1 International Expert’s Meeting on Protection against Extreme Earthquakes and Tsunamis in the Light of the Accident at the Fukushima Daiichi Nuclear Power Plant (IEM3) Paper PR28 THE SEISMIC SAFETY EVALUATION PROGRAMME OF THE ATUCHA I (CNA-I) NPP-ARGENTINA AT THE LIGHT OF LESSONS LEARNED FROM FUKUSHIMA DAIICHI NPP ACCIDENT Technical Session 2: Seismic and Tsunami Safety A.R. Godoy and J.J. Johnson (James J. Johnson & Associates) Alicia Couto and Carolina Romano (Nucleoeléctrica Argentina S.A. (NA-SA)) IAEA IEM September 2012
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
1
International Expert’s Meeting on Protection against Extreme Earthquakes and Tsunamis in the Light of the Accident at the Fukushima Daiichi Nuclear Power Plant
(IEM3)
Paper PR28 THE SEISMIC SAFETY EVALUATION PROGRAMME
OF THE ATUCHA I (CNA-I) NPP-ARGENTINA AT THE LIGHT OF LESSONS LEARNED FROM
A.R. Godoy and J.J. Johnson (James J. Johnson & Associates)
Alicia Couto and Carolina Romano (Nucleoeléctrica Argentina S.A. (NA-SA))
IAEA IEM September 2012
2
Background: Atucha I
•Atucha I – PHWR (Heavy water reactor) - KWU (Germany), 357 MWe capacity; CNA I started in June 1968 and commercial operation in June 1974; 72% availability over 37 years; –Internal event PRA models; –Operator - Nucleoeléctrica Argentina S.A. (NA-SA) –No seismic design.
•Seismic Safety Evaluation Program –Needed to comply with safety evaluations against external events as a result of the Fukushima accident in Japan –In compliance with new updated international safety standards and worldwide recognized engineering practice for such assessments.
2
3
Main Objectives of the Seismic Safety Evaluation Programme for Atucha I NPP
• Evaluate and quantify the seismic capacity of CNA-I – Ability to cope with a specified earthquake ground motion
at the site – CNA-I “as-is” conditions – Estimate the seismic safety margin defined by High
Confidence of Low Probability of Failure (HCLPF) • Take into account the lessons learned from the experience of
all recent strong earthquakes in Japan and their effects on nuclear power plants.
3
4
Specific Objectives of the Seismic Safety Evaluation Programme for Atucha I NPP
•Demonstrate the seismic safety margin conditional on Review Level Earthquake ground motion (RLE) •Confirm no cliff edge effects exist •Identify weak links and vulnerabilities in physical and operational aspects due to seismic events. •Provide input for risk informed decision making. •Identify and prioritize possible upgrades.
4
5
Comprehensive Five-Phase Programme
• Phase 1: Scoping Study and Preliminary Plant Walkdown ‒ Completed – November 2011
• Phase 2: Development of the Safe Shutdown Equipment List (SSEL), System Walkdown, Training Class
− SSEL for walkdown – April 2012, Final – August 2012 • Phase 3: Seismic Response and Structure Capacity
• Many “easy fixes” were installed during outage!!
10
Phase 2: Development and Review of Safe Shutdown Equipment List (SSEL), System Walkdown, and Training Course
• Success paths • Two for safe shutdown - one mitigates small LOCA; • Containment and containment isolation; • Spent fuel cooling. • Refuelling Machine and tilting bottle (continuous operation) • Fire extinction system
• NA-SA-CNA I personnel (systems, operations and engineering staff) developed success paths (training and peer reviewed by JJJ Team)
• Safe Shutdown Equipment List (SSEL) – 627 items – In accordance with methods applied to address Fukushima issues,
e.g., European stress tests • Status – 99% complete (some refinements on-going)
10
11
Phase 2: Development and Review of Safe Shutdown Equipment List (SSEL), System Walkdown, and Training Course
• Training Course: – Familiarity and training NA-SA staff in Seismic Evaluation
Methods (SMA and GIP) approaches for Plant Walkdown (Phase 4) and maintaining seismic capacity in the future (configuration control)
– Participants • Atucha I and II, Embalse, NA-SA Headquarters, CAREM (about 25
• Presentation and report submitted to ARN on 14 March 2012 for review - approval May 2012
15
Atucha NPP Site: Recommended and Accepted DBE/RLE
0.0000
0.1000
0.2000
0.3000
0.4000
0.5000
0.10 1.00 10.00 100.00
RLE-DBE…
Frequency (Hz)
Spec
tral
Acc
eler
atio
n (g
)
ATUCHA NPP SITE - PROPOSED ENVELOPE RLE-DBE
16
6. Seismic Capability Walkdown
• Perform in-plant seismic capacity evaluation of SSEL items ‒Find and evaluate all items on the SSEL (currently 647) ‒Apply screening rules from EPRI NP-6041 Rev. 1 (note, meeting
screening rules may allow capacity verification to be for PGA=0.3g conditional on anchorage evaluation and seismic systems interaction issues)
‒Performed during outage ‒Evaluate seismic systems interaction issues ‒Document SSEL item data ‒ Status
‒ Detailed plant walkdown – 4 weeks, completed 4 May 2012 ‒ Documentation near completion ‒ HCLPF calculations on-going
17
6. Seismic Capability Walkdown
• Document SSEL item data using iPad system • Seismic Evaluation Work Sheets (SEWS) • SEWS – 27 categories of equipment/components/structural
elements • Drawings, photos, videos, field notes, etc. • iPAD data processing and storage • Uploaded to server daily
• Advantages • Consistent electronic record of walkdown results – long term
storage, printed copies, revisions for future activities • Summary Excel table yielding data for decision-making (operator,
regulator, reviewers) • Disadvantages
• Dressed out use difficult • Need additional photos from those of iPad – lighting, resolution
18
6. Seismic Capability Walkdown
• Status: • SSEL = 627 total items
• Completed data = 627 items • Acceptable = 76%, including Rule-of-the-Box • Unknown (meaning more information needed or analysis to be
performed) = 12% • Not acceptable = 12% (examples on following slides)
19
6. Seismic Capability Walkdown: Observations
• Excellent cooperation and support from staff (systems, engineering, operations) – very knowledgeable
• Atucha I is very clean and appears well maintained • Mechanical equipment generally met the seismic
experience-based screening criteria • Electrical equipment needs evaluation and possible
• Piping not seismically supported – generally, judged OK based on earthquake experience data and EPRI screening guidelines
• Piping not supported at valve locations - generally, judged OK based on earthquake experience data
• HVAC ducts weak or missing supports – to be evaluated on a sample basis
• Raised floors well restrained horizontally – lack of vertical uplift restraints to be evaluated
• Connection of grout pads to floors to be evaluated, e.g., vertical tanks
• Secondary heat sink building capacity evaluation needed • Unreinforced masonry walls in vicinity of SSEL equipment to
be evaluated
21
6. Seismic Capability Walkdown: EDGs potential flooding and falling hazards
Feedwater tank floor above – day tank no anchorage - block wall adjacent
22
6. Seismic Capability Walkdown: To be evaluated
23
6. Seismic Capability Walkdown: To be evaluated
24
6. Seismic Capability Walkdown: To be evaluated
25
iPad Data Collection
25
26
6. Seismic Capability Walkdown: Summary from iPad Data Collection
Equipment ID No.
Equipment Description
EPRI Equip Class SEWS No. Remarks
Safety System
Success Path Building
Floor Elevation
(m)
Item Elevation
(m)
Room No.
Row/Col/ Cabinet
TB11S06 Pressure Reducing Valve GEN SEWS-25-251 Valve to reduce air pressure on quick-opening valv Reactor Building-S 0.50 2.00 1-307 TB21S06 Pressure Reducing Valve GEN SEWS-25-252 Identical to TB11S06 Reactor Building-S 0.50 1.00 1-307 TB31S06 Pressure Reducing Valve GEN SEWS-25-253 Identical to TB11S06 Reactor Building-S 0.50 1.50 1-307 HA51 Cabinet I&CP SEWS-05-002 Cabinet with Command Modules HA 1-SP01 Auxiliary Building 6.00 0.47 2-311 HA51HB53 Cabinet I&CP SEWS-05-003 Cabinet for Interlocking Logic Cards. Identical to H HB 1-SP01 Auxiliary Building 6.00 0.47 2-311 HB53RA01S04 Pressure safety valve (m AOV SEWS-13-001 Safety valve from Steam Generator 1 RA 1-SP01 Auxiliary Building 23.00 0.00 2-600 RA01S06 Motor Operated Valve MOV SEWS-14-004 Isolation Valve of the vent from Steam Generator 1 RA 1-SP01 Auxiliary Building 25.00 1.70 2-600 HB03RA02S06 Motor Operated Valve MOV SEWS-14-005 Isolation Valve of the vent from Steam Generator 2 RA 1-SP01 Auxiliary Building 25.00 1.70 2-600 HB03RA07S01 Motor Operated Valve MOV SEWS-14-006 Vent valve to atmosphere RA 1-SP01 Auxiliary Building 25.00 2.00 -600 RA07S02 Motor Operated Valve MOV SEWS-14-007 Vent valve to atmosphere RA 1-SP01 Auxiliary Building 25.00 2.00 2-600 IXION CABLE CCable DS SEWS-26-008 Cable for interconnection IX 1-SP01 CNAI - CNAII -2.00?? -2.00?? Tunnel Cabinet IXION Cabinet IXION I&CP SEWS-05-010 Cabinet for Electric Interconnection between CNAI- IX 1-SP01 CNAII 0.00 1.50 CNAII BAZ16 Switchgears MCC, LVS, MVSSEWS-01-011 Switchgear 6,6kV IX 1-SP01 CNAII 0.00 0.00 CNAII XKA -20 Diesel Generator EG SEWS-09-009 CNAII Diesel Generator IX 1-SP01 CNAII 0.00 0.00 CNAII
Equipment ID No.
BELOW ~40'?
(B)
CAP SPEC (B)
DEM SPEC (B)
CAP>DEM? (B)
EVAL OK? (C)
AUX EVAL OK? (D)
RELAY OK? ( E )
ANCHOR OK? (F)
INTER OK? (G) EQUIP OK?
Lead for same / similar?
Master for ROB? ROB with Same as Similar to
TB11S06 Yes 0.8g P SGA RLE Peak Yes Yes N/A N/A Yes Yes Yes L No TB21S06 Yes 0.8g P SGA RLE Peak Yes Yes N/A N/A Yes Yes Yes No No TB11S06 TB31S06 Yes 0.8g P SGA RLE Peak Yes Yes N/A N/A Yes Yes Yes No No TB11S06 HA51 Yes 0.8g P SGA RLE Peak Yes Yes N/A Unknown No No No L No HB53 Yes 0.8g P SGA RLE Peak Yes Yes N/A Unknown No No No No No HA51 RA01S04 No 1.2g P SGA ISRS Yes Yes N/A N/A N/A Yes Yes No No RA01S06 No 1.2g P SGA ISRS Yes Yes N/A N/A N/A Yes Yes L No RA02S06 No 1.2g P SGA ISRS Yes Yes N/A N/A N/A Yes Yes No No RA01S06 RA07S01 No 1.2g P SGA ISRS Yes Yes N/A N/A N/A Yes Yes L No RA07S02 No 1.2g P SGA ISRS Yes Yes N/A N/A N/A Yes Yes No No RA07S01 IXION CABLE C N/A N/A N/A N/A N/A N/A Yes No No Cabinet IXION N/A No No BAZ16 BAZ16 Yes 0.8g P SGA RLE Peak Yes Yes N/A Unknown Yes Yes Unknown No M XKA -20 Yes 0.8g P SGA RLE Peak Yes Yes Unknown Yes Yes Yes Unknown No No
27
6. Seismic Capability Walkdown: Observations
• 75% of SSEL items meet EPRI Screening Tables for PGA = 0.3g
• Anchorage capacity and seismic systems interaction issues – determine HCLPF
28
Phase 5: Detailed Analysis and Evaluation
•High Confidence of Low Probability of Failure (HCLPF) calculations – high importance items not treated in Phase 4 due to resource limitations – refueling machine, NSSS components, etc. •Structure/building capacity evaluation •NSSS fracture mechanics evaluation for double-ended guillotine break as needed (CNA-II like analyses)
28
29
Future Activities
• Phase 5 • Configuration Management
– Essential to maintain seismic capacity of CNA-I – Procedures to be developed
• Designs include engineering • Sign offs on new installations and replacement items –
engineering, systems, operations • Can use SEWS methodology as aid and documentation
• Containment and containment systems evaluated to seismic hazard probability of exceedance of 10-5
29
30
Future Activities
• Geotechnical to be evaluated (steep slope – pump house and plant grade, etc.)
• Seismically- induced fire and flooding evaluation – Collaboration with CNA-I fire and flooding experts – In-building seismically induced flood (sprinkler system,
tank failures, etc.) - completed during walkdown – Yard sources of seismically induced flood – External to plant boundary flood potential – Consequences to turbine building DG flooding, etc.
30
31
Future Activities
• Seismic instrumentation – None installed. In the process of procurement. – Shutdown and re-start decisions difficult if earthquake ground
motion is felt • Operations
– Need procedures to address occurrence of ground motion at Atucha site. IAEA SR 66 is being used.