    Area 1

    A: 399 meters AREA HAND-OVER: 272 meters (68.0%) Gridline 22 1/2-6f

    Description Unit BOQ Qty New QtyQuantity as per

    Hand-over (A)

    Actual

    Installed (B)

    Remaining

    Qty (A-B)

    % Accom

    (B / A)

    EARTHWORKS

    SITE CLEARANCE m2 9,754.00 8,910.00 8,910.00 7,218.00 1,692.00 81.0%

    FILLING TO MAKE UP LEVELS

    Dredge fill over site m3 8,258.00 5,022.00 5,022.00 5,022.00 0.00 100.0%

    150mm thick compacted crusher run

    over sitem

    3 1,464.00 1,464.00 - -

    50mm thick and bedding over site m3 9,754.00 7,260.88 - -

    COMPACTION TEST (PROVISIONAL)

    CBR Test no. 4.00 4.00 4.00 0.00 100.0%

    Field Density Test no. 4.00 4.00 4.00 0.00 100.0%

    TEMPORARY HOARDING (WITHIN BOUNDARY OF SITE)

    Supply & Install 2.4m high metal hoarding m 376.00 - - -

    DOUBLE LEAVES SWING GATE

    Supply & Install of 7.4x2.4m high metal

    swing gateno.

    1.00 - - -

    SOFT LANDSCAPING WORKS

    ALL LANDSCAPE PLANTING AREAS

    Trimming , leveling , compacting bottoms Item 1.00 1.00 an ng an s ru ng nc u ng any e -

    inItem 1.00 1.00

    Complying with the Architect'sItem 1.00 1.00

    Removal of excavated materials off-site Item 1.00 1.00

    Hoisting of planting media and plant

    materialsItem

    1.00 1.00 - - - -

    Supply and delivery to site the approved

    imported filling mat.Item

    1.00 1.00 - - - -

    CULTIVATING

    To turf area m2

    500.00 500.00

    To planting areas; trees & palms m2

    141.00 141.00

    To planting areas; shrubs m2

    500.00 500.00

    EARTHMOUNDING AND FINE GRADING 486.35 416.01 70.34 85.5%

    Handling and delivering of sweet soil to

    lantin areasm

    3 490.00 306.09 306.09 262.97

    Handling and delivering, contouring andfine radin of soil fillin

    m3 180.26 180.26 153.04

    SUPPLY AND PLANT TURF

    Paspalum Vaginatum (Seashore

    Pas alum); close turfinm

    2 500.00 500.00

    SUPPLY AND PLANT PALM AND TREES

    TREE

    Delonix Regia no. 15.00 15.00

    Tabebuai Rosea no. 23.00 23.00

    Lagerstroemia Indica no. 3.00 3.00

    e op orum p erocarpum ( e ow

    Flameno. 9.00 9.00

    Thevitia Peruviana no. 6.00 6.00

    Filicium Decipiens no. 6.00 6.00

    PALM

    Phoenix dactylifera (Date Palm) no. 5.00 5.00

    Livistonia Rotundifolia no. 5.00 5.00

    PALM DEIRA

    PROMENADE AT DEIRA ISLAND FRONT

    AREA 1- BILL OF QUANTITIES

    Page 1 of 14 Updated as of February 12, 2009

  • 8/2/2019 Area 1 Accomplishment

    2/14

    Area 1

    A: 399 meters AREA HAND-OVER: 272 meters (68.0%) Gridline 22 1/2-6f

    Description Unit BOQ Qty New Qty

    Quantity as per

    Hand-over (A)

    Actual

    Installed (B)

    Remaining

    Qty (A-B)

    % Accom

    (B / A)

    PALM DEIRA

    PROMENADE AT DEIRA ISLAND FRONT

    AREA 1- BILL OF QUANTITIES

    Bismarkia Nobilis (Fan Palm) no. 5.00 5.00

    SUPPLY AND PLANT SHRUBS & CLIMBERS

    SHRUBS

    Petunia spp. no. 740.00 740.00

    Helicornia Psitacorum 'rubra' no. 230.00 230.00

    Pennisetum Rubrum no. 135.00 135.00

    Helicornia Psitacorum (Golden Torch) no. 100.00 100.00

    Catharanthus Rosea (Madagascar

    Periwinkle)no. 120.00 120.00

    Bougainvilla Spectabilis no. 250.00 250.00

    Petunia Hybrida no. 475.00 475.00

    Hibiscus Rosa Sinensis no. 230.00 230.00

    PROVISION OF MAINTENANCE

    all costs and expences in connection with

    maintenanceItem 1.00 1.00

    Provision for Water Item 1.00 1.00

    HARD LANDSCAPING WORKS

    PRECAST CONCRETE PLANKS

    4500mm x 600mm x 75mm (Type I) m2 4,172.00 - - - -

    1000mm x 600mm x 75mm (Type II) m2 2,971.00 - - - -

    PRECAST CONCRETE PLANTER BOX (TREE PITS)

    Type 1 no. 64.00 63.00 46.00 46.00 0.00 100.0%

    Type 2 ; including coping no. 11.00 12.00 8.00 8.00 0.00 100.0%

    PRECAST CONCRETE STEP

    to rc step; along tree pits type 1 m 256.00 256.00

    PRECAST CONCRETE BENCH

    1000mm width x 450mm x 100mm thk;

    Type 3 bench; along planter boxm 290.00

    mm x mm x mm g rea e

    hardwood bench with 460mm x 15mm

    thk steel column Architect's approval;

    no. 20.00

    PRECAST CONCRETE SEAT

    to sand box; 1500 girth no. 2.00 1.00 0.00

    PRECAST CONCRETE STUMPmm x mm mm o ra ng

    no. 100.00 - - - -

    PRECAST CONCRETE TURF BOX

    to turf box perimeter; 675mm high

    x150mm thickno. 9.00 9.00 5.00 5.00 0.00

    100.0%

    JOINTS

    Expansion joint to precast concrete

    planks type 1m 325.00 325.00

    METAL RAILING

    1100 high x 125mm x 75mm Hot dipalvanized railin

    m 273.00

    LOOSE FURNITURE

    BENCH

    to bench type 1 no. 20.00

    Page 2 of 14 Updated as of February 12, 2009

  • 8/2/2019 Area 1 Accomplishment

    3/14

    Area 1

    A: 399 meters AREA HAND-OVER: 272 meters (68.0%) Gridline 22 1/2-6f

    Description Unit BOQ Qty New QtyQuantity as per

    Hand-over (A)

    Actual

    Installed (B)

    Remaining

    Qty (A-B)

    % Accom

    (B / A)

    PALM DEIRA

    PROMENADE AT DEIRA ISLAND FRONT

    AREA 1- BILL OF QUANTITIES

    DUST BIN

    1100mm high x 570mm diameter ; type 1 no. 35.00 20.00

    FINISHES

    Cement and sand (1:3) screed as described:

    20mm thick protective screed to received

    homo enous tilesm

    2 325.00

    20mm thick protective screed to received

    ranite tiles.m

    2 2,971.00

    20mm thick protective screed to received

    Agglomerate cement tiles finish.m

    2 4,172.00

    400mmx400mmx15mm thick homogenous tiles

    to floor ; to pavements and walkways m2 325.00

    to floor ; to precast planks m2 2,971.00

    to precast rc seat; bench- type 2 no. 11.00 - -

    to juxtaposed green no. 1.00 1.00 - - - -

    to turf box no. 9.00 9.00 6.00

    to floor ; to precast planks m2 4,172.00

    CHENGAL" hardwood Timber Deck

    100mmx450mmx25mm m 32.00

    100mmx125mmx25mm; to sides m 64.00

    LUMINAIRES AND LAMPS

    Pole Light no. 65.00 39.00 26.00 66.7%

    a. Installation of foundation 26.00 26.00 0.00 100.0%

    b. Installation of sleeves & cables 26.00 26.00 0.00 100.0%

    c. Installation of Pole light 26.00 0.00 26.00 0.0%

    Bollard Light no. 100.00 75.00 47.00 8.00 39.00 17.0%

    Wall Light no. 40.00 10.00 0.00

    Uplight no. 120.00 107.00 76.00 24.00 52.00 31.6%

    LED Micro Light m 600.00 439.00

    Step Light no. 70.00 28.00 20.00 0.00 20.00

    UTILITIES

    TELECOMMUNICATION 896.00 730.50 730.50 0.00 100.0%

    Bed laying of four way D54 duct m - 316.00 267.25 267.25 0.00 100.0%

    Filling of granular material bed &

    backfillingm - 316.00 267.25 267.25 0.00

    100.0%

    Excavate, lay and backffill D56 house

    connectionm - 258.00 190.00 190.00 0.00

    100.0%

    Installation of Type JRC 14 Manhole no. - 6.00 6.00 6.00 0.00 100.0%

    ELECTRICAL 31.3%

    Electrical works for substation (excluding

    transformer and incoming cables)no. - 1.00 1.00 1.00

    0.0%

    Electrical substation civil works no. - 1.00 1.00 1.00 0.00 100.0%

    WATER SUPPLY 764.00 680.00 679.00 1.00 99.9%

    Bed laying of 150mm GRE pipes m - 318.00 276.00 276.00 0.00 100.0%

    Filling of granular material bed &

    backfillingm - 318.00 276.00 276.00 0.00

    100.0%

    Page 3 of 14 Updated as of February 12, 2009

  • 8/2/2019 Area 1 Accomplishment

    4/14

    Area 1

    A: 399 meters AREA HAND-OVER: 272 meters (68.0%) Gridline 22 1/2-6f

    Description Unit BOQ Qty New QtyQuantity as per

    Hand-over (A)

    Actual

    Installed (B)

    Remaining

    Qty (A-B)

    % Accom

    (B / A)

    PALM DEIRA

    PROMENADE AT DEIRA ISLAND FRONT

    AREA 1- BILL OF QUANTITIES

    Install buried type 150mm Gate Valve no - 1.00 1.00 0.00 1.00 0.0%

    Testing of waterline unit - 1.00 1.00 1.00 0.00 100.0%

    Waterhouse connection tapping oun

    150mm GRP lineno - 12.00 12.00 12.00 0.00

    100.0%

    Lay HDPE 1" house connection hose

    between taping point and kioskm - 114.00 114.00 114.00 0.00

    100.0%

    IRRIGATION WORKS 85.1%

    Main Irrigation Lines 578.00 578.00 0.00 100.00%

    Main irrigation 4" uPVC pipe including

    5m taping point at grid 12m - 400.00 303.00 303.00 0.00

    100.0%

    Main irrigation 1.5" Conduit pipe m - 400.00 275.00 275.00 0.00 100.0%

    Main irrigation 2.0" Conduit pipe m - 45.00 30.00 30.00 0.00 100.0%

    Irrigation Lateral Drip Lines 904.00 904.00 0.00 100.00%

    Irrigation lateral drip uPVC pipe lines m - 1,175.00 810.00 810.00 0.00 100.0%

    Drip riser 16mm classC LDPE pipe m - 200.00 90.00 90.00 0.00 100.0%

    Solenoid & gate valves for drip no - 6.00 4.00 4.00 0.00 100.0%

    Irrigation Lateral Spray Lines 470.00 191.00 279.00 40.64%

    Irrigation lateral spray uPVC pipe lines m - 215.00 191.00 191.00 0.00 100.0%

    Spray riser 16mm classC LDPE pipe m - - - -

    Solenoid & gate valves for spray no - 6.00 4.00 0.00 4.00 0.0%

    In drip line at 2.3lph at 50cm spacing m - 400.00 275.00 275.00 0.0%

    2,006.00 1,998.00 8.00 99.60%

    15 series spray nozzles no - 63.00 42.00 42.00 0.00 100.0%

    Pop-up spray head body no - 63.00 42.00 42.00 0.00 100.0%

    Pull boxes no - 12.00 9.00 9.00 0.00 100.0%

    4" dia size Isolation valve with manhole no - 1.00 1.00 1.00 0.0%

    Irrigation controller no - 1.00 1.00 1.00 0.0%

    Water tank (5000 gallons) no - 1.00 1.00 1.00 0.0%

    Valve boxes no - 9.00 6.00 2.00 4.00 33.3%

    Satellite Controller no - 1.00 1.00 1.00 0.0%

    Common wire AWG (Red, Black, Green,

    White)m - 1,600.00 1,600.00 1,600.00 0.00

    100.0%

    Underground warning tapes m - 400.00 303.00 303.00 0.00 100.0%SEWERAGE 791.00 1,029.00 1,010.00 19.00 98.2%

    uPVC pipes laid & jointed as specified

    Depth not exceeding 3m

    200mm UPVC pipes m - 301.00 200.00 200.00 0.00 100.0%200mm UPVC (Connection to main

    additionalm - 140.00 140.00 0.00 100.0%

    100mm UPVC house connection m - 200.00 200.00 0.00 100.0%

    Depth not exceeding 4m

    200mm UPVC pipes m - 40.00 40.00 40.00 0.00 100.0%

    200mm HDPE Pipe m - 15.00 15.00 0.00 15.00 0.0%

    Filling of granular material bed &

    backfilling

    m - 380.00 380.00 380.00 0.00

    100.0%Reinforced Concrete Manhole

    Manhole no - 4.00 3.00 3.00 0.00 100.0%

    Chamber no 4.00 4.00 0.00 4.00 0.0%

    Page 4 of 14 Updated as of February 12, 2009

  • 8/2/2019 Area 1 Accomplishment

    5/14

    Area 1

    A: 399 meters AREA HAND-OVER: 272 meters (68.0%) Gridline 22 1/2-6f

    Description Unit BOQ Qty New Qty

    Quantity as per

    Hand-over (A)

    Actual

    Installed (B)

    Remaining

    Qty (A-B)

    % Accom

    (B / A)

    PALM DEIRA

    PROMENADE AT DEIRA ISLAND FRONT

    AREA 1- BILL OF QUANTITIES

    600mm Chamber & connections no 25.00 25.00 25.00 0.00 100.0%

    200mm backdrop no 2.00 2.00 2.00 0.00 100.0%

    Relocation of 1200mm manholes no - 3.00 3.00 3.00 0.00 100.0%

    Relocation of 600mm manholes no - 5.00 5.00 5.00 0.00 100.0%

    Straight specials as rocker pipes at

    bends and manholesno - 12.00 12.00 12.00 0.00

    100.0%

    Description Unit Qty New QtyQuantity as per

    Hand-over (A)

    Actual

    Installed (B)

    Remaining

    Qty (A-B)

    % Accom

    (B / A)

    ADDITIONAL LUMINAIRES & LAMPS

    Pillar Light no - 20.00 50.0%

    a. Installation of foundation 14.00 14.00 0.00 100.0%

    b. Installation of Pillar light 14.00 0.00 14.00 0.0%

    Recessed Light no - 23.00 20.00 2.00 18.00 10.0%

    ELECTRICAL MANHOLES no - 12.00 12.00

    a. Installation of electrical manhole 14.00 12.00 12.00 0.00 100.0%

    b. Casting of manhole cover 14.00 12.00 12.00 0.00 100.0%

    SIGNAGE

    Advertising Signage no - 2.00

    a. Installation of foundation 1.00 1.00 0.00 100.0%

    b. Installation of advertising signage 1.00 1.00 0.0%

    Directional Signage no - 3.00

    a. Installation of foundation 2.00 2.00 0.00 100.0%

    b. Installation of directional signage 2.00 2.00 0.0%

    DUST BIN

    Supply & installation of

    1450x400x1200mm high dust bin

    fabricated from aluminum sheet andangles including GI mesh bushket. Finish

    shall be owder coated to standard RAL

    no. 35.00

    LOOSE FURNITURE

    BENCH

    Bench type 1 (curved shape) no. 34.00

    Bench type 2 (rectangular shape) no. 20.00

    PRECAST CONCRETE PLANKS 0.00

    Pedestrian (2200x500x125) m2

    - - 73.39%

    Fixed Size m2 2,532.20 2,274.80 257.40 89.8%

    Custom Size no. 671.00 75.90 595.10 11.3%

    Vehicular (2250x500x150) m2

    - - 66.79%Fixed Size m

    2 1,068.75 806.63 262.12 75.5%

    Custom Size no. 139.00 0.00 139.00 0.0%

    Modified Vehicular (2410x500x150) m2

    - - 0.00%

    Fixed Size m2 589.25 0.00 589.25 0.0%

    Custom Size no. 103.00

    AREA 1- VARIATIONS

    Page 5 of 14 Updated as of February 12, 2009

  • 8/2/2019 Area 1 Accomplishment

    6/14

    Area 1

    A: 399 meters AREA HAND-OVER: 272 meters (68.0%) Gridline 22 1/2-6f

    Description Unit BOQ Qty New QtyQuantity as per

    Hand-over (A)

    Actual

    Installed (B)

    Remaining

    Qty (A-B)

    % Accom

    (B / A)

    PALM DEIRA

    PROMENADE AT DEIRA ISLAND FRONT

    AREA 1- BILL OF QUANTITIES

    PRECAST CONCRETE STEPS 16.67%

    to rc step; along grid D m 35.00

    a. Perma beams for steps set 7.00 6.00 2.00 4.00 33.3%

    b. Precast planks for steps

    PC2- (S1) no 28.00 24.00 8.00 16.00 33.3%

    PC2- (S2) no 28.00 24.00 24.00 0.0%

    PC2- (S3) no 28.00 24.00 24.00 0.0%

    PRECAST CONCRETE BENCH 450.40 450.40 440.40 10.00 97.8%

    Bench type 3 (61nosx2.5m) m 100.00

    100.00 97.50 2.50 97.5% Bench type 2 (Along T-wall)-48nos x2.5m m 120.00 120.00 117.50

    2.50 97.9%

    Precast Boundary Wall (88nosx2.5m) m 220.00 220.00 215.00 5.00 97.7%

    Precast Sidewall (10nos) m 10.40 10.40 10.40 0.00 100.0%

    FINISHES

    For Foot Path Tiles ln 973.00 735.00 644.00 91.00 87.6%

    500mm x 500mm 20mm thk Consent

    Traniex tiles, Sand Blast finish.

    Grid A ln 399.00 297.00 267.00 30.00 89.9%

    Grid B ln 175.00 141.00 131.00 10.00 92.9%

    Grid C ln 399.00 297.00 246.00 51.00 82.8%

    For Granite Cladding m2 547.88 485.43 265.03 220.40 54.6%

    Bench type 3 m2 91.25 91.25 63.05 28.20 69.1%

    Bench type 2 (Along T-wall) m2 96.00 96.00 58.00 38.00 60.4%

    Precast Boundary Wall & Side Wall m2 175.75 175.75 60.00 115.75 34.1%

    Turf Box (9 nos) m2 30.00 19.94 19.94 0.00 100.0%

    Sand Box (1 nos) m2 25.37 0.00 0.00 0.00

    -

    Juxtaposed (1 nos) m2 37.50 37.50 37.50 0.00

    100.0%

    Tree pits Type 1 (63 Nos) m2 57.45 41.95 23.66 18.29 56.4%

    Tree pits Type 2 (12 Nos) m2 34.56 23.04 2.88 20.16 12.5%

    For Wood Cladding m2 194.46 180.98 3.28 177.70 1.8%

    Bench type 3 m2 110.00 110.00 0.00 110.00 0.0%

    Bench type 2 (Along T-wall) m2 42.00 42.00 0.00 42.00 0.0%

    Sand Box (1 nos) m2 13.48 0.00 0.00 0.00

    -

    Tree Pit Type 2 (12 Nos) m2 22.09 22.09 3.28 18.81 14.8%

    Juxtaposed Green (1 Nos) m2 6.89 6.89 0.00 6.89 0.0%

    Page 6 of 14 Updated as of February 12, 2009

  • 8/2/2019 Area 1 Accomplishment

    7/14

    Area 1

    Remarks

    med as per payment.

    ted as per ERI No. 7

    pplicable.

    plete

    plete

    ted as per ERI No. 4

    ted as per ERI No. 6

    plete

    Page 7 of 14 Updated as of February 12, 2009

  • 8/2/2019 Area 1 Accomplishment

    8/14

    Area 1

    Remarks

    ed sizes.

    ed sizes.

    plete

    plete

    not ready.

    pplicable.

    plete

    Page 8 of 14 Updated as of February 12, 2009

  • 8/2/2019 Area 1 Accomplishment

    9/14

    Area 1

    Remarks

    ange to new design.

    plete

    lled sleeves & cable

    not ready.

    nits uplight boxes.

    lled sleeves & cable

    plete

    plete

    plete

    plete

    er DEWA scope

    plete

    plete

    plete

    Page 9 of 14 Updated as of February 12, 2009

  • 8/2/2019 Area 1 Accomplishment

    10/14

    Area 1

    Remarks

    yet installed

    plete

    plete

    plete

    plete

    plete

    plete

    plete

    plete

    plete

    plete

    aining

    aining

    pleteplete

    plete

    aining

    aining

    aining

    aining

    aining

    plete

    plete

    plete

    plete

    plete

    plete

    plete

    ers not installed.

    Page 10 of 14 Updated as of February 12, 2009

  • 8/2/2019 Area 1 Accomplishment

    11/14

    Area 1

    Remarks

    plete

    plete

    plete

    plete

    plete

    Remarks

    plete

    led sleeves & cable

    k-up

    plete

    plete

    led sleeves & cable

    plete

    led sleeves & cable

    Page 11 of 14 Updated as of February 12, 2009

  • 8/2/2019 Area 1 Accomplishment

    12/14

    Area 1

    Remarks

    aining @grid (22-

    (12-13)

    aining @grid (22-

    (12-13)aining @grid (12-

    15

    plete

    Hand-overed to

    O.

    plete

    Handover to ARCO.

    Page 12 of 14 Updated as of February 12, 2009

  • 8/2/2019 Area 1 Accomplishment

    13/14

    Week no. 56

    Week Ending: 12-Mar-09

    Planned Actual Planned Actual Planned Actual

    AREA 1 - WATER (297 meters H/O)

    1 Earthworks 1.45% 1.45% 1.45% 1.45% 1.45% Completed

    2 Hard Landscape 10.56%

    a. Planter Box 0.66% 0.66% 0.66% 0.66% 0.66% 0.00% Completed

    b.Turf Flat / Juxtaposed Green 0.18% 0.18% 0.18% 0.18% 0.18% 0.00% Completed

    b. Linear Bench 0.93% 0.93% 0.91% 0.00% 0.93% 0.91% -0.02% 97.84% Completed

    Bench type 3 0.28% 97.50% 97.50%Bench type 2 (Along T-wall) 0.28% 97.90% 97.90%

    Precast Boundary Wall 0.28% 97.70% 97.70%

    Precast Sidewall 0.09% 95.00% 5.00% 100.00%

    c. Permatrak Planks 3.58% 3.58% 2.18% 0.09% 3.58% 2.27% -1.40% 63.4% Completed

    Pedestrian (2200x500x125) 2.33% 69.64% 3.75% 73.39%

    Vehicular (2250x500x150) 0.84% 66.14% 0.65% 66.79%

    Modified Vehicular (2410x500x150) 0.41% 0.00% 0.00%

    d. Precast Concrete Steps 1.18% 1.18% 0.20% 0.00% 1.18% 0.20% -0.98% 17% Completed

    to rc step; along grid D 1.18% 16.67% 16.67%

    e. Finishes 4.03% 4.03% 2.44% 0.15% 4.03% 2.59% -1.59% 64% Completed

    For Foot Path Tiles 2.02% 87.60% 87.60%

    For Granite Cladding 1.49% 44.80% 9.80% 54.60%

    For Wood Cladding 0.52% 1.80% 1.80%

    3 Soft Landscape 1.17% 1.17% 0.15% 0.00% 1.17% 0.15% -1.02% 13% Completed

    All Landscape Planting Material 0.14%

    Cultivating 0.1313%

    Earth Mounding and Fine Grading 0.23% 63.40% 63.40%

    Supply and Plant Palm & Trees 0.20%

    Provision of Maintenace 0.47%

    4 Landscape Fixtures & Finishes 3.38%

    a. Pole Lights 0.66% 0.66% 0.44% 0.66% 0.44% -0.22% 66.7% Completed

    b. Bollard Lights 0.45% 0.45% 0.08% 0.45% 0.08% -0.37% 18% Completed

    c. Wall Lights 0.09% 0.09% 0.09% 0.00% -0.09% Area not ready

    d. Up Lights 0.46% 0.46% 0.15% 0.46% 0.15% -0.31% 33% Completed

    e. LED Lights 0.97% 0.97% 0.97% 0.00% -0.97%

    f. Step Lights 0.11% 0.11% 0.11% 0.00% -0.11%

    g. Precast Seat to Sand Box 0.16% 0.16% 0.16% 0.00% -0.16%

    h. Metal Railing 0.35% 0.35% 0.35% 0.00% -0.35%

    i. Dust Bin 0.13% 0.12% 0.008% 0.13% 0.00% -0.13%

    5 Utili ties/ MEP 3.18% 0.00% 0.00%

    a. Telecommunication 0.48% 0.48% 0.48% 0.48% 0.48% 0.00% Completed

    b. Electrical (Substation) 0.48% 0.48% 0.15% 0.48% 0.15% -0.33% 31% Completed

    c. Water Supply 0.79% 0.79% 0.78% 0.79% 0.78% -0.01% 99% Completed

    d. Irrigation 0.48% 0.48% 0.41% 0.48% 0.41% -0.07% 81% Completed

    e. Sewerage 0.95% 0.95% 0.93% 0.95% 0.93% -0.02% 98% Completed

    6 Kiosk Construction 34.49% 33.30% 1.99% 1.23% 34.53% 1.99% -32.54% 5.8% Completed

    Sub-structure 15.52% 12.81%

    Super structure 18.97%

    7 Water Features/ Reflected Pool 31.97% 28.17% 1.28% 29.45% 0.00% -29.45%

    Sub-structure 14.39%

    Super structure 17.58%

    8 Metal Sculpture 13.80% 12.77% 1.06% 13.83% 0.00% -13.83%

    100.00% 93.97% 13.39% 3.58% 0.24% 97.55% 13.63% -83.98%

    Total Cumulative Progress Percentage Of Area 1 TO DATE (Actual) 13.63%

    Sr.

    No.Project Components/Activities %

    Cumulative Progress-Previous Progress This Week Cumulative Progress To DateVariance REMARKS

    TOTAL PROGRESS OF AREA 1

    Total Cumulative Progress Percentage Of Area 1 TO DATE (Planned) 97.55%

  • 8/2/2019 Area 1 Accomplishment

    14/14

    PLANNED VS. ACTUAL % AGE FOR AR

    18-22 23-29 1-7 8-14 15-21 22-28 29-4 5-11 12-18 19-25 26-2 3-9 10-16 17-23 24-30 31-6 7-13 14-20 21-27 28-4 5-11 12-18 19-25 26-1 2-8 9-15 16-22 23-29 30-5 6-12 13-19

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

    1 Earthworks 0.145% 0.145% 0.145% 0.145% 0.145% 0.145% 0.145% 0.145% 0.145% 0.145%

    2 Hard Landscaping

    a. Planter Box 0.66% 0.060% 0.060% 0.060% 0.060% 0.060% 0.060% 0.060% 0.060% 0.060% 0.060%

    b. Turf Flat 0.18% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015% 0.015%

    c. Linear Bench 0.93% 0.072% 0.072% 0.072%

    d. Permatrak Planks 3.58% 0.163% 0.163% 0.163% 0.163% 0.163% 0.163% 0.163% 0.163% 0.163% 0.163% 0.163% 0.163%

    e. Precast Concete Steps 1.18%

    f. Finishes 4.03%

    3 Soft Landscaping

    4 Landscape Fixtures

    a. Pole Lights 0.66% 0.025% 0.025% 0.025%

    b. Bollard Lights 0.45% 0.017% 0.017% 0.017%

    c. Wall Lights 0.09% 0.003% 0.003% 0.003%

    d. Uplights0.46% 0.018% 0.018% 0.018%

    e. LED Lights 0.97% 0.037% 0.037% 0.037%

    f. Step Lights 0.11% 0.004% 0.004% 0.004%

    g.Precast Seat to Sand Box 0.16% 0.012%

    h. Metal Railing 0.35%

    i. Dust Bin 0.13%

    5 Utilities/ MEP

    a. Telecommunication 0.48% 0.044% 0.044% 0.044% 0.044% 0.044% 0.044% 0.044% 0.044% 0.044% 0.044% 0.044%

    b. Electrical 0.48% 0.028% 0.028% 0.028% 0.028% 0.028% 0.028% 0.028%

    c. Water Supply 0.79% 0.049% 0.049% 0.049% 0.049% 0.049% 0.049% 0.049% 0.049% 0.049% 0.049%

    d. Irrigation 0.48% 0.030% 0.030% 0.030% 0.030% 0.030% 0.030% 0.030% 0.030% 0.030% 0.030% 0.030% 0.030% 0.030% 0.030%

    e. Sewerage 0.95% 0.045% 0.045% 0.045% 0.045% 0.045% 0.045% 0.045% 0.045% 0.045% 0.045% 0.045% 0.045% 0.045% 0.045% 0.045%

    6 Kiosk Construction 1.232% 1.232% 1.232%

    7 Water Features/ Reflected Pool

    8 Metal Sculture

    TOTAL

    Planned Weekly Progress % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.05% 0.08% 0.08% 0.28% 0.28% 0.41% 0.41% 0.41% 0.43% 0.43% 0.43% 0.43% 1.84% 1.84% 1.81%

    Cumulative Planned Progress % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.15% 0.30% 0.45% 0.60% 0.75% 0.90% 1.05% 1.20% 1.35% 1.50% 1.55% 1.63% 1.71% 1.99% 2.27% 2.68% 3.09% 3.50% 3.93% 4.36% 4.79% 5.22% 7.06% 8.90% 10.71%

    Actual Weekly Progress % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.12% 0.15% 0.21% 0.21% 0.95% 0.65% 0.26% 0.60% 0.31% 0.60% 0.60% 0.30% 0.18% 0.56% 0.00% 0.45% 0.84% 0.56%

    Cumulative Actual Progress % 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.12% 0.27% 0.48% 0.69% 1.64% 2.29% 2.55% 3.15% 3.46% 4.06% 4.66% 4.96% 5.14% 5.70% 5.70% 6.15% 6.99% 7.55%

    Apr-08

    Sr.No.

    Project Components/Activities Wt. %

    Feb-08 Mar-08 May-08 Jun-08 Jul-08 Aug-08 Sep-08

    34.49%

    31.97%

    13.80%

    100.00%

    AREA 1 - WATER (297 meters H/O)

    1.45%

    10.56%

    1.17%

    3.38%

    3.18%