Beer Game Results 1
Beer Game Results
1
-150
-100
-50
0
50
100
150
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
retailer
retailer
Muddy Charles Inventory
2
-150
-100
-50
0
50
100
150
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
distributor
distributor
Muddy Charles Inventory
3
-150
-100
-50
0
50
100
150
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
wholesaler
wholesaler
Muddy Charles Inventory
4
-150
-100
-50
0
50
100
150
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
factory
factory
Muddy Charles Inventory
5
-150
-100
-50
0
50
100
150
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
retailer
wholesaler
distributor
factory
Muddy Charles Inventory --- total cost = $3601
6
0
5
10
15
20
25
30
35
40
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Muddy Charles retailer orders
retailer
7
0
5
10
15
20
25
30
35
40
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
wholesaler
wholesaler
Muddy Charles wholesaler orders
8
0
5
10
15
20
25
30
35
40
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
distributor
distributor
Muddy Charles distributor orders
9
Muddy Charles factory orders
0
5
10
15
20
25
30
35
40
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
factory
factory
10
Muddy Charles orders
0
5
10
15
20
25
30
35
40
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
retailer
wholesaler
distributor
factory
11
-75
-60
-45
-30
-15
0
15
30
45
60
75
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Ali baba retailer inventory
retailer
12
-75
-60
-45
-30
-15
0
15
30
45
60
75
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Ali baba wholesaler inventory
wholesaler
13
-75
-60
-45
-30
-15
0
15
30
45
60
75
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Ali baba distributor inventory
distributor
14
-75
-60
-45
-30
-15
0
15
30
45
60
75
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Ali baba factory inventory
factory
15
Ali Baba Amazon Inventory -- total cost = $2219
-75
-60
-45
-30
-15
0
15
30
45
60
75
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
retailer
wholesaler
distributor
factory
16
0
5
10
15
20
25
30
35
40
45
50
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Ali baba retailer orders
retailer
17
0
5
10
15
20
25
30
35
40
45
50
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Ali baba wholesaler orders
wholesaler
18
0
5
10
15
20
25
30
35
40
45
50
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Ali baba distributor orders
distributor
19
0
5
10
15
20
25
30
35
40
45
50
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Ali baba factory orders
factory
20
0
5
10
15
20
25
30
35
40
45
50
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
retailer
wholesaler
distributor
factory
Ali Baba Amazon Orders
21
22
23
24
25
26
27
Project Ideas
28
Strategies
• Work in teams – we might enlist an LGO student(s)
• You propose your own project – Research
– Start-up
– Other connections
• We propose project – Not necessarily clear cut
– You are still the “entrepreneur”
– Take it as far as you want
29
Air Liquide
• Explore feasibility of delivering Oxygen to hospitals in developing countries
– Choice of technology
– Design of supply chain; make-buy choices
– Business model, including financing
– Cameroon and Ghana are possible target markets
30
ARTI- Tanzania
• How to improve the operation of new production line for Ag-waste charcoal briquettes
– Grinder
– Mixer
– Extruder
• Likely to require consideration of upstream and downstream operations
• D-Lab scale-up partner
31
WeCycler
• As the business continues to expand, a project could:
– Look at how to achieve more efficient routing of vehicles
– Examine how to improve customer retention
• D-Lab scale-up partner
32
Ghonsla
• Examine transportation of product (insulation panels) from manufacturing facility to sales region
• Focus on cost and time
• Likely to require consideration of upstream and downstream operations, which are linked by the transportation
• D-Lab scale-up partner
33
Organic Waste processing with BSF
• Mapping of supply chain
• Make – Buy choices
• Cost modeling
34
MIT OpenCourseWarehttp://ocw.mit.edu
15.772J / EC.733J D-Lab: Supply ChainsFall 2014