Engineering & Construction Division State Atomic Energy Corporation ROSATOM ASE Group ASE Multi-D® platform Pavel Bruk Deputy CIO
Engineering & Construction Division State Atomic Energy Corporation ROSATOM
ASE Group
ASE Multi-D® platform
Pavel BrukDeputy CIO
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Design and Construction of NPPs, Research Reactors, SNF and
RAW facilities
ASE Group – ROSATOM EPC Division
2
Uranium Mining
Uranium Enrichment
Fuel Fabrication
Electricity Generation
EquipmentManufacturing
NPPOperations and
Upgrade
Nuclear Power Complex Applied and BasicScience
Nuclear and Radiation Safety
ASE Group
Nuclear-Powered Ice-breaker Fleet
ROSATOM
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
100%
19 countriescurrent business presence
22 500 employees
including
5500 design engineers
30+ NPP blocks
>30% of all nuclear projects worldwide
100% of CIS NPP construction market
ASE market share worldwide
ASE Key Figures
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
From Individual Services to Complex Capital Projects
4
ЕРС, ЕРСM
Design
Engineering Assistance
Licensing (docs & support)
РМС
Personnel training
Financing
PMC Services for Lifecycle Management
of Complex Engineering Projects
NPP Design,Engineering, Construction,
Modernization
TPP Design,Engineering, Construction,
ModernizationWaste & Spent Fuel
Management, Decommissioning
SMR, Research Reactors &
Scientific Centers
Complex Infrastructure
Projects
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Multi-D®: Lifecycle management for capital projects
Design Construction
E
P
C
МMulti-D engineering
Supply chain management
3D design
Field engineering
Procurement
Work packages
Operations
!
!
!
!
Project management
Cost management
management
construction
procurement
engineering
Maintenance simulation
Object status monitoring
TCO
Asset management
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
UIM
Unified Information Model
Complete Configured 3D Model
GIS Data
Multi-D® IMSInformation Management System
Equipment
Construction Data
Costs, risks, requirements, schedules
Documentation
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Multi-D IMS functional architecture
7
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Multi-D Configuration Management
8
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Multi-D® Requirements Management
•ASE developed methodology•15 000+ requirements•Dramatically improves performance of decision making processes
Stakeholders requirements
Technical specifications
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Multi-D® IMS: TDMS
! !
§ All approvals and notifications from the Customer are provided in electronic form
§ Detailed design documents are issued directly from 3D model
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Multi-D® e-Catalogue
Multi-D Catalogue:ü engineering and
design 3D modelsü system of standards
for the equipment information on equipment class and coding
ü industry-based guidelines
ü technical documents
Customer
Engineering Company
Equipment manufacturers
Nuclear Plant Operator
§ Costs§ Delivery times§ Manufacturers
§ Specifications§ Drawings and 3D-models§ Certificates, licenses§ Financial documents
§ Operations manual§ Drawings§ Instructions§ Specs, etc.
§ Specifications§ Certificates§ Licenses
Evaluation of the info
Initial Specs
Appropriate equivalent & similar items
Info on the design requirements
Operation historical records
Product documentation
Info on the product
e-Catalogue functional applications
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Multi-D® e-Catalogue: Russian NPP industry standard
! Equipment and materials classifier more than 2000 types of products of all NPP systems
! Database of suppliers and manufacturers more than 630 companies
! Design and technical documentation more than 20 000 files
! 3D models more than 20 000 unique 3D models
! Price for more than 56 000 cards of the equipment
! Suppliers quality data for more than 2500 units of equipment
Based on DS ENOVIA
http://www.eoncom.niaep.ru
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Multi-D® SCM: Supplier management applications§ Barcoding
§ Speed-up incoming inspection procedures
§ As-built documentation quality improvements
§ Online information on equipment delivery status (directly at the construction site)
§ Direct link with accounting systems
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Multi-D® Unified Project Scheduling
Procurement scheduleDesign and construction schedule
Issue identified
Details and impact
•OOTB solution•Real-time data•Automatic schedule collisions detection•Automatic reporting•Imports data from any project management software
•Primavera•MS Project•etc.
•Web-access
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Multi-D® Construction Management
Complete real-time construction simulation
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Multi-D® Field Engineering
16
Производственный экран
Координаты**работ* Смета* Организация*
План.*числен,*чел.*
Облицовка*пола.*Помещение*А021/1,2*
R3.00098.3.0.28*изм.2*
РОССЭМ* 2*
Облицовка*пола.*Помещение*А027*R3.00098.3.0.28*изм.2*
РОССЭМ* 4*
Облицовка*пола.*Помещение*А024*R3.00098.3.0.28*изм.2*
РОССЭМ* 2*
Обрещетка*пола.*Помещение*А025*R3.00098.3.0.28*изм.2*
РОССЭМ* 4*
Облицовка*пола.*Помещение*А032*R3.00098.3.0.28*изм.2*
РОССЭМ* 1*
М/к*под*опоры.*Помещение*А016* ** СЕЗАМ* 6*
Устройство*чистовых*полов.*Пом.*АЭ014*
R3.01801.3.0.28**
СМУP1* 2*
Устройство*чистовых*полов.*Пом.*АЭ053*
R3.01801.3.0.28**
СМУP1* 2*
Устройство*чистовых*полов.*Пом.*АЭ054/1*
R3.01801.3.0.28**
СМУP1* 2*
Устройство*чистовых*полов.*Пом.*АЭ060*
R3.01801.3.0.28**
СМУP1* 2*
Монтаж*м/к.*Пом.*АЭ004/1,2*R3.01249.3
.0.28*ЮГЭЛЕКТР
О*8*
М/к*под*прокладку*коробов.*Пом.АЭ052*
R3.02589.3.0.36*изм.2*
ЭСКМ* 5*
Шлифовка*пола.*Помещение*А031/2,*А017/1,3*
R3.00097.3.0.28*изм.1*
РСК* 6*
М/к*под*прокладку*коробов.*Пом.*А006*
R3.02589.3.0.36*изм.2*
ЭСКМ* 5*
** ** ИТОГ:* 57*
Объект:*Реакторное*отделение*на#отм.##(4,200;#(3600*
Visual modeling studio. Information booths. Weekly-daily work packages with 3D.
Production screens. HR control via built-in RFID helmets.
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Multi-D® Cost and Risk Management
Equipment spendings report
• Construction costs calculations during all lifecycle phases• Cost limits assignment per spending type• Costing forecast generator• Deviations analyzer• Advanced risks assessment
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to ASE group and its affiliated companies. ASE disclaims all responsibility for any and all mistakes, quality and completeness of the information.
Multi-D® OperationsDecommissioning
(10-20 years)Operations(40-60 years)
Engineering, Construction, Commissioning (10 years)
Multi-DOperation
Multi-DEPC
Multi-DD&D
E
P
C
§“As-build” in real time §Multi-D® for upgrade, maintenance and repairs
DnD Data
ü Equipment databaseü TDMSü 3D Data Managementü Requirements Mgmtü Configuration Mgmt
Virtual NPP Blockü simulation models and
math calculations
Virtual NPP BlockØ Complex calculationsØ Tests verification
3D-UIMØ MROØ ModernizationØ Visualization
NPP Unified Information Model Support during all lifecycle