Top Banner

of 224

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.1

    F O R E W O R D T O I N S T R U C T I O N S

    These recommendations and instructions have been written as a direction to the starting up

    and operation of the 2 X 26.4 TPH Waste Heat Recovery Boiler supplied to M/s. BHATIA

    COKE & ENERGY LIMITED, GUMMIDIPOONDI, TAMILNADU.

    The recommendations and instructions are for the guidance of competent and responsible

    engineers having knowledge of standard operational procedure and routine maintenance of

    boiler plant.

    It is appreciated that conditions on individual plant may require minor modifications to the

    instructions, but major changes should not be made without prior consultation with the

    boiler manufacturer.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.2

    Important Instruction to End User

    The instruction provided in this manual are Standard practices on boiler maintenance as per

    manufacturer / consultants years of experience in the field of Pressure and Process

    equipment operation and maintenance. It is highly recommended for the end user to ensure

    the operation team is familiar & qualified to operate Waste Heat Recovery Steam Generator

    as per the instructions of Original Equipment Manufacturer [EGBPSPL] for operations &

    maintenance of the system. The Operational parameter will vary drastically, if the

    recommended input parameter is not maintained.

    Quality of Feed Water and Boiler water should be maintained as per the

    recommendation to avoid the failure in pressure parts.

    Hot Flue Gas (COFG) Quality & Quantity should be within the Manufacture

    recommended range.

    Over-Loading of Equipments is not recommended at any point of time.

    Utility inputs from End user should be within the recommendation.

    EGBPSPL here by confirm that the user is responsible for the cause and failure of boiler

    unit due to violation of recommendation given at the Project stage.

    ENMAS GB POWER SYSTEMS PROJECTS LIMITED,

    CHENNAI INDIA.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.3

    VOLUME - I

    BOILER OPERATIONS

    CONTENTS

    CHAPTER

    No DESCRIPTION PAGE No

    1. INTRODUCTION AND SCOPE 4

    2. GENERAL & TECHNICAL INFORMATION 18

    3. DESCRIPTION OF BOILER PLANT 22

    4. DESIGN DATA FOR BOILER PERFORMANCE 49

    5. BOILER PLANT SAFETY AND PROTECTION 54

    6. FEED AND BOILER WATER 61

    7. BOILER OPERATIONS 96

    8. SHUT DOWN, TUBE FAILURES, TROUBLE SHOOTING 184

    9. BOILER MAINTENANCE 201

    10. ANNEXURE 223

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.4

    CHAPTER 1

    INTRODUCTION AND SCOPE

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.5

    CHAPTER 1

    INTRODUCTION AND SCOPE

    CONTENTS

    SL.NO. DESCRIPTION PAGE NO

    a. Radiant Chamber 8

    b. Steam Drum 8

    c. Water Wall Panel 8

    d. Super Heaters 9

    e. Supports & Hangers 9

    f. Buck Stays 9

    g. Economizer 10

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.6

    CHAPTER 1

    INTRODUCTION AND SCOPE

    The boiler supplied for this contract is of WHRB (Waste Heat Recovery Boiler) which is

    located at downstream of Coke Oven to recover waste heat from the Oven exhaust. The

    salient features of the boiler are as described below:-

    The boiler is of Water tube, natural circulation, bottom supported, single drum, all welded

    type pressure part design, negative/suction draft waste heat recovery steam generator

    type. The boiler allows unrestricted and uniform upward expansion ensuring better leak

    tightness and low thermal stress for pressure parts over prolonged periods.

    The boiler has enclosure of radiant chamber surrounded by water cooled walls to ensure

    better optimum recovery of heat from the hot flue gas from coke oven exhaust.

    The supporting structure consists of the main columns, their foundation, the framework for

    the boiler and the built-in auxiliarys supports and the section girders for bracing the

    structure. The calculations of the column strength takes into account an earthquake

    resistant factor.

    The gallery supports outside and over the main structure consisting of a sectional girder

    frame properly spaced and braced, for the safe working at different levels as well as to

    approach highest elevation in the boiler, for the operation and maintenance of the boiler.

    Hot flue gases, from the Coke oven exhaust is supplied normally at 900 to 950 C which is

    considered for sizing the boiler pressure parts. The Hot flue gas shall be supplied at

    approximately 0.0 m elevation with a flange to connect the hot flue gas duct to the boiler.

    The duct cross section considered is approximately 2.875 x 1.555 (ID) m. The flue gas is

    routed through refractory lined hot flue duct to the boiler.

    1 No. Hydraulic Operated Guillotine water cooled damper of bottom supported

    arrangement is placed in the hot flue gas to the boiler and 1 No. Hydraulic

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.7

    Operated Guillotine water cooled damper of the bottom supported arrangement is

    placed in the cold flue gas connecting the ID fan and existing process stack, with the

    guillotine operating in vertical direction. Provision for drying chamber with manual

    damper/valve is provided in the flue gas duct from ID fan outlet and process stack inlet

    before the Hydraulic Operated Guillotine water cooled damper.

    The WHRB units have been designed and arranged in 2 vertical passes with the hot flue

    gases received in the first pass horizontally into the Screen tubes of the Water

    wall radiant chamber, and then flows vertically upwards through the Primary Super

    heater, Secondary Super heater and Evaporator coil assemblies; cross over to the second

    pass Economizer section and flows vertically downwards.

    All the heating surfaces of Primary Super heater, Secondary Super heater, and Economizer

    are arranged horizontally; and the Evaporator coils are arranged with a slight slope to the

    horizontal.

    The Vertical sections are of the self supporting type; and are of bottom supported

    design And will be rested on the supporting steel work of boiler, the high temperature

    water wall section.; and the Economizer section at a higher level. Ash collection

    hoppers are provided below radiant chamber and economiser sections.

    The steam drum is located at the front side of boiler, above the top Water wall

    headers and is supported on 2 No. Large sized down comer pipes which is mounted on a

    slide bearing arrangement on the structure for thermal movement of down comer when

    boiler is heated up with waste heat gases.

    The boiler is provider with proper circulation system consisting of bottom water wall

    headers, top water wall headers, relief and supply tubes. Circulation system of boiler

    provides appropriately sized system with unheated down comers, which avoids formation of

    De-nucleate boiling at all operating conditions.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.8

    All required structural steel, platforms & stairs, piping & duct supports; Weather

    Rain protection roof covering arrangement over each boiler are provided. Flue gas from

    Economizer outlet will be drawn by an ID fan and delivered to Process stack.

    A brief pressure part description of boiler is as follows:

    a. Radiant Chamber

    The primary purpose of the radiant chamber is to provide a gas tight enclosure for complete

    absorption of heat source from coke oven flue gas to the water walls.

    b. Steam Drum

    The boiler is provided with sufficiently sized steam drum which houses baffles, cyclones and

    scrubbers to remove water particles from saturated steam before it enters super heater

    coils. Steam drum is also provided with necessary nozzles for mountings, feed water and

    chemical injection. Steam drum is also provided with manhole entries on either side with

    door and bull dog clamp arrangement for its closure. Necessary air vent and pressure

    tapings were provided as per the requirements.

    c. Water Wall Panel

    The Water wall section provided essentially covers all 4 sides of the Inlet Radiant

    chamber to enclose Primary and Secondary Super heater sections and the Evaporator

    section. All four sides of water wall is membrane wall construction having bottom and top

    headers, which are connected by supply pipes and risers tubes respectively. The entire

    water walls are robust in construction with gas tight conditions. The water wall is also

    provided with dilution duct arrangement along with necessary damper to control the gas

    temperature entering the radiant chamber.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.9

    d. Super Heaters

    The Super heater consists of Primary and Secondary Super heater sections located in the

    radiant chamber. The secondary super heater is located just above the primary super heater

    coil arrangement.

    The Primary SH and Secondary SH had been arranged as counter and parallel flow type

    and fully drainable type. The Primary super heater coil assemblies; and the Secondary

    super heater coil assemblies are horizontal, in-line tube arrangement, with the main

    inlet and outlet headers located outside the Water wall enclosure.

    The PSH & SSH heat recovery surfaces are placed inside welded water wall

    enclosures; suspended through Evaporative hanger tubes from the top side of Water wall

    section; and is free to expand upwards, along with the hanger tubes.

    e. Supports & Hangers

    The boiler is bottom supported construction with free upward movement. The entire boiler

    is supported from external steel work. The heaviest girders are formed as a support

    framework below the bottom side wall headers and down comer. All the pressure parts of

    the boiler and integral piping are supported from this frame work with sling rod

    construction.

    f. Buck Stays

    The buck stays are provided around the radiant chamber wall to ensure the structural

    rigidity when there is a pressure increase or decrease inside the radiant chamber due to

    mal-operation of draft system. The buck stays are acting likes a stiffener to the boiler

    enclosure. Buck stay also guides the boiler thermal expansion.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.10

    g. Economizer

    Boiler is provided with huge economizer sections in the 2nd pass of the gas to recover the

    heat from hot flue gas coming out of evaporator section. Bottom side of the economizer is

    also provided with hopper and slide gate arrangement to remove fly ash coming out of

    boiler.

    The following are the components of major equipments for the boiler:

    1. Steam Drum

    Steam drum with nozzles and manholes.

    Steam drums internals with cyclones, baffles, Primary & Secondary separators.

    Feed distribution sparge flange pipe with thermal sleeve.

    Chemical distribution pipe.

    Continuous Blow down Line.

    2. Water Walls

    Tubes with attachments / fins / Membrane wall.

    Openings for access doors, inspection doors, Temperature & Pressure instrument tapping

    Top headers along with stubs and attachments.

    Bottom headers with stubs and attachments.

    Structural attachments.

    3. Evaporative Boiler Bank System

    Evaporative Bank tubes.

    Bottom Headers.

    Top Headers.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.11

    4. Primary Super Heater

    Inlet header along with stubs and attachments.

    Outlet header along with stubs and attachments.

    Lugs and spacers for Coils.

    5. Attemperator

    Complete Attemperator with spray nozzles,

    Thermal Sleeve and Venturi.

    6. Final Super Heater

    Super heater elements.

    Inlet header along with stubs and attachments.

    Outlet header along with stubs and attachments.

    Lugs and spacers for the same.

    7. Economizer

    Economizer Elements.

    Inlet header along with stubs and attachments.

    Outlet header along with stubs and attachments.

    Lugs and spacers & spectacle plates for the same.

    Erosion shields.

    Cassette baffles.

    Hoppers

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.12

    8. Integral Piping

    Large bore down-comers with stubbed ends.

    Supply pipes.

    Riser pipes.

    Saturated steam pipe to Primary Super Heater.

    Link between Primary Super heaters to Attemperator.

    Link pipe between Attemperator to Secondary Super heater.

    Main steam flow nozzle.

    Link pipe between Attemperator tap off point to Attemperator control station inlet.

    Link pipe between Attemperator control station outlets to inter stage Attemperator.

    Attemperator water flow orifice.

    Link pipe between battery limit and feed control station.

    Link pipe from outlet of Feed Control Station to economizer inlet header.

    Feed water flow orifice.

    Link pipe between economizer outlet and steam drum.

    Start -up vent piping.

    Link between drum to Blow down Tank.

    Super heater and boiler drains to drain header.

    Drain header to Blow down Tank.

    Intermediate blow down piping.

    Piping to sample coolers.

    9. Low Pressure vessels and piping

    Safety Valve exhausts piping.

    Blow Down tank with drains.

    Blow Down tank escape / vent piping.

    Cooling water piping to sample coolers.

    Temporary piping for steam blowing.

    HP chemical dosing system.

    Piping from HP chemical system to drum.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.13

    10. Piping supports

    Supports for Main Steam piping.

    Supports for Feed Water control station to Economizer inlet.

    Supports for Economizer to Drum Piping

    Supports for risers piping

    Supports for Saturated Steam Line piping

    Supports for Supply Line piping

    Supports for Down comer

    Supports for start-up vent piping.

    Supports for safety valve escape piping.

    Supports for BD tank escape piping.

    Supports for Primary Super Heater to Attemperator piping.

    Supports for Attemperator to Secondary Super Heater piping.

    Supports for Attemperator spray water line piping.

    Supports for all drain piping.

    Supports for risers.

    Supports for supply pipes.

    11. Casing, Flue Gas Ducting System

    1. Refractory lined hot flue gas duct from coke oven exhaust to inlet radiant chamber.

    2. Flue gas from boiler exit to economizer.

    3. Economizer casing.

    4. Flue gas duct from economizer to existing common flue gas duct.

    5. Duct from common flue gas duct to ID inlet.

    6. ID discharge duct to stack.

    7. All expansion joints.

    8. Necessary supports.

    9. Measurement tapping on ducts.

    10. Necessary fasteners.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.14

    12. Structural

    Total boiler structure along with main columns, bracing, tie beams, & ceiling structure.

    13. Galleries and Ladders

    Galleries, platform, stairs.

    Hand rails and guard plats.

    14. Hot Structures

    Buck Stays and Tie Bars.

    Stand Off Plates.

    Corner connections.

    Earthquake restrains.

    Boiler thermal anchors and ties.

    Arch support beams, channels and structures.

    Economizers hot support beams.

    15. Supports and hangers.

    Necessary guide for steam drum along with saddles.

    Necessary slide bearings for water wall along with saddles.

    Necessary supports for final / primary super heaters along with saddles / lugs.

    16. Miscellaneous Structures

    Structures for handling equipment.

    Run way beams.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.15

    17. Castings

    Access door with mounting plate.

    Inspection door with mounting plate.

    18. Dampers and expansion bellows

    All Manual dampers as per the P & I drawings.

    Hot flue gas duct bellows as required.

    19. Insulation and Cladding

    Complete boiler insulation and cladding.

    Insulation and cladding for flues and ducts.

    Insulation and cladding for air integral piping.

    20. Refractory

    Refractory at radiant hopper region.

    Refractory at the inlet of flue gas duct.

    Refractory on doors / openings

    21. Pumps

    Boiler Feed Pumps.

    HP Chemical dosing pump.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.16

    22. Valves

    Manual and motorized valves as per P & ID.

    Super heater safety valve.

    Drum safety valves.

    Motorized main steam stop valve.

    All air release valves.

    All header drain valves.

    Chemical line valves.

    Necessary root valves.

    All control valves as per P & I.

    1 x 100% Pneumatic Feed Control Valve.

    1 x 30% Pneumatic Feed Control Valve

    1 x 100 % manual feed by- pass valve.

    23. Silencers

    Silencer for startup vent.

    Silencer for main steam line safety valve.

    24. Electrical

    Local Isolators (only for LT, MOV and dampers).

    Local Push button stations.

    Junction Boxes.

    Inter connecting power and control cabling.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.17

    25. Motors

    Motors for ID fans.

    Motors for Feed pump.

    Motors for chemical dosing systems / agitators.

    Motors for all motorized dampers and Valves

    26. Instrumentation

    Field mounted instruments as shown in P & ID.

    Local gauge instruments as shown in P & ID.

    Instrument Cables.

    Local junction boxes and instrument racks.

    Instrument cable trays.

    Instrumentation piping.

    Instrument air piping.

    27. Major Mountings

    Drum safety valves

    Drum level Direct Water Level gauge.

    Drum Level Remote Water Level Indicator with 4 20 mA DC Output.

    Drum Level level Transmitter & indicator.

    Pressure and temperature gauge.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.18

    CHAPTER 2

    GENERAL AND TECHNICAL INFORMATION

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.19

    CHAPTER 2

    GENERAL AND TECHNICAL INFORMATION

    CONTENTS

    SL.NO. DESCRIPTION PAGE NO

    1. General Information 20

    2. Technical Information 20

    2.1 Boiler 20

    2.2 Electrical & Instrumentation 21

    2.3 Process Steam 21

    2.4 Instrument Air 21

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.20

    CHAPTER 2

    GENERAL AND TECHNICAL INFORMATION

    1. GENERAL INFORMATION

    SL.No Description Information

    1. Plant 2 X 26.4 TPH Waste Heat Recovery

    Steam Generator in M/s. BHATIA COKE

    & ENERGY LTD,Gummidipoondi,Tamilnadu

    2. Elevation Above Sea Level About 15 M (approx) above MSL

    3. Road Link NH 5

    4. Air Port Chennai about 65 KM

    5. Rail Link Gummidipoondi

    6. Seismic Zone & Co efficient Seismic Zone III (Light to Moderate)

    9. Relative humidity - Design 90 %

    10. Ambient Temperature 50C

    2. TECHNICAL INFORMATION

    2.1 Boiler

    SL. No Description

    1. Numbers and type of Boiler 2 off Single drum, Natural circulation, Bottom

    supported Fully drainable Waste heat recovery Boiler.

    SL. No DESCRIPTION UNITS VALUES

    APPROXIMATE

    2. Final Super Heater Flow at 100 % BMCR TPH 26.4

    3. Steam Pressure at Main Steam Stop Valve Outlet

    (MSSV) kg/cm2(g) 71

    4. Boiler Steam Drum Design Pressure kg/cm2(g) 85

    5. Main Steam Temperature at Super Heater Outlet C 4905

    6. Boiler Feed Water Inlet Temperature C 140

    7. Maximum Flue Gas Temperature at Boiler Outlet C 160

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.21

    2.2 Electrical & Instrumentation

    For all drive motors : 415V; 50 Hz, 3 Phase

    For Controls : 220 V

    Instrumentation Interlocks and Annunciation : 24V (2 Wire) DC

    Voltage Variation : 10%

    Frequency Variation : 5%

    Combined Variation : 10%

    2.3 Instrument Air

    Quality : Oil and Moisture Free

    Pressure : 7.0 Kg/cm2 (g)

    Dew Point : -40C

    Temperature : Ambient

    2.4 Cooling Water

    Water inlet Temperature : 32C

    Pressure : 5 Kg/cm2 (g)

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.22

    CHAPTER 3

    DESCRIPTION OF BOILER PLANT

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.23

    CHAPTER 3 DESCRIPTION OF BOILER PLANT

    CONTENTS

    SL.NO. DESCRIPTION PAGE NO.

    a. Feed control Station 24

    b. Circulation System & Steam Drum 25

    c. Boiler Water Wall Systems 27

    d. Evaporator Section 29

    e. Super Heater Section 30

    f. Attemperator Unit 34

    g. Economizer Section 35

    h. Boiler Inter Connecting Piping 36

    i. Boiler Internal / Trim Piping 37

    J. Valves & Fittings 38

    k. Non-Pressure Parts 40

    l. Boiler Supporting Structural, Platforms & Stairs 41

    m. Economizer Casing & Supporting Steel 42

    n. Flue Gas Ducting 42

    o. Hot Flue Gas I/L Duct to WHRB 42

    p. Slide Bearings Supports 43

    q. Ash Hoppers 43

    r. Buckstays 43

    s. Refractory Materials, Insulation & Outer Casing 44

    t. Induced Draft Fan 45

    u. Guillotine Dampers 45

    v. Dosing System 46

    w. De-aerator, Feed Storage Tank 47

    x. Boiler Feed Pumps & Drives 47

    y. Soot Blower 48

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.24

    CHAPTER 3

    DESCRIPTION OF BOILER PLANT

    PRESSURE PARTS BRIEF DESCRIPTION AND DETAILS

    The High Pressure Boiler primarily consists of the following Pressure Parts:

    1. Feed Control Station

    2. Circulation System & Steam Drum (with internals)

    3. Water walls system (including the inlet radiant section)

    4. Super heaters consisting of Primary and Secondary Sections

    5. Attemperator unit

    6. Evaporator Sections

    7. Economizer Sections

    8. All the Boiler Connecting Piping (between Economizer Drum Evaporator; and

    between Super heater sections etc.): Feed control station to Economizer feed piping;

    Main Steam piping up to MS stop valve.

    9. All the Boiler integral / Trim piping

    10. One number BD Tank

    11. Valves and Fittings (Steam & Water System)

    The Pressure parts design materials and thickness has been conservatively chosen, with

    required margins over the code requirements for trouble free unit operation. The Access

    doors are provided on both side of the boiler, to which required access platforms are

    provided.

    The Brief Description and Details of the various Pressure parts are as follows:

    a. Feed Control Station

    Feed control station is meant for controlling feed water to boiler. The feed water line

    comprises of following:

    - 100 % Pneumatic feed control valve.

    - 30 % Pneumatic feed control valve.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.25

    - 100 % manual by-pass valve.

    - Manual isolation Valves for Control Valve.

    - Drain Valve located before Feed water Regulator valve.

    - Feed check valve and Shut-off Valve.

    - Pressure Gauge Isolation valves.

    - Thermo well box with Thermo well.

    - Feed water sampling valves.

    - Initial filling line valve.

    - Root & Isolation valve for all HP tappings.

    b. Circulation System & Steam Drum

    The heated feed water from outlet

    of Economizer is discharged into

    the drum, below the Normal Water

    level, where it gets mixed with hot

    water in the steam drum. From the

    drum, the water flows down

    through the unheated down comer

    pipes to the bottom headers of

    water wall section. The water flows

    through the heat absorbing walls

    and gets partly evaporated into

    steam. The steam water mixture

    flows to the drum through riser

    pipes. The internals provided in the

    steam drum separates steam from

    the water. The water particles fall

    down and enter the circulation

    system again, while the saturated

    steam leaves the drum for super

    heaters.

    Figure 1: Circulation System

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.26

    Boiler is provided with two main down comer which supply water to water wall, evaporator

    and hanger tubes. Evaporator circuit is provided with four supplies and six risers. Hanger

    tube is provided with two supplies and two risers. Water wall is provided with bottom and

    top headers along with down comer and raisers.

    Steam Drum

    The Boilers are of the single drum type. The steam drum of each WHRB unit is placed

    horizontally on the RHS side of the boiler, at an elevation of approx. 33.0 m above

    ground level. The drum is supported on 2 Nos. Large size vertical down comer pipes.

    FIGURE 2: ELEVATION (Steam Drum)

    (View looking from Rear of Boiler)

    The steam drum will be of fusion welded construction, with semi ellipsoidal dished

    ends with a manhole doors. Cyclone separator type drum internals are provided, for

    this high pressure duty to achieve assured steam purity over wide operating conditions.

    The steam drum is sized sufficiently large to have sufficient water holding between the NWL

    and Trip level for full load operation.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.27

    The dimensions of the Steam Drum are as below:

    Number of Drum / Boiler - One

    Drum ID / Raw Plate Thickness mm 1220 X 55

    Minimum Shell Length mm 3400

    Dished Ends Type - Semi Ellipsoidal

    Material of Drum Plates - SA 515/516 Gr 70 or

    Equal: Carbon Steel

    Drum Internals 2 Stage - Turbo Separators and

    Screen dryers.

    Water Holding Capacity (NWL Trip Level) Max

    at 100% BMCR. minute One

    Number of Down Comer Pipes - 2 (Two)

    Drum Supporting Arrangement - On 2 Nos. Down Comer

    pipes

    Drum Design Pressure kg/cm (g) 85

    Key Drawing:

    Steam Drum : ICAA0200-1-F-03-01-0352

    c. Boiler Water Wall Systems (Including the inlet Radiant Section)

    The Water wall section provided essentially covers all 4 sides of the Inlet Radiant

    chamber, the Primary and Secondary Super heater sections and the Evaporator section

    as shown in the figure-3. All required bottom and top headers are provided.

    The water wall system will be designed for a pressure of 400 mm WC, and

    required Buck stays and tie bars are provided. Required access doors and soot blower

    openings etc. are provided in the water wall panels. The entire Water wall will be supported

    at about ~ 7.0 m level over structural support steel work and is free to expand upwards.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.28

    The dimensions of the Water wall systems

    are as below:

    Description Design Values

    Boiler

    Width W 3657.6 mm

    Depth D 2349.8 mm

    CL of WW Top Header

    [Height] 30700 mm

    WW Tubes [OD X T]

    Front & Rear (50.8 X 4.0) mm

    WW Tubes [OD X T]

    LHS & RHS (50.8 X 4.0) mm

    WW Tubes [OD X T]

    Roof Tubes (50.8 X 4.0) mm

    Material Tubes SA 210 Gr A1

    WW Tubes [OD X T]

    Front & Rear 76.2 mm

    WW Tubes [OD X T]

    LHS & RHS 76.2 mm

    WW Tubes [OD X T]

    Roof Tubes 76.2 mm

    WW Fins [W X T] (25.4 X 6) mm

    Material Fins IS 2062 Gr C

    WW Header OD

    [Top/Bottom]

    (219.1/219.1)

    mm

    Hanger Tube Header

    OD [Inlet/Outlet]

    (219.1/219.1)

    mm

    Material Header

    [WW/Hanger]

    SA 106 Gr B/ SA

    106 Gr B

    WW Heating Surface

    Area 440 m

    FIGURE 3: ELEVATION

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.29

    Key Drawing:

    Arrangement of Water Wall Panel : ICAA0200-1-F-04-01-0939

    d. Evaporator Section

    The Evaporator heating surfaces consist

    of a number of Evaporator coil

    assemblies, in-line tubes; each element

    arranged at 9 to the horizontal.

    The coil assemblies are connected at

    the inlet and outlet end by large size

    headers. The Evaporator heating surfaces

    are arranged inside the welded wall

    enclosure. The Evaporator coils are

    suspended through Evaporator hanger

    tubes from the top side of the Water

    wall section; and is free to expand

    downwards along with the hanger tubes.

    FIGURE 4: ELEVATION (Arrangement of

    Evaporator Coils with Sling Tubes)

    (View looking from R.H.S of Boiler)

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.30

    The dimensions of the Evaporator Section are as below:

    Description Units Design Values

    Number of V Tube Section = One

    Type of Flow =

    Parallel Flow (With

    Saturated water flowing

    upwards)

    Tube OD X Thk mm = 60.3 X 4.0

    Materials - Tube = SA 106 Gr. B/

    SA 210 Gr. A1

    Materials Header [Inlet & Outlet] = SA 106 Gr. B/C

    On load cleaning System = Steam soot blower

    (Rotary Type)

    Total Bed Evaporator Coil Heating Surface

    Provided m = 868

    Key Drawing

    Evaporator Coil Assembly : ICAA0200-1-F-04-35-0001

    e. Super Heater Section

    The waste heat recovery boilers is provided with two stage super heater (primary and

    secondary) and inter stage attemperator to have better control to the final steam

    temperature. The Primary super heater coil assemblies; and the Secondary super heater

    coil assemblies are horizontal, in-line tube arrangement, with the main inlet and

    outlet headers located outside the Water wall enclosure. The Primary SH and Secondary SH

    have been designed as counter and parallel flow type and fully drainable type.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.31

    FIGURE 5: ELEVATION (Arrangement of PSH with Sling Tubes)

    (View looking from RHS of Boiler)

    FIGURE 6: ELEVATION (Arrangement of SSH With Sling Tubes)

    (View looking from RHS of Boiler)

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.32

    The PSH & SSH heating surfaces are placed inside welded water wall enclosures;

    suspended through Evaporative hanger tubes from the top side of Water wall section; and is

    free to expand down wards, along with the hanger tubes.

    FIGURE 7: STEAM FLOW DIAGRAM

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.33

    The dimensions of the Super Heater Section are as below:

    Sl.No Description Units Primary Super Heater Secondary Super Heater

    1.

    Number of

    Sections/WHRB

    -

    One One

    2.

    Location in the gas path

    (In the direction of gas

    flow)

    -

    Rear Side Front Side

    3. Type of flow - Counter & Parallel

    Flow Counter & Parallel Flow

    3. SH tubes OD X Thick mm 50.8 X 4.0 50.8 X 4.0 & 5.0

    4. Material of SH Tubes (all

    as required per IBR)

    - SA 210Gr.A1

    &

    SA 213Gr.T11

    SA 213 T11 & T22

    5.

    SH Headers materials

    (all as required per IBR)

    - SA 106Gr. B /

    SA 335 P11

    SA 335 P11 /

    SA 335 P22

    6.

    Size / Material of SH

    Inter connecting pipes

    (PSH -SSH)

    -

    100 NB / SA 335 P11

    7.

    Enclosure Side Water

    wall tubes & Screen

    tubes [OD X T]

    -

    50.8 X 4.0 50.8 X 4.0

    8. WW Headers Material - SA 106 Gr. B/C

    9.

    Total heating surface of

    the Super heaters

    sections (approx.)

    m2 126 103

    Key Drawing:

    Arrangement of PSH : ICAA0200-1-F-05-01-0149

    Arrangement of SSH : ICAA0200-1-F-05-06-0052

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.34

    f. Attemperator Unit

    To have a wide range of controlling from 50% to 100 % of MCR steam flow for the final

    steam temperature an attemperator is located in the connecting piping, between PSH outlet

    and the SSH inlet connecting pipe.

    FIGURE 8: ATTEMPERATOR ASSEMBELY

    The dimensions of the De-Super Heater Section are as below:

    Number of DSH - One

    Type - Spray Type (Variable Orifice)

    Control of Spray - By Spray Control Valve

    DSH OD mm 114.3

    Material - SA 335 P11

    Control Range - 50% to 100% of Boiler MCR

    Key Drawing:

    De Super Heater Assembly : ICAA0200-2-F-06-03-0064

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.35

    g. Economizer System

    The Economizer heating surfaces are arranged in the

    second pass of gas flow. The Economizer coil

    assemblies consist of horizontally arranged inline

    tubes, with the inlet and outlet headers located

    outside the gas path. The Economizer coil assemblies

    are supported / suspended over support beams and

    the coils are free to expand.

    The Economizer heating surfaces are enclosed in a

    steel casing, suitably stiffened and arranged with a

    structural steel system. Economizer section as a whole

    is of the self supporting type, and of bottom supported

    design.

    The Economizer is the last stage of heat recovery, placed

    in the gas path, on the downstream side of the

    Evaporator surfaces. Each bank height of the

    economizer will be approximately 3000 mm and

    interbank gap will be 700 mm. Necessary soot blowers

    for periodically cleaning the soot at the economizer

    sections are provided.

    FIGURE 9: ELEVATION

    (View looking from RHS of Boiler)

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.36

    The dimensions of the Economizer Section are as below:

    Number of Economizer Sections - One

    Type -

    Counter flow (With FW flow

    upwards and gas flow

    downwards

    Tube Outer Diameter x Thickness (38.1 x 3.6) mm

    Material of Tubes - SA 210 Gr A1

    Header Outer Diameter - 141.3 mm

    Header Material and Connecting Pipes - SA 106 Gr B

    Enclosure of Economizer Coil Assembly - 6 mm Carbon steel plates

    Total Heating Surface Area Economizer (approx) - 1969 m

    Key Drawing:

    Arrangement of Economizer : ICAA0200-1-F-02-01-0043

    h. Boiler Inter connecting piping

    1. Economizer Sections & System Feed Pipe

    Sl.No Description Pipe Size Material

    1. Feed Control station to Economizer inlet 80 NB SA 106 Gr B

    2. Economizer outlet to drum 80 NB SA 106 Gr B

    2. Evaporator Sections / Circulating System

    Sl.No Description Pipe Size Material

    1. Down comer Pipes -From Drum 200 NB SA 106 Gr B

    2. Supply Pipes DC Pipes to Evaporator & Water Wall 125 NB SA 106 Gr B

    3. Riser Pipes - From Evaporator & WW Top Outlet 125 NB SA 106 Gr B

    4. Connecting Pipes to Drum (Risers) Distribution at

    Drum end 125 NB SA 106 Gr B

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.37

    3. Super Heater section (Saturated Steam Pipes)

    Sl.No Description Pipe Size Material

    1. Saturated Steam Pipe - Drum to PSH Inlet 100 NB SA 106 Gr B

    2. SH Inter Connecting Pipe & DSH Connecting PSH &

    SSH 100 NB SA 335 P11

    3. Main Steam Piping up to MS Stop Valve 100 NB SA 335 P11

    i. Boiler Internal / Trim Piping

    a) The complete requirements of boiler integral trim piping will be supplied for each

    boiler. This will include the following.

    Drain piping

    Vent piping

    Drum emergency drains / Intermittent Blow down piping

    Exhaust piping for Safety valves and starting vent

    Drain header for HP drains

    Steam / water piping connections for instrument connection

    De-Super Heater spray water piping

    Chemical feed piping

    De SH spray water Pipings

    Sampling piping to Sample coolers

    b) A Blow down tank (Common for both intermittent blow down and Continuous Blow

    Down) will be provided for each WHRB unit. All the drain of super heater and boiler drain

    lines, IBD, CBD are terminated at a common header collecting water / condensate from the

    mentioned sources are connected to the BD tank. The BD tank is provided with a vent

    piping to atmosphere at safe elevation. The condensate drain is passing through a siphon

    into the blow down pit. The condensate drain is passing through a siphon into the blow

    down pit.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.38

    j. Valves and fittings (Steam & Water System)

    The Steam Generator are equipped with all required Valves and fittings for safe and efficient

    unit operation as part of the Boiler Integral pressure part system. The details, arrangement

    and location of Valves and fittings are shown in the P&IDs enclosed in Volume II

    (Mechanical Drawings).

    For the ready reference, we had enclosed herewith the list of major valves and fittings.

    LIST OF MAJOR LARGE SIZE VALVES AND FITTINGS

    (Refer P&ID Steam and Water system also for details)

    Sl.No Service / Description NB No.

    provided

    Operation Remarks

    A BOILER FEED WATER

    SYSTEM

    1

    Feed Control valve(100%

    capacity)

    NB 50

    (On NB 80

    feed line)

    1 Pneumatic At feed control

    station

    2

    Feed Control valve(30%

    capacity) for low load

    operation

    NB 25/32

    (On NB 40

    feed line)

    1 Pneumatic At feed control

    station

    3

    Bypass Feed Control valve

    (100% capacity) NB 80 1 Hand

    At feed control

    station

    4

    Isolation valves for the

    100% capacity valve NB 80 2 Hand

    At feed control

    station

    5

    Isolating valves for the 30%

    capacity valve NB 40 2 Hand

    At feed control

    station

    6 Feed stop valve NB 80 1 Hand Eco inlet

    7 Feed check valve NB 100 1 Auto Eco inlet

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.39

    8 Flow Nozzle NB 80 1 - Inlet of feed

    control station

    Sl.No Service / Description NB No.

    provided

    Operation Remarks

    B DRUM EVAPORATION

    SYSTEM

    1

    Drum Safety valves (Without

    silencers) NB 25 2

    Auto spring

    loaded Steam Drum

    2 Direct water level gauges NB 25 2 - Steam Drum

    3

    Electronic water level

    indicator unit (with local &

    remote indication)

    NB 25 1 - Steam Drum

    4

    Blow down valve

    CBD

    NB 25

    1

    Hand

    (Angle

    Type)

    In CBD Line

    5 Blow down valve isolation NB 25 1 Hand In CBD Line

    6.

    Drum emergency drain

    valve NB 25 1 Hand In IBD Line

    7.

    Drum emergency drain

    isolation valve NB 25 1 Hand In IBD Line

    C SUPERHEATED STEAM

    SYSTEM

    1 Super heater safety valve

    with silencer NB 25 1

    Auto spring

    loaded

    MS Line at FSH

    outlet

    2 Start up vent valves (30%

    capacity) with silencer NB 50 1 Hand

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.40

    3 Isolating valve to start up

    vent valve NB 50 1 Hand

    4 Main steam stop valve (with

    integral MO bypass) NB 100 1 Motor

    5 Main steam check valve NB 100 1 Auto

    6 Main steam flow nozzle NB 100 1 -

    D DESH SPRAY WATER

    1 Flow orifice NB 15 1 - Spray water line

    2 Spray water control valve NB 15 1 Pneumatic

    Spray water

    control station

    3 Standby Spray water Motor

    Operated valve NB 15 1 Hand

    4 Isolating valves for Spray

    Control valve and Regulating

    valve

    NB 15 2 Hand

    k. Non-Pressure parts

    The main Non Pressure parts of the each WHRB units, essentially consist of the following:

    Boiler supporting structurals and connected steel work; Platforms; Stairways; Supports

    for Boiler Connecting Piping and Ducting, etc.

    Economizer Casing and Supporting steel work.

    Hoppers (below the vertical gas passes).

    Flue ducting from outlet of Evaporator and inlet of Economizer; Flue ducting at

    Eco outlet side, from the outlet of Economizer to inlet of ID fan; and ID fan to

    stack (with the required supporting steel)

    Hot flue gas inlet duct (at inlet of Radiant Boiler section) with supporting steel, as

    required.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.41

    Structural support steel for Boiler roof and sides covering (weather protection).

    Buck stays (for the Water wall enclosure section).

    Other miscellaneous supports; Structural steel for ID fan and motor handling

    arrangement.

    The Structural steel supporting steel system will include all the main and auxiliary

    columns, beams and bracings, Duct and piping supports, equipments, support

    structures, etc. as required.

    The brief description and details of the various non pressure parts will be as

    follows:

    The brief description and details of the various non pressure parts are as follows:

    l. Boiler Supporting Structural, Platforms & Stairs

    The complete Boiler Pressure parts in 2 vertical sections, and the Drum & Piping etc.

    will be supported from bottom side, on the structural steel work (at approx. 7.0

    m elevation).

    The complete structural system will be of the Welded Construction.

    The Steam drum is provided with flooring all around, for access to the manhole

    doors, various valves and fittings etc.

    The Platforms and stairs have been provided on one side of the boiler (giving

    approach to the Access doors, valves and fittings, etc.).

    Slope of stairways will be between 40-45: Ladders are provided only wherever

    required. The Slope of the stairways will be preferably 41.

    A Stairways arrangement up to drum level has been provided, as per the GA drawings.

    The Width of Stairways and platform is 750 mm and will be as per ENMAS

    standards. Hand railing design and arrangement will be as per ENMAS standards.

    Handrails made out of 34.2 and 27.3 OD pipes.

    Floor grating and stair (step) treads will be about 25 mm thickness open type, as per

    ENMAS standards.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.42

    The supporting steel for boiler roof covering materials.

    Please refer to GA drawings of boiler for general details of

    the arrangement of the supporting structurals, platform and

    stairs, etc.

    m. Economizer Casing & Supporting Steel

    Complete Structural steel for the Economizer section, with platforms is provided.

    Economizer casing are fabricated of 6 mm thick Carbon steel plates, suitably stiffened.

    The Economizer sections are provided in separate gas passes, with separate ash hoppers.

    The Structural supporting steel materials and manufacture will be as that of main

    Boiler supporting steel. This arrangement is to facilitate O & M even under adverse

    operating conditions.

    n. Flue Gas Ducting

    Flue gas duct work connecting Evaporator and Economizer section (min. 6 mm thick.)

    will be supplied including required expansion joint.

    The complete flue gas ducting from Eco outlet, up to stack will be fabricated

    with min. 5 mm thick Carbon steel plates and suitably stiffened. Flue ducting will be

    of rectangular cross section, with suitable stiffeners. This duct will be laid out as

    shown in the GA drawing enclosed in Volume II (Mechanical Drawing).

    All required metallic / non-metallic type expansion joints and dampers as

    required per design, will be provided for the gas ducting. Required steel supports

    for this flue ducting are provided.

    The supporting steel materials and manufacture will be as that of main boiler

    steel work.

    Notes

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.43

    o. Hot Flue Gas Inlet Duct to WHRB

    A small length of Hot flue gas duct is provided at inlet to the SH section and the

    same will be fabricated with 5 mm thickness, carbon steel, suitably stiffened. This duct

    will be lined with suitable 2 layer high temperature refractory materials on the inside,

    applied over SS anchors; This duct will be supported over the boiler structural steel work.

    The flue gases from stacks is to be tapped off at 0.0 m elevation through the

    T off connection from the existing hot flue gas duct to stack. At the inlet of hot flue gas

    duct to boiler 100 % leak proof guillotine damper is provided.

    p. Slide Bearings Supports

    The Water wall enclosure and Down Comer pipes are supported at the bottom side

    on structural base at approx. 7.0 m elevation. To ensure free thermal expansion at

    each of the support locations special slide bearings were provided and mounted over

    the supporting structural frame.

    q. Ash Hoppers

    In order to collect fly ash from the hot flue gas from the coke oven a hopper is provided

    both below radiant section and economiser section which is made out of 6 mm thick Carbon

    steel plates. The outlet of the hoppers will be of approx. size 400 x 400; and will

    be kept closed by slide gates. The slide gates shall be opened to remove fly ash as and

    when required.

    r. Buckstays

    The hot inlet flue gas passes water wall enclosure section will be provided with a system

    of Buckstays and Tie bars, at various levels, to withstand any unusual variations in gas

    pressure in the boiler. Buck stays are designed for a internal gas pressure of 400 mmWC

    and are allowing free thermal Expansion of pressure parts.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.44

    Key Drawing:

    Arrangement of Buck stay : ICAA0200-0-F-04-28-0035

    s. Refractory Materials, Insulation & Outer Casing

    1. Refractory

    The hot flue gas inlet duct will be lined with suitable high temperature refractory

    material: SS anchors will be welded to the inlet duct for holding the refractory in its

    position.

    The ash hoppers of (the Water wall section) below Radiant section will be also

    refractory lined over SS anchors welded to the hoppers, as required.

    All access doors, peep hole doors provided on the radiant chamber will be refractory

    lined to with stand the high temperature.

    The refractory materials which are to be used in the hot flue inlet gas duct are as given

    below:

    SL.NO. Location Refractory Material

    1.

    a) Hot Flue Gas inlet duct from existing coke

    oven exhaust to radiant chamber.

    Hot face will be ACC:WHYT HEAT

    C = 200 mm (thick)

    And

    Cold face will be calcium silicate

    block = 50 mm (thick)

    b) Anchors

    Stainless steel SS 310

    Stud / Anchors will be welded to

    carbon steel duct.

    2. Insulation

    Boiler is provided with lightly bonded insulating mattress and cladding over all hot surfaces

    to prevent heat burn to personnel as well as to reduce the radiation losses while boiler is in

    operation.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.45

    Similarly all integral and process pipes are provided with required thickness of insulation

    and cladding material.

    t. Induced Draft Fan

    The boiler is having 2 x 85 % MCR capacity Induced Draft Fans to suck hot flue gas from the

    coke oven exhaust duct which passes through all pressure parts located in the downstream

    of inlet guillotine damper located at inlet hot flue gas duct. ID fan also discharges the low

    temperature flue gas to stack after heat is recovered by various section of WHR boiler. The

    ID fans were designed in such a way that at MCR flow the suction pressure will be

    maintained at -33mmWC at the inlet to the WHR Boiler.

    1. No. of Fans / WHRB - 2 (Two) both in operation.

    2. Type - Backward curved, Over hung; Plate

    bladed design, Variable speed operation

    3. Drive - Motor driven

    4. Control of Fan - Multi Loure dampers in suction ducts, of

    the fan; with pneumatic actuator / VFD

    Sl.No Particulars/Fans Units 100% MCR Load (2 Fan Operation)

    1. Flow m/Sec 14.99

    2. Temperature C 160

    3. Suction Pressure mmWC -420

    u. Guillotine Dampers

    Two Number water cooled guillotine dampers one at the hot flue gas inlet and another at ID

    discharge duct to stack were provided for each WHR boiler to ensure 100 % sealing.

    1. Number provided/WHRB = 2 No. (one in each hot flue gas

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.46

    duct,

    connected from tap of point to boiler

    and the other in the cold flue gas

    duct to process stack )

    2. Type =

    Water cooled disc - Refractory lined

    on casing and on Disc, at the gas

    flow section

    3. Duty / Service =

    Gas side isolation of Coke oven flue

    gases at WHR Boiler inlet - 100%

    open/close

    4. Arrangement / damper blade opening

    / location =

    Vertical shaft with horizontal Gas

    Flow - Damper supported at the

    bottom (on structural base)

    5. Gas flow to damper - Normal

    (100%MCR) =

    63000 Nm3/hr at 950C Hot

    Flue Gas duct to boiler inlet

    6. Design temperature = 1000C

    7. Operating pressure = -33 mmWC

    8. Dust loading in COFG mg/Nm3 = 150 (max)

    9. Sealing efficiency (on cross sectional

    area basis) = 98%

    10. Method of operation = Hydraulic

    v. Dosing Systems

    HP Dosing Units

    Boiler is provided with a High pressure chemical dosing unit which consists of SS tank for

    mixing motorized agitator and 2X100% capacity Hydrazine Dosing pumps simplex,

    reciprocating plunger type positive displacement pump along with necessary valves and

    fittings.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.47

    w. De-aerator, Feed Storage Tank (Common for Two WHRB Unit)

    1. De-aerator

    The boiler is provided with common De-aerator along with Feed Storage Tank to scavenge

    oxygen from the DM water before feed water is fed into the boiler. The Deaerator is spray

    cum tray type with SS trays located in the Deaerator tower which is mounted on the feed

    storage tank. The Deaerator is complete with all the connected piping (Auxiliary steam,

    Condensate & DM Water) Valves and Fittings as required. Spray nozzles and Trays of

    Deaerator are of Stainless steel. The De-aerator has been sized considering boiler operation

    2 X 26.4 TPH.

    2. Feed Storage Tank

    Number of Unit - One

    Type / Orientation - Horizontal, Cylindrical

    Supports arrangement & Location - 2 No. Saddle supports;

    Size approx.: ID x Shell Length - 2400 mm x 5000 mm

    Capacity of water holding (as - 12 min

    specified) (between NWL and Trip)

    Operating pressure and temperature - 2.7 kg/cm (g); 140 C

    The Feed Water Storage Tank is complete, with all the connected piping, valves and fittings.

    x. Boiler Feed Pumps & Drives

    The High pressure feed pump located below the Deaerator supplies water to WHR Boiler.

    Feed pumps are motor driven and provided with minimum circulation mechanical valve

    (ARC) to ensure that minimum quantity of water is always circulated through the feed pump

    to prevent over heating of pump internals and thereby failure of internal components.

    No. of Feed pumps provided

    (2 operating + 2 stand-by) - 4 x 100% Both Motor driven

    Type - Multistage, Centrifugal, Horizontal axis,

    Constant speed, direct motor driven

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.48

    Parameters of pump (Each)

    4 X 100 %

    MCR TB

    1. Volume of Flow TPH 27.19 29.9

    2. Feed Water Temperature C 140 140

    3. Density of Water kg/m 926.13 926.13

    4. Delivery Pressure kg/cm (g) 91.5 95.97

    5. Feed Pump Suction Pressure kg/cm (g) 2.7 2.7

    6. Speed RPM 2980

    7. Power required at Pump Shaft KW 160

    y. Soot Blower

    Boiler is provided with soot blower to remove soot deposition on the pressure parts during

    running of the WHRB unit. Two long retractable soot blowers one each to clean primary and

    secondary super heaters. Similarly 6 Nos. of rotary type soot blowers were located at the

    economizer zone. Necessary PRV station for reducing the steam pressure to require steam

    blowing pressure through soot blower along with Program logic controller to take care of

    sequential logic control for soot blower operation is provided. Soot blowing shall be always

    carried out only above 60% of MCR load of the boiler to avoid metal temperature increase

    during steam blowing operation from the soot blower.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.49

    CHAPTER 4

    DESIGN DATA FOR BOILER PERFORMANCE

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.50

    CHAPTER 4

    DESIGN DATA FOR BOILER PERFORMANCE

    CONTENTS

    SL.NO. DESCRIPTION PAGE NO

    4.1 Design Data 51

    4.2 Waste Gas 51

    4.2.1 Predicted Hot Flue Gas (approx. values) 51

    4.2.2 Ambient Conditions 51

    4.2.3 Properties of COFG 52

    4.3 Predicted Performance Details 52

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.51

    CHAPTER 4

    DESIGN DATA FOR BOILER PERFORMANCE

    4.1 Design Data

    SL.No Description Remarks

    1. Number and type of

    boiler

    2off Single drum, Natural circulation, Balanced

    draft Waste Heat Recovery Steam Generator Unit.

    SL.No Desciption Units Values

    2. Final Super Heater Flow at 100 % BMCR per

    WHRB Unit TPH 26.4

    3. Steam Pressure at Main Steam Stop Valve

    Outlet (MSSV) kg/cm (g) 71 kg/cm (g)

    4. Boiler Steam Drum Design Pressure kg/cm (g) 85

    5. Main Steam Temperature at Super Heater

    Outlet C 490+5

    6. Main Steam Temperature Control Range. % BMCR 50 to 100

    7. Feed Water Temperature at Economizer I/L C 140

    8. Maximum Flue Gas Temperature leaving

    economizer to ID Fan and to stack C 160

    9. Quantity of COFG & temperature required

    at inlet of each WHRB

    Nm/hr &

    C

    63,000

    950

    10. Dust Concentration in Hot Flue Gas mg/Nm 150

    4.2 Waste gas

    4.2.1 The predicted approximate hot flue gas requirement are given below

    Sl.No Description Unit Values

    1. 100% MCR Load Condition Nm/hr 63,000

    2. 50% MCR Load Condition Nm/hr 31,500

    4.2.2 Ambient Conditions (For Performance Design of Boiler) are given below

    Sl.No Description Unit Values

    1. Temperature C 50

    2. Relative Humidity % 90

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.52

    The Proposed Waste gas analysis for the boiler are given below

    4.2.3 Properties of COFG

    Sl.No Constituents Symbols Unit Values

    1. Nitrogen N2 % Vol. 68.65

    2. Sulphur Di-Oxide SO2 % Vol. 00.05

    3. Carbon Di-Oxide CO2 % Vol. 04.10

    4. Oxygen O2 % Vol. 13.70

    5. Water Vapour H2O % Vol. 13.50

    6. Total - % Vol. 100.00

    7. COFG Flow rate per WHRB Unit - Nm/hr 63,000

    8. Inlet temperature of COFG per WHRB - C 950

    4.3 Predicted Performance Details as per Technical Specification

    The following is the Predicted Performance of the each WHRB unit and Auxiliaries, based on

    the Basic Design Parameters and Data, detailed in the specification as follows:

    Boiler Parameters Units

    100% MCR-

    Maxi. Flue Gas

    Flow

    Proportionate steam generation TPH 26.4

    SH steam pressure at outlet of MS stop valve kg/cm2(g) 71

    SH steam temperature at outlet of MS stop valve C 4905C

    Feed water temperature entering Economizer C 140

    Temp of Hot inlet flue gases at entry to each WHB C 950

    Hot inlet flue gases at entry to each WHB Nm/hr 63000

    Gas Temperature

    COFG entering Inlet screen tubes of Radiant section C 950

    Entering Primary Super heater C 834

    Entering Secondary Super heater C 716

    Entering Evaporator section C 644

    Entering Economizer section C 349

    Entering ID Fan Entering Stack C 160

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.53

    Water & Steam Temperature

    Feed inlet of Economizer C 140

    Feed outlet of Economizer C 277

    Drum operating (Saturated - Entering Pry. SH section) C 289

    Steam leaving Pry. SH C 415

    Steam entering Sec. SH C 402

    Steam leaving Sec. SH C 490 5

    Spray water quantity kg/hr 363

    Flue Gas Pressure

    Radiant Chamber mmWC -59

    Super Heater O/L mmWC -76

    Evaporator O/L mmWC -112

    Economizer O/L mmWC -312

    ID Fan I/L mmWC -337

    ID Fan O/L mmWC +25

    These are all the above values for information purpose only.

    Notes

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.54

    CHAPTER 5

    BOILER PLANT SAFETY AND PROTECTION

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.55

    CHAPTER - 5

    BOILER PLANT SAFETY AND PROTECTION

    CONTENTS

    SL.NO DESCRIPTION PAGE NO

    a. General Requirements 56

    b. Safety Precautions 56

    c. Radiant Chamber Inspection 56

    d. Maintenance Work 56

    e. Steam & Water Source Isolation 57

    f. Residual Pressure (or) Vacuum 57

    g. Safety Measures for Internal Inspection and during Start-Up

    57

    h. Residual Heat 57

    i. Hot dust and/or Noxious / inflammable gas 58

    j. Flue Gas Leakage and Firefighting equipment 58

    k. Burning / welding within Boiler interior 58

    l. Deviation from Recommended Procedures 58

    m. Maintenance Equipment 59

    n. Work Permits 59

    o. Dampness 59

    p. Steam & Water at Elevated Pressure & Temperature 59

    q. Mechanical Equipments 60

    r. Flue Gases 60

    s. HP and LP dosing Chemicals 60

    t. Noise 60

    u. Protective Materials and Clothing 60

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.56

    CHAPTER 5

    BOILER PLANT SAFETY

    a. General Requirements

    In the interest of safety of all personnel who are operating the unit, the compliance with the

    instructions on the boiler plant safety should be effected by or under the supervision of

    responsible, competent and properly trained personnel familiar with the operating and

    maintenance procedures relevant to this type of plant.

    It should be clearly under stood that for plant of this complexity; it is not practicable to

    anticipate all the possible circumstances, which may arise during the operating life of the

    plant.

    b. Safety Precautions

    To ensure that the boiler and its auxiliaries operated efficiently and reliably as possible, the

    periodic maintenance of all Equipments and auxiliaries should be done. Procedures

    recommended by the various manufacturers for preventive and corrective maintenance

    should be implemented to obtain the maximum plant utilization and safety.

    c. Radiant Chamber Inspection

    When opening the radiant chamber inspection door to view hot flue gas, dark glasses should

    be worn and care should be taken to stand to one side to guard against a chamber

    disturbance. Never open a radiant chamber inspection door to view the flue gas without the

    prior knowledge of the boiler operator.

    d. Maintenance work

    Before commencing any maintenance work on the boiler unit or auxiliaries particularly

    those items connected to an electrical power supply the Equipment must be completely

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.57

    isolated, both mechanically and electrically, in accordance with current Safety Regulations

    laid down for the plant.

    e. Steam and Water Source Isolation

    Prior to opening up a boiler for inspection, cleaning, or maintenance, the boiler must be

    cool, and extreme care must be taken to prevent steam or hot water entering the unit from

    systems that may be under pressure from other sources. This includes steam and feed

    piping, drains and blow down lines, which can be connected to systems in use, and it is

    imperative therefore to avoid serious accidents that the boiler is completely isolated

    from any steam and water sources by locked shut off valves and blanking if required.

    f. Residual Pressure or Vacuum

    In necessity demands, opening up any pressure part on a hot boiler, a check must be made

    to ensure that there is no residual pressure, or a vacuum, by means of the releasing the air

    by opening the vent provided on the pressure parts, pressure gauge readings are not to be

    taken for granted under these circumstances.

    g. Safety Measures For Internal Inspection & During Start Up

    When inspecting the boiler unit internally, protective clothing goggles and gloves, footwear,

    and helmet must be worn before entering any enclosed internal space. A hand held

    inspection lamp of the twenty four volt (24 volt) type or a torch should be taken inside for

    checking. Before going for internal inspection of radiant chamber or other enclosed space,

    there must be another person posted outside at the inspection / access door monitoring the

    movements of the operator inside so that, if necessary, external assistance may be sought

    for due to any emergency situation.

    h. Residual Heat

    Before entering the radiant chamber or gas passages to carry out an inspection,

    maintenance, or water washing, the amount of residual heat must be carefully considered.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.58

    i. Hot Dust and / or Noxious / Inflammable gas

    Accumulations of dust / flue gas contaminant particles can retain high temperatures inside

    for extended periods and on contact with water can generate sufficient steam to injure any

    unprotected person in the immediate vicinity.

    The effect is accentuated in a confined space. Precautions must therefore be taken to avoid

    scalding of operators and adequate ventilation must be ensured to guard against the

    possible presence of noxious or inflammable gas.

    j. Flue Gas Leakage and Fire Fighting Equipment

    Firing galleries should be kept clean. Any flue gas leaks should be immediately arrested. All

    precautions should be taken to avoid boiler front fires and the firefighting equipment must

    be maintained in good order as prescribed by the manufacturer. The Fire Extinguisher

    should be appropriate for Class of Fire.

    k. Burning / Welding within Boiler Interior

    Any burning or welding work to be carried out within the boiler interior, the space must be

    adequately ventilated, and suitable firefighting equipment must be available, together with

    a bucket of water for cooling any dismantled part. Staging complying with the Factory Acts

    must also be used in those places inaccessible to the radiant chamber assess equipment.

    Skill Worker has to attend the work, to avoid damage of pressure parts.

    l. Deviation from Recommended Procedure

    The maintenance instructions must be followed as closely as possible, although

    circumstances can arise which may necessitate a deviation from the recommended

    procedure. In any instance where doubt can exist that will involve risk to personnel, the

    decision must rest with a responsible engineer who must examine every aspect of the

    particular case before giving a decision whether or not to proceed with the work in question.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.59

    m. Maintenance Equipment

    Generally however, full use must be made of the maintenance equipment provided access

    doors, walkways, and ladders, runway beams hoists, and cable reeling drums rather than

    improvising for the sake of expediency.

    n. Work Permits

    Where doubt exists concerning the safety of mechanical or electrical plant, then the station

    Safety Regulations are to be followed, complete isolation of all mechanical and electrical

    equipment in accordance with the Permit to work system - must be obtained by

    the responsible Engineer before the work is commenced. Guards on rotating machinery, belt

    drives etc., must be refitted before plant is re- commissioned after maintenance.

    o. Dampness

    Certain equipment, although located within the plant building, can be subject to dampness

    or condensation. Cubicles housing electrical or other control equipment, if located in a cold

    draft position, are particularly vulnerable to this condition. Therefore, precautions must be

    taken against dampness occurring. Cubicle doors must be closed and locked to prevent

    them being inadvertently left open. Electric heaters can be installed or, if in short supply,

    carbon filament lamps may be used.

    p. Steam and Water at Elevated Pressures & Temperatures

    Saturated steam is generated in the boilers. This is visible. However, extreme care should

    be taken when trying to locate it. Sampling of steam and water must be carried out with

    care, Gloves and face masks must be worn.

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.60

    q. Mechanical Equipment

    Moving machinery can always be dangerous, should be treated with respect. It should be

    ensured that guards are in place on all operating machinery.

    r. Flue Gases

    Flue gases have very low oxygen content and will cause asphyxiation if breathed even for a

    short time. Usually flue gas will at a temperature of above 100 C, so it is dangerous for the

    persons who working near to the flue gas leakages or passing from the radiant chamber

    zone.

    s. H P & L P Dosing Chemicals

    Water treatment chemicals used in H. P. and L. P. dosing are both irritants and toxic if

    ingested. Gloves and eye protection must be worn when handling these chemicals.

    t. Noise

    Noise can permanently damage the hearing ability. Hence, care should be taken for ear

    protection at all times when in the plant.

    u. Protective Materials and Clothing

    Table below indicates the name of the protective materials and clothing that may be used

    for protection of the operating and maintenance personnel.

    SL. No. Description Protection

    1 Safety Boots Foot Protection

    2 Overalls Body Protection

    3 Hard Hat Head Protection

    4 Goggles or Face mask Face and Eye Protection

    5 Dust Mask Lung Protection

    6 Safety Gloves (leather and PVC) Hand Protection

    7 Ear Plugs Hearing Protection

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.61

    CHAPTER 6

    FEED AND BOILER WATER

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.62

    CHAPTER - 6

    FEED AND BOILER WATER

    CONTENTS

    SL.NO. DESCRIPTION PAGE

    NO.

    6.1 WATER CONDITIONING 63

    6.2 DE AERATION 71

    6.3 ALKALINITY CAUSTIC SODA, AMMONIA, AMINES 76

    6.4 SUPPLEMENTARY WATER TREATMENT 80

    6.5 SIGNIFICANT SALT SOLUTIONS PROPERTIES 90

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A & IB004A

    GUMMIDIPOONDI, TAMILNADU 2 x 26.4 TPH/71 kg/cm/4905 C WHR BOILER.

    BOILER OPERATION & MAINTENANCE MANUAL Page.No.63

    6.1 - WATER CONDITIONING

  • ENMAS GB POWER SYSTEMS PROJECTS LIMITED Chennai 600 018 INDIA

    OPERATION AND MAINTENANCE MANUAL

    CUSTOMER: BHATIA COKE & ENERGY LTD PROJECT CODE : IB002A