The controlled version of this document is registered. All other versions are uncontrolled Document Number: PLN-00055 Version Date: 24/04/2013 Page: 1 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S Asbestos Management Plan
The controlled version of this document is registered. All other versions are uncontrolled
Document Number: PLN-00055 Version Date: 24/04/2013 Page: 1 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
Asbestos
Management Plan
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled
Document Number: PLN-00055 Version Date: 24/04/2013 Page: 2 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
Table of Contents
1 Introduction .............................................................................................................................. 4
2 Scope ...................................................................................................................................... 4
3 Definitions ................................................................................................................................ 5
4 Responsibilities ........................................................................................................................ 7
4.1 Board of Directors ............................................................................................................. 7
4.2 Executive Management .................................................................................................... 7
4.3 Workplace Health and Safety (WHS) Manager ................................................................. 7
4.4 Managers .......................................................................................................................... 8
4.5 Workers ............................................................................................................................ 8
4.6 Contractors & Suppliers .................................................................................................... 8
4.7 Visitors .............................................................................................................................. 9
5 Process .................................................................................................................................... 9
5.1 Risk Overview ................................................................................................................... 9
5.2 Asbestos Surveys ........................................................................................................... 10
5.3 Asbestos Registers ......................................................................................................... 11
5.3.1 Developing Registers ............................................................................................... 12
5.3.2 Register Changes and Maintenance ........................................................................ 12
5.3.3 Asbestos Register Reviews ..................................................................................... 12
5.4 Communication & Consultation ....................................................................................... 12
6 Management Options & Controls for ACM ............................................................................. 13
6.1 Asbestos Management Options ...................................................................................... 13
6.2 Management of In-situ Asbestos ..................................................................................... 16
6.2.1 Re-survey and Inspections ...................................................................................... 16
6.2.2 Labelling .................................................................................................................. 16
6.3 Removal of ACM ............................................................................................................. 17
6.3.1 Asbestos Removal Plans ......................................................................................... 18
6.3.2 Work Permits ........................................................................................................... 19
6.3.3 Clearance Inspections ............................................................................................. 19
6.4 Maintenance or Service work involving ACM .................................................................. 19
6.5 Work Method Statements (WMS) .................................................................................... 19
6.6 Damaged ACM ............................................................................................................... 20
6.6.1 Health Surveillance .................................................................................................. 20
6.6.2 Notification ............................................................................................................... 20
7 Training .................................................................................................................................. 21
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled
Document Number: PLN-00055 Version Date: 24/04/2013 Page: 3 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
7.1 Induction ......................................................................................................................... 21
7.2 Work with Asbestos ........................................................................................................ 21
7.3 Contractors ..................................................................................................................... 22
8 Reviewing and Updating the Management plan ..................................................................... 22
8.1 Reviews .......................................................................................................................... 22
8.2 Updates & Changes ........................................................................................................ 22
9 Records ................................................................................................................................. 22
10 References ......................................................................................................................... 22
10.1 Legislation ...................................................................................................................... 22
10.2 Procedures ..................................................................................................................... 23
10.3 Forms & Registers .......................................................................................................... 23
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled
Document Number: PLN-00055 Version Date: 24/04/2013 Page: 4 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
1 INTRODUCTION
Seqwater has a legal obligation and responsibility to protect the health and safety of its staff,
contractors and visitors from the possible exposure to asbestos. This Asbestos Management Plan
(AMP) identifies the objectives, scope, management, practices and procedures required to ensure
that Seqwater legal obligations are carried out effectively.
It provides staff, contractors and visitors to Seqwater facilities and structures with an outline of
responsibilities and management procedures for dealing with asbestos products and materials.
The AMP and its associated plans, instructions, registers, forms and procedures integrate and
operate under the Seqwater WHSMS. Certain terminology and abbreviations are defined under
section 3.
Management of asbestos in Seqwater is structured around 4 main levels:
1. AMP – This document provides the high level commitment and functions required to
manage asbestos by providing directions for sites to follow and utilise for managing
Asbestos Containing Materials (ACM).
2. Asbestos Registers – A Seqwater Asbestos Database provides the complete data for
all facilities from which site specific registers can be provided. Each site must have its
own register which contains asbestos information such as location, condition, risk levels
and controls.
3. Procedures – The procedures relate to the processes required for working on or near
asbestos.
4. Forms – The Forms provide a process to gather evidence or information regarding the
management of asbestos at Seqwater sites.
2 SCOPE
This Seqwater Asbestos Management Plan is to be applied to all relevant Seqwater owned
structures and leased premises where the lease deems Seqwater responsible for compliance with
the Code of Practice How to Manage and Control Asbestos in the Workplace (2011).
Asbestos was widely used as construction and insulation material in buildings until the late 1980s
when bans on its manufacture and use were put in place. However, the use of asbestos was only
completely prohibited on 31 December 2003. As the bans were not absolute prior to 2003 and
building materials may have been stockpiled, stored, or recycled and used, it is possible that
asbestos may be present in buildings that were constructed up to 31 December 2003 and possibly
later.
Seqwater has undertaken asbestos surveys (using competent persons) of all facilities including
residential dwellings to determine the presence of asbestos containing materials (ACM), and the
information has been compiled in a database. The Asbestos Database is kept electronically on the
network by the WHS Department and contains information about all identified Seqwater structures
containing asbestos. From this database, an individual site’s asbestos register can be downloaded
and printed.
This document identifies and defines how Seqwater will manage the ACM at its facilities and
addresses Seqwater’s legal obligation under the Work Health and Safety Act, as it relates
specifically to the presence of asbestos on Seqwater owned or leased property. The AMP is a
working document designed to effectively manage and minimise asbestos-related health risks to
personnel working on or visiting Seqwater sites as well as any other person that may be affected
as a result of work undertaken by Seqwater.
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled
Document Number: PLN-00055 Version Date: 24/04/2013 Page: 5 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
3 DEFINITIONS
Word/Acronym Definition
ACM Asbestos Containing Materials
AM Asset Management/Manager
AMP Asbestos Management Plan
Asbestos Means the fibrous form of mineral silicates belonging to the serpentine and
amphibole groups of rock-forming minerals, including actinolite, Amosite
(brown asbestos), Anthophyllite, chrysotile (white asbestos), crocidolite
(blue asbestos), tremolite, or any mixture containing one or more of the
mineral silicates belonging to the serpentine and amphibole groups.
Asbestos Removalist Means a competent person who performs asbestos removal work.
Note: An asbestos removal licence is required in all State and Territory
jurisdictions for the removal of friable ACM. Some States and Territories
also require a licence for removal of specified quantities of AMC,
regardless of whether they are friable, and relevant OHS authorities should
be consulted prior to any removal work.
Asbestos Removal
Control Plan
Means a document which identifies the control measures which will be
implemented to ensure workers and other persons are not at risk when
asbestos removal work is being conducted.
AS/NZS Australian Standard/ New Zealand Standard
Bonded Asbestos Means ACM containing a bonding compound reinforced with asbestos
fibres, e.g. Asbestos cement pipes and flat or corrugated asbestos cement
sheets consist of sand and cement reinforced with asbestos fibres. For
removal of bonded asbestos the person must have a B Class licence1 or
work under the supervision of a business that has an A Class licence and
has a supervisor on site that is deemed a competent person for asbestos
removal work. All persons will need to follow a WMS for removal.
Clearance Inspection Means an inspection, carried out by a competent person, to verify that an
asbestos work area is safe to be returned to normal use after work
involving the disturbance of ACM has taken place. A clearance inspection
must include a visual inspection, and may also include clearance
monitoring and/or settled dust sampling.
Note: A clearance inspection should only be carried out when the asbestos
work area is dry.
Clearance Monitoring Means air monitoring using static or positional samples to measure the
level of airborne asbestos fibres in an area following work on ACM. An
area is ‘cleared’ when the level of airborne asbestos fibres is measured as
being below 0.01 fibres/ml.
Competent Person
for Friable asbestos
removal
A person who is competent under Information Paper AR2 (Requirements
for a competent person to supervise work to remove friable asbestos
containing material) issued by Department of Employment & Industrial
Relations.
Competent Person Means a person possessing adequate qualifications, such as suitable
1 Seqwater requirement
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled
Document Number: PLN-00055 Version Date: 24/04/2013 Page: 6 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
Word/Acronym Definition
for Clearance
Inspections
training and sufficient knowledge, experience and skill, for the safe
performance of the specific work.
Control Monitoring
Means air monitoring, using static or positional to measure the level of
airborne asbestos fibres in an area during work on ACM. Control
monitoring is designed to assist in assessing the effectiveness of control
measures. Its results are not representative of actual occupational
exposures, and should not be used for that purpose.
Note: Static of positional samples are taken at fixed locations which are
usually between one and two metres above floor level.
COP Code of Practice
Friable Asbestos Means asbestos-containing material which, when dry, is or may become
crumbled, pulverised or reduced to powder by hand pressure. The
removal of friable asbestos can only be done by a business that has an A
Class licence and has a supervisor on site that is deemed a competent
person for asbestos removal work. All persons will need to follow a WMS
for removal.
IMS Integrated Management System
In situ Means fixed or installed in its original position, not having been moved.
Inaccessible area Means areas which are difficult to access, such as wall cavities and the
interiors of plant and equipment.
OHSMS Occupational Health & Safety Management System
NOHSC National Occupational Health & Safety Commission (former now known as
Worksafe Australia)
P.C. Principal Contractor
PPE Personal Protective Equipment
Person with control Means, in relation to premises, a person who has control of premises used
as a workplace. The person with control may be
a) The owner of the premises
b) A person who has, under any control or lease, an obligation to maintain
or repair the premises
c) A person who is occupying the premises
d) A person who is able to make decisions about work undertaken at the
premises; or
e) An employer at the premises
RA Risk Assessment
Site Includes the associated buildings, workplaces, facilities, plant etc within a
business address or property e.g. Wivenhoe Dam or 240 Margaret St.
Structure Includes but not limited to:
a) a building, construction, wall, mast, tower, pylon, structural cable or
telecommunications structure; or
b) underground works (including shafts and tunnels),pipe, pipeline, river
works, earthworks or earth retaining construction or other construction
designed to preserve or alter a natural feature; or
c) a road or highway, footpath or driveway, railway line or siding, tramway
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled
Document Number: PLN-00055 Version Date: 24/04/2013 Page: 7 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
Word/Acronym Definition
line, dock or harbour, water storage or supply system (including a
constructed lagoon), sewerage or drainage system, electricity or gas
generation facility, transmission or distribution facility,
d) gasholder, park or recreation ground (including, for example, a playing
field or swimming pool); or
e) production, storage or distribution facilities for heavy industries; or
f) fixed plant;
WHS Workplace Health & Safety
WHSC Workplace Health & Safety Committee
HSR Health & Safety Representative
WMS Work Method Statement
4 RESPONSIBILITIES
Seqwater has an overall responsibility to:
Develop and implement and maintain an asbestos management plan.
Assess all Seqwater premises for the potential presence of ACM.
Develop and maintain a register of the identified or suspected ACM, including details on
its location, accessibility, condition, risk assessments and control measures.
Assess the condition of ACM that are found and the associated risks.
Develop measures to remove or manage the ACM to minimise the risks and prevent
exposure to asbestos.
Ensure the control measures are implemented and are maintained as long as the ACM
remain in the workplace.
4.1 Board of Directors
Ensure that Seqwater complies with this AMP and any WHS Legislative or other
requirements relating to ACM.
Review a summary of any Asbestos survey results and any asbestos related incidents
annually.
Ensure sufficient resources are allocated to allow management to successfully implement
and manage compliance with legislation relating to ACM.
Ensure senior management instigates systems for the AMP to be implemented,
monitored, maintained and updated.
4.2 Executive Management
Assist the Board in ensuring that Seqwater complies with the AMP and any legislative or
other requirements relating to ACM.
Ensure the AMP requirements are implemented in Seqwater facilities.
Ensure facilities maintain a site-specific Asbestos Register.
Review any survey results and any asbestos related incidents prior to the annual Board
Review.
4.3 Workplace Health and Safety (WHS) Manager
To maintain this AMP, and inform Executive Management when changes occur.
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled
Document Number: PLN-00055 Version Date: 24/04/2013 Page: 8 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
Ensure that the Asbestos Database is maintained for all known sites where ACM has
been identified, and the information is kept up to date.
Ensure site-specific Asbestos Registers can be obtained for all facilities from the
Asbestos Database.
Ensure this AMP is available to all personnel including contractors, and undertake
reviews of the AMP as required.
Audit relevant sites for the management of asbestos and the AMP.
Report to Executive Management any survey results and any asbestos related incidents
annually.
Facilitate for competent persons to conduct regular (at least biennial) surveys of ACM
locations to report on the condition of ACM.
4.4 Managers
Ensure that Asbestos Registers are documented and maintained at each site, and
provide updated information as site conditions change.
Ensure Risks Assessments are conducted when working around/with areas containing
ACM.
Ensure that all required notices and labels are in place for ACM on site.
Ensure that personnel including contractors, suppliers, visitors and the public are
informed and/or made aware of ACM at specific sites.
Ensure all personnel who work on or near ACMs have been trained on the relevant
asbestos procedures.
Implement the controls identified from surveys where ACM are damaged.
Implement and maintain appropriate controls for the removal or control of exposure to
ACM fibres.
Notify the WHS Manager of any asbestos related incidents.
Monitor work areas containing ACM to check for any damage, deteriorations or defects.
Report any changes to ACM to the WHS Manager and appropriate Level 3 Manager.
Manage any works done to ACM by licensed contractors.
Report anyone potentially affected by ACM to the WHS Manager.
4.5 Workers
To comply with the requirements of this AMP.
To follow WMS and procedural requirements and wear the identified PPE when working
with ACM or as directed.
Not to put themselves or any other person at risk by the use of inappropriate behaviour
and Work Practices.
To notify the WHS Manager of any incidents associated with ACM that may expose
persons to the risk of exposure or damage to ACM.
Notify Manager and/or WHS personnel of any suspected ACM materials disposed on
Seqwater property.
4.6 Contractors & Suppliers
To not interfere with ACM without appropriate Seqwater approval, and compliance with
this AMP.
When working with ACM to have developed the required WMS and risk assessment
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled
Document Number: PLN-00055 Version Date: 24/04/2013 Page: 9 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
To work with/remove ACM individuals must hold a B Class Asbestos Licence for working
with bonded asbestos, and hold A Class Asbestos Licence for removal of friable asbestos
and have a “competent person” to directly supervise the removal works.
To notify the site Coordinator of any incidents associated with ACM that may expose
persons to the risk of exposure or damage to ACM.
4.7 Visitors
To follow instructions given by Seqwater staff in relation to ACM.
Wear any required PPE.
Report any asbestos related incidents to Seqwater.
5 PROCESS
The following section provides an overview of how Seqwater manages the ACM identified at its
facilities. The flowcharts provide a summary of the AMP and should be used as a checklist for
processes to manage ACM at Seqwater facilities.
5.1 Risk Overview
Asbestos within a building represents a health risk to people only when the asbestos fibres are
airborne, and are subsequently inhaled. The risk to health increases as the number of fibres
inhaled increases, that is, the health risk is related to the dose, or level of exposure.
Asbestos that is in a stable matrix, or effectively encapsulated or sealed, and remains in a sound
condition while left undisturbed, represents a negligible asbestos-related health risk.
It is necessary to differentiate between 'asbestos hazard' and 'asbestos risk'. 'Hazard' indicates
potential for harm, while 'risk' refers to the probability of that harm becoming real. For example, the
presence of asbestos in a building is a hazard, but while that asbestos remains in sound condition
and does not release fibres into the air, the risk is negligible.
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled
Document Number: PLN-00055 Version Date: 24/04/2013 Page: 10 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
Process Flowchart (PF) 1 – Updating ACM Information
5.2 Asbestos Surveys
As documented in the flowchart above, Seqwater has already undertaken detailed Asbestos
surveys of all facilities and identified those sites where ACM is present. This information about the
ACM has been extracted and incorporated in the sites’ Asbestos Registers.
A qualitative asbestos risk assessment is undertaken each time an asbestos survey of Seqwater
buildings or structures is conducted. The risk assessment must take account of information
including:
1. The condition of the ACM (e.g. whether they are friable or bonded and stable, and
whether they liable to damage or deterioration);
2. The likelihood of exposure (considering accessible, condition);
3. Whether the nature or location of any work to be carried out is likely to disturb the
ACM; and
4. Results from monitoring and/or samples taken.
Updating ACM Information
Licensed ContractorSupervisorACM Survey
ConsultantSite CoordinatorWHS Team
Asbestos
Register
available for site
Conduct ACM
survey
Engage
consultant to
conduct ACM
survey
Review existing
information and
conduct site
visits
Check signs/
labels, site
register, ACM
condition
Update
database with
information from
survey
Action plan
developed to
address
deficiencies
Work orders
created to
address
deficiencies
Update hardcopy
Asbestos Register
following changes
Updated
Asbestos
Registers
reviewed
Update database
and reissue
Asbestos Register
Conduct
scheduled
condition
inspections
Report any
changes to
conditions
Make repairs or
remove ACM
(refer PF2)
Engage licensed
contractor to rectify
issues (assistance
from WHS)
Review report
and provide
guidance
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled
Document Number: PLN-00055 Version Date: 24/04/2013 Page: 11 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
Each asbestos situation is allocated either an “Immediate”, 'High', 'Medium' or 'Low' risk rating.
These ratings are defined as follows:
Immediate: Asbestos containing material (ACM) is in poor or significantly deteriorated condition
and elevated levels of respirable airborne fibre are probable with minimal disturbance. The ACM is
readily accessible, prone to further disturbance and poses an immediate health risk to personnel.
Area should be isolated immediately and abatement (removal or repair) required as soon as
practicable.
High: Asbestos containing material shows moderate signs of deterioration and/or unsealed.
Elevated levels of respirable airborne fibre are possible, and further disturbance due to routine
building activity and/or maintenance is likely. Includes unsealed friable ACM in air conditioning
systems.
Medium: Asbestos containing material shows moderate signs of deterioration and/or unsealed.
Low levels of respirable asbestos fibre is possible, and further disturbance due to routine building
activity and/or maintenance is likely. Includes accessible damaged asbestos containing materials
and asbestos cement debris.
Low: Asbestos containing materials shows no or very minor signs of damage/deterioration.
Routine accessibility is unlikely to cause significant deterioration, or the material is adequately
sealed.
Should ACM of unknown composition, or materials suspected of containing asbestos, be
encountered on site, and are not documented in the existing asbestos register, such materials
should be treated as if they were asbestos until sample analysis confirms otherwise. In the event
that additional asbestos is identified, a risk assessment shall then be conducted by a suitably
qualified and competent person. For example, in the event that demolition or refurbishment works
are to be carried out in areas previously not inspected for the presence of asbestos, such as
inaccessible wall cavities or beneath floors, an inspection and risk assessment should be
performed by a suitably qualified person prior to the commencement of the planned
demolition/refurbishment works.
5.3 Asbestos Registers
A register is required for all sites where ACM exists, is suspected to exist. The register contains
information that is relevant to managing ACM and is essential to all people that work at the site
including contractors and others.
The register contains information on:
The date(s) on which the inspection/identification of ACM was made and details on the
competent person(s) who carried out the inspection/identification;
Details on the locations, types (i.e. friable or non-friable) and condition (i.e. damaged or
intact) of any ACM identified on the premises, including ACM in items of plant and
equipment, and the type of asbestos involved (i.e. blue, brown or white);
Details on any material presumed to contain asbestos;
Any inaccessible areas that are likely to contain ACM;
The results of any analysis to confirm a material is or is not an ACM;
The results of any air monitoring for airborne asbestos fibres and an assessment of these
results
Risk assessments of the ACM;
The controls recommended for the ACM; and
Any work carried out on the ACM including; the company or persons involved, the date
and scope of the work undertaken and details on clearance certificates.
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled
Document Number: PLN-00055 Version Date: 24/04/2013 Page: 12 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
Developing Registers 5.3.1
Registers will need to be developed or redeveloped where sites/structures do not have a register;
this may be through acquisition or merger of sites. Where a site does not have a register, an ACM
survey will be undertaken by the competent person (contractor) to determine what ACM is present
at the premises, and the Asbestos Database will be updated to incorporate the information from
the survey for the premises.
Register Changes and Maintenance 5.3.2
To keep the register maintained and up to date, changes that occur that may affect the register
need to be included such as reviews or removal of ACM from an area. The following are examples
of where changes need to be included and/or updated:
Dates of damage, removal and reviews.
Change in risk levels because of damage or removal.
Change in controls as management decision.
New samples taken and their outcomes.
New areas located where ACM exists or is suspected to exist.
New structures within a site that have been found or purchased.
These changes need to be included in the site hard copy of the register and sent to the WHS
Manager to update the Asbestos Database. The WHS Manager will then issue a new Asbestos
Register for that site.
Asbestos Register Reviews 5.3.3
All site-specific Asbestos Registers are to be reviewed regularly either via an asbestos survey
(biennial) or following a scheduled inspection by the Supervisor or WHS Advisor. Reviews will also
be required when any of the following occur:
There is evidence that the risk assessment is no longer valid;
There is evidence that any control measures are not effective;
A significant change is proposed for the workplace or for work practices or procedures
relevant to the risk assessment;
There is a change in the condition of the ACM; or
The ACM have changed (been removed, enclosed or sealed).
The review process will be undertaken through a visual inspection of identified ACM. The review
process must as a minimum assess:
1. Removals recorded/removed and not recorded e.g. removed after last register issued.
2. Risk levels – change of risk levels e.g. there is further deterioration or damage, old
switchboards opened (e.g. needs to change from low to medium risk)
3. Recommendations/Controls – e.g. may need to remove, dispose, remove on next
service, signs needed etc.).
5.4 Communication & Consultation
It is important that personnel are involved in the implementation and review of the AMP, associated
procedures and the sites’ Asbestos Registers. This AMP is to be reviewed by the Seqwater WHS
Team in consultation with the Regional WHS Committees and WHS Consultative Committee to
allow personnel to be involved in the AMP. The reviewed AMP will be tabled at the next available
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled
Document Number: PLN-00055 Version Date: 24/04/2013 Page: 13 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
meetings for distribution and comment. The following avenues of communication will also be made
available for information regarding ACM:
Corporate and Contractor WHS Inductions will provide an overview of the AMP and
requirements regarding ACM
Site specific induction will highlight the presence of an Asbestos Register, its location,
and any specific conditions regarding the ACM
When conditions of ACM change, personnel working on the site will be notified through
toolbox or pre-start meetings, and any specific conditions in force
When ACM is being removed, personnel will be notified of the timing and conditions to
minimise exposure to asbestos fibres
Where Seqwater property is to be leased the Asbestos Register must be made available
and be up to date with review requirements.
6 MANAGEMENT OPTIONS & CONTROLS FOR ACM
Where identification of asbestos in structures has been found, the preferred management option is
to be the recommendation of the competent person conducting the asbestos survey. The
appropriate controls are to be listed in the register and action taken to minimise the risk. The
hierarchy of control must be followed when managing ACM in structures:
1) Elimination/removal (most preferred);
2) Isolation/enclosure/sealing;
3) Engineering controls;
4) Safe Work Practices (administrative controls); and
5) Personal Protective Equipment (PPE) (least preferred).
6.1 Asbestos Management Options
There are four possible options to take in order to reduce the risk associated with the ACM:
1. Removal
2. Encapsulation or sealing
3. Enclosure
4. Deferment
The table below provides guidance around the rationale for each control method.
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled Document Number: PLN-00055 Version Date: 24/04/2013 Page: 14 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
Method of
Control
Description Appropriate When: Not Appropriate When: Advantages: Disadvantages:
Removal
Removal of asbestos must be
performed under certain controlled
conditions, depending on the type of
ACM to be removed. Where
demolition or refurbishment works are
to occur, and this work is likely to
impact on ACM, the ACM must be
removed under controlled conditions
prior to the commencement of any site
works.
Surface friable or
asbestos poorly bonded
to substrata.
Asbestos is severely
damaged or liable to
further damage or
deterioration.
Located in A/C duct.
Airborne asbestos
monitoring results
exceed recommended
exposure standard.
Other control techniques
inappropriate.
Located on complex or
inaccessible areas.
Removal extremely
difficult & other
techniques offer
satisfactory alternative.
Hazard removed
and no further
action required.
Cost-effective
long term option.
Increases immediate risk
of exposure especially to
removal workers.
Creates major disturbance
in building.
Highest cost, most
complex & time
consuming method.
Removal may increase fire
risk within building;
substitute required.
Possible contamination of
structure and increase in
airborne fibre levels in
adjacent occupied areas if
the removal program is not
strictly controlled.
Encapsulate or Seal
Coating of the outer surface of the
ACM by the application of some form
of sealant compound that usually
penetrates to the substrate and
hardens the material making it
impermeable to asbestos.
Helps protect the ACM from
mechanical damage, and is designed
to reduce the risk of exposure by
inhibiting the release of asbestos
fibres into the airborne environment,
and increase the length of
serviceability of the material.
Removal difficult or not
feasible.
Firm bond to substrata.
Damage unlikely.
Short life structure.
Readily visible for regular
assessment.
Asbestos deteriorating.
Application of sealant
may cause damage to
material.
Water damage likely.
Large areas of
damaged asbestos.
Quick and
economical for
repairs to
damaged areas.
May be adequate
technique to
control release of
asbestos dust.
Hazard remains.
Cost for large areas may
be near removal cost.
Eventual removal may be
more difficult and costly.
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled Document Number: PLN-00055 Version Date: 24/04/2013 Page: 15 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
Method of
Control
Description Appropriate When: Not Appropriate When: Advantages: Disadvantages:
Enclosure
Enclosure involves installing a barrier
between the ACM and adjacent areas
where it is effective in inhibiting further
mechanical damage to the asbestos.
The type of barrier installed may
include plywood or sheet metal
products, constructed as a boxing
around the asbestos.
Removal extremely
difficult.
Fibres can be completely
contained within
enclosure.
Most of surface already
inaccessible.
Disturbance to or entry
into enclosed area not
likely.
Enclosure itself liable
to damage.
Water damage likely.
Asbestos material
cannot be fully
enclosed.
May minimise
disturbance to
occupants.
Provides an
adequate method
of control for
some situations.
Hazard remains.
Maintenance of enclosure.
Need to remove enclosure
before removal of ACM.
Precautions for entry into
enclosure.
Defer The identification of ACM in a building
does not automatically necessitate its
immediate removal. Asbestos in a
stable condition and not prone to
mechanical damage can generally
remain in situ. The ACM will need to
be inspected on a regular basis (as
part of monthly Supervisor inspections
and at 12 months to update the
register) to ensure its integrity is
maintained.
No risk of exposure.
Asbestos inaccessible
and fully contained.
Asbestos stable and not
liable to damage.
Possibility of
deterioration or
damage.
Airborne asbestos
monitoring results
exceed recommended
exposure standard.
No initial cost.
Cost of removal
deferred.
Hazard remains.
Need for continuing
assessment and
management.
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled Document Number: PLN-00055 Version Date: 24/04/2013 Page: 16 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
6.2 Management of In-situ Asbestos
In-situ asbestos refers to Leave As-is, Encapsulation or Enclosure. The management of in situ
asbestos is important to ensure ACM are not damaged or deteriorated to such an extent that
Seqwater staff, external contractors, visitors or members of the public are unnecessarily exposed
to airborne asbestos fibres. The requirements of the contractor site induction and permit to work
system will aid in the management of in situ ACM. It is also the policy of Seqwater to incorporate
asbestos issues into building works contracts, designed to ensure any asbestos on, or in Seqwater
sites is dealt with in the appropriate manner.
Re-survey and Inspections 6.2.1
A re-survey of ACM remaining on site are to be conducted by a competent person. Such re-
surveys will comprise a visual assessment of the condition of the materials to determine whether
the material remains in a satisfactory condition, or if deterioration has occurred since the previous
survey. Such re-surveys will determine if any remedial action, such as encapsulation, isolation or
removal of the asbestos containing materials, is required. Re-surveys will be performed on a
regular basis for ACM. Seqwater will have ACM re-surveyed every two years.
More regular assessments of ACM will be undertaken by site Supervisors during scheduled
workplace inspections to determine if conditions have changed. This inspection will assess
whether:
Damage or deterioration has occurred since the previous inspection; and
Labels or signs have been removed.
Normally, re-sampling of materials would not be required during re-surveys. If, however, previously
unidentified or undocumented asbestos, or materials suspected of containing asbestos, are
encountered during the re-survey process, sampling and analysis will need to be performed. The
Asbestos Register will be updated and re-issued at the completion of the re-survey work.
Following a scheduled inspection, if the condition of the ACM has changed, the Supervisor or WHS
Advisor must amend the hardcopy of the register on-site and provide a copy to the WHS Manager
to update the Asbestos Database. A new copy of the register will be re-issued to site.
Labelling 6.2.2
The use of warning signs and labels is one of many recognised methods of asbestos risk control.
Such systems are designed to alert personnel to the presence of asbestos, thereby reducing the
risk of inadvertent damage to the ACM (which may liberate asbestos fibres to the airborne
environment) by the actions of personnel.
The Queensland Work Health and Safety Regulation 2011 makes it mandatory for those who
manage or control a workplace to indicate the presence and location of asbestos or ACM
identified, and indicate the presence and location of the asbestos or ACM by a label, such as those
provided below.
For Seqwater, these signs shall be placed at all of the main entrances to the work areas where
asbestos is present. Any such notice shall comply with Australian Standard 1319 (Safety signs for
the occupational environment). The notice shall be made of durable materials and be weatherproof
for outdoor applications. It would be prudent to include generic titles on the sign to allow for
changes in personnel responsible for administering the Asbestos Register. Specific asbestos
locations will be labelled for identification, where possible.
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled Document Number: PLN-00055 Version Date: 24/04/2013 Page: 17 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
6.3 Removal of ACM
Removal of ACM from Seqwater structures must only be completed using licensed contractors.
The contractor must be supplied with relevant information for the safe removal of the ACM,
including the Asbestos and Risk Registers for the site. When removal has been done the
Asbestos Register will be updated to reflect the changes. The process flowchart (PF2) provides an
overview of the work requirements which must be met.
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled Document Number: PLN-00055 Version Date: 24/04/2013 Page: 18 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
Process Flowchart (PF) 2 – Working with Asbestos
Asbestos Removal Plans 6.3.1
A site-specific Asbestos Removal Plan shall be developed by the contract company removing the
asbestos. The plan shall include the following:
i. Details of the ACM to be removed (e.g. the location(s), whether it is friable or non-friable,
type, condition and the quantity to be removed).
ii. Consultation details with Seqwater
iii. Assigned responsibilities for the removal
iv. Program of commencement and completion dates
Work with Asbestos
Clearance
ContractorWHS ManagerSite Coordinator/Property ManagerLicensed Contractor
Engage
Licensed
Contractor for
Asbestos work
Does work
require in-situ
treatment?
Asbestos
removal workNo
Class B Licence
and WMSYes
Complete work
encapsulation or
enclosure
Maintain records
and provide
updates
Class A Licence,
Asbestos
Removal Plan and
WMS
Obtain Access,
Permit to Work, 2nd
Tier permits, and
Asbestos Register
Undertakes
removal work in
accordance with
plan
Maintain records
and provide
updates
Provide records
of works and
disposal
certificates
Update
Asbestos
Database and
re-issue register
Undertake
Clearance
Inspection and
provide certificate
Friable
Asbestos?Yes
Class B Licence,
Asbestos
Removal Plan and
WMS
No
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled Document Number: PLN-00055 Version Date: 24/04/2013 Page: 19 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
v. Asbestos removal boundaries, including the type and extent of isolation or containment
required and the location of any signs and barriers.
vi. Control of electrical and lighting installations
vii. Personal protective equipment (PPE) to be used, including respiratory protective equipment
(RPE).
viii. Waste storage and disposal program
ix. Methods for removing the ACM (wet or dry methods)
x. Asbestos removal equipment (spray equipment, tools etc.)
xi. Control measures to be used to contain asbestos within the asbestos work area.
xii. Detailed procedures for workplace decontamination, the decontamination of tools and
equipment, personal decontamination and the decontamination of non-disposable PPE.
xiii. Methods of disposing of asbestos wastes, including details on the disposal of disposable
protective clothing and equipment, and
xiv. Develop an emergency plan to include site specific emergencies, evacuations, first aid and
equipment.
Work Permits 6.3.2
Contractors will be required to obtain a permit to work that has been approved by the Seqwater
Access Officer in addition to other requirements such as isolation of services which will be
dependent upon the type of work and/or the work environment. Second tier permits may also be
required which include confined space entry and work at heights.
Clearance Inspections 6.3.3
Before clearance is granted for an asbestos work area to be re-occupied there must be a thorough
clearance inspection. The clearance inspection must be conducted by a competent person who is
independent from the person responsible for the removal work; this does not have to be a separate
company but a competent person who was not involved in the removal work.
Where friable asbestos removal occurs this must be accompanied by monitoring results that
establish that fibre levels are <0.01 fibres/ml. These records are to be kept by Seqwater.
6.4 Maintenance or Service work involving ACM
Prior to any work being conducted on site involving penetration methods on walls, floors, ceilings,
roofs or other parts of building structure, the site Asbestos Register must be reviewed to determine
if the location of the work is to be in contact with or near ACM. Any work by Seqwater staff or
contractors that may damage or interfere with the condition of ACM must:
have a detailed WMS providing details of how any invasive work into the ACM will
minimise airborne particles, and what controls will be used
have a permit-to-work for approval of the activity
follow the relevant Seqwater procedures when undertaking the work. The contractor may
have more detailed procedures (refer Reference Section below) to follow if they are a
licensed asbestos removal contractor.
Include an update in the site Asbestos Register for any changes that took place
6.5 Work Method Statements (WMS)
A WMS must be developed for any works involving asbestos such as sealing, drilling or removal.
The WMS provides the details of the hazards, risks and controls identified for each task being
undertaken, and must include the following:
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled Document Number: PLN-00055 Version Date: 24/04/2013 Page: 20 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
The name, address, Asbestos Licence Number if removing asbestos and ABN of the
contractor doing the work.
The specific control measures proposed to be used to undertake the task.
The way the contractor proposes to perform the activity, including how the control
measures are to be implemented.
How the effectiveness of the control measures will be monitored and reviewed.
Provisions for training of workers into the WMS, and communication of the activity to
Seqwater personnel.
Where friable asbestos is to be removed provisions for supervision by a competent
person for asbestos removal.
Be signed and dated.
Be reviewed at least annually
6.6 Damaged ACM
When conditions arise where the risk to exposure through dust inhalation from ACM changes, such
as through fire, storm or malicious damage, the process in the flowchart below must be followed.
Health Surveillance 6.6.1
Seqwater must arrange for health surveillance of personnel that have been potentially exposed to
asbestos fibres such as through changes to ACM condition. The Seqwater Health Surveillance
Procedure for Hazardous Substances must be followed.
Notification 6.6.2
Where ACM has been severely damaged including where a person might have been potentially
exposed to asbestos fibres without protection, then WHS Queensland should be contacted,
following the Seqwater notification procedure. Seqwater personnel working on the affected site
will also be notified as soon as possible, including any conditions and controls to minimise
exposure.
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled Document Number: PLN-00055 Version Date: 24/04/2013 Page: 21 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
Process Flowchart (PF) 3 – Change to ACM Condition
7 TRAINING
7.1 Induction
All personnel and contractors must be inducted before accessing any Seqwater facility. The
induction will address the requirements of the AMP, site Asbestos Registers, and identify that
specific procedures exist for working with ACM.
7.2 Work with Asbestos
Where Seqwater personnel are to work with ACM such as drilling or cutting, then they must be
engaged in the development of a specific WMS for the task, and be trained in specific procedures
that apply. The applicable procedures will be recorded on the WMS.
Change of ACM Condition
Property ManagerSupervisor/
CoordinatorWHS ManagerIndivdual
Becomes aware
of damaged
ACM
Notified of
damaged ACM
Completes
incident report
form
Is facility
leased to
others?
No
Notified of
damaged ACMYes
Receives
incident report
form
Personnel
exposed to
fibres?
Undertake
Health
Surveillance
of personnel
Yes
Provides
assistance with
controls
No
Implement
controls
including
exclusion
Completes
incident report
form
Implement
controls
including
exclusion
Where required,
engage contractor
for removal (refer
PF2)
Where required,
engage contractor
for removal (refer
PF2)
Update register
and inform
Update register
and inform
Update database
and re-issue site
Asbestos Register
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled Document Number: PLN-00055 Version Date: 24/04/2013 Page: 22 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
7.3 Contractors
Contractors who are going to work with ACM such as for removal, cleaning, sealing etc. on
Seqwater sites must be trained their own procedures and be able to show evidence of the training.
Where licences are required, evidence must also be provided.
8 REVIEWING AND UPDATING THE MANAGEMENT PLAN
8.1 Reviews
Reviews must be done where any relevant legislative changes or WHSMS changes will impact on
the content and application of the either site Asbestos Registers or the AMP. As a minimum, the
AMP is to be reviewed at least biennially by WHS team.
8.2 Updates & Changes
Changes to the AMP can only be made by the WHS Manager with approval by the Seqwater WHS
Consultative Committee. These changes are to be done in accordance with all consultative or
document control requirements.
9 RECORDS
Seqwater shall maintain detailed records of all activities and work permits relating to asbestos
works which have been undertaken on Seqwater premises. The records kept should include:
copies of all asbestos survey reports, including updates and amendments
copies of all 'permit to work' documents which will be kept at the respective site
site induction records pertaining to the informing of contractors about the presence of
asbestos on site, and that such contractors have been appropriately trained in safe work
procedures and practices
records pertaining to the informing of Seqwater employees about the presence of
asbestos on site, and that such employees have been appropriately trained in safe work
procedures and practices
records of any asbestos management works performed on site, including clearance
certificates indicating areas are safe to re-occupy after asbestos management works, will
be kept by the Coordinator. Copies of disposal certificates will also be kept
asbestos fibre air monitoring results which will be kept by the WHS Manager.
Records must be stored and retained in accordance with the IMS requirements for Seqwater.
Documents and completed records must also be accessible by all relevant personnel for the
transfer of information.
10 REFERENCES
This AMP has been developed referencing the following documentation.
10.1 Legislation
REG-00003 Work Health and Safety Act 2011
REG-00003 Work Health and Safety Regulation 2011
REG-00003 Code of Practice How to Manage and Control Asbestos in the Workplace [Safe Work
Australia 2011]
REG-00003 Code of Practice How to Safely Remove Asbestos [Safe Work Australia 2011]
Corporate Safety – Plan Asbestos Management
The controlled version of this document is registered. All other versions are uncontrolled Document Number: PLN-00055 Version Date: 24/04/2013 Page: 23 of 23 Document Owner: Y. Dong Document Approver: Manager WH&S
10.2 Procedures
The procedures to be utilised by Seqwater personnel are:
PRO-00996 Corporate Safety - Drilling of ACM Procedure
PRO-00999 Corporate Safety - Safe Work on Switchboards with Asbestos
Procedure
PRO-01001 Corporate Safety - Tool and Equipment Decontamination Procedure
PRO-01003 Corporate Safety - Personal Decontamination Non Friable ACM
Procedure
PRO-01006 Corporate Safety - Use of PPE for work with ACM Procedure
10.3 Forms & Registers
The Forms and Registers that are specific to this AMP are:
FRM-00203 Corporate Safety - Asbestos Induction Training Checklist Form
FRM-00204 Corporate Safety - Contractor Asbestos Information Form
FRM-00205 Corporate Safety - Asbestos Removal Plan Checklist Form