Top Banner

of 35

Bil 1 Jun Klcc

Jun 03, 2018

Download

Documents

Maria Millano
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/12/2019 Bil 1 Jun Klcc

    1/35

    A STUDY ON THE INTELLEGENCE CRITERIA

    ON PETRONAS TOWERS BUILDING.

    POLYTECHNIC SULTAN AZLAN SHAH

    DEPARTMENT OF CIVIL ENGINEERING

    Prepared by:

    NORHAYATI BINTI JAMIL

    ANIZA BINTI TAHIR

    LALITHAMBIGAI A/P SIVANGANAM

  • 8/12/2019 Bil 1 Jun Klcc

    2/35

    TABLE OF CONTENTS

    CONTENTS PAGE

    Terms of Reference i

    Acknowledgements ii

    Table of Contents iii

    List of illustrations iv

    I INTRODUCTION 1

    A. Background 2B. Objectives 3C. Literature Review

    (i) What Technology ? 4

    (ii) Effect of Technology 5

    (iii) Intelligence Township 5

    (iv) Intelligence Buildings 6

    (v) System Interoperability 7

    D. Methodology(i) Methodology Flow Chart 9

    II FINDINGS 10A. Questionnaire 27

    III CONCLUSIONS 28

    IV RECCOMMENDATIONS 29

    Appendixes

    iii

  • 8/12/2019 Bil 1 Jun Klcc

    3/35

  • 8/12/2019 Bil 1 Jun Klcc

    4/35

    ii

    I A. BACKGROUND

    As long as Petronas Towers are well known as one of the intelligencebuilding in this country, this study was carried out to gathered information and to

    find out what are the intelligence facilities or criteria, that the Petronas Towers has.

    The information was gathered through an interview with Ass. Prof. Ir. Dr. Khafilah

    bt. Din, a skybridge project coordinator, who is at present a lecturer in Faculty of

    Civil Engineering, UiTM. In addition an interview with Petronas Officer, Mr.

    Zulkarnain Abdullah was also held for the same purpose. Some information was

    also gathered from Internet.

    The intelligence criteria and facilities that has been discovered in this study could be

    summarised as follows:

    i) The conceptcity-within-a-city.ii) Building structure and materials used.iii) Building control system.iv) Telecommunication system.v) Energy saving system.vi) Elevator system.vii) Public parkdesign concept and facilities.viii) Infrastructure.

  • 8/12/2019 Bil 1 Jun Klcc

    5/35

    2

    I INTRODUCTION

    Petronas Towers (Kuala Lumpur, Malaysia)

    452 meters high

    The worl d's tall est reinf orced concrete off ice bui lding,

    a symbol of the new Asia

    Malaysia is a nation on the rise. In its energetic capital Kuala Lumpur a

    gigantic project is under way that symbolizes the emerging of the new Asia. The

    Kuala Lumpur City Center (KLCC) project is a complex of office buildings, hotels

    and an industrial center. At its heart is the Petronas Twin Towers intelligent office

    building, which began construction in 1994.

    The 88-floor Petronas Twin Towers have stood 452 meters tall, surpassing

    the 443-meter Sears Tower in Chicago to become the world's tallest building.

    Among reinforced concrete buildings this stunning architectural triumph will also

    far exceed the 295 meters of Chicago's 311 South Wacker Drive. Soon Asia will be

    home to the world's tallest building.

    The soaring twin cylindrical towers appear to embrace their smaller

    adjoining wings, and are connected by a sky bridge at the -meter level. The metal

    curtain wall adopted for the exterior design reflects Islamic architecture, blending

    tradition with a futuristic image and achieving a rich beauty that sets this building

    apart from earlier skyscrapers.

    Nowadays this intelligent building is applying the latest in architectural

    engineering technology to create the world's tallest building.

    Petronas Towers is raising the curtain on the new Asia, and adding a bright

    page to architectural history.

  • 8/12/2019 Bil 1 Jun Klcc

    6/35

  • 8/12/2019 Bil 1 Jun Klcc

    7/35

    3

    I C. LITERATURE REVIEW

    1.1 WHAT TECHNOLOGY ?

    The new technology era that we shall be witnessing in the next

    millennium will focus more on technologies that encapsulate knowledge-

    based systems. We shall be talking about intelligent systems that react

    dynamically on data input. Theses knowledge based systems will almost

    always rely on high technology information technology equipment. Most

    people may think that such technology is better discussed in other forums

    such as electronics, computing, electrical or mechatronics but the painful

    part about technology is the indirect impact that it may have on all other

    aspect of our lives. It should not be taken for granted that such technology

    will not affect Civil Engineering work, as technology itself is currently

    being used in most civil engineering design systems. It becomes more

    complex when human needs on housing and infrastructure facilities

    change with the coming of new technology. It therefore becomes

    important for civil engineers and anybody dealing with civil engineering

    work to acknowledge the technologies concerned.

    The technology incumbent in the millennium would be technologies

    related to the use of up-to-date information on all aspect of design and

    operation. It can be coined simply as Information Technology (IT). This is

    clearly manifested in the vision of Malaysia to implement the Multimedia

    Super Corridor, which shall focus on the efficient use of information

    technology in all its development and functions. Town and regional

    planners need to think about regional development with infrastructure to

    support the efficient use of information technology. Building architecture

    and design need to cater for information technology device to be

    introduced within buildings. Structural members designed by civil

    engineers must incorporate possible fluctuation of loads due to the

    presence of IT driven parts such as mobile roof that react to the position of

    the sun and others.

  • 8/12/2019 Bil 1 Jun Klcc

    8/35

    4

    1.2 EFFECT OF TECHNOLOGY

    The advent of new IT equipment for measurements as well as design

    changes the way an engineer would work in the design office. New

    surveying instruments that incorporate IT concepts allows surveyors and

    civil technician to conduct better and faster site investigation. Construction

    control has been made accurate through the use of such equipment.

    It is through the availability of these devices that we may have to

    change some of the way we work and perhaps some of the design criteria in

    our architectural and engineering design. Building services thus become one

    of the important design aspects to be taken into consideration in civil

    engineering construction work. Building structures need also take into

    account that part of the structure that may need to host special IT devices to

    monitor structural behavior and even perhaps control some of the dynamic

    movement of the structural member.

    These technology also affects other periphery activities such as

    highways, wastewater treatment plants, bridges and dams may require some

    review as to the additional high technology design tools that are available

    now and the provisions such design need to consider to include IT related

    devices in their structures.

    1.3 INTELLIGENT TOWNSHIP

    The development of the Multimedia Super Corridor (MSC) between

    Kuala Lumpur City Center to the new Kuala Lumpur International Airport is

    an example of an Intelligent Township. The whole development incorporate

    construction techniques that take into account the preservation of the

    ecology around the development area as well as ensuring that the various IT

    infrastructure is blended carefully within the built structure. All structure has

    provisions to include IT services that is built within its central building

    services ducting and external infrastructure had to be built in tandem with

    5

  • 8/12/2019 Bil 1 Jun Klcc

    9/35

    the development of the cables required for the information superhighway. It

    is envisioned that all building and structures within the MSC are wired to

    have IT services available upon completion of the project.

    1.4 INTELLIGENT BUILDINGS

    The process of designing, constructing, starting up, controlling and

    maintaining an intelligent building is very complex. The construction of

    such building requires the engineer to understand the various devices require

    to be installed within the structures. Such devices require an intelligent

    system to be developed to manage interactively the environment within the

    building. If done properly, the final product delivers comfort, safety, and a

    healthy environment and operates efficiently at reasonable cost. The key to

    managing this complex process of designing and operating buildings

    efficiently lies in the ability to manage information, deliver it efficiently to

    the proper controlling equipment and devices, and to use it effectively for

    the control of the building environment.

    Among the type of intelligent buildings are designed to be energy

    conscious yet environmentally comfortable to its occupants. This would

    usually be building that stores solar energy for its energy supply and

    maintains its comfort through having properly designed windows and

    opening within its structure. There might be a need to allow certain parts of

    the building to be mobile.

    Special system need to be developed an in corporate within the

    building services control system to manage and monitor the environment of

    the building.

    6

  • 8/12/2019 Bil 1 Jun Klcc

    10/35

    1.5 SYSTEM INTEROPERABILITY AND CONTROL

    The trend in equipment design and control systems is to embed

    greater intelligence in individual components. This distributed

    intelligence present new opportunities to optimise dynamic building

    systems resulting in lower energy use, energy cost and maintenance costs

    while maximizing building performance environmental quality and comfort.

    Tomorrows control system will be networked to operate as

    integrated systems. The system will include a robust performance tracking

    database technology to monitor and archive information on a broad spectrum

    of building systems and their real time attributes including HVAC, lighting

    and shell component s. Integrated building systems and their control

    technology will be linked to software modules that compare actual

    performance to original design objectives, metrics and functional intent.

    Some specific control developments will include:

    Adaptive/optimized/self-generating control algorithms:

    Development of techniques whereby control algorithms adapt

    to changing building or system conditions adjust, set points

    and eventually algorithms themselves to be optimal and

    eventually support automatic generation of control strategies

    based on the equipment and systems present

    Advanced control technique: Development of control

    techniques based on artificial neural networks, fuzzy logic

    and genetic algorithms.

    7

  • 8/12/2019 Bil 1 Jun Klcc

    11/35

    The following elements of interoperable and integrated information

    across the building life cycle:

    Formats for data exchange between design tools, commissioningtools, controls and sensor suites, facilities maintenance management

    systems and related software.

    Standardized schema for archiving building simulation,

    commissioning, control and operational data sets.

    Process and workflow management techniques in the use ofinteroperable and integrated systems to ensure that data required as

    input to software modules are supplied by the database archive or

    related software module.

    A user interface or browser that can interact with the data archive to

    obtain a global view of the data for a building project.

    8

  • 8/12/2019 Bil 1 Jun Klcc

    12/35

    I D. METHODOLOGY

    METHODOLOGY FLOW CHART

    9

    1. LITERATURE

    REVIEW

    2. INTERVIEW WITH

    PROF.MADYA DR KHAFILAH

    BINTI DIN

    3. ANALYSE INFORMATION

    GATHER FOR FURTHER

    INVESTIGATION

    4. SITE VISIT AND

    INTERVIEW WITH

    OFFICER IN

    CHARGE

    5. COMPILE ALL THE

    INFORMATION

    GATHERED

    6. IDENTIFY THE

    INTELLIGENCE

    CRITERIA OF KLCC

    7. PREPARE THE

    REPORT

  • 8/12/2019 Bil 1 Jun Klcc

    13/35

    II FINDINGS

    2.1 CONCEPTS

    The concept of KLCC is a self-contained, city-within-a-city.

    The integrated mixed-use development provides more than 1.67 million sq.

    meters (18 million sq. feet) of:

    commercialretailhotelresidentialentertainment facilities

    The winning Master plan submitted by Klages, Carter, Vail & Partners

    delineated the site into 22 freehold lots located around a 20-hectare (50-acre)

    park.

    The KLCC project is being implemented in phases. Phase One was launched in

    1992 comprising:

    the 88-storey PETRONAS Twin Towers; Suria KLCC - the six-level, 1.5 million sq. feet shopping centre; the 49-storey Menara Maxis; the 30-storey Menara Esso; the 32-storey Mandarin Oriental Kuala Lumpur Hotel; a 20-hectare (50-acre) Public Park; two District Cooling Centres; a Mosque

    10

  • 8/12/2019 Bil 1 Jun Klcc

    14/35

    2.2 KLCC Logo:

    The logo is derived from a "Dualism Theme"; the twinning of KLCC with

    the city itself. The corporate colours are in blue and green. Blue for the highrise

    with the blue sky and waterscape, green for the park and the landscape.

    Architect

    The 88-storey PETRONAS Twin Towers are designed by Cesar

    Pelli, the award winning, world renowned architect and founder of the firm

    of Cesar Pelli and Associates. Other prominent works of the former dean of

    Yale University's School of Architecture include:

    Canary Wharf, London World Financial Centre, Manhattan Crile Clinic Building, Cleveland Rice University's Herring Hall, Houston Carnegie Hall Tower, New York City Owens-Corning World Headquarters, Toledo

    11

  • 8/12/2019 Bil 1 Jun Klcc

    15/35

    2.3 BUILDING STRUCTURE & MATERIALS USED

    2.3.1 PETRONAS Twin Towers At A Glance

    Number of storeys = 88

    Height = 452 meters above street level

    Total built-up area = 341,760 sq.meters (3.7 million sq. feet)

    Design/Architecture = Cesar Pelli & Associates [U.S.] in association

    with KLCC architects.

    Location of skybridge = Levels 41 and 42

    Length of skybridge = 58.4 meters

    Height of skybridge = 170 metres above street levelVertical transportation = 29 double-deck high speed passenger

    lifts in each tower

    Number of escalators = 10 in each tower

    Stainless steel cladding = 65,000 sq. metres

    Vision glass = 77,000 sq. metres

    Concrete [various strengths up to grade 80] = 160,000 cubic metres

    in the superstructures [see also foundation description below]

    Steel = 36,910 tonnes of beams, trusses and reinforcement

    Foundation = 4.5 metre [15 feet] thick raft containing 13,200 cubic

    meters of grade 60 reinforced concrete, weighing approximately

    32,550 tonnes under each Tower, supported by 104 barrette piles

    varying from 60 to 115 metres in length.

    The floor-plate of the Tower is designed based on geometric

    patterns common in architecture of Islamic heritage. It is composed of two

    rotated and superimposed squares with small circular infills. These

    geometric figures have been described by architects as symbolising unity,

    harmony, stability and rationality - all important principles of Islam.

    Like the exterior design, the Towers' entrance design was also

    inspired by the country's cultural heritage, incorporating contemporary

    Malaysian motifs adapted from traditional handicrafts such as songket and

    12

  • 8/12/2019 Bil 1 Jun Klcc

    16/35

    timber carvings. The overall character of the building is high-tech and

    international but distinctively Malaysian.

    At the podium level, the PETRONAS Twin Towers feature the following :

    The 864-seat Dewan Filharmonik PETRONAS, a venue of architecturaland acoustic distinction. It is also home to the Malaysian Philharmonic

    Orchestra.

    A reference library on energy, petroleum, petrochemical and relatedindustries.

    The Towers were topped-out in March 1996 and occupation began

    in early 1997. Tower One is currently being occupied by PETRONAS, the

    state-owned petroleum corporation. Tower Two is being occupied by

    PETRONASassociate companies while the remaining space is being leased

    out to multinationals.

    The PETRONAS Twin Towers are located on the northern boundary

    of the Multimedia Super Corridor (MSC) and has state-of-the-art

    communication facilities. MSC is the launching pad to propel Malaysia into

    the frontline of the information age.

    2.3.2 SkybridgeThe skybridge is an essential functional component linking the Twin

    Towers to facilitate movement between the two towers.

    The 58.4 meters double-decked skybridge is located at levels 41 and

    42 joining the sky lobbies situated in both towers.

    Engineering Design Assembly of Skybridge Lifting of Skybridge

    13

  • 8/12/2019 Bil 1 Jun Klcc

    17/35

    Engineering Design

    The structural system selected utilises a 'two-hinge arch' springing

    from supports at level 29 and rising at 63 degrees to support a pair of parallel

    two-span continuous bridge girders at Level 41.

    The structure of the two-level bridge is conventional framing

    constructed of structural steel with beams moment-connected to columns

    which bear on the level 41 continuous girders. The bridge is 58.4 m long and

    weighs about 750 tonnes.

    The two-hinge arch supporting the bridge has rotational pins

    (spherical bearings) at the end of each leg or 'spring point' and at the top or

    'crown' of the arch (bearings). The main bridge girders have a rotational

    (centering) pin directly over the arch crown to permit the crown to rise and

    fall as the Towers move closer or further apart.

    The arch is a centering device, equalising joint movement at both

    Towers. As the Towers move together or apart, the legs change slope, the

    spherical bearings rotate at spring points and the legs flex at their top end.

    The bridge mid-point sinks or rises, flexing the two main girders.

    The girders are pinned on the arch crown, which stays centered

    between the Towers, while both girder and blocks slide on pads. The mid-

    span centering pin and two girder slip pads accommodate this movement.

    Continuous expansion joints provided through the level 42 and 43

    structure, facade and roof to each side of the bridge mid point. Providing

    14

  • 8/12/2019 Bil 1 Jun Klcc

    18/35

    expansion joints at mid-point reduces the effect of girder flexure on bridge

    glazing, as window panel movement is then limited to each half-span rather

    than cumulating over the whole girder length.

    When the Towers move side-to-side in opposite directions, or when

    they 'twist', the arch spring points twist on the spherical bearings and bridge

    end bearings slide in opposing directions guided by 'sliding keeper' blocks

    on bridge centreline.

    In the event that it loses its arch support, the bridge structure would

    not collapse but deflect and stay in position.

    Lifting of Skybridge

    VSL Heavy Lifting, a specialist in this field, was appointed for the

    lifting of the skybridge studies and preparation for the lifting was carried out

    for more than a year in several countries including the United States and

    South Korea, simulating various wind and weather conditions including

    those based on actual load data over the past 50 years.

    There are nine main steps in the lifting of the skybridge.

    STEP ONE

    The skybridge's legs are lifted up one at a time by tower cranes. Once

    they are in position, control cables are used to lower them over their

    permanent bearings at level 29.

    STEP TWO

    The two end block girder frames of the skybridge are lifted

    individually. The blocks are installed about 100mm above their final

    position at level 41. They are also retracted about 100mm into the tower to

    provide sufficient clearance for the skybridge centre section during lifting.

    15

  • 8/12/2019 Bil 1 Jun Klcc

    19/35

    STEP THREE

    The four lifting jacks located at level 50 of both towers are connected

    on the bridge centre. The other four lifting jacks located on level 48 of both

    towers are connected to the bridge ends.

    STEP FOUR

    The centre section which weighs 325 tonnes is lifted about 11 metres

    and restrained. This is to allow the upper 10 metres of the legs to be

    connected to the girder on the bridge.

    STEP FI VEAfter a final check, lifting of the centre section commences.

    STEP SIX

    At a minimum lifting speed of 12 metres per hour, the centre section

    is gradually lifted to its final level.

    STEP SEVEN

    Steps Seven to Nine took about two weeks. A temporary connection

    secures together the centre section and the end block girder frame to ensure

    there is no stress.

    STEP EIGHT

    The legs are moved into place. When the legs are in their final

    position, the skybridge end blocks are lowered on their permanent bearings

    at Level 41. The centre section is then lowered to meet the legs.

    STEP NINE

    After the lifting system has been removed, the floors were concreted,

    the skybridge roofed. The maintenance equipment is set up on stainless steel

    rails on top of the bridge.

    16

  • 8/12/2019 Bil 1 Jun Klcc

    20/35

    At about 7.40 p.m., on 9 August 1995, after 32 hours of lifting

    operation, the sky bridge was lifted to its final position at the 41st and 42nd

    levels of the PETRONAS Twin Towers.

    Construction and installation of skybridge

    17

  • 8/12/2019 Bil 1 Jun Klcc

    21/35

    2.4 BUILDING CONTROL SYSTEMThe Building Control System [BCS] provides central management

    and monitoring for air conditioning control, lighting control, and electrical

    and chilled water status monitoring, as well as providing energy

    management services.

    The local area network system is based on a two-tier LAN structure,

    where the primary network links the controllers to the command centre and

    the secondary LAN facilitates communication with the end devices. The

    BCS also interfaces to the life safety system, which is designed to overridethe BCS, in the event of an emergency.

    The air conditioning requirements for the KLCC Development,

    including the Towers is served by a 30,000-ton chilled water plant [District

    Cooling Centres], which combines natural gas-driven cogeneration

    equipment with various forms of steam turbine-driven chillers and electric

    chillers.

    The air-conditioning system selected for the Towers uses the latest

    development in floor-by-floor air handling units, utilising the chilled water.

    The floor-by-floor system solves the problems of acoustics, compactness,

    ease of maintenance and control.

    This system also provides the most advanced approach to engineered

    smoke control. It allows for a pressure sandwich between the floor on fire

    and the adjacent floors, thus allowing the fire to be contained during the

    evacuation process.

    The raised floor system utilised in the Towers allows for the effective

    flexible distribution of electric power and telecommunication cables to meet

    current and future needs.

    18

  • 8/12/2019 Bil 1 Jun Klcc

    22/35

    2.5 BUILDING SECURITY SYSTEM

    The Building Security System [BSS] is designed to operate via a LAN

    [local area network]

    High level software running on the integrated security network captures

    all data to ensure fully automated coordination among the BSS sub-systems,

    which include: -

    Card Access and Alarm Monitoring System Voice Intercoms Alarm Monitoring System Audio Alarm Surveillance System Closed Circuit Television System - CCTV Photo Identification System

    2.6 TELECOMMUNICATION SYSTEM

    At the heart of the building management system is a structured

    cabling system comprising vertical and horizontal cabling; inter building

    cabling and connectivity to telecommunications carrier companies. The

    system is designed to achieve maximum flexibility to accommodate present

    and future communication needs.

    Connectivity is provided from the main subscriber distribution frame

    to the end-user workstations, minimising re-cabling and cable-removal.

    The telecommunications infrastructure is designed as a local loop

    communications system within the boundaries of the KLCC site. The hub of

    the system is a Central Telecommunications Office [CTO], which serves as

    a local communications exchange and gateway to the outside world.

    19

  • 8/12/2019 Bil 1 Jun Klcc

    23/35

  • 8/12/2019 Bil 1 Jun Klcc

    24/35

    2.8 ELEVATOR SYSTEM

    The PETRONAS Twin Towers are serviced by a total of 76 lifts, of

    which 58 are double-deck lifts. The double-deckers result in better utilisation

    of the core space and require less hoistway thus maximing the efficiency of

    passenger transportation.

    The system features two passenger cabs, one above the other in the

    same car frame, sharing the same hoistway. Each double-deck unit is

    capable of carrying 26 persons per deck.

    The shuttle elevators can carry 26 persons per deck, or 52 per trip,

    while each of the other double-deck lifts is designed to take 23 passengersper deck. Traveling time is between 3.5m/second and 7 m/second depending

    on which zone they are servicing.

    Tenants / visitors going to 'even' floors embark on lifts at the ground floor while

    those traveling to 'odd' floors take the escalator to the mezzanine level before

    embarking on their respective lifts.

    21

  • 8/12/2019 Bil 1 Jun Klcc

    25/35

    2.9 PUBLIC PARK

    The beautifully landscaped park at KLCC is the last inspired

    masterpiece by the versatile and talented Brazilian master of gardens, the late

    Roberto Burle Marx.

    Spread over 50-acres [20-hectares], the lush tropical garden provides a

    haven of tranquility for those seeking a respite from the stress of city life

    The KLCC Park is unique in its theme and concept. Designed to

    showcase a heritage of tropical greenery by integrating man's creation with

    nature, the beautifully landscaped KLCC Park offers a calm and harmonious

    environment in the midst of the hustle and bustle of a busy and dynamic city.

    The late Roberto Burle Marx uses a combination of trees, shrubs,

    structures of cement, stones and wood as well as various water features in his

    creations. Elements of shapes, texture and topography are merged to create

    attractive and breathtaking masterpieces while at the same time imposing an

    illusion of space. Colour and form are achieved by using various combinationsof trees, shrubs and sculptures, thus dispelling the notion of a garden as a static

    creation.

    The conservation factor was another key consideration in the planning

    of the park. About 23 of the mature and rarer specimens were saved from the

    former Selangor Turf Club, and eventually transplanted on to the park

    grounds.

    About 1900 indigenous trees and 66 species of palms have been

    planted at the park. Much thought proceeded the selection of these plants, with

    the objective of encouraging bio-diversity. Among other attractions at the park

    are the magnificent lake symphony fountains, programmed to provide

    numerous different dramatic animations following a Symphony Overture

    sequence, the ornamental water features, the children's pool and the children's

    playground.

    22

  • 8/12/2019 Bil 1 Jun Klcc

    26/35

    The park is well interspersed with various amenities such as shelters,

    benches, rest areas, drinking fountains and public toilets. For health

    enthusiasts, there is also a 1.3 km jogging track encircling the park.

    Another interesting element of the park is the 43 meter elevated bridge.

    The centrally located bridge provides visitors with a vantage view of the park

    and the majestic PETRONAS Twin Towers.

    Part of the park is also designed as a haven for birds and other local

    fauna. Much research and thought went into the selection of indigenous tree

    species whose fruits attract local and migratory birds. Through such careful

    effort, it is expected that the KLCC Park in the heart of bustling Kuala

    Lumpur will become an important link in the 'bird corridors' of the region.

    PARK PLAN

    Lake Symphony

    The Symphony Lake with an approximate area of 10,000 square metres

    features mesmerising fountain displays. The displays consist of 5

    programmers with over 380 individually sequenced effects shooting up to a

    maximum height of 42 metres. These effects are displayed along the arc and

    the two rings totaling 80 metres in length. The Lake Symphony fountains are

    on from 12 noon till 2.00 p.m. and 6.00 p.m. till 11.00 p.m. on weekdays.

    23

  • 8/12/2019 Bil 1 Jun Klcc

    27/35

    Especially for weekends and public holidays, the fountains are on from 10.00

    a.m. till midnight.

    Jogging Track

    A 1.3 km. long jogging track is laid with EPDM, a special rubberised material

    to ensure comfort and safety for fitness enthusiasts.

    Rest Areas

    Rest areas are located on various nodes of the interconnecting footpaths. They

    are numbered as shown on the maps found on the Park's entry and feature

    identification signs. The numbering system can be used as points of reference

    for way finding and setting a rendezvous.

    Ornamental Water Features

    Waterfalls, Cascades, Reflecting Pools and Bird's Pool add to both the

    excitement and tranquility of the respective zones in the park.

    Other Amenities

    The KLCC Park has been provided with various amenities such as

    Toilets complete with modern fittings and facilities for the disabled and

    baby change.

    Male and female changing rooms annexed to the toilet near the Children's

    Pool.

    Drinking fountains with filtered water.

    Shelters and benches.

    24

  • 8/12/2019 Bil 1 Jun Klcc

    28/35

    MOSQUE

    Designed by KLCC architects, this 6,000 capacity Asy-Syakirin

    Mosque is known as the "Jewel in the Park".Skilled Uzbekistan craftsmen were employed to render intricate

    Uzbek's carvings and calligraphy on the interior and the internal facade of the

    dome. The main prayer hall, the three-storey air-conditioned building can

    accommodate 2,500 people while the lower prayer hall on the ground floor

    can accommodate an additional 3,500 people.

    Trellis Area

    25

    Dome Interio

  • 8/12/2019 Bil 1 Jun Klcc

    29/35

    INSFRASTRUCTURE

    The KLCC Project is located at the apex of the Multimedia Super Corridor

    (MSC) and is easily accessible to:

    the new Kuala Lumpur International Airport Government's new administrative centre, Putrajaya Port Klang, the country's main port 12 vehicular accesses and 14 bus stops Kuala Lumpur's inner ring road and a major highways to the suburbs Light Rail Transit (LRT)

    Accessibility from KLIA

    Accessibility within the

    city

    26

  • 8/12/2019 Bil 1 Jun Klcc

    30/35

    III CONCLUSIONS

    3.1 The intelligence criteria of the Petronas Towers could be summarized

    as follows:

    1. Store solar energy as it energy supply.

    2. First class Telekom provided by STM.

    3. Purpose built fireproof data storage rooms.

    4. Intergrated power, lighting, electronis, and control wiring.

    5. Direct digital control network.

    6. Time controlled secure accesses.

    3.2 The intelligence technology and materials used in Petronas Towers are:1. Building control system2. Building security system.

    3. Telecommunication system.

    4. Energy saving system.

    3.3 Intelligence buildings differ from conventional building in the someaspect such as :

    1. Automated building services.

    2. Information management.

    3. Control of environment.

    4. Conductivity determined by internal cabling and access to externalservices.

    28

  • 8/12/2019 Bil 1 Jun Klcc

    31/35

    IV RECOMMENDATION

    As a recommendation, we suggest that :

    4.1 We would like to proposed to Polytechnic to take the afford to add inthe syllabus for civil engineering degree course on intelligence

    structures such as the skybridge that Petronas Towers has.

    4.2 All developer should try to adapt a building intelligent criteria into theirproject.

    4.3 Malaysian architect and engineers should try to involve and built abuilding with fully intelligent aspects.

    29

  • 8/12/2019 Bil 1 Jun Klcc

    32/35

    II A. QUESTIONAIRE (BY INTERVIEW METHOD )

    (1) What is the Intelligent Building ?

    (2) What is the advantages and disadvantages of Intelligent Building ?

    (3) How to define /classify IB (Intelligent Building) ?

    (4) What is the technology used in construction of Intelligent Building ?

    (5) What is the purpose of having Intelligent Building ?

    (6) What makes KLCC an Intelligent Building ?

    (7) How Intelligent Building facilities in the building function ?

    (8) What is the concept of architecture of this building ?

    (9) What are the differences between Intelligent Buildings and Conventional

    Buildings ?(10)How do the intelligent buildings functions ?

    27

  • 8/12/2019 Bil 1 Jun Klcc

    33/35

    Terms of Reference

    On 23rdDecember 2001, Pn. Hjh. Shehah Bt. Mansor, the English lecturer

    of language centre, instructed the students to conduct a research on the

    intelligent criteria on Petronas Twin Towers Building.

    The purpose of the study is to find and to identify the intelligent criteria on

    Petronas Twin Towers. A report of the findings is to be submitted by

    February 2002

    The project team members are proud to submit the report together with ourrecommendations.

    i

  • 8/12/2019 Bil 1 Jun Klcc

    34/35

    List of Illustrations

    1. Park plan showing a public park in KLCC. 232. Map showing the accessibility pf infrastructure from KLIA and 26

    within the city.

    iv

  • 8/12/2019 Bil 1 Jun Klcc

    35/35