Application for an Environmental Authorisation for the proposed construction of the new Rietkuil Private Railway Siding, Haul Road, Pollution Control Dam, and Associated Infrastructure, Exxaro Coal Mpumalanga (Pty) Ltd, Mpumalanga Province Report Prepared for Exxaro Coal Mpumalanga (Pty) Ltd Report Number 467209 MDARDLEA Reference Number: 17/2/3N-340 Report Prepared by October 2014
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Application for an Environmental Authorisation for the proposed construction of the new Rietkuil Private Railway Siding, Haul Road, Pollution Control Dam, and Associated Infrastructure, Exxaro Coal Mpumalanga (Pty) Ltd, Mpumalanga Province
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Application for an Environmental Authorisation for the proposed construction of the new Rietkuil Private Railway Siding, Haul Road, Pollution Control Dam, and Associated Infrastructure, Exxaro Coal (Pty) Ltd, Mpumalanga Province
DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT
Exxaro Coal Mpumalanga (Pty) Ltd
SRK Consulting (South Africa) (Pty) Ltd. Block A, Menlyn Woods Office Park
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Table of Contents
Executive Summary ..................................................................................................................................... ii
Disclaimer ................................................................................................................................................... xiii
List of Abbreviations .................................................................................................................................. xiv
1.1 Details of the Applicant ....................................................................................................................... 2
1.2 Details of the EAP ............................................................................................................................... 2
1.2.1 Statement of independence .................................................................................................... 4
Spiders and scorpions ...................................................................................................................... 39
4.7 Surface Water ................................................................................................................................... 40
4.9 Air quality .......................................................................................................................................... 54
4.9.1 Mining activities in the region ................................................................................................ 54
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
List of Tables Table 1-1: Applicant Contact Details ............................................................................................................. 2
Table 1-2: Details of the Environmental Impact Assessment Project Team ................................................. 3
Table 1-3: Specialist Team ............................................................................................................................ 4
Table 5-5: Impacts on Habitat for Floral Species during the Construction Phase of the Project ................ 85
Table 5-6: Impacts on Flora Diversity.......................................................................................................... 86
Table 5-7: Impacts on Flora Species of Conservation concern during the Construction Phase of the Project ........................................................................................................................................ 87
Table 5-8: Impacts on Faunal Habitat during the Construction Phase of the Project ................................. 87
Table 5-9: Impacts on Faunal Diversity During the Construction Phase of the Project .............................. 88
Table 5-10: Impact on RDL and Protected Fauna Species During the Construction Phase of the Project .. 88
Table 5-11: Impacts on Loss of Wetland Habitat and Ecological Structure during the Construction Phase of the Project .................................................................................................................................. 89
Table 5-12: Changes to Wetland Ecological and Sociocultural Service provision ........................................ 90
Table 5-13: Impacts on Wetland Hydrological Function during the Construction Phase of the Project ....... 91
Table 5-14: Impacts Relating to Soil Compaction during the Construction Phase of the Project ................. 92
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Table 5-15: Impacts Relating to Soil Erosion During the Construction Phase of the Project ....................... 92
Table 5-16: Impacts Associated With the Sterilization of Topsoil Layer During the Construction Phase of the Project .................................................................................................................................. 93
Table 5-17: Impacts associated with Chemical Soil Pollution ....................................................................... 93
Table 5-18: Impacts on the loss of current Land Capability during the Construction Phase of the Project .. 94
Table 5-19: Surface and Groundwater Impacts during the Construction Phase of the Project .................... 94
Table 5-20: Heritage related Impacts during the Construction Phase of the Project .................................... 96
Table 5-21: Traffic Related Impacts during the Construction Phase of the Project ...................................... 97
Table 5-22: Noise Related Impacts during the Construction Phase of the Project ....................................... 99
Table 5-23: Creation of Temporary Employment Opportunities during the Construction Phase of the Project ...................................................................................................................................... 100
Table 5-24: Creation of permanent Employment Opportunities During the Construction Phase of the Project ...................................................................................................................................... 101
Table 5-25: Surface and Groundwater during the Operational Phase of the Project ................................. 101
Table 5-26: Traffic Impacts during the Operational Phase Of The Project ................................................. 103
Table 5-27: Noise related Impacts during the Operational Phase of the Project ........................................ 104
Table 5-28: Impacts associated with PM10 during the Operational Phase of the Project ........................... 107
Table 5-29: Impacts Associated with Dust Fallout during the Operational Phase of the Project ................ 107
Table 5-30: Impacts Associated with PM2.5 during the Operational Phase of the Project .......................... 107
Table 5-31: Impacts associated with Soil Compaction during the Decommission Phase of the Project .... 109
Table 5-32: Surface and Groundwater Related Impacts during the Decommission Phase of the Project . 109
Table 5-33: Noise Impacts during the Decommission Phase of the Project ............................................... 110
Table 6-1: Approach to Impact Management ............................................................................................ 114
Table 7-1: List and Location of the Site Notices placed for the proposed Project .................................... 117
Table 7-2: Actions Taken during Public Participation Process ................................................................. 121
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
List of Figures Figure 2-1: Overall Layout Map of the proposed Transport Route ............................................................... 17
Figure 2-2: Layout Map of the proposed Road Upgrades ............................................................................ 18
Figure 2-3: Layout Map of the proposed Private Railway Siding And Associated Infrastructure. ................ 19
Figure 4-1: Percentiles of Monthly Rainfall and Annual Rainfall (Inset) for the Klippan-Nooitgedacht Dam-Leeuwpan Combined Record .................................................................................................... 25
Figure 4-2: Average Monthly Rainfall for the Klippan-Nooitgedacht Dam-Leeupan Combined Record (1904 – 2012) and Symons Pan Evaporation from WR2005 ............................................................... 26
Figure 4-4: Land Capability of the Proposed New Access Road to the proposed new Rietkuil Private Railway Siding ............................................................................................................................ 31
Figure 4-5: Land Capability of the proposed new Rietkuil Private Railway Siding Road Upgrade (Map 1) . 32
Figure 4-6: Land Capability of the proposed new Rietkuil Private Railway Siding Road Upgrade (Map 2) . 33
Figure 4-7: Land Capability of the proposed new Rietkuil Private Railway Siding Road Upgrade (Map 3) . 34
Figure 4-8: Land capability map of the proposed new Rietkuil Private Railway Siding Pollution Control Dam and Coal Loading Facility development footprint area ...................................................... 35
Figure 4-9: Surrounding land use map of the proposed new Rietkuil Private Railway Siding ..................... 36
Figure 4-10: Catchment map of the proposed new Rietkuil Private Railway Siding and associated infrastructure study area ............................................................................................................ 43
Figure 4-11: Seepage from Shallow Groundwater ........................................................................................ 44
Figure 4-12: Floodline extent for the proposed new Rietkuil Private Railway Siding and associated infrastructure .............................................................................................................................. 47
Figure 4-13: Illustration of the wetlands in and around the proposed new Rietkuil Private Railway Siding and associated infrastructure project area ................................................................................. 49
Figure 4-14: Wetland types associated with the proposed new Rietkuil Private Railway Siding and associated infrastructure ............................................................................................................ 50
Figure 4-15: Wetland Types Associated with the upgrading of the D1770 ................................................... 51
Figure 4-15: Noise sources in the vicinity of the proposed new Rietkuil Private Railway Siding and associated infrastructure site ..................................................................................................... 57
Figure 4-16: Noise sensitive areas in the vicinity of the proposed new Rietkuil Private Railway Siding and associated infrastructure. ........................................................................................................... 60
Figure 4-17: Site layout plan depicting locations of heritage sites ................................................................. 67
Figure 4-18: Location of the Recorded Sites at the Rietkuil Private Railway Site .......................................... 68
Figure 4-19: Location of the Recorded Sites Along the Provincial Roads ..................................................... 68
Figure 4-19: Photographic Reference for Site 1 ............................................................................................. 69
Figure 4-20: Photographic Reference for Site 2 ............................................................................................. 70
Figure 4-21: Photographic Reference for Site 4 ............................................................................................. 70
Figure 4-22: Physical Location of Site 5 ......................................................................................................... 71
Figure 4-23: Photographic Reference for Site 6 ............................................................................................. 71
Figure 4-24: Photographic Reference for Site 7 ............................................................................................. 72
Figure 4-25: Photographic Reference for Site 8 ............................................................................................. 73
Figure 4-26: Photographic Reference for Site 9 ............................................................................................. 73
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Table 1-6: Listed NEMA Activities
Number and date of relevant notice
Activity No(s)
(in terms of the relevant notice)
Description of each listed activity as per the government notice and the detailed project description
Description of the proposed activities in relation to the listed activities being applied for
GN R544 9 The construction of facilities or infrastructure exceeding 1000 metres in length for the bulk transportation of storm water with a peak throughput of 120 litres per second or more.
The construction of storm water management systems for the management of clean and dirty water around the coal stockpile. These systems will be sized to accommodate the 1:50 year flood and may thus exceed the 120 l/s peak flow.
11 The construction of channels and bridges where such construction occurs within a watercourse or within 32 metres of a watercourse, measured from the edge of a watercourse.
The construction of culverts, channels at river/stream crossings associated with the upgrade of the D 1770 and the new access road.
12 The construction of facilities or infrastructure for the off-stream storage of water, including dams and reservoirs, with a combined capacity of 50000 cubic metres or more, unless such storage falls within the ambit of activity 19 of Notice 545 of 2010;
Construction of a PCD with a capacity of approximately 51 230 cubic metres with a vertical wall height not exceeding 3 metres.
18 The infilling or depositing of any material of more than 5 cubic metres into, or the dredging, excavation, removal or moving of soil, sand, shells, shell grit, pebbles or rock of more than 5 cubic metres from a watercourse.
The construction of culverts, channels at river/stream crossings associated with the upgrade of the D 1770 and the new access road. This will result in the dredging or moving of 5 cubic meters of soil or more from two unnamed tributaries
22 The construction of a road, outside urban areas, with a reserve wider than 13,5 meters.
The construction of an access road with servitude ranging between 23 m and 150 m. The access road will be approximately 6.5 km long and intersecting with the existing D 1555 Road. The access road will accommodate both bi-directional and single directional traffic flow. The width of the access road will vary between an approximate 4 m and 8 m respectively. Further to the above the access road will be designed with a 1 m gravel shoulder on either side of the road.
47 The widening of a road by more than 6 metres, or the lengthening of a road by more than 1 kilometre where the existing reserve is wider than 13,5 meters.
The widening and upgrade the existing D 1770 Road by more than 6 metres to accommodate increased traffic load.
GN R545 5 The construction of facilities or infrastructure for any process or activity which requires a permit or license in terms of national or provincial legislation governing the generation or release of emissions,
The construction of a PCD requiring a water use license in terms of Section 21 of the NWA.
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Number and date of relevant notice
Activity No(s)
(in terms of the relevant notice)
Description of each listed activity as per the government notice and the detailed project description
Description of the proposed activities in relation to the listed activities being applied for
pollution or effluent and which is not identified in Notice No. 544 of 2010 or included in the list of waste management activities published in terms of Section 19 of the National Environmental Management: Waste Act, 2008 (Act No. 59 of 2008) (NEM: WA) in which case that Act will apply.
11 The construction of a railway lines, stations or shunting yards. The construction of a private railway siding of approximately 3.5 km in length. This distance includes the loading and run around lines.
19 Physical alteration of undeveloped, vacant or derelict land for residential, retail, commercial, recreational, industrial or institutional use where the total area to be transformed is 20 hectares or more.
The construction of:
A new Rietkuil Private Railway Siding of approximately 3.5 km in length;
A coal stockpile of approximately 54 000 tons;
A PCD with a capacity of approximately 51 230 cubic metres;
Other associated infrastructure including construction camps; and
The cumulative area is anticipated to exceed 20 hectares.
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Section 21
of the
NWA
Description of each listed activity as per the government notice and the detailed
project description
Siding and surface water runoff from the coal stockpile in the pollution control dam; and
using the waste water from the pollution control dam as dust suppression measure. These
activities will take place on the Portion 4 of the Farm Tweefontein, Farm No 458 JS.
21 (i) Altering the bed, banks, course or characteristics of a watercourse
Upgrading approximately 3 km of the provincial road D 1770, on Portions 9 and 10 of the
Farm Blyvooruitzicht, Farm No 383 JT, which will include the construction of a new culvert.
Constructing a new private access road of approximately 6.5 km, with culverts approximately
every 200m through the wetland area on the Portion 4 of the Farm Tweefontein, Farm No
458 JS, Portions 6 and 16 of the Farm Grootlaagte, Farm No 449 JS. This new access will
intersect with the existing D 1555 Road.
All activities taking place within 500m of a wetland or watercourse will be licensed under
Section 21 (j).
1.5.8 National Heritage Resources Act (Act No. 25 of 1998)
The protection and management of South Africa’s heritage resources are controlled by the
National Heritage Resources Act (Act No. 25 of 1999) (NHRA). The enforcing authority for this
act is the South African Heritage Resources Agency (SAHRA). In terms of the NHRA, historically
important features such as graves, trees, archaeology and fossil beds are protected. Similarly,
culturally significant symbols, spaces and landscapes are also afforded protection. In terms of
Section 38 of the NHRA, SAHRA can call for a Heritage Impact Assessment (HIA) where certain
categories of development are proposed. The Act also makes provision for the assessment of
heritage impacts as part of an EIA process and indicates that if such an assessment is deemed
adequate, a separate HIA is not required. Should a permit be required for the damage or
removal of specific heritage resources, Exxaro will submit a separate application for these
activities to the SAHRA for approval, should these resources be potentially damaged or removed.
The activities identified in the NHRA requiring notification to SAHRA include:
Section 38 states:
“(1) (a): The construction of a road, wall, power line, pipeline, canal or other similar form of linear development or barrier exceeding 300 m in length;
(c): Any development or other activity which will change the character of a site
i. exceeding 5 000 m² in extent ; or ii. involving three or more existing erven or subdivisions thereof ; or iii. involving three or more erven or divisions thereof which have been
consolidated within the past 5 years; or iv. the costs of which will exceed a sum in terms of regulations by
SAHRA or a provincial heritage resource authority.”
A HIA will be conducted as part of this project. The terms of reference for the HIA can be
found in Section 4.12.
1.5.9 Conservation of Agricultural Resources Act (Act No. 43 1983)
The Conservation of Agricultural Resources Act (Act No. 43 of 1983) (CARA) aims to provide for
control over the utilisation of natural agricultural resources in order to promote the conservation of
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
1.6 Legislative requirements
The content of this Draft EIAr complies with the requirements of Regulation 31 of GN R543 of 18
June 2010. The regulatory requirements can be found in the sections of the report indicated in
Table 1-8.
Table 1-8: Regulatory Requirements
Regulation Content Section of Report
GN R543
31(2)(a) Details of—
(i) the EAP who prepared the report; and
(ii) the expertise of the EAP to carry out scoping procedures.
Section 1.2
31(2)(b) A description of the proposed activity. Section 3
31(2)(c) A description of the property on which the activity is to be undertaken and the location of the activity on the property, or if it is—
(i) a linear activity, a description of the route of the activity; or
(ii) an ocean-based activity, the coordinates where the activity is to be undertaken;
Section 2.1.3
31(2)(d) Description of the environment that may be affected by the activity and the manner in which the physical, biological, social, economic and cultural aspects of the environment may be affected by the proposed activity
Section 4
31(2)(e) Details of the public participation process conducted in terms of sub-regulation (1), including—
Section 0
31(2)(e)(i) Steps undertaken in accordance with the plan of study Section 7.2
31(2)(e)(ii) A list of persons, organizations and organs of state that were
Registered as interested and affected parties;
Appendix D
31(2)(e)(iii) A summary of comments received from, and a summary of
Issues raised by registered interested and affected parties, the date of receipt of these comments and the response of the EAP to those comments; and
Appendix D
31(2)(e)(iv) Copies of any representations and comments received from registered interested and affected parties;
Appendix D
31(2)(f) A description of the need and desirability of the proposed activity
Section 3.1
31(2)(g) A description of identified potential alternatives to the proposed activity, including advantages and disadvantages that the proposed activity or alternatives may have on the environment and the community that may be affected by the activity;
Section 3.3
31(2)(h) An indication of the methodology used in determining the significance of potential environmental impacts
Section 5.2
31(2)(i) A description and comparative assessment of all alternatives identified during the environmental impact assessment process
Section 3.3
31(2)(j) A summary of the findings and recommendations of any specialist report or report on a specialized process
Section 5.3
31(2)(k) A description of all environmental issues that were identified during the environmental impact assessment process, an assessment of the significance of each issue and an indication of the extent to which the issue could be addressed by the adoption of mitigation measures;
Section 4
31(2)(l) An assessment of each identified potentially significant Section 5.3
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Regulation Content Section of Report
impact, including—
(i) cumulative impacts;
(ii) the nature of the impact;
(iii) the extent and duration of the impact;
(iv) the probability of the impact occurring;
(v) the degree to which the impact can be reversed;
(vi) the degree to which the impact may cause irreplaceable loss of resources; and
(vii) the degree to which the impact can be mitigated
31(2)(m) A description of any assumptions, uncertainties and gaps in knowledge
Section 5.1
31(2)(n) A reasoned opinion as to whether the activity should or should not be authorized, and if the opinion is that it should be authorized, any conditions that should be made in respect of that authorisation
Section 8
31(2)(o) An environmental impact statement which contains—
(i) a summary of the key findings of the environmental impact assessment; and
(ii) a comparative assessment of the positive and negative implications of the proposed activity and identified alternatives;
Section 8.2
31(2)(p) A draft environmental management programme containing the aspects contemplated in regulation 33;
Appendix E
31(2)(q) Copies of any specialist reports and reports on specialized processes complying with regulation 32
Appendix C
31(2)(r) Any specific information that may be required by the competent authority; and
N/A
31(2)(s) Any other matters required in terms of sections 24(4)(a) and (b) of the act.
N/A
2 Background Exxaro intends exporting a percentage of the coal mined at the proposed Belfast Coal Mine and
requires a suitable siding accessible to the existing coal line to RBCT. Therefore, Exxaro
undertook a number of studies to determine the viability and nature of the transport system and
infrastructure required for the railage of coal mined at their proposed Belfast Coal Mine.
Subsequently to these viability and feasibility studies Exxaro identified the need for them to
construct the proposed development south-west of the proposed Belfast Coal Mine.
The proposed development will be located parallel and north-west of the existing TFR Rietkuil
Station and situated within the existing Exxaro Arnot Coal Mine’s, Mining Right area. This
proposed development with associated infrastructure will cover a footprint of at approximately 45
hectares. It is proposed to construct a proposed development, a coal stockpile area, a storm
water management system, a PCD, the construction, upgrade and widening of access roads, the
construction, expansion and rectification of the culverts, and the construction of other associated
infrastructure.
2.1 Background of the project
2.1.1 Existing infrastructure
The only existing infrastructure associated with the activities proposed to take place is the
existing road network and railway infrastructure. No other infrastructure exists on the site where
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
the proposed private railway siding, the coal stockpile area, the storm water management system
and the PCD are proposed to be constructed. Further, existing road infrastructure will be
upgraded from unpaved to paved roads. The sections where the road upgrades are proposed
will be widened and culverts will be installed.
2.1.2 Existing approvals/authorisations
There are no active EAs associates with the site where the activities are proposed to take place.
2.1.3 Project Area Description
In terms of the administrative boundaries, the proposed project is located within the Mpumalanga
Province. The project is located within the Steve Tshwete and Emakhazeni Local Municipalities
of the Nkangala District Municipality. The proposed new Rietkuil Private Railway Siding and
associated infrastructure will be located within Ward 7 of the Steve Tshwete Local Municipality
with the upgrade of the D 1110 and the upgrade and widening of the D 1770 road located within
Wards 1 and 8 of the Emakhazeni Local Municipality. The towns, cities, and residential areas
close to the proposed project area are given in Table 2-1 with line-of-sight distances.
Table 2-1: Nearest Towns to the Proposed Development
Town Distance (km) Direction
Rietkuil 3.8 km South of the coal stockpile and private railway siding
Belfast 17 km North-east of the D 1770 and D 1110 road upgrades
Pullenshope 20 km West of the coal stockpile and private railway siding
Carolina 29 km South-east of the D 1770 and D 1110 road upgrades
Bankfontein 30 km North-west of the coal stockpile and private railway siding
Machadodorp 34 km North-east of the D 1770 and D 1110 road upgrades
Middleburg 34 km North-west of the coal stockpile and private railway siding
Emalahleni 52 km West of the coal stockpile and private railway siding
The proposed new Rietkuil Private Railway Siding and associated infrastructure will be located on
the farm portions listed in Table 2-2 and the table also provides a description of the activities
proposed to take place on each farm portion.
Table 2-2: List of Affected Farms and Farm Portions Illustrating the Relevant Activities
Farm Portions Proposed Activities
Arnot East 984 JS Farm is not subdivided
PCD and Access Road
Blesbokspruit 455 JS Portion 3 and 4 Upgrade of the D 1110 provincial road
Blyvooruitzicht 383 JT Portion 9 and 10 Upgrade of the D 1770 provincial road
Grootlaagte 449 JS Portions 6, and 16 Siding Access Road (and construction of culverts)
Kaalplaats 453 JS Portion 1, 4 and 5 Upgrade and widening of the D 1770 (and construction of culverts) provincial road and upgrade of the D 1110 provincial road
Leeuwbank 427 JS Portion 3 and 16 Upgrade of the D 1110 provincial road
Tweefontein 458 JS Portion 4 and the Remainder
Coal stockpile area, PCD, private railway siding and new access road (and construction of culverts)
Wonderfontein 428 JS Portion 19 Upgrade of the D 1110 provincial road
The proposed new Rietkuil Private Railway Siding and associated infrastructure is located
approximately 38 km southwest of the town of Belfast, approximately 38 km southeast of the
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
3 Project Description
3.1 Need and Desirability
In addition to the local sales of thermal coal to Eskom the proposed Belfast project aims to support
the strategic vision of Exxaro by increasing Exxaro Coal’s steam coal exports and thereby its share
of the South African coal market as well as extend the life of mine of the Exxaro North Block
Complex (NBC).
A percentage of coal mined by the proposed Belfast Coal Mine will be exported via the RBCT.
South Africa has substantial coal reserves and there is scope for expanding its coal exports, which
may in turn generate much needed export earnings which may reduce South Africa’s negative trade
balance and current account deficit (Eberhard, 2011). Coal exports remain a source of foreign
revenue for South Africa.
The upgrade of the D 1110 and the upgrade and widening of the D 1770 provincial road will be
required in order to allow a safe hauling route from the proposed Belfast Coal Mine to the proposed
private siding. The upgrade of these roads will further be required to minimise safety risks and
generation of noise and dust during construction and operational activities of the proposed
development.
3.2 Detailed Project Description
The proposed new Rietkuil Private Railway Siding and associated infrastructureis planned to be
located parallel and northwest of the existing TFR Rietkuil station within the existing Exxaro Arnot
Coal Mine’s Mining Right area. The proposed development will cover a footprint of approximately 45
hectares, on the farm portions listed in Section 2.1.3. A site layout plan is contained in Appendix A.
The proposed construction activities will include the following:
The construction of a private railway siding of approximately 3.5 km in length, this includes the loading and run around lines;
The establishment of a coal stockpile of approximately 54 000 tons, with associated operational facilities;
Construction of a PCD with a capacity of approximately 51 230 cubic metres (described in Section 3.2.2);
The construction of a storm water management system for the management of clean and dirty water around the coal stockpile. The coal loading platform slopes away from the railway track work with a slope of 2% (1:50). Surface run-off from the loading facility and adjacent access road is collected in a concrete lined drain on the northern edge of the coal loading platform. The contaminated run-off flows under gravity and passes through a silt trap into the PCD on the South Western boundary of the site. Clean surface run-off water is diverted from the dirty water catchment area by means of cut-off channels and berms (described in Section 3.2.3);
Upgrading of the provincial D 1110 and D 1770 roads and the construction of a new private access road (described in Section 3.2.4);
The construction, expansion and rectification of the culverts associated with the new private access road and the provincial road D 1770 at wetland/river/stream crossings (described in Section 3.2.5);
The construction of other associated infrastructure (below the legal thresholds/triggers) including, but not limited to, construction camps, a weighbridge, offices, an approximately 26 500 litre capacity self-bonded diesel storage tank, complete with a hydrocarbon separator, and an 11kV 3 phase power route with a 200 kVA 3 phase transformer to provide electricity to the site.
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Following the feasibility studies conducted for the proposed project, the location of the new Rietkuil Private Railway Siding at Rietkuil was deemed most preferable as the facilities will be in close proximity to the existing RBCT line and adjacent to an existing private railway siding.
Exxaro Glisa Siding at Belfast;
The Glisa site was eliminated at basic feasibility stage due to site congestion and the operational complexity of serving the site (shunting and train movements).
Transfer Freight Rail at Wonderfontein;
The TFR Wonderfontein site was eliminated on the basis of environmental and access constraints surfaced during previous attempts to activate this facility.
No location alternatives for the coal stockpile was assessed as the coal stockpile must be located in
close proximity to the private railway siding.
No alternatives for the road upgrades of the D 1110 and D 1770 to accommodate the hauling to and
from the proposed Belfast Coal Mine have been assessed. The existing gravel roads will be
upgraded to paved roads which will reduce the generation of dust and increase the safety of road
users.
No alternatives were considered for the construction of the new private access road from the
proposed new Rietkuil Private Railway Siding to the intersection of the D 1550 as all environmental
sensitivities were considered during the feasibility study and specialist studies conducted for this
project.
3.3.2 Technology Alternatives
Linear Railway Siding and Coal Stockpile Area (Preferred Technology Alternative)
The linear railway siding will consist of a loading and run around railway line parallel to the existing
rail network in a disturbed and transformed area with no environmental sensitivities. The
construction of a linear railway siding will result in a reduced footprint thereby minimising the
anticipated biophysical, social and cultural impacts in the immediate vicinity. Loading of coal onto
empty waggons will be done through the use of front end loaders. Loading by means of front end
loaders will prolong the loading time compared to the use of a balloon siding where conveyors are
utilised for the loading of coal onto the empty waggons. However, the use of front end loaders will
increase the employment opportunities during the operation phase of proposed facility.
Balloon Railway Siding (Technology Alternative 1)
The balloon railway siding will result in a railway loop being constructed to the north of the coal
stockpile area. The balloon siding will utilise conveyors for the loading of coal onto the empty
waggons from storage silos. A balloon type siding will reduce the loading time of empty waggons.
However, this would entail larger disturbance footprint to accommodate the silos, the conveyors and
railway line. It was concluded by the specialist studies that the area where the proposed
balloon railway siding could be accommodated comprise of environmental sensitivities,
wetlands and the spoor of the Parahyaena brunnea (Brown Hyaena) that was found in the
area. This proposed alternative is not regarded as viable or feasible to the applicant and the
impacts will not be further assessed in this report.
3.3.3 ‘No-Go’ Alternative
It is envisaged that the proposed Belfast Coal Mine will mine approximately 2.2 million tons coal per
annum. Exxaro intends to increase its coal exports and a percentage of the coal mined by the
proposed Belfast Coal Mine will be exported via the proposed new Rietkuil Private Railway Siding to
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
least equal to the current national average for these crops, or is currently being irrigated successfully.
Criteria for Grazing
Land
Land, which does not qualify as wetland or arable land;
Has soil, or soil-like material, permeable to roots of native plants, that is more than 250-mm thick and contains less than 50 % by volume of rocks or pedocrete fragments larger than 100-mm;
Supports, or is capable of supporting, a stand of native or introduced grass species, or other forage plants, utilizable by domesticated livestock or game animals on a commercial basis.
Criteria for
Wilderness Land
Land, which does not qualify as wetland, arable land or grazing land.
Based on this system, the soil and land types identified in the study area could all be classified into
three different land capability classes. Deeper soils of the Hutton, Pinedene, and Bloemdal forms
have arable land capabilities which are suitable for dryland crop production. The Glencoe soil form
has grazing land capability. The Katspruit, Kroondal, Longlands and Willowbrook soil forms (6.72 ha
or 9.59% of the study site) have wetland land capability. Figure 4-4, Figure 4-5, Figure 4-6, Figure
4-7 and Figure 4-8 depicts the land use capability of the area.
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
RIETKUIL PRIVATE RAILWAY SIDING AND ASSOCIATED
INFRASTRUCTURE Project No.
467209
Figure 4-8: Land capability map of the proposed new Rietkuil Private Railway Siding Pollution Control Dam and Coal Loading Facility development footprint area
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
The prevailing ambient noise levels in the different areas within the study area demonstrated
that there is already a disturbance from non-residential activities such as existing train
activities, ventilation shaft noise, conveyor activities, hauling activities and traffic to which the
people living in the vicinity of these point and line sources are exposed to. There is at times
an increase of the prevailing ambient noise levels due to traffic which make use of the gravel
road and along the railway line. During seasonal agricultural activities there will be an
increase in the prevailing ambient noise level in and around the noise sensitive areas near
crops. Table 4-10 illustrates the distance in meters between proposed siding, haul road and
the noise sensitive areas. The noise level along a section of the N4 road is normal for this
type of road with a constant flow of traffic during the day and night periods. The existing
feeder roads are existing gravel roads which will be upgraded and tarred whereas the other
feeder roads are already tarred surfaces. There will be an increase in the traffic volume along
these roads which will create a finite type increase after which the prevailing ambient noise
level will be maintained.
The noise at the proposed new Rietkuil Private Railway Siding and associated infrastructure
can however be controlled by means of approved acoustic screening measures, state of the
art equipment, proper noise management principles and compliance to the Local Noise
Control Regulations, and the International Finance Corporation’s Environmental Health and
Safety Guidelines.
4.10.1 Existing Road Network
The existing external road that might be directly affected by new traffic generated is listed in
Table 4-11 below.
Table 4-11: Overview of the Existing Road Network and Jurisdiction
Road Link
Jurisdiction Class
of road
Function of the Road
Road Surfacing Cross Section
(Typical Width of the road)
N4 SANRAL C1 The road is an east-west, Provincial Class 1 national road. The N4 Road connects Komatipoort border post with Lobatsi border post.
The road is paved and the surface condition is good*.
Dual carriageway (4 lanes: two lanes per direction) with median and turning lanes at intersections.
D1110 Mpumalanga Department of Roads and Transport (MDRT)
R2 The road is a north-south, Provincial Class 2 rural road with a collector-distributor function. The D1110 Road connects the N4 Road with the D1770 Road.
The road is a gravel road and the surface condition is fairly adequate**.
Single carriageway (2 lanes: one lane per direction)
D1770 MDRT R2 The road is an east-west, Provincial Class 2 rural road with a collector-distributor function. The D1770 Road connects the D1110 Road with the N4 Road.
The road is a gravel road and the surface condition is fairly adequate**.
Single carriageway (2 lanes: one lane per direction)
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Road Link
Jurisdiction Class
of road
Function of the Road
Road Surfacing Cross Section
(Typical Width of the road)
D1555 MDRT R2 The road is an east-west, Provincial Class 2 rural road with a collector-distributor function. The D1555 Road connects the R104 Road with the D383 Road.
The road is a paved road and the surface condition is good*.
Single carriageway (2 lanes: one lane per direction), with gravel shoulders
D383 MDRT R2 The road is a north-south, Provincial Class 2 rural road with a collector-distributor function. The D383 Road connects the P15-1 Road with the N4 Road.
The road is a paved road and the surface condition is good*.
Single carriageway (2 lanes: one lane per direction), with gravel shoulders
P15-1 MDRT R2
The road is a north-south, Provincial Class 2 rural road with a collector-distributor function. The P15-1 Road connects the N4 Road with the D383 Road.
The road is a paved road and the surface condition is good*.
Single carriageway (2 lanes: one lane per direction), with gravel shoulders
“Good” = road maintenance standard, include surface of road, sight distance, road signs, road markings, driver experience, etc.
“Fairly adequate” = require road maintenance, improvement of road markings, road signs, surfacing, driver experience less than freeway, etc.
4.10.2 Existing Rail Network
Transnet has a major rail line located north of the N4 Road. This railway line is part of the
national major rail network between Komatipoort and Gauteng. The main focus of this
existing railway line is on transporting main commodities like coal, iron and passengers. The
railway line feeds large volumes of bulk traffic into and through Mpumalanga area. The
nearest railway station to the proposed Belfast Coal Mine is Wonderfontein and Rietkuil
Stations.
4.10.3 Area of Influence
As mentioned in Section 4.10.1 above, the following external link roads might be directly
affected by new traffic generated by the proposed Belfast Coal Mine development:
N4 Road;
D1110 Road;
D1770 Road;
P15-1 Road;
D383 Road;
D1555.
The area of influence area for this study was determined by the locality of the site and based
on the proposed Belfast Coal Mine transport needs (origins and destination).
The following intersections have been investigated as part of the Traffic Impact Assessment:
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
industry boundaries can also only be effectively addressed at Provincial and National
Government levels.
The environmental impact assessment section of the report outlined the potential impacts
identified by the respective specialists. These impacts were given a significance rating before
and after implementation of the mitigation measures. The impact after mitigation measures
(residual impacts) were combined with the impact before mitigation measures (initial impacts)
to describe the cumulative impact to the environment.
5.3.1 Pre-construction phase
No impacts are anticipated to take place during the pre-construction phase of the project.
5.3.2 Construction phase
The following impacts are anticipated to occur during the construction phase of the Rietkuil
private railway siding project:
Biodiversity (Fauna & Flora)
It is anticipated that construction of the proposed new Rietkuil Private Railway Siding and
associated infrastructure will have a ‘Low’ to ‘Low-Medium’ impact on the ecological receiving
environment post implementation of the recommended mitigation measures. A complete list
of the floral species, South African threatened RDL species (including Invertebrates,
Amphibians, Reptile, Avifaunal, Mammalian) and the potentially occurring faunal species are
included in Appendix E as part of the EMPr. Adequate recommendations were included in
the specialist study to mitigate impacts on the receiving environment. These
recommendations and mitigation measures form part of the EMPr.
Table 5-5: Impacts on Habitat for Floral Species
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
3 2 5 5 3 80 Medium-
High
Key management measures:
The boundaries of the development footprint areas are to be clearly defined and it should be ensured that all activities remain within defined footprint areas and that no vegetation is cleared outside the development footprint area.
Edge effects of all construction and operational activities, such as erosion and alien plant species proliferation, which may affect flora habitat, need to be strictly managed.
Vehicles should be restricted to travelling only on designated roadways to limit the ecological footprint of the proposed Rietkuil Private Railway Siding development activities.
It must be ensured that construction related waste or spillage and effluent do not affect the immediate and surrounding habitat boundaries.
Proliferation of alien and invasive species is expected within any disturbed areas. These species should be eradicated and controlled to prevent their spread beyond the development footprint areas. Alien plant seed dispersal within the top layers of the soil within footprint areas, has to be controlled.
Recommended mitigation measures:
All soils compacted as a result of construction activities falling outside of development footprint areas should be ripped and profiled. Special attention should be paid to alien and invasive control within these areas. Alien and invasive vegetation control should take place throughout all development phases including rehabilitation phases to prevent loss of floral habitat in surrounding areas.
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
management
Status (+/-) Low (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Table 5-6: Impacts on Flora Diversity
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration
Frequency of Activity
Frequency of Impact
Impact before management
3 2 5 4 2 60 Low-
Medium
Key management measures:
All development footprint areas and areas affected by the proposed Rietkuil Private Railway Siding development should remain as small as possible and should not encroach onto surrounding areas. It must be ensured that these areas are off-limits to construction vehicles and personnel to prevent impacts on vegetation.
Removal of the alien and weed species encountered on the property must take place in order to comply with existing legislation (amendments to the regulations under the Conservation of Agricultural Resources Act, 1983 and Section 28 of the National Environmental Management Act, 1998, and the National Environmental Management: Biodiversity Act, 2004). Removal of species should take place throughout the construction, operational and rehabilitation/ maintenance phases.
Species specific and area specific eradication recommendations:
o Care should be taken with the choice of herbicide to ensure that no additional impact and
loss of indigenous plant species occurs due to the herbicide used.
o Footprint areas should be kept as small as possible when removing alien plant species.
Informal fires in the vicinity of development area should be prohibited during all development phases.
Recommended mitigation measures:
It must be ensured that all roads and construction areas are regularly sprayed with water in order to curb dust generation. This is particularly necessary during the dry season when increased levels of dust generation can be expected. These areas should not be over-sprayed causing water run-off and subsequent sediment loss in the vicinity of the study area.
Impact after management
2 1 3 3 2 30 Low
Status (+/-) Low (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Table 5-7: Impacts on Flora Species of Conservation concern
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
3 3 5 2 2 44 Low
Key management measures:
All proposed Rietkuil Private Railway Siding development footprint areas and areas affected by the proposed development should remain as small as possible and should not encroach onto surrounding areas. It must be ensured that these areas are off-limits to construction vehicles and personnel.
Recommended mitigation measures:
Should any RDL or protected flora species, be encountered within study area, the following should be ensured:
If any threatened species, or nationally or provincially protected flora will be disturbed, ensure effective relocation of individuals to suitable similar habitat. Arrangement with the relevant authorities needs to take place to rescue and relocate the species.expected. These areas should not be over-sprayed causing water run-off and subsequent sediment loss in the vicinity of the study area.
Impact after management
2 2 5 2 2 36 Low
Status (+/-) Low (-)
Cumulative impact
The cumulative impact of the current activities and the future activities will not increase the impact rating from a Low Impact as rated in the initial impact assessment
Based on the above assessment it is evident that there are three possible impacts on the
floral ecology within the study area. In the consideration of mitigation it is assumed that a
high level of mitigation takes place but which does not lead to prohibitive costs. From the
abovementioned tables it is evident that prior to management measures being put in place,
one Medium-High, one Medium-Low and one Low significance impact is likely. If effective
management takes place, all impacts could be reduced to low significance impacts.
Table 5-8: Impacts on Faunal Habitat
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
4 3 5 5 3 96 Medium-
High
Key management measures:
All development footprint areas should remain as small as possible and should not encroach onto surrounding undisturbed and natural areas. It must be ensured that these areas are off-limits to construction vehicles and personnel.
If it is absolutely unavoidable that wetlands will be impacted, especially during bridge construction, disturbance to any wetland crossings must be minimised and suitably rehabilitated.
It must be ensured that any wetland crossings allow fauna species to continue to migrate through the wetlands which act as migratory corridors.
In the event of a breakdown, maintenance of vehicles must take place with care and the recollection of spillage should be practiced near the surface area to prevent ingress of hydrocarbons into topsoil.
Vehicles should be restricted to travelling only on designated roadways to limit encroachment in the study area and onto adjacent habitats.
Recommended mitigation measures:
Demarcation of construction footprints should be considered.
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Rehabilitate all fauna habitat areas to ensure that the faunal ecology is re-instated.
Impact after management
2 2 5 4 3 56 Low-
Medium
Status (+/-) Low-Medium (-)
Cumulative impact:
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Table 5-9: Impacts on Faunal Diversity
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
4 3 5 4 3 84 Medium-
High
Key management measures:
No trapping or hunting of fauna is to take place.
All development footprint areas should remain as small as possible and should not encroach onto surrounding sensitive wetland areas. It must be ensured that these areas are off-limits to construction vehicles and personnel.
It must be ensured that any wetland crossings allow fauna species to continue to migrate through the wetlands which act as migratory corridors.
Vehicles should be restricted to travelling only on designated roadways to limit the ecological footprint of the proposed Rietkuil Private Railway Siding development activities
Impact after management
3 2 3 3 3 48 Low-
Medium
Status (+/-) Low-Medium (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Table 5-10: Impact on RDL and Protected Fauna Species
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
3 3 3 2 2 45 Low
Key management measures:
Erect roadside signs warning motorists of potential RDL bird species, especially at wetland crossings.
All development footprint areas should remain as small as possible and should not encroach onto surrounding sensitive wetland areas. It must be ensured that these areas are off-limits to construction vehicles and personnel.
If it is absolutely unavoidable that wetlands will be affected, disturbance to any wetland crossings must be minimised and suitably rehabilitated.
It must be ensured that any wetland crossings allow fauna species to continue to migrate through the wetlands which act as migratory corridors.
Vehicles should be restricted to travelling only on designated roadways to limit the ecological footprint of the proposed construction activities.
No trapping or hunting of fauna is to take place. Access control into more sensitive habitat areas
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
must be implemented to ensure that no illegal trapping or poaching takes place.
Should any RDL species be encountered within the study area, these species should be monitored and if required, relocation of these species to similar habitat within or in the vicinity of the study area with the assistance of a suitably qualified specialist must be considered.
Recommended mitigation measures
Rehabilitate all fauna habitat areas to ensure that faunal ecology is re-instated during all phases.
Impact after management
3 3 3 2 2 36 Low
Status (+/-) Low (-)
Cumulative impact
The cumulative impact of the current activities and the future activities will not increase the impact rating from a Low Impact as rated in the initial impact assessment
Based on the above assessment it is evident that there are three possible impacts on the
faunal ecology within the study area. From the tables above it is evident that if effective
management takes place, all potential faunal impacts may be reduced.
Wetlands
It is anticipated that construction of the proposed new Rietkuil Private Railway Siding and
associated infrastructure will have a ‘Low’ to ‘Low-Medium’ impact on the wetlands post
implementation of the recommended mitigation measures. This will ensure that the wetland
ecology of the proposed construction areas as well as surrounding areas are being protected
or adequately rehabilitated in order to minimize impacts on the wetlands. Adequate
recommendations were included in the specialist study to mitigate impacts on the wetlands.
These recommendations and mitigation measures form part of the EMPr.
Table 5-11: Impacts on Loss of Wetland Habitat and Ecological Structure
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
3 4 5 5 3 96 Medium-
High
Essential mitigation measures:
All development footprint areas should remain as small as possible and should, ideally, not encroach onto wetland areas.
If it is absolutely unavoidable that wetlands will be affected, especially during bridge or culvert construction, disturbance to any wetland crossings must be minimised and suitably rehabilitated. The design of such culverts / bridges should allow for wetland soil conditions to be maintained both upstream and downstream of the crossing to such a degree that wetland vegetation community structures upstream and downstream of the crossing are maintained. In this regard, special mention is made of:
o The design of such culverts and/or bridges should ensure that the permanent wetland
zone should have inundated soil conditions throughout the year extending to the soil
surface.
o The design of such culverts and/or bridges should ensure that the seasonal wetland zone
should have water-logged soils within 300mm of the soil surface at all times.
o Temporary wetland zone areas should have waterlogged soil conditions occurring to
within 300m of the land surface during the summer season.
Ensure that no incision and canalisation of the wetland system takes place as a result of the
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
construction of the culverts.
It must be ensured that flow connectivity along the wetland features is maintained.
Re-profiling of the banks of disturbed wetland areas.
Reinforce banks and drainage features where necessary with gabions, reno mattresses and geotextiles.
It must be ensured that all hazardous storage containers and storage areas comply with the relevant SABS standards to prevent leakage. All vehicles must be regularly inspected for leaks. Re-fuelling must take place on a sealed surface area to prevent ingress of hydrocarbons into topsoil.
All spills should be immediately cleaned up and treated accordingly.
Appropriate sanitary facilities must be provided and all waste removed to an appropriate waste facility.
Implement alien vegetation control program within wetland areas.
Monitor all systems for erosion and incision.
Recommended mitigation measures
Restrict construction to the drier winter months if possible to avoid sedimentation of wetland features in the vicinity of the proposed mine development areas.
Re-vegetate all disturbed areas with indigenous wetland species
Impact after management
3 3 2 2 5 54 Low-
Medium
Status (+/-) Low-Medium (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Table 5-12: Changes to Wetland Ecological and Sociocultural Service provision
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
4 4 5 4 3 91 Medium-
High
Essential mitigation measures:
If it is absolutely unavoidable that wetlands will be affected, especially during bridge construction, disturbance to any wetland crossings must be minimised and suitably rehabilitated.
It must be ensured that flow connectivity along the wetland features is maintained.
Re-profiling of the banks of disturbed wetland areas.
Reinforce banks and drainage features where necessary with gabions, reno mattresses and geotextiles.
Monitor all systems for erosion and incision.
Edge effects of activities including erosion and alien / weed control need to be strictly managed in the wetland areas.
As much vegetation growth as possible should be promoted within the wetland areas in order to protect soils. In this regard, special mention is made of the need to use indigenous vegetation species where hydroseeding, wetland and rehabilitation planting (where applicable) are to be implemented.
Implement alien vegetation control program within wetland areas associated with the proposed development.
Recommended mitigation measures:
Restrict construction to the drier winter months if possible to avoid sedimentation of wetland features in the vicinity of the proposed development areas.
Re-vegetate all disturbed areas with indigenous wetland species.
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact after management
2 3 5 3 3 60 Low-
Medium
Status (+/-) Low-Medium (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Table 5-13: Impacts on Wetland Hydrological Function
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
4 4 5 4 3 91 Medium-
High
Essential mitigation measures:
The boundaries of development footprint areas are to be clearly defined and it should be ensured that all activities remain within these defined areas.
If it is absolutely unavoidable that wetlands will be affected, especially during construction, disturbance to any wetland crossings must be minimised and suitably rehabilitated.
It must be ensured that flow connectivity along the wetland features is maintained.
Re-profiling of the banks of disturbed wetland areas.
Reinforce banks and drainage features where necessary with gabions, reno mattresses and geotextiles.
All vehicles should remain on designated roads with no indiscriminate driving through area.
Rehabilitate the wetland zone to ensure that the watercourse functions are re-instated.
Implement alien vegetation control program within wetland areas.
Recommended mitigation measures:
Revegetate all disturbed areas with indigenous wetland species.
Impact after management
2 2 5 2 3 45 Low
Status (+/-) Low (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Based on the above assessment it is evident that there are three possible impacts that may
affect the wetland ecology of the study area. In the consideration of mitigation it is assumed
that a high level of mitigation takes place but which does not lead to prohibitive costs. From
the tables above it is evident that prior to mitigation all of the impacts are medium-high level
impacts. If mitigation and effective management takes all impacts will be reduced to a low
level.
Soils, Land Use and Land Capability
Land use after decommissioning should aim to re-establish the cattle farming and crop
production potential of the land. No serious soil chemical issues such as soil salinity or
sodicity occur on site.
It is anticipated that proposed construction of the proposed new Rietkuil Private Railway
Siding and associated infrastructure will have a ‘Low’ to ‘High’ impact on the soils, land use
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
and land capability post implementation of the recommended mitigation measures. Adequate
recommendations were included in the specialist study to mitigate impacts on the receiving
environment. These recommendations and mitigation measures form part of the EMPr.
Table 5-14: Impacts Relating to Soil Compaction
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
5 4 4 3 5 108 High
Mitigation measures:
When stripping machinery is used for stripping, stockpiling and ‘topsoiling’ operations, it should operate when the soil moisture content is below approximately 8 % (during the dry winter months) in order to limit soil compaction and machinery getting stuck.
For use on site, tracked vehicles are more desirable than wheeled vehicles due to their lower point loading and slip, while vehicle speed should be maintained in order to reduce the duration of applied pressure, thereby minimizing compaction.
The width of the levelled or disturbed area for haul roads must be minimized as much as possible. Unnecessary dirt tracks (outside of the area to be disturbed) should be avoided during the construction of the haul road.
Impact beyond the site boundary can be reduced by using existing roads and reducing new roads to a minimum.
Impact after management
2 3 5 4 4 80 Medium-
High
Status (+/-) Medium-High (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Table 5-15: Impacts Relating to Soil Erosion
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
4 3 5 5 4 108 High
Mitigation measures:
Stripping of topsoil should not be conducted earlier than required (maintain grass cover for as long as possible) in order to prevent the erosion (wind and water) of organic matter, clay and silt.
Stripped soils should be stockpiled as a berm upslope (majority) and surrounding the disturbed area.
Soil stockpiles must be sampled, ameliorated (fertilized) and re-vegetated as soon after construction as possible. This is in order to limit raindrop and wind energy, as well as to slow and trap runoff, thereby reducing soil erosion. Grassland and shrub species indigenous to the area are preferred, given both their hardy nature as well as their lower maintenance requirements.
The soils stripped for levelling purposes must be stockpiled as a berm along the entire length of haul roads (upslope).
Erosion control measures such as intercept drains and toe berms must be constructed where necessary.
Gravel roads must be well drained in order to limit soil erosion.
The vegetative (grass) cover on the soil stockpiles (berms) must be continually monitored in order to maintain a high basal cover. Such maintenance will limit soil erosion by both the mediums of water (runoff) and wind (dust).
The layered haul road drainage system and surface must be well maintained in order to limit soil erosion
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact after management
2 3 4 4 4 72 Low-
Medium
Status (+/-) Low-Medium (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Table 5-16: Impacts Associated With the Sterilization of Topsoil Layer
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
4 3 4 5 5 110 High
Mitigation measures:
The measurable effect of the construction and operational phase on this resource and the likeliness of preventing or reducing the effect by utilizing mitigation measures are negligible
Impact after management
4 3 4 5 5 110 High
Status (+/-) High (-)
Cumulative impact
Even with the implementation measurable effect of the construction and operational phase on this resource and the likeliness of preventing or reducing the effect by utilizing mitigation measures are negligible. The cumulative effect of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially as the area is transformed and already impacted upon.
Table 5-17: Impacts associated with Chemical Soil Pollution
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
4 3 4 5 5 110 High
Mitigation measures:
An intercept drain should be constructed upslope of construction and operational areas, in order to re-direct clean water away to avoid soil chemical pollution to clean groundwater resources.
An intercept drain should possibly be constructed downslope of polluted areas, in order to drain potentially polluted water into a pollution control dam.
Drains and intercept drains should be maintained to ensure that it continue to redirect clean water away from the polluted areas.
Conduct proper chemical waste management to avoid spillage of chemicals during all the phases of the project cycle.
Impact after management
3 1 3 2 3 35 Low
Status (+/-) Low (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Table 5-18: Impacts on the loss of current Land Capability
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
2 3 5 5 5 100 High
Mitigation measures:
Although the stockpiles will be re-vegetated, it is not anticipated that areas where arable land capability was lost will be remediated to such an extent that the land capability will return. At most, the site will be rehabilitated to grazing land capability. However, it is still recommended that the natural vegetation be re-established once the coal loading operations have ceased and that the grazing capacity is restored as good as possible. Should the land capability be re-established, the impact after mitigation is considered to be medium-low
Impact after management
2 3 4 4 4 72 Low-
Medium
Status (+/-) Low-Medium (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Surface and Groundwater
The surface water impact of the construction of the proposed new Rietkuil Private Railway
Siding and associated infrastructure will be limited as the area impacted represents a loss off
catchment of less than 1%, therefore the loss of runoff from this catchment is not likely to
significantly impact flows in the Bosmanspruit. The proposed construction of the proposed
new Rietkuil Private Railway Siding and associated infrastructurewill not impact negatively on
the surface and groundwater quality of the receiving environment. Adequate
recommendations were included in the specialist study to mitigate impacts on the receiving
environment. These recommendations and mitigation measures form part of the EMPr. It is
anticipated that proposed construction of the proposed new Rietkuil Private Railway Siding
and associated infrastructure will have a ‘Very Low’ to ‘Low-Medium’ impact on the surface
and groundwater post implementation of the recommended mitigation measures. Adequate
recommendations were included in the specialist study to mitigate impacts on the receiving
environment. These recommendations and mitigation measures form part of the EMPr.
Table 5-19: Surface and Groundwater Related Impacts
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
4 3 4 5 4 99 Medium-
High
Mitigation measures:
Remove seepage with drains, channels, toe paddocks to pollution control dam, contain dirty water and reduce infiltration with stormwater control. Re-use dirty water
Impact after management
2 2 4 5 4 72 Low-
Medium
Change in catchment runoff
Impact before management
2 3 4 4 3 63 Low-
Medium
Mitigation measures:
Separate clean water from dirty water. Divert clean water to natural water courses.
Impact after management
1 2 4 4 3 49 Low
Erosion
Impact before management
2 2 2 4 4 48 Low
Mitigation measures:
Construct gabions to prevent erosion
Impact after management
1 1 2 3 3 24 Very Low
Status (+/-) Low-Medium to Very-Low (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Heritage
The construction of the proposed new Rietkuil Private Railway Siding and associated
infrastructure will not impact negatively on the cultural, heritage and archaeological nature of
the receiving environment. Adequate recommendations were included in the specialist study
to mitigate impacts on the receiving environment. It is anticipated that construction of the
proposed new Rietkuil Private Railway Siding and associated infrastructure will have a ‘Very
Low’ impact on heritage resources post implementation of the recommended mitigation
measures. Adequate recommendations were included in the specialist study to mitigate
impacts on the receiving environment. These recommendations and mitigation measures
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
The site is located peripheral
Impact after management
1 2 2 2 1 15 Very Low
Status (+/-) Very-Low (-)
Cumulative impact
The cumulative impact of the current activities and the future activities will not increase the impact rating from a Low Impact as rated in the initial impact assessment
Traffic
Based on the findings of the Traffic Impact Assessment conducted for proposed new Rietkuil
Private Railway Siding and associated infrastructure it is evident that the traffic volumes
generated by the proposed Belfast Coal Mine development will not have a significant impact
on the external road network. However, the interaction (turning movements) between public
transport and privates vehicles might impose some safety hazardous to the vehicles drivers.
It is anticipated that the proposed construction of the proposed new Rietkuil Private Railway
Siding and associated infrastructure will have a ‘Low-Medium’ impact on traffic post
implementation of the recommended mitigation measures. Adequate recommendations were
included in the specialist study to mitigate traffic related impacts. These recommendations
and mitigation measures form part of the EMPr.
Table 5-21: Traffic Related Impacts
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Gravel access roads of approximately 9km; D1110 & D1770
Impact before management
4 4 5 5 5 130 Very High
Mitigation measures:
Surfacing of D1110 Road and D1770 Road between the N4 Road / D1110 Road intersection and the access to the Belfast mine approximately 13km.
Ensure that the existing lighting at the intersections of the N4 Road / D1110 Road and N4 Road / P15-1 are at sufficient standards to improve safety.
No on-street pick up/drop off’s at the intersections of the D1110 and D1770 Roads and the access to the mine should be allowed (drop-offs / pickup should be done on site).
Impact after management
2 3 4 1 5 54 Low-
Medium
D1110 / D1770 Intersection
Impact before management
4 4 5 5 5 130 Very High
Mitigation measures:
Surfacing of D1110 Road and D1770 Road between the N4 Road / D1110 Road intersection and the access to the Belfast mine approximately 13km.
Ensure that the existing lighting at the intersections of the N4 Road / D1110 Road and N4 Road / P15-1 are at sufficient standards to improve safety.
No on-street pick up/drop off’s at the intersections of the D1110 and D1770 Roads and the access to the mine should be allowed (drop-offs / pickup should be done on site).
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact after management
2 3 4 1 5 54 Low-
Medium
N4 Road / D1110 Road Intersection (safety)
Impact before management
4 4 5 5 5 130 Very High
Mitigation measures:
Surfacing of D1110 Road and D1770 Road between the N4 Road / D1110 Road intersection and the access to the Belfast mine approximately 13km.
Ensure that the existing lighting at the intersections of the N4 Road / D1110 Road and N4 Road / P15-1 are at sufficient standards to improve safety.
No on-street pick up/drop off’s at the intersections of the D1110 and D1770 Roads and the access to the mine should be allowed (drop-offs / pickup should be done on site).
Impact after management
2 3 4 1 5 54 Low-
Medium
New access road between Rietkuil Station and D1550 Road
Impact before management
2 3 4 1 5 54 Low-
Medium
Mitigation measures:
Surfacing of D1110 Road and D1770 Road between the N4 Road / D1110 Road intersection and the access to the Belfast mine approximately 13km.
Ensure that the existing lighting at the intersections of the N4 Road / D1110 Road and N4 Road / P15-1 are at sufficient standards to improve safety.
No on-street pick up/drop off’s at the intersections of the D1110 and D1770 Roads and the access to the mine should be allowed (drop-offs / pickup should be done on site).
Impact after management
2 3 4 1 5 54 Low-
Medium
Status (+/-) Low-Medium (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Noise
The construction of the proposed new Rietkuil Private Railway Siding and associated
infrastructure will not impact negatively on the noise quality of the receiving environment. It is
anticipated that proposed construction of the proposed new Rietkuil Private Railway Siding
and associated infrastructure will have a ‘Very-Low’ to ‘Low’ noise impact post implementation
of the recommended mitigation measures. Adequate recommendations were included in the
specialist study to mitigate impacts on the receiving environment. These recommendations
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
acoustically screened off;
Baseline noise monitoring (EMPr).
Impact after management
1 2 3 3 1 24 Very-Low
Upgrade of the existing gravel roads between the railway siding and the Belfast
Impact before management
2 3 2 4 2 48 Low
Mitigation measures:
Machinery with low noise levels to be used;
Vehicles with low noise levels to be used;
Construction activities to take place during daytime period only;
Generators must be placed in such a manner that it is away from noise sensitive areas or acoustically screened off;
Baseline noise monitoring (EMPr).
Impact after management
1 2 3 3 1 24 Very-Low
Diesel emergency generators.
Impact before management
2 3 2 4 2 48 Low
Mitigation measures:
Machinery with low noise levels to be used;
Vehicles with low noise levels to be used
Construction activities to take place during daytime period only; and
Generators must be placed in such a manner that it is away from noise sensitive areas or acoustically screened off.
Baseline noise monitoring (EMPr)
Impact after management
1 2 3 3 1 24 Very-Low
Status (+/-) Very-Low (-)
Cumulative impact
The cumulative impact of the current activities and the future activities will not increase the impact rating from a Low Impact as rated in the initial impact assessment
Socio-economic
It is anticipated that the proposed development will contribute to the local employment market
through the creation of various temporary and permanent employment opportunities. The
proposed development could also contribute to the potential generation of export earnings for
South Africa and contribute towards reducing South Africa’s negative trade balance and
current account deficit, whilst being a source of foreign revenue.
Table 5-23: Creation of Temporary Employment Opportunities
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
No mitigation measures are recommended.
Impact after management
2 1 1 4 1 80 Medium-
High
Status (+/-) Medium-High (+)
Cumulative impact
The cumulative impacts of the construction of the Rietkuil private railway project will result in indirect impacts such as local economic contribution/expenditure and it as a result the impact will be a larger positive impact on the environment that was assessed initially.
Table 5-24: Creation of permanent Employment Opportunities
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
2 3 2 1 5 42 Low
No mitigation measures are recommended.
Impact after management
2 1 1 4 1 80 Medium-
High
Status (+/-) Medium-High (+)
Cumulative impact
The cumulative impacts of the construction of the Rietkuil private railway project will result in indirect impacts such as local economic contribution/expenditure and it as a result the impact will be a larger positive impact on the environment that was assessed initially.
5.3.3 Operational phase
In addition to the abovementioned impacts the following additional impacts are anticipated to
occur during the operational phase of the Rietkuil private railway siding project:
Surface and Groundwater
Table 5-25: Surface and Groundwater
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact on groundwater quality (Leachate seeping from coal loading bay to underlying aquifers)
Impact before management
2 3 4 4 4 72 Low-
Medium
Mitigation measures:
Compact base, clay lining, remove seepage with drains to pollution control dam, contain dirty water with stormwater control.
Impact after management
1 2 4 4 3 49 Low
Impact on groundwater quality (Leachate seeping from pollution control dam to underlying aquifers)
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
2 2 2 4 4 48 Low
Mitigation measures:
Construct gabions to prevent erosion.
Impact after management
1 1 2 3 3 24 Very Low
Status (+/-) Very-Low (-)
Cumulative impact
The cumulative impact of the current activities and the future activities will not increase the impact rating from a Low Impact as rated in the initial impact assessment
Traffic
Table 5-26: Traffic Related Impacts
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Gravel access roads of approximately 9km; D1110 & D1770
Impact before management
2 3 4 1 5 54
Very High
Mitigation measures:
Surfacing of D1110 Road and D1770 Road between the N4 Road / D1110 Road intersection and the access to the Belfast mine approximately 13km.
Ensure that the existing lighting at the intersections of the N4 Road / D1110 Road and N4 Road / P15-1 are at sufficient standards to improve safety.
No on-street pick up/drop off’s at the intersections of the D1110 and D1770 Roads and the access to the mine should be allowed (drop-offs / pickup should be done on site).
Impact after management
2 3 4 1 5 54 Low-
Medium
D1110 / D1770 Intersection
Impact before management
2 3 4 1 5 54 Very High
Mitigation measures:
Surfacing of D1110 Road and D1770 Road between the N4 Road / D1110 Road intersection and the access to the Belfast mine approximately 13km.
Ensure that the existing lighting at the intersections of the N4 Road / D1110 Road and N4 Road / P15-1 are at sufficient standards to improve safety.
No on-street pick up/drop off’s at the intersections of the D1110 and D1770 Roads and the access to the mine should be allowed (drop-offs / pickup should be done on site).
Impact after management
2 3 4 1 5 54 Low-
Medium
N4 Road / D1110 Road Intersection (safety)
Impact before management
2 3 4 1 5 54 Very High
Mitigation measures:
Surfacing of D1110 Road and D1770 Road between the N4 Road / D1110 Road intersection and the access to the Belfast mine approximately 13km.
Ensure that the existing lighting at the intersections of the N4 Road / D1110 Road and N4 Road /
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
P15-1 are at sufficient standards to improve safety.
No on-street pick up/drop off’s at the intersections of the D1110 and D1770 Roads and the access to the mine should be allowed (drop-offs / pickup should be done on site).
Impact after management
2 3 4 1 5 54 Low-
Medium
New access road between Rietkuil Station and D1550 Road
Impact before management
2 3 4 1 5 54 Low-
Medium
Mitigation measures:
Surfacing of D1110 Road and D1770 Road between the N4 Road / D1110 Road intersection and the access to the Belfast mine approximately 13km.
Ensure that the existing lighting at the intersections of the N4 Road / D1110 Road and N4 Road / P15-1 are at sufficient standards to improve safety.
No on-street pick up/drop off’s at the intersections of the D1110 and D1770 Roads and the access to the mine should be allowed (drop-offs / pickup should be done on site).
Impact after management
2 3 4 1 5 54 Low-
Medium
Status (+/-) Low-Medium (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Noise
Table 5-27: Noise Related Impacts
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Removal and hauling of top soil from the site
Impact before management
2 2 4 4 3 56 Low-
Medium
Mitigation measures:
Vehicles to comply with the standards as provided in the IFC’s Environmental Health & Safety Regulations.
Earthmoving and hauling vehicles with low noise levels to be used.
Generators must be placed in such a manner that it is away from noise sensitive areas
Conveyor to be screened off.
Maintenance plan in place for regular maintenance of conveyor and electric motors.
Baseline noise monitoring on an annual basis
Impact after management
1 2 3 3 1 24 Very-Low
Earthmoving equipment at the foot print area
Impact before management
2 2 4 4 3 56 Low-
Medium
Mitigation measures:
Vehicles to comply with the standards as provided in the IFC’s Environmental Health & Safety
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact after management
1 2 3 3 1 24 Very-Low
Diesel emergency generators
Impact before management
2 2 4 4 3 56 Low-
Medium
Mitigation measures:
Vehicles to comply with the standards as provided in the IFC’s Environmental Health & Safety Regulations.
Earthmoving and hauling vehicles with low noise levels to be used.
Generators must be placed in such a manner that it is away from noise sensitive areas
Conveyor to be screened off.
Maintenance plan in place for regular maintenance of conveyor and electric motors.
Baseline noise monitoring on an annual basis
Impact after management
1 2 3 3 1 24 Very-Low
Stockpile management
Impact before management
2 2 4 4 3 56 Low-
Medium
Mitigation measures:
Vehicles to comply with the standards as provided in the IFC’s Environmental Health & Safety Regulations.
Earthmoving and hauling vehicles with low noise levels to be used.
Generators must be placed in such a manner that it is away from noise sensitive areas
Conveyor to be screened off.
Maintenance plan in place for regular maintenance of conveyor and electric motors.
Baseline noise monitoring on an annual basis
Impact after management
1 2 3 3 1 24 Very-Low
Status (+/-) Very Low (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Air Quality
The construction of proposed new Rietkuil Private Railway Siding and associated
infrastructure will not impact negatively on the air quality of the receiving environment and will
be compliant against the standards and will have a low impact on the closest receptors and
surrounding environment. It is anticipated that construction of the proposed new Rietkuil
Private Railway Siding and associated infrastructure will have a ‘Low’ air quality post
implementation of the recommended mitigation measures. Adequate recommendations were
included in the specialist study to mitigate impacts on the receiving environment. These
recommendations and mitigation measures form part of the EMPr.
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Table 5-28: Impacts associated with PM10
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
2 1 2 4 2 30 Low-
Medium
Mitigation measures:
In places of high vehicular traffic, dust suppression measures on the roads may be implemented to reduce dust levels from the entrainment of dust. These measures will range from watering of roads, application of a chemical dust suppressant and/or paving of roads.
Reduce vehicle speeds on roads to less than 40 km/hr within the project area.
If possible a chemical dust suppressant should be used to suppress dust emissions on the coal stockpiles if 12% moisture content cannot be maintained over a long period of time to lower dust emissions.
Impact after management
1 1 1 4 1 15 Low
Status (+/-) Low (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Table 5-29: Impacts Associated with Dust Fallout
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
2 1 2 4 2 30 Low-
Medium
Mitigation measures:
In places of high vehicular traffic, dust suppression measures on the roads may be implemented to reduce dust levels from the entrainment of dust. These measures will range from watering of roads, application of a chemical dust suppressant and/or paving of roads.
Reduce vehicle speeds on roads to less than 40 km/hr within the project area.
If possible a chemical dust suppressant should be used to suppress dust emissions on the coal stockpiles if 12% moisture content cannot be maintained over a long period of time to lower dust emissions from the handling processes.
Impact after management
1 1 1 4 1 15 Low
Status (+/-) Low (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Table 5-30: Impacts Associated with PM2.5
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
2 1 2 4 2 30 Low-
Medium
Mitigation measures:
In places of high vehicular traffic, dust suppression measures on the roads may be implemented to
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
reduce dust levels from the entrainment of dust. These measures will range from watering of roads, application of a chemical dust suppressant and/or paving of roads.
Reduce vehicle speeds on roads to less than 40 km/hr within the project area.
If possible a chemical dust suppressant should be used to suppress dust emissions on the coal stockpiles if 12% moisture content cannot be maintained over a long period of time to lower dust emissions.
Impact after management
1 1 1 4 1 15 Low
Status (+/-) Low (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Geochemical
The geochemical study concluded that the proposed coal stockpile will not generate acidic
drainage but rather a neutral drainage. This is because the coal has excess neutralisation
potential in the form of calcite and dolomite that buffers the pH at neutral conditions of 6.7.
However, there is still an expectation that secondary minerals that may have formed as a
result of the oxidation of pyrite and subsequent neutralisation of the acidity may be mobilised
to form a neutral but saline runoff or seepage, depending on the period in which the coal is
retained in the stockpile.
It is anticipated that the proposed new Rietkuil Private Railway Siding and associated
infrastructure will not impact negatively on the geochemical composition of the receiving
environment. In order to mitigate any impacts arising from secondary minerals,
recommendations are included the specialist study contained in Appendix C. These
recommendations and mitigation measures form part of the EMPr. These recommendations
include the following:
Appropriate stockpile management should be enforced at the siding, where the residence
time of the material in stockpile is minimised. Furthermore, stockpile management should
include mechanisms to ensure that the entire volume of material is removed periodically,
rather than retaining a layer at the base of the stockpile which does not get removed. This
will minimise the time period in which pyrite oxidation can occur which in turn should limit
the salinity of runoff and seepage from the stockpiles.
The liners below the stockpile and the PCD should be engineered in a manner to ensure
that the potential permeability through the liners is minimised with runoff and seepage
flow into the PCD maximised.
The stockpiles and PCD should be operated in a manner to ensure that the integrity of
the liners included in the design is maintained and regular monitoring of the integrity of
the liners is undertaken.
The level in the PCD should be maintained to ensure that there is adequate flood buffer
zone in the facility to store the design flood event without overtopping as the quality of
water in the PCD is likely to be saline.
If the PCD water is used for dust suppression as intended, then spraying should only
occur on areas lined to minimise the potential of the salinization of the soils not covered
by liners.
The concentrations of the constituents of concern, Ca, Cl, TDS and Zn, should be
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
5.3.4 Decommissioning / Rehabilitation phase
In addition to the abovementioned impacts the following additional impacts are anticipated to
occur during the decommissioning/rehabilitation phase of the Rietkuil private railway siding
project:
Soils, Land Use and Land Capability
Table 5-31: Impacts associated with Soil Compaction
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration Frequency of Activity
Frequency of Impact
Impact before management
5 4 4 3 5 108 High
Mitigation measures:
When stripping machinery is used for stripping, stockpiling and ‘topsoiling’ operations, it should operate when the soil moisture content is below approximately 8 % (during the dry winter months) in order to limit soil compaction and machinery getting stuck.
For use on site, tracked vehicles are more desirable than wheeled vehicles due to their lower point loading and slip, while vehicle speed should be maintained in order to reduce the duration of applied pressure, thereby minimizing compaction.
The width of the levelled or disturbed area for haul roads must be minimized as much as possible. Unnecessary dirt tracks (outside of the area to be disturbed) should be avoided during the construction of the haul road.
Impact beyond the site boundary can be reduced by using existing roads and reducing new roads to a minimum.
Impact after management
2 3 5 4 4 80 Medium-
High
Status (+/-) Medium-High (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
Surface and Groundwater
Table 5-32: Surface and Groundwater Related Impacts
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration
Frequency of Activity
Frequency of Impact
Impact on groundwater quality (Leachate seeping from coal loading bay to underlying aquifers)
Impact before management
2 3 4 4 3 2 Low-
Medium
Mitigation measures:
Ensure that all coal removed from site prior to removal of liner. Liner to be removed in a manner where efflorescence that may have formed on the liners is not released to the environment
Impact after management
3 2 2 1 3 28 Low
Impact on groundwater quality
Impact before management
3 4 3 2 4 3 Low-
Medium
Mitigation measures:
Evaporate surplus water in the dam, prior to decommissioning. Once dry, remove accumulated
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration
Frequency of Activity
Frequency of Impact
sediments prior to liner removal.
Impact after management
2 2 3 2 3 35 Low
Impact on Bosmanspruit (Seepage of contaminated groundwater into the river)
Impact before management
3 2 2 2 3 3 Low
Mitigation measures:
Phase closure to ensure that contact water can be separated from non-contact water and contact water contained during all phases.
Impact after management
2 2 2 2 3 30 Low
Impact on Bosmanspruit (Contaminated runoff flowing into the river)
Impact before management
3 3 1 1 3 3 Low
Mitigation measures:
Phase closure to ensure that contact water can be separated from non-contact water and contact water contained during all phases.
Impact after management
2 1 1 1 3 16 Very Low
Change in catchment runoff
Impact before management
1 3 4 1 3 1 Low
Mitigation measures:
Rehabilitation of site
Impact after management
1 1 1 1 2 9 Very Low
Status (+/-) Very Low - Low (-)
Cumulative impact
The cumulative impact of the current activities and the future activities will not increase the impact rating from a Low Impact as rated in the initial impact assessment
Noise
Table 5-33: Noise Related Impacts
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration
Frequency of Activity
Frequency of Impact
Rehabilitation of railway siding
Impact before management
2 2 4 4 3 56 Low-
Medium
Mitigation measures:
Vehicles to comply with the standards as provided in the IFC’s Environmental Health & Safety Regulations.
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
Impact
Consequence Likelihood Significance
Rating Mitigation
Rating Severity Spatial Duration
Frequency of Activity
Frequency of Impact
Impact after management
1 2 4 4 2 42 Low
Demolition of plant and infra-structure
Impact before management
2 2 4 4 3 56 Low-
Medium
Mitigation measures:
Vehicles to comply with the standards as provided in the IFC’s Environmental Health & Safety Regulations.
Impact after management
1 2 4 4 2 42 Low
Diesel emergency generators
Impact before management
2 2 4 4 3 56 Low-
Medium
Mitigation measures:
Vehicles to comply with the standards as provided in the IFC’s Environmental Health & Safety Regulations.
Impact after management
1 2 4 4 2 42 Low
Status (+/-) Low (-)
Cumulative impact
If the abovementioned mitigation measures are implemented successfully the cumulative impacts of the construction of the Rietkuil private railway project should not result in an impact larger than was assessed initially.
5.4 Uncertainties, assumptions and gaps in knowledge
This section provides a description of the assumptions, risks, and gaps in knowledge
associate with the proposed project. Assumptions made by the specialist during their
assessments are detailed in the section.
5.4.1 Uncertainties
No uncertainties were encountered on this project.
5.4.2 Assumptions
Various assumptions were made when compiling this report including:
The scope of work, methodologies and databases provided in the original Terms of
Reference (ToR) were updated and revised to be applicable to site specific conditions
and methodologies were employed according to best record the fauna and flora
assemblages, habitat integrity and wetlands on-site. However, all ecological parameters
on-site are considered to have been accurately recorded and sufficient ecological
baseline data was gathered to inform the impact assessment.
With conservation databases being regularly updated, other databases than those
indicated in the ToR may have been utilised during the study in order to ensure that the
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
communities most directly affected by the proposed project. These principles have guided
the EIA process and the compilation of the EMPr.
The EMPr covers information on the management and mitigation measures that will be
implemented to address impacts in respect of:
Planning;
Construction;
Operation;
Rehabilitation;
Decommissioning;
Impact statement.
6.3 Approach to the EMPr
The responsibility of the EMPr implementation will ultimately reside with Exxaro. Table 6-1
illustrates the range of approaches used in the compilation of the EMPr in order to manage
potential impacts associated with the project activities.
Table 6-1: Approach to Impact Management
Avoidance Avoiding activities that could result in adverse impacts and/or resources or areas considered sensitive
Prevention Preventing the occurrence of negative environmental impacts and/or preventing such an occurrence having negative impacts
Preservation Preventing any future actions that might adversely affect an environmental resource
Minimization Limiting or reducing the degree, extent, magnitude or duration of adverse impacts through scaling down, relocating, redesigning and/or realigning elements of the project
Mitigation Measures taken to minimize adverse impacts on the environment
Enhancement Magnifying and/or improving the positive effects or benefits of a project
Rehabilitation Repairing affected resources, such as natural habitats or water resources
Restoration Restoring affected resources to an earlier (possibly more stable and productive) state, typically ‘background’ or ‘pristine’ condition
Compensation Compensating for lost resources, and where possible, the creation, enhancement or protection of the same type of resource at another suitable and acceptable location
6.4 Implementation of the EMPr
The full EMPr is presented in Appendix E. This document includes the roles and
responsibilities of all the role players during the different phases of the proposed new Rietkuil
Private Railway Siding and associated infrastructure.
Role players in the implementation of the EMPr management and mitigation measures
include:
Exxaro project management team;
Project implementers;
Contractors;
Environmental Control Officer (for construction phase).
6.5 Rehabilitation and Closure
The purpose of the rehabilitation plan is that it describes the activities associated with the
rehabilitation of the siding footprint and give guidelines on how rehabilitation must be
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
7.2 Actions taken during the Public Participation Process
Table 7-2: Actions Taken during Public Participation Process
GN R. 543 Action required Action taken Dates
54(2)(a) Fixing a notice board at a place conspicuous to the public at the boundary or on the fence of—
The site where the activity to which the application relates is or is to be undertaken; and
Any alternative site mentioned in the application;
Announcement Phase:
Thirteen (13) site notices site notices, announcing the application for EA were placed at the following locations:
Western edge of the siding and PCD
Coal loading facility;
Beginning of alternative balloon;
Rietkuil Public Library;
Intersection of the N 4 and D 1110;
Along the D 1110;
Intersection of the D 1110 and D 1770;
Along the D 1770;
Belfast Public Library;
Middleburg Public Library;
Emakhazeni Local Municipality;
Steve Tshwete Local Municipality;
Nkangala District Municipality.
Appended to this report as Appendix D
2014/01/31
54(2)(b) Giving written notice to -
54(2)(b)(i) The owner or person in control of that land if the applicant is not the owner or person in control of the land;
The applicant 2014/01/31
54(2)(b)(ii) The occupiers of the site where the activity is or is to be undertaken or to any alternative site where the activity is to be undertaken;
The occupiers of land within 100 metres of the boundary of the proposed site
2014/01/31
54(2)(b)(iii) Owners and occupiers of land adjacent to the site where the activity is or is to be undertaken or to any alternative site where the activity is to be undertaken;
The owners of land and occupiers within 100 metres of the boundary of the proposed site
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
GN R. 543 Action required Action taken Dates
54(2)(b)(iv) The municipal councillor of the ward in which the site or alternative site is situated and any organisation of ratepayers that represent the community in the area;
Municipal departments
Local and district municipalities;
Ward councillors
2014/01/31
54(2)(b)(v) The municipality which has jurisdiction in the area Municipal departments;
District and Local Municipalities;
Ward councillors.
2014/01/31
54(2)(b)(vi) Any organ of state having jurisdiction in respect of any aspect of the activity; and
Government organisations;
Non-governmental organizations, research and conservation groups;
Relevant national and provincial governmental officials.
2014/01/31
54(2)(b)(vii) Any other party as required by the competent authority Non-governmental organizations, research and conservation groups
2014/01/31
54(2)(c) Placing an advertisement in—
(i) one local newspaper; or
(ii) any official gazette that is published specifically for the purpose of providing public notice of applications or other submissions made in terms of these regulations
Lowvelder
Appended to this report as Appendix D
2014/01/31
54(2)(d) Placing an advertisement in at least one provincial newspaper or national newspaper, if the activity has or may have an impact that extends beyond the boundaries of the metropolitan or local municipality in which it is or will be undertaken: Provided that this paragraph need not be complied with if an advertisement has been placed in an official Gazette referred to in [sub-regulation (c)(ii)] paragraph (c)(ii); and
Mpumalanga News
Appended to this report as Appendix D
2014/01/30
54(2)(e) Using reasonable alternative methods, as agreed to by the competent authority, in those instances where a person is desiring of but unable to participate in the process due to—
(i) illiteracy;
(ii) disability; or
(iii) any other disadvantage.
N/A
54(3) A notice, notice board or advertisement referred to in sub regulation (2) must—
Notice boards, complying with these requirements, were placed, a copy of the notice boards can be found in
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
GN R. 543 Action required Action taken Dates
(a) give details of the application which is subjected to public participation; and
(b) state—
(i) that the application has been submitted to the competent authority in terms of these Regulations[, as the case may be];
(ii) whether basic assessment or scoping procedures are being applied to the application, in the case of an application for environmental authorisation;
(iii) the nature and location of the activity to which the application relates;
(iv) where further information on the application or activity can be obtained; and
(vi) The manner in which and the person to whom representations in respect of the application may be made.
Appendix D.
54(4) A notice board referred to in sub-regulation (2) must—
(a) be of a size at least 60cm by 42cm; and
(b) display the required information in lettering and in a format as may be determined by the competent authority
Notice boards, complying with these requirements, were placed, a copy of the notice boards can be found in Appendix D.
2014/01/31
54(5) Where deviation from sub-regulation (2) may be appropriate, the person conducting the public participation process may deviate from the requirements of that sub-regulation to the extent and in the manner as may be agreed to by the competent authority.
N/A
54(6) Where a basic assessment report, scoping report or environmental impact assessment report as contemplated in regulations 22, 28 and 31 respectively is amended because it has been rejected or because of a request for additional information by the competent authority, and such amended report contains new information, the amended basic assessment report, scoping report or environmental impact assessment report must be subjected to the processes contemplated in regulations 21, 27 and 31, as the case may be, on the understanding that the application form need not be resubmitted
N/A.
No reports were rejected to date as the reports submitted to the Competent Authority complied with the minimum legal requirements.
54(7) When complying with this regulation, the person conducting All information are being available to potential interested and affected parties and are encouraged to take part in
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
GN R. 543 Action required Action taken Dates
the public participation process must ensure that—
(a) information containing all relevant facts in respect of the application is made available to potential interested and affected parties; and
(b) Participation by potential interested and affected parties is facilitated in such a manner that all potential interested and affected parties are provided with a reasonable opportunity to comment on the application.
the PPP
Appended to this report as Appendix D
Scoping Report)
2014/05/16 (Final Scoping Report)
2014/10/20 (Draft EIAr)
54(8) Unless justified by exceptional circumstances, as agreed to by the competent authority, the applicant and EAP managing the environmental assessment process must refrain from conducting any public participation process during the period of 15 December to 2 January.
N/A
55(1) An EAP managing an application must open and maintain a register which contains the names, contact details and addresses of—
(a) all persons who, as a consequence of the public participation process conducted in respect of that application in terms of regulation 54, have submitted written comments or attended meetings with the applicant or EAP;
(b) all persons who, after completion of the public participation process referred to in paragraph (a), have requested the applicant or the EAP managing the application, in writing, for their names to be placed on the register; and
(c) All organs of state which have jurisdiction in respect of the activity to which the application relates.
An I&AP register was opened and is updated as new requests for I&AP registrations are received.
Appended to this report as Appendix D
Ongoing
56(1) A registered interested and affected party is entitled to comment, in writing, on all written submissions, including draft reports made to the competent authority by the applicant or the EAP managing an application, and to bring to the attention of the competent authority any issues which that party believes may be of significance to the consideration of the application, provided that—
(a) comments are submitted within—
(i) the timeframes that have been approved or set by the competent authority; or
The I&APs were notified of the availability of the Draft Scoping Report for comment;
The I&APs were notified of the availability of the Final Scoping Report for comment;
The I&APs will be notified of the availability of the Draft EIAr for comment.
VDMW/HINM 467209_20141007_DRAFT EIAr Rietkuil railway siding_Final for client submission.docx October 2014
GN R. 543 Action required Action taken Dates
(ii) any extension of a timeframe agreed to by the applicant or EAP;
(b) a copy of comments submitted directly to the competent authority is served on the EAP; and
(c) the interested and affected party discloses any direct business, financial, personal or other interest which that party may have in the approval or refusal of the application
56(2) Before the EAP managing an application for environmental authorisation submits a final report compiled in terms of these Regulations to the competent authority, the EAP must give registered interested and affected parties access to, and an opportunity to comment on the report in writing.
The Draft Scoping Report was made available for a 40 day commenting period;
The Final Scoping Report was made available for a 21 day commenting period.
Appended to this report as Appendix D
2014/03/14
2014/05/16
56(3) and (4)
The draft versions of reports referred to in sub regulation (3) must be submitted to the competent authority prior to awarding registered interested and affected parties an opportunity to comment
The Draft Scoping Report was made available for a 40 day commenting period;
The Draft EIAr will be made available for a 40 day commenting period
Appended to this report as Appendix D
2014/03/14
2014/10/20 (Draft EIAr)
56(5) Registered interested and affected parties must submit comments on draft reports contemplated in sub regulation (4) to the EAP, who should record it in accordance with regulations 21, 28 or 31
Appended to this report as Appendix D
57(1)(6) The EAP managing an application for environmental authorisation must ensure that the comments of interested and affected parties are recorded in reports and that such written comments, including records of meetings, are attached to the report, submitted to the competent authority in terms of these Regulations