ends.
STEP FOUR
The centre section which weighs 325 tonnes is lifted about 11 metres
and restrained. This is to allow the upper 10 metres of the legs to be
connected to the girder on the bridge.
STEP FI VEAfter a final check, lifting of the centre section commences.
STEP SIX
At a minimum lifting speed of 12 metres per hour, the centre section
is gradually lifted to its final level.
STEP SEVEN
Steps Seven to Nine took about two weeks. A temporary connection
secures together the centre section and the end block girder frame to ensure
there is no stress.
STEP EIGHT
The legs are moved into place. When the legs are in their final
position, the skybridge end blocks are lowered on their permanent bearings
at Level 41. The centre section is then lowered to meet the legs.
STEP NINE
After the lifting system has been removed, the floors were concreted,
the skybridge roofed. The maintenance equipment is set up on stainless steel
rails on top of the bridge.
16
8/12/2019 Bil 1 Jun Klcc
20/35
At about 7.40 p.m., on 9 August 1995, after 32 hours of lifting
operation, the sky bridge was lifted to its final position at the 41st and 42nd
levels of the PETRONAS Twin Towers.
Construction and installation of skybridge
17
8/12/2019 Bil 1 Jun Klcc
21/35
2.4 BUILDING CONTROL SYSTEMThe Building Control System [BCS] provides central management
and monitoring for air conditioning control, lighting control, and electrical
and chilled water status monitoring, as well as providing energy
management services.
The local area network system is based on a two-tier LAN structure,
where the primary network links the controllers to the command centre and
the secondary LAN facilitates communication with the end devices. The
BCS also interfaces to the life safety system, which is designed to overridethe BCS, in the event of an emergency.
The air conditioning requirements for the KLCC Development,
including the Towers is served by a 30,000-ton chilled water plant [District
Cooling Centres], which combines natural gas-driven cogeneration
equipment with various forms of steam turbine-driven chillers and electric
chillers.
The air-conditioning system selected for the Towers uses the latest
development in floor-by-floor air handling units, utilising the chilled water.
The floor-by-floor system solves the problems of acoustics, compactness,
ease of maintenance and control.
This system also provides the most advanced approach to engineered
smoke control. It allows for a pressure sandwich between the floor on fire
and the adjacent floors, thus allowing the fire to be contained during the
evacuation process.
The raised floor system utilised in the Towers allows for the effective
flexible distribution of electric power and telecommunication cables to meet
current and future needs.
18
8/12/2019 Bil 1 Jun Klcc
22/35
2.5 BUILDING SECURITY SYSTEM
The Building Security System [BSS] is designed to operate via a LAN
[local area network]
High level software running on the integrated security network captures
all data to ensure fully automated coordination among the BSS sub-systems,
which include: -
Card Access and Alarm Monitoring System Voice Intercoms Alarm Monitoring System Audio Alarm Surveillance System Closed Circuit Television System - CCTV Photo Identification System
2.6 TELECOMMUNICATION SYSTEM
At the heart of the building management system is a structured
cabling system comprising vertical and horizontal cabling; inter building
cabling and connectivity to telecommunications carrier companies. The
system is designed to achieve maximum flexibility to accommodate present
and future communication needs.
Connectivity is provided from the main subscriber distribution frame
to the end-user workstations, minimising re-cabling and cable-removal.
The telecommunications infrastructure is designed as a local loop
communications system within the boundaries of the KLCC site. The hub of
the system is a Central Telecommunications Office [CTO], which serves as
a local communications exchange and gateway to the outside world.
19
8/12/2019 Bil 1 Jun Klcc
23/35
8/12/2019 Bil 1 Jun Klcc
24/35
2.8 ELEVATOR SYSTEM
The PETRONAS Twin Towers are serviced by a total of 76 lifts, of
which 58 are double-deck lifts. The double-deckers result in better utilisation
of the core space and require less hoistway thus maximing the efficiency of
passenger transportation.
The system features two passenger cabs, one above the other in the
same car frame, sharing the same hoistway. Each double-deck unit is
capable of carrying 26 persons per deck.
The shuttle elevators can carry 26 persons per deck, or 52 per trip,
while each of the other double-deck lifts is designed to take 23 passengersper deck. Traveling time is between 3.5m/second and 7 m/second depending
on which zone they are servicing.
Tenants / visitors going to 'even' floors embark on lifts at the ground floor while
those traveling to 'odd' floors take the escalator to the mezzanine level before
embarking on their respective lifts.
21
8/12/2019 Bil 1 Jun Klcc
25/35
2.9 PUBLIC PARK
The beautifully landscaped park at KLCC is the last inspired
masterpiece by the versatile and talented Brazilian master of gardens, the late
Roberto Burle Marx.
Spread over 50-acres [20-hectares], the lush tropical garden provides a
haven of tranquility for those seeking a respite from the stress of city life
The KLCC Park is unique in its theme and concept. Designed to
showcase a heritage of tropical greenery by integrating man's creation with
nature, the beautifully landscaped KLCC Park offers a calm and harmonious
environment in the midst of the hustle and bustle of a busy and dynamic city.
The late Roberto Burle Marx uses a combination of trees, shrubs,
structures of cement, stones and wood as well as various water features in his
creations. Elements of shapes, texture and topography are merged to create
attractive and breathtaking masterpieces while at the same time imposing an
illusion of space. Colour and form are achieved by using various combinationsof trees, shrubs and sculptures, thus dispelling the notion of a garden as a static
creation.
The conservation factor was another key consideration in the planning
of the park. About 23 of the mature and rarer specimens were saved from the
former Selangor Turf Club, and eventually transplanted on to the park
grounds.
About 1900 indigenous trees and 66 species of palms have been
planted at the park. Much thought proceeded the selection of these plants, with
the objective of encouraging bio-diversity. Among other attractions at the park
are the magnificent lake symphony fountains, programmed to provide
numerous different dramatic animations following a Symphony Overture
sequence, the ornamental water features, the children's pool and the children's
playground.
22
8/12/2019 Bil 1 Jun Klcc
26/35
The park is well interspersed with various amenities such as shelters,
benches, rest areas, drinking fountains and public toilets. For health
enthusiasts, there is also a 1.3 km jogging track encircling the park.
Another interesting element of the park is the 43 meter elevated bridge.
The centrally located bridge provides visitors with a vantage view of the park
and the majestic PETRONAS Twin Towers.
Part of the park is also designed as a haven for birds and other local
fauna. Much research and thought went into the selection of indigenous tree
species whose fruits attract local and migratory birds. Through such careful
effort, it is expected that the KLCC Park in the heart of bustling Kuala
Lumpur will become an important link in the 'bird corridors' of the region.
PARK PLAN
Lake Symphony
The Symphony Lake with an approximate area of 10,000 square metres
features mesmerising fountain displays. The displays consist of 5
programmers with over 380 individually sequenced effects shooting up to a
maximum height of 42 metres. These effects are displayed along the arc and
the two rings totaling 80 metres in length. The Lake Symphony fountains are
on from 12 noon till 2.00 p.m. and 6.00 p.m. till 11.00 p.m. on weekdays.
23
8/12/2019 Bil 1 Jun Klcc
27/35
Especially for weekends and public holidays, the fountains are on from 10.00
a.m. till midnight.
Jogging Track
A 1.3 km. long jogging track is laid with EPDM, a special rubberised material
to ensure comfort and safety for fitness enthusiasts.
Rest Areas
Rest areas are located on various nodes of the interconnecting footpaths. They
are numbered as shown on the maps found on the Park's entry and feature
identification signs. The numbering system can be used as points of reference
for way finding and setting a rendezvous.
Ornamental Water Features
Waterfalls, Cascades, Reflecting Pools and Bird's Pool add to both the
excitement and tranquility of the respective zones in the park.
Other Amenities
The KLCC Park has been provided with various amenities such as
Toilets complete with modern fittings and facilities for the disabled and
baby change.
Male and female changing rooms annexed to the toilet near the Children's
Pool.
Drinking fountains with filtered water.
Shelters and benches.
24
8/12/2019 Bil 1 Jun Klcc
28/35
MOSQUE
Designed by KLCC architects, this 6,000 capacity Asy-Syakirin
Mosque is known as the "Jewel in the Park".Skilled Uzbekistan craftsmen were employed to render intricate
Uzbek's carvings and calligraphy on the interior and the internal facade of the
dome. The main prayer hall, the three-storey air-conditioned building can
accommodate 2,500 people while the lower prayer hall on the ground floor
can accommodate an additional 3,500 people.
Trellis Area
25
Dome Interio
8/12/2019 Bil 1 Jun Klcc
29/35
INSFRASTRUCTURE
The KLCC Project is located at the apex of the Multimedia Super Corridor
(MSC) and is easily accessible to:
the new Kuala Lumpur International Airport Government's new administrative centre, Putrajaya Port Klang, the country's main port 12 vehicular accesses and 14 bus stops Kuala Lumpur's inner ring road and a major highways to the suburbs Light Rail Transit (LRT)
Accessibility from KLIA
Accessibility within the
city
26
8/12/2019 Bil 1 Jun Klcc
30/35
III CONCLUSIONS
3.1 The intelligence criteria of the Petronas Towers could be summarized
as follows:
1. Store solar energy as it energy supply.
2. First class Telekom provided by STM.
3. Purpose built fireproof data storage rooms.
4. Intergrated power, lighting, electronis, and control wiring.
5. Direct digital control network.
6. Time controlled secure accesses.
3.2 The intelligence technology and materials used in Petronas Towers are:1. Building control system2. Building security system.
3. Telecommunication system.
4. Energy saving system.
3.3 Intelligence buildings differ from conventional building in the someaspect such as :
1. Automated building services.
2. Information management.
3. Control of environment.
4. Conductivity determined by internal cabling and access to externalservices.
28
8/12/2019 Bil 1 Jun Klcc
31/35
IV RECOMMENDATION
As a recommendation, we suggest that :
4.1 We would like to proposed to Polytechnic to take the afford to add inthe syllabus for civil engineering degree course on intelligence
structures such as the skybridge that Petronas Towers has.
4.2 All developer should try to adapt a building intelligent criteria into theirproject.
4.3 Malaysian architect and engineers should try to involve and built abuilding with fully intelligent aspects.
29
8/12/2019 Bil 1 Jun Klcc
32/35
II A. QUESTIONAIRE (BY INTERVIEW METHOD )
(1) What is the Intelligent Building ?
(2) What is the advantages and disadvantages of Intelligent Building ?
(3) How to define /classify IB (Intelligent Building) ?
(4) What is the technology used in construction of Intelligent Building ?
(5) What is the purpose of having Intelligent Building ?
(6) What makes KLCC an Intelligent Building ?
(7) How Intelligent Building facilities in the building function ?
(8) What is the concept of architecture of this building ?
(9) What are the differences between Intelligent Buildings and Conventional
Buildings ?(10)How do the intelligent buildings functions ?
27
8/12/2019 Bil 1 Jun Klcc
33/35
Terms of Reference
On 23rdDecember 2001, Pn. Hjh. Shehah Bt. Mansor, the English lecturer
of language centre, instructed the students to conduct a research on the
intelligent criteria on Petronas Twin Towers Building.
The purpose of the study is to find and to identify the intelligent criteria on
Petronas Twin Towers. A report of the findings is to be submitted by
February 2002
The project team members are proud to submit the report together with ourrecommendations.
i
8/12/2019 Bil 1 Jun Klcc
34/35
List of Illustrations
1. Park plan showing a public park in KLCC. 232. Map showing the accessibility pf infrastructure from KLIA and 26
within the city.
iv
8/12/2019 Bil 1 Jun Klcc
35/35