Top Banner
Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic Chapter
20

Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

Dec 14, 2015

Download

Documents

Isaias Boote
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

Alternate Bidding: The West Virginia Experience

2011Virginia Concrete ConferenceMarch 3, 2011Richmond, VA

Bob LongExecutive Director

ACPA Mid-Atlantic Chapter

Page 2: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

Evolution of Alternate Design Alternate Bid (ADAB) Procedures

Joint efforts began in the Fall 2007 including WVDOH, FHWA and industry.

Formal procedures implemented in July 2008 All procedures finalized June 2010

Page 3: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

CORRIDOR H – US 48 MOOREFIELD (July 2008)

First “formal” Alternate Bid pavement project 10.6 miles 4-lane arterial No life cycle cost adjustment (C factor) Included asphalt escalator Asphalt by the ton and PCCP by the SY

Page 4: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

CONCRETE PAVEMENT DESIGN

Description: Perpetual pavement design provided

by Industry using Westergaard Equations Design

10” Jointed Plain Concrete Pavement on 4” free draining base

15’ doweled joints Full depth tied concrete shoulders

Assumptions:•Analysis period = 50 yrs•Initial performance period = 22 yrs•Rehab performance period for CPR = 14 yrs•Rehab performance period for Overlay = 14 yrs•No Salvage value @ year 50

•Rehab #1 – diamond grinding and 7.5% joint patching•Rehab #2 – overlay w/2” skid resistant mix w/PMA and 2% joint patching

10” Jointed Plain Concrete Pavement

4” Free Drain Base

Pavement Typical

Page 5: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

ASPHALT PAVEMENT DESIGN

Description: Perpetual pavement design provided

by Industry using PerRoad 3.2 Design Program

13.5” HMA on 4” free draining base Use PG 76-22 polymer modified

asphalt (PMA) binder in top 4.5” and on future overlays

Increase AC by 0.5% in bottom 5”

Assumptions:•Analysis period = 50 yrs•Initial performance period w/PMA = 22 yrs•Rehab performance period w/PMA = 14 yrs•No salvage value @ year 50

•Rehab #1 – mill and resurface w/2” skid resistant mix w/PMA•Rehab #2 – mill and resurface w/2” skid resistant mix w/PMA

2” 12.5mm skid w/76-22 AC

2.5” 19mm mix w/76-22 AC

4” 25mm mix w/64-22 AC

5” 37.5mm mix w/64-22 AC + 0.5% AC content

4” Free Drain Base

Pavement Typical

Page 6: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

PROJECT NUMBER & BIDDERS

BID

 APD-0484(308)  (X312-H-93.38)  

Kokosing Construction Co., Inc. (PCCP)

34,544,899.90

Hi-Way Paving, Inc. (PCCP) 36,137,190.09Anthony Allega Cement Contractor, Inc. (PCCP)

36,995,205.73

West Virginia Paving, Inc. (Asphalt)

38,072,526.42

McCarthy Improvement Company (PCCP)

41,096,902.30

Cherry Hill Construction, Inc. (PCCP)

44,354,677.45

West Virginia Department of TransportationDivision of Highways

Bid Results - Letting of July 15, 2008

Page 7: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

SECTION 690

MAINLINE PAVEMENT 690 – GENERAL 690.1 - DESCRIPTION:

This Special Provision shall define the requirements to construct mainline pavement, which includes roadway pavement and full depth paved shoulders, to the limits as shown by the contract plans. The contractor shall construct one of the pavement systems as described herein and by the contract plans.

Page 8: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

CONCRETE PAVEMENT SYSTEM: A concrete pavement system shall be constructed as defined by the concrete typical section(s) and all other documents referenced in the contract plans. This work and materials shall include jointed plain concrete pavement, free draining base, fabric for separation, subgrade, and subgrade preparation

ASPHALT PAVEMENT SYSTEM: An asphalt pavement system shall be constructed as defined by the asphalt typical section(s) and all other documents referenced in the contract plans. This work and materials shall include asphalt wearing surface, asphalt base courses, free draining base, fabric for separation, subgrade, and subgrade preparation.

.

Page 9: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

RECENT ADAB PROJECTSWV 10 – 3.7 miles

4-lane arterial on new alignment – pre-graded 10” PCCP vs. 12.25” Asphalt Bid by the SY of Mainline Pavement 4 of the 6 bidders bid concrete and the low concrete bid was

17% lower than asphalt Low SY price was $60.00

King Coal US52 – 9.5 miles Pre-graded and bid by the SY of Mainline Pavement 10” PCCP vs. 11.5” Asphalt 5 out of 6 bidders went concrete and the concrete bid was 3%

lower than asphalt Low SY price was $48.45

Page 10: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

RECENT ADAB PROJECTS

WV Corridor H, US 48 – 3.3 miles 4-lane arterial on new alignment – pre-graded 10” PCCP vs. 13.5” Asphalt Bid by the SY of Mainline Pavement 4 of the 5 bidders bid concrete and the low concrete bid

was 29% lower than asphalt Low SY price was $46.40

Page 11: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.
Page 12: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

RECENT ADAB PROJECTS

US Route 35, Putnam County – 14.5 miles Design build – lump sum bid 4-lane arterial with structures on new alignment – grade,

drain, pave & structures Bid by the SY of Mainline Pavement 10” PCCP vs. 12.5” Asphalt Four proposers – 3 confirmed use of concrete pavement Successful team went with concrete

Page 13: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

RECENT ADAB PROJECTS

WV Corridor H, US 48 – 6.0 miles Design bid build 4-lane arterial with structures on new alignment – grade,

drain, pave & structures Bid by the SY of Mainline Pavement 10” PCCP vs. 12.5” Asphalt Low bidder went with concrete Low SY price was $44.50

Page 14: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

THE RESULTS

8 out of 9 projects went concrete when bid as an alternate to asphalt

On these projects about 80% of the bidders have bid concrete and all have had at least 4 bidders

WVDOH has saved $9,800,000 just on the four paving jobs alone over the low asphalt bids.

Page 15: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

UPCOMING ADAB PROJECTS

1. Route 9 - Charlestown - VA line – 3.1 miles paving only

2. Corridor H - Rte. 1 to Mount Storm – 11.8 miles paving only

3. Corridor H - Mount Storm to Parsons - 10 miles grade, drain, & pave

Page 16: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

Why ADAB “Works” in WV

WVDOH senior management support Strong new construction program Equivalent designs Economized PCCP design (no seal, no

dowels in shoulder, no cure on CTOGB Most asphalt work controlled by one

company

Page 17: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.
Page 18: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.
Page 19: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

Alternate Design Alternate Bid

Questions?????

Page 20: Alternate Bidding: The West Virginia Experience 2011Virginia Concrete Conference March 3, 2011 Richmond, VA Bob Long Executive Director ACPA Mid-Atlantic.

THANK YOU!

www.midatlantic.pavement.com

www.pavement.com