Alternate Pavement Bidding in Missouri Natalie Roark, P.E. Missouri Department of Transportation March 3, 2011
Feb 25, 2016
Alternate Pavement Bidding in Missouri
Natalie Roark, P.E.Missouri Department of Transportation
March 3, 2011
5,000 miles of Major Roads
27,000 miles of Minor Roads
10,000 Bridges
Radical Cost ControlResponsibility
Annual Pavement QuantitiesYear Asphalt Concrete
Tons $$ YD3 $$1992 4,950,706 106,542,443 599,575 30,760,634
1995 2,110,902 50,445,371 744,506 63,910,232
2000 5,115,218 200,192,172 1,141,790 108,794,341
2005 8,035,462 397,618,849 604,216 78,585,4452006 2,467,655 134,679,642 573,052 77,422,513
2007 3,745,808 178,237,592 867,917 103,433,9072008 2,087,204 122,035,246 667,354 90,891,896
2009 4,719,775 258,484,735 853,350 112,257,492
Cost Control in Missouriimplementation - the road to success
• Past Decade – Letting schedules optimized• Spring 2002 – Performance Specs written
• Fall 2003 – Alternate bidding pavements required
• December 2004 – Practical Design concept pitched to Commission
• Spring 2005 – Districts challenged to cut STIP 10%
• Fall 2005 – First Practical Design Policy written
• Fall 2007 – First ATC Project
• 2006 – First Design/Build Projects
Radical Cost Control• Concrete or asphalt? Let the marketplace decide.
Alternate Pavement Biddingmaximizing competition
ASPHALTCONCRETE
First Alternate Bidding PilotMissouri let five pilot projects in 1996Project conditions included
Design costs within 15% of each otherAt least one mile of pavingPrimary work was pavingMinimal grade change impactArea unit prices
An LCCA adjustment factor was used
First Alternate Bidding Pilot
Bidding Results: 3 Asphalt / 2 ConcreteLow paving prices, but not lower than
expected
Higher number of bidders per project
Overall - no verdict, process went dormant
Alternate Bidding RestartFall 2002
Pavement Team Developed: Composed of MoDOT, PCC and HMA paving industry, and FHWA representatives;
Recommended in 2003 to restart alternate pavement design bidding
Initial hesitation by concrete industry
LCCA assumptions difficult to reach consensus on
Alternate BiddingPavement Design
From 1993 – 2004 a simple catalogue design, derived from the 1986 AASHTO Guide for the Design of Pavement Structures, was used for new Jointed Plain Concrete pavements.
The Pavement Team recommended adopting a mechanistic-empirical (M-E) design approach for pavements in Missouri.
M-E Pavement Design GuideBeneficial component of making the Alternate Pavement
Bidding process successful.
Design method had common input parameters for both pavement types.
Adopted by AASHTO as state of the art design method.
Had industry support to make it successful.
‘Structurally Equivalent’ concrete
and asphalt construction and rehabilitation solutions
Life Cycle Cost Analysis Adjustment factor applied to the asphalt bid
Alternate Pavement Design
M-E Design ImplementationStarted using nationally-calibrated MEPDG program
at the beginning of 2005 for PCC and HMA designs.Average PCC thicknesses reduced by
~ 2” for high truck volume routes~ 1” for low to medium truck volume routes
Average HMA thicknesses reduced by~ 3-4” for high truck volume routes~ 1-2” for low to medium truck volume routes
Alternate Pavements - Policy
• Alternate pavement design with a LCCA factor for projects with 7500 sq yd in a continuous area
• New full depth and major rehabilitation construction
• Optional pavement designs without a LCCA factor for smaller paving quantities
Alternate Pavement Designs
New construction (based on M-E Design Guide)ConcreteAsphalt
Rehabilitation8“ Unbonded PCC overlay (UBOL)Rubblization w/ 12“ HMA overlay
Design TransitionNot as bad as initially thought
After several iterations the procedures were simplified to one set of designs
Alternate (or optional) bid designs have become second nature to MoDOT and consultant designers
Method of MeasurementNew PCC and HMA measured in square yardsUnbonded overlays measured in cubic yards for
furnishing and square yards for placingHMA overlay (on rubblized PCC) measured in
wet tons
Alternate DesignLife Cycle Costs
LCCA used solely to determine adjustment factor for 45-year design life
Life cycle costs consideredInitial ConstructionMaintenanceRehabilitationSalvage valueUser costs
Rehabilitation Assumptions
AsphaltMill and fill wearing course at 20 years in
driving lanesMill and fill wearing course at 33 years across
whole surfaceConcrete
Diamond grind whole surface and perform full-depth repairs on 1.5% of surface area at 25 years
Adjustment FactorAdjustment Factor =Present Worth of Future Asphalt Rehab - Present Worth of Future Concrete Rehab
Adjustment Factor
Spreadsheet Used by
Central Office Estimating
Section
Alternate Bid Selection
Low bidder = lower of (PCC bid price) vs. (HMA bid price + adjustment factor)
Alternate Bid Example #121 miles of grading and paving new dual lane on US
63 in Macon/Adair CountiesAdjustment factor = $1,541,000Low HMA construction bid = $22,220,790Low HMA bid for comparison = $23,761,790Low PCC construction bid = $24,320,546Winner low HMA bidAdjustment factor has no impact
Alternate Bid Example #28 miles of grading, paving, and bridges for new dual
lane on US 36 in Macon CountyAdjustment factor = $964,800Low HMA construction bid = $40,499,627Low HMA bid for comparison = $41,464,427Low PCC construction bid = $35,322,473Winner low PCC bidAdjustment factor has no impact
Alternate Bid Example #311 miles of grading and paving new dual lane on US
63 in Randolph CountyAdjustment factor = $1,469,200Low HMA construction bid = $25,262,509Low HMA bid for comparison = $26,731,709Low PCC construction bid = $26,452,184Winner low PCC bidAdjustment factor HAS impact
Alternate Pavement Update for Jobs Thru Dec 2010 with LCCA Factor
187 Alternate Projects to Date ($2.234 bil)174 Full Depth ($2.052 bil)13 Rehabilitation ($182.1 mil)
Full Depth59 Asphalt Awards ($539.4 mil)115 Concrete Awards ($1.513 bil)
Rehabilitation1 Asphalt Award ($2.6 mil)12 Concrete Awards ($179.5 mil)
Results: Difference in Low Bids
Low PC Bids vs. Low AC Bids LCCA Factor not AppliedPC Total – $854,428,378AC Total - $871,075,824Difference - $16,647,446 (1.9%)
Low PC Bids vs. Low AC Bids LCCA Factor AppliedPC Total – $854,428,378AC Total - $901,988,624Difference - $47,560,246 (5.6%)
LCCA Factor has Determined Low Bid 4 Times since October 2003.
Number of Bidders
Price Summaries
Start of Alt Paving in 2003-2005 price difference from alt to non-alt for same items of work - 10%
Since then still savings but all jobs are alt so hard to make a valid comparison.
Other Optional BiddingIntermediate overlays
5 ¾” HMA vs.5” ‘big block’ PCC
Thinner overlays3 ¾” HMA vs.4” ultrathin PCC
Other Optional BiddingThin overlays
1 ¾” HMA vs.1” HIR plus surface treatment
and
3 ¾” HMA vs.4” CIR plus surface treatment
Optional Shoulder Designs
A2 design5 ¾” HMA
5 ¾” PCC
A3 design3 ¾” HMA
4” PCC (also roller compacted option)
An independent third party peer review was performed in late 2005 by a respected national consultant on MoDOT’s alternate
pavement bidding process.
“It appears that MoDOT has developed a balanced, innovative program that could
serve as a national model for other highway agencies throughout the nation
and beyond.”
Thank You and Questions!For more information including example plans and
specifications go to:http://epg.modot.mo.gov
Natalie Roark, [email protected]
(573) 751-3726
Alternate Bidding: The West Virginia Experience
2011Virginia Concrete ConferenceMarch 3, 2011Richmond, VA
Bob LongExecutive Director
ACPA Mid-Atlantic Chapter
Evolution of Alternate Design Alternate Bid (ADAB) Procedures
Joint efforts began in the Fall 2007 including WVDOH, FHWA and industry.
Formal procedures implemented in July 2008
All procedures finalized June 2010
CORRIDOR H – US 48 MOOREFIELD (July 2008)
First “formal” Alternate Bid pavement project10.6 miles4-lane arterialNo life cycle cost adjustment (C factor)Included asphalt escalator Asphalt by the ton and PCCP by the SY
CONCRETE PAVEMENT DESIGNDescription: Perpetual pavement design
provided by Industry using Westergaard Equations Design
10” Jointed Plain Concrete Pavement on 4” free draining base
15’ doweled joints Full depth tied concrete shoulders
Assumptions:• Analysis period = 50 yrs• Initial performance period = 22 yrs• Rehab performance period for CPR = 14 yrs• Rehab performance period for Overlay = 14 yrs• No Salvage value @ year 50
• Rehab #1 – diamond grinding and 7.5% joint patching• Rehab #2 – overlay w/2” skid resistant mix w/PMA and 2%
joint patching
10” Jointed Plain Concrete Pavement
4” Free Drain Base
Pavement Typical
ASPHALT PAVEMENT DESIGN
Description: Perpetual pavement design
provided by Industry using PerRoad 3.2 Design Program
13.5” HMA on 4” free draining base Use PG 76-22 polymer modified
asphalt (PMA) binder in top 4.5” and on future overlays
Increase AC by 0.5% in bottom 5”
Assumptions:• Analysis period = 50 yrs• Initial performance period w/PMA = 22 yrs• Rehab performance period w/PMA = 14 yrs• No salvage value @ year 50
• Rehab #1 – mill and resurface w/2” skid resistant mix w/PMA• Rehab #2 – mill and resurface w/2” skid resistant mix w/PMA
2” 12.5mm skid w/76-22 AC
2.5” 19mm mix w/76-22 AC
4” 25mm mix w/64-22 AC
5” 37.5mm mix w/64-22 AC + 0.5% AC content
4” Free Drain Base
Pavement Typical
PROJECT NUMBER & BIDDERS
BID
APD-0484(308) (X312-H-93.38)
Kokosing Construction Co., Inc. (PCCP)
34,544,899.90
Hi-Way Paving, Inc. (PCCP) 36,137,190.09Anthony Allega Cement Contractor, Inc. (PCCP)
36,995,205.73
West Virginia Paving, Inc. (Asphalt)
38,072,526.42
McCarthy Improvement Company (PCCP)
41,096,902.30
Cherry Hill Construction, Inc. (PCCP)
44,354,677.45
West Virginia Department of TransportationDivision of Highways
Bid Results - Letting of July 15, 2008
SECTION 690
MAINLINE PAVEMENT 690 – GENERAL 690.1 - DESCRIPTION:
This Special Provision shall define the requirements to construct mainline pavement, which includes roadway pavement and full depth paved shoulders, to the limits as shown by the contract plans. The contractor shall construct one of the pavement systems as described herein and by the contract plans.
CONCRETE PAVEMENT SYSTEM: A concrete pavement system shall be constructed as defined by the concrete typical section(s) and all other documents referenced in the contract plans. This work and materials shall include jointed plain concrete pavement, free draining base, fabric for separation, subgrade, and subgrade preparation
ASPHALT PAVEMENT SYSTEM: An asphalt pavement system shall be constructed as defined by the asphalt typical section(s) and all other documents referenced in the contract plans. This work and materials shall include asphalt wearing surface, asphalt base courses, free draining base, fabric for separation, subgrade, and subgrade preparation.
.
RECENT ADAB PROJECTSWV 10 – 3.7 miles
4-lane arterial on new alignment – pre-graded 10” PCCP vs. 12.25” Asphalt Bid by the SY of Mainline Pavement 4 of the 6 bidders bid concrete and the low concrete bid
was 17% lower than asphalt Low SY price was $60.00
King Coal US52 – 9.5 miles Pre-graded and bid by the SY of Mainline Pavement 10” PCCP vs. 11.5” Asphalt 5 out of 6 bidders went concrete and the concrete bid
was 3% lower than asphalt Low SY price was $48.45
RECENT ADAB PROJECTSWV Corridor H, US 48 – 3.3 miles
4-lane arterial on new alignment – pre-graded 10” PCCP vs. 13.5” Asphalt Bid by the SY of Mainline Pavement 4 of the 5 bidders bid concrete and the low concrete bid
was 29% lower than asphalt Low SY price was $46.40
Corridor H 2008 Route 10 2009 Route 52 2009 Corridor H 20100
5
10
15
20
25
30
35
40
45
WV ADAB Bid ResultsMillions of Dollars
AsphaltConcrete
RECENT ADAB PROJECTSUS Route 35, Putnam County – 14.5 miles
Design build – lump sum bid 4-lane arterial with structures on new alignment – grade,
drain, pave & structures Bid by the SY of Mainline Pavement 10” PCCP vs. 12.5” Asphalt Four proposers – 3 confirmed use of concrete pavement Successful team went with concrete
RECENT ADAB PROJECTSWV Corridor H, US 48 – 6.0 miles
Design bid build 4-lane arterial with structures on new alignment – grade,
drain, pave & structures Bid by the SY of Mainline Pavement 10” PCCP vs. 12.5” Asphalt Low bidder went with concrete Low SY price was $44.50
THE RESULTS8 out of 9 projects went concrete when
bid as an alternate to asphalt On these projects about 80% of the
bidders have bid concrete and all have had at least 4 bidders
WVDOH has saved $9,800,000 just on the four paving jobs alone over the low asphalt bids.
UPCOMING ADAB PROJECTS
1. Route 9 - Charlestown - VA line – 3.1 miles paving only
2. Corridor H - Rte. 1 to Mount Storm – 11.8 miles paving only
3. Corridor H - Mount Storm to Parsons - 10 miles grade, drain, & pave
Why ADAB “Works” in WVWVDOH senior management supportStrong new construction programEquivalent designsEconomized PCCP design (no seal, no dowels in
shoulder, no cure on CTOGB Most asphalt work controlled by one company
Alternate Design Alternate Bid
Questions?????
THANK YOU!
www.midatlantic.pavement.comwww.pavement.com