ASSEMBLY LINE BALANCING KOUSHIK S V-11P624 MANIVANNAN V -11P629 SIBI VISHVAK-11P643 VIGNESH D-11P648
Dec 08, 2015
ASSEMBLY LINE BALANCING
KOUSHIK S V-11P624
MANIVANNAN V -11P629
SIBI VISHVAK-11P643
VIGNESH D-11P648
ASSEMBLY LINE BALANCING
ASSEMBLY LINE BALANCING
The assignment of tasks to work stations along an assembly line in such a way as to achieve the same or close to same working times at each work station.
The goal is to create a smooth,continuous flow of products through the assembly line for maximum productivity and minimum idle time at each work station.
ASSEMBLY LINE BALANCING
Assigning each task to a workstation within an assembly line in order to meet the required production rate and to achieve a minimum amount of idle time.
Line balancing is the procedure in which tasks along the assembly line are assigned to work station so each has approximately same amount of work.
In production line,workstations and work centers are arranged in a sequence of task to be done along a straight or curved line.
CAFETERIA LINEStation 1
Trays, Plates, Utensils
Station 2Appetizers
Station 3Entrees
Station 4Desserts
Station 5Cashier
ASSEMBLY LINE BALANCINGGOALS
Number of workstations needed.Type of task to be assigned to each
workstation.To know the minimum number of
workers,tools and machines that can be used to provide the required amount of capacity.
ASSEMBLY LINE BALANCINGOBJECTIVES
Assigning a task to each workstation in such a way that there is only a little idle time.
Increased efficiency. Increased productivityLow cost manufacturing.Potential increase in costs.
TERMINOLOGIES RELATED TO PRODUCTION LINE ANALYSIS
TASKS:All the elements of the work. TASK PRECEDENCE:The sequence in which
tasks are performed. TASK TIMES: Time required by a well-trained
worker or unattended machine to perform a task.This is usually expressed inn minutes.
CYCLE TIME: The time expressed in minutes between two simultaneous products coming off the end of a production line.
CONTINUED… PRODUCTIVE TIME PER HOUR: The average
number of minutes a workstation in an hour. WORKSTATION:A physical area where a worker
performs a particular set of task in a production line.
WORKCENTRE: A small group of identical workstations,where each workstation performs the same set of task.
NUMBER OF WORKSTATIONS WORKING:The amount of workdone at a work centre expressed in number of work stations.
CONTINUED… MINIMUM NUMBER OF WORKSTATIONS:The
least number of workstations that provides the required production.
ACTUAL NUMBER OF WORKSTATIONS:This is the total number of workstations required on the entire production line.It is calculated as the next higher integer of the number of workstation working.
UTILISATION:The percentage of time a production line is working.
LINE BALANCING PROCEDURE1. Determination of tasks that must be performed
to complete one unit of a product.
2. Determining the order or sequence of performing the whole set of tasks.
3. Drawing precedence diagram. In this flowchart circles represents task and joining arrows represents precedence.
4. Estimation of task time.
5. Calculation of cycle time.
6. Determination of minimum number of workstation required.
7. Use of heuristics to assign a task.
COMPUTERISED LINE BALANCING
Line balancing by hand becomes unwieldy as the problems grow in size.
There are software packages that will balance
large lines quickly. IBM's COMSOAL (Computer
Method for Sequencing Operations for Assembly
Lines) and GE's ASYBL (Assembly Line
Configuration Program) can assign hundreds of
work elements to workstations on an assembly
line.
CONTINUED…
They use various heuristics, to balance the line at an acceptable level of efficiency.
The POM for Windows software lets the user select from five different heuristics: ranked positional weight, longest operation time, shortest operation time, most number of following tasks, and least number of following tasks. These heuristics specify the order in which work elements are considered for allocation to workstations.
UNBALANCED LINE
High work load in some stages (Overburden) Maximizes wastes (over-processing, inventory, waiting, rework,
transportation, motion) High variation Restrict one piece flow Maximizes Idle time Poor efficiency
Work Station 1
Work Station 4
Work Station 3
Work Station 2
!? Zzz Zzz
Overproduction!
40 sec 15 sec 15 sec
10 sec
BALANCED LINE
Work Station 1
Work Station 4
Work Station 3
Work Station 2
25 sec 25 sec 20 sec 15 sec
Promotes one piece flowAvoids excessive work load in some stages (overburden)Minimizes wastes (over-processing, inventory, waiting, rework…)Reduces variationIncreased EfficiencyMinimizes Idle time
INDIVIDUAL TASK TIMES These are set well in advance by industrial
engineers and time & motion specialists.
They are called standard task times and consist of normal time to perform a particular task and extra time allowances for fatigue, personal needs, and unavoidable, but recurring delays.
ASSEMBLY LINE BALANCING CONCEPTS
The Assembly Line
Station1
Station2
Station3
TO WAREHOUS
E
If the cycle time were 10 minutes,each station would hand its WIP to the next at the end of 10 minutes.
PERFECTLY BALANCED ASSEMBLY LINE
NOT PERFECTLY BALANCED ASSEMBLY LINE
PROBLEM STATEMENT A firm wants to
produce 160 units for each 8-hour day production on an assembly line.
Nine separate tasks are needed to complete the product.
Assume no break time.
Develop the assembly line!!
TASK PREDECESSOR STANDARD TIME
A none 60
B A 80
C none 30
D C 40
E B,D 40
F none 50
G F 100
H D,G 70
I E,H 30
Σ = 500 seconds
THE PRECEDENCE DIAGRAM
A network showing the sequential relationships among all tasks to be performed on the assembly line, together with their respective standard times.
An optional, useful tool for avoiding precedence relationship violations when assigning tasks to work stations, without benefit of the computer.
THE PRECEDENCE DIAGRAM
THE CYCLE TIME FORMULA
Total Available Daily Production Time
Daily Production Quota
28,800 Seconds
160 Units( FROM THE PROBLEM )
= 180 Seconds
MINIMUM NUMBER OF WORK STATIONS
Total Task Time Per Unit of Product
The Cycle Time
500 Seconds
180 Seconds= 2.77 ≈ 3.00
FRACTIONS ARE ALWAYS ROUNDED UP( i.e. “2.01” becomes “3.00” )
THE LINE BALANCING SPREADSHEET
Cycle Time
180seconds
180seconds
180seconds
540seconds
Station1
Station2
Station3
ProductiveTime
Per Cycle
Idle Time
Per Cycle
LINE BALANCING HEURISTICS
There are two types of heuristics used for line balancing:
Incremental utilisation heuristic Longest task time heuristic
INCREMENTAL UTILISATION HEURISTIC
Tasks are added to each workstation in order of task precedence one at a time until utilization is 100 percent or is observed to fall.
Used when one or more task time is equal to or greater than the cycle time.
LONGEST TASK TIME HEURISTIC
Add tasks to a workstation one at a time in the order of task precedence.
If a choice must be made between two or more tasks, the one with the longest task time is added.
This has the effect of assigning as quickly as possible the tasks that are the most difficult to fit into a station.
Tasks with shorter times are then saved for fine-tuning the solution.
CONDITIONS1. It can be used only when each and every
task time is less than or equal to the cycle time.
2. There can be no duplicate work stations.
If each and every task time is less than or equal to the cycle time, and if the primary focus of the analysis of production lines is minimizing the number of workstations and the amount of tools and equipment required, then this heuristic would be appropriate.
STEPS IN LONGEST TASK TIME HEURISTIC
1. Lei i = I. where i is the number of the workstation being formed.
2. Make a list of all the tasks that are to be assigned to a workstation. Have to satisfy the following conditions
a. It cannot have been previously assigned to this or any previous workstation.
b. Its immediate predecessors must have been assigned to this or a previous workstation.
c. The sum of its task time and all other times of tasks are already assigned to work station must be less than or equal to the cycle time . If no such tasks are found. Go to step 4.
3. Assign the from the list with the longest task time to the workstation. Go back to the step 2.
4. Close the assignment of tasks to Workstation i. This can occur in two ways. If there are no tasks on the list for the work station but there are still tasks to be assigned, set i=i+1 and go back to step 2. If there are no more tasks, the procedure is completed.
PRECEDENCE DIAGRAM LEGEND
X
Y
Z
NON-CANDIDATE TASKS
( SHOWN IN BLUE )
A
D
AN ASSIGNED TASK( SHOWN WITH “X”)
X
CANDIDATES FOR THE NEXTTASK ASSIGNMENT( SHOWN IN RED )
B
C DX
DX
THE PRECEDENCE DIAGRAM
A60
C30
F50
B80
D40
G100
E40
H70
I30
1st TASK ASSIGNMENTCANDIDATES FOR
STATION 1
THE LINE BALANCING SPREADSHEET
Cycle Time
180seconds
180seconds
180seconds
540seconds
Station1
Station2
Station3
ProductiveTime
Per Cycle
Idle Time
Per Cycle
TASK A( 60 sec )
THE PRECEDENCE DIAGRAM
A60
C30
F50
B80
D40
G100
E40
H70
I30
2nd TASK ASSIGNMENTCANDIDATES FOR
STATION 1X
THE LINE BALANCING SPREADSHEET
Cycle Time
180seconds
180seconds
180seconds
540seconds
Station1
Station2
Station3
ProductiveTime
Per Cycle
Idle Time
Per Cycle
TASK A( 60 sec ) TASK B( 80 sec )
THE PRECEDENCE DIAGRAM
A60
C30
F50
B80
D40
G100
E40
H70
I30
3rd TASK ASSIGNMENTCANDIDATES FOR
STATION 1X X
THE LINE BALANCING SPREADSHEET
Cycle Time
180seconds
180seconds
180seconds
540seconds
Station1
Station2
Station3
ProductiveTime
Per Cycle
Idle Time
Per Cycle
TASK A ( 60 sec )TASK B ( 80 sec )TASK C ( 30 sec )
10seconds
THE PRECEDENCE DIAGRAM
A60
C30
F50
B80
D40
G100
E40
H70
I30
1st TASK ASSIGNMENTCANDIDATES FOR
STATION 2X X
X
THE LINE BALANCING SPREADSHEET
Cycle Time
180seconds
180seconds
180seconds
540seconds
Station1
Station2
Station3
ProductiveTime
Per Cycle
Idle Time
Per Cycle
TASK A ( 60 sec )TASK B ( 80 sec )TASK C ( 30 sec )
10seconds
TASK F( 50 sec )
THE PRECEDENCE DIAGRAM
A60
C30
F50
B80
D40
G100
E40
H70
I30
2nd TASK ASSIGNMENTCANDIDATES FOR
STATION 2X X
X
X
THE LINE BALANCING SPREADSHEET
Cycle Time
180seconds
180seconds
180seconds
540seconds
Station1
Station2
Station3
ProductiveTime
Per Cycle
Idle Time
Per Cycle
TASK A ( 60 sec )TASK B ( 80 sec )TASK C ( 30 sec )
10seconds
TASK F ( 50 sec) TASK G (100 sec)
30seconds
THE PRECEDENCE DIAGRAM
A60
C30
F50
B80
D40
G100
E40
H70
I30
1st TASK ASSIGNMENTCANDIDATES FOR
STATION 3X X
X
X X
THE LINE BALANCING SPREADSHEET
Cycle Time180
seconds180
seconds180
seconds540
seconds
Station1
Station2
Station3
ProductiveTime
Per Cycle
Idle Time
Per Cycle
TASK A ( 60 sec )TASK B ( 80 sec )TASK C ( 30 sec )
10seconds
TASK F (50 sec) TASK G (100 sec)
30seconds
TASK D( 40 sec )
THE PRECEDENCE DIAGRAM
A60
C30
F50
B80
D40
G100
E40
H70
I30
2nd TASK ASSIGNMENTCANDIDATES FOR
STATION 3X X
X
X X
X
THE LINE BALANCING SPREADSHEET
Cycle Time180
seconds180
seconds180
seconds540
seconds
Station1
Station2
Station3
ProductiveTime
Per Cycle
Idle Time
Per Cycle
TASK A ( 60 sec )TASK B ( 80 sec )TASK C ( 30 sec )
10seconds
TASK F (50 sec) TASK G (100 sec)
30seconds
TASK D (40 sec)TASK H (70 sec)
THE PRECEDENCE DIAGRAM
A60
C30
F50
B80
D40
G100
E40
H70
I30
3rd TASK ASSIGNMENTCANDIDATES FOR
STATION 3X X
X
X X
X
X
THE LINE BALANCING SPREADSHEET
Cycle Time180
seconds180
seconds180
seconds540seconds
Station1
Station2
Station3
ProductiveTime
Per Cycle
Idle Time
Per Cycle
TASK A ( 60 sec )TASK B ( 80 sec )TASK C ( 30 sec )
10seconds
TASK F (50 sec) TASK G (100 sec)
30seconds
TASK D (40 sec)TASK H (70 sec)TASK E (40 sec)
THE PRECEDENCE DIAGRAM
A60
C30
F50
B80
D40
G100
E40
H70
I30
4th TASK ASSIGNMENTCANDIDATES FOR
STATION 3X X
X
X X
X
X
X
THE LINE BALANCING SPREADSHEET
Cycle Time180
seconds180
seconds180
seconds540
seconds
Station1
Station2
Station3
ProductiveTime
Per Cycle
Idle Time
Per Cycle
TASK A ( 60 sec )TASK B ( 80 sec )TASK C ( 30 sec )
10seconds
TASK F (50 sec) TASK G (100 sec)
30seconds
TASK D (40 sec)TASK H (70 sec)TASK E (40 sec)TASK I (30 sec)
0seconds
500seconds
40seconds
TOTAL
EVALUATING THE BALANCED LINE
Efficiency =
total productive time on the assemblyline per cycle
total available time on the assemblyline per cycle
500 seconds
540 seconds= 92.6%
EFFICIENCY => 90% IS CONSIDERED ACCEPTABLE
EVALUATING THE BALANCED LINE
Balance Delay Factor ( % IDLE TIME )
line idle time per cycle
line total time per cycle=
40 seconds
540 seconds= = 7.4%
A BALANCE DELAY FACTOR=< 10% IS CONSIDERED TO
BE ACCEPTABLE
CONCLUSION Effectiveness is achieved when the assembly line
meets the daily production quota. As the efficiency is more than 90% the assembly
line is expected to meet the daily production quota.
ASSEMBLY LINE BALANCING
APPLICATIONS
CARWASH LINE
CAFETERIA LINE
APPLIANCE MANUFACTURING LINE
AUTOMOBILE MANUFACTURING LINE
FABRICATION LINE
DISSASSEMBLY LINE