Top Banner
 www.tjprc.org [email protected] PREVENTION OF FAILURE TO GIVE A GUARANTEE CONSTRUCTION OF BORED PILES FOUNDATION AT LEMAH IRENG BRIGDE, SEMARANG – SOLO TOLL ROAD, INDONESIA EDY PURWANTO Department of Civil Enginering , Faculty of Civil Engineering and P lanning, Islamic University of Indonesia, Yogyakarta, Indonesia ABSTRACT Lemah Ireng Bridge, section VI, Semarang – Solo toll road is a monumental stru cture for PT. Trans Marga Jateng Tbk., Publics Work Departement, Province of Central Java, Indonesia. The bridge has span of : 85 m – 130 m – 85 m and 25 m width, more than 35 m height above the land surface. The upper structure of the bridge is box girder and the sub-structure is bored piles foundation. The bridge consists of two piers (P-1 and P-2) and two abutments (Abut-1 and Abut-2). The Construction staging of Lemah Ireng bridge is a balanced cantilever method. The pier P-1 is located on valey with a slope steep and the foundation structure laids on the clay shale, so to ensure the structure stabilities needs geotechnical studies. This paper presents the historical case failure of the slope above the Pier P-1, results of Inclinometer measurement and analysis of slope stability uses Plaxis version 8.50. KEYWORDS: Lemah Ireng Bridge, Clay shale, Slope Failure, Inclinometer, Slope Stability INTRODUCTION Toll road construct ion is verry important activity to provide a good transportation public and to s olve the traffics  jam in the national road fro m Semarang to Solo and the traffic jam in the national road relies the surrounding cities in the Central Java province. Toll road Semarang – Solo is constructed in two phases . Phase I is Semarang - Bawen section and the second phase is Bawen - Solo section. The main road alinnement passes at the villages, hilleys, forresters and agricultures areas. Based on the topography, the bridge should be bulit along from station 22+125 to station 22+840, that is Lemah Ireng bridge. The structure of the bridge consists of two piers (Piers P1 and P2) and two abutments (Abutment A1 and A2). The Lemah Ireng Bridge has tree spans of 85 m – 130 m – 85 m and 25 m witdh. The upper structure of the bridge is box girder and the sub structure is bored piles foundation. The Construction staging of Lemah Ireng bridge is a balanced cantilever method. (see Figure 1) Lemah Ireng bridge has a span 300 meters length and high from ground level more than 30 meters is a monumental project for PT. Trans Marga Jateng Tbk., Publics Work Department, Province of Central Java. That's because the amount of building bridges, in this project new and high technology used and the amount of the cost allocated, so that development requires expertise, supervision measured and well planned in order to get the maximum out according to plan.  International Journal of Civil, Structural, Environmental and Infrastructure Engineering Research and Development (IJCSEIERD) ISSN(P): 2249-6866; ISSN(E): 2249-7978 Vol. 5, Issue 2, Apr 2015, 69-80 © TJPRC Pvt. Ltd.
12

9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

Jun 01, 2018

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

8/9/2019 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

http://slidepdf.com/reader/full/9-civil-ijcseierd-prevention-of-failure-at-edy-purwanto-indonesia 1/12

 

www.tjprc.org  [email protected]

PREVENTION OF FAILURE TO GIVE A GUARANTEE CONSTRUCTION

OF BORED PILES FOUNDATION AT LEMAH IRENG BRIGDE,

SEMARANG – SOLO TOLL ROAD, INDONESIA

EDY PURWANTO

Department of Civil Enginering , Faculty of Civil Engineering and Planning, Islamic University of Indonesia,

Yogyakarta, Indonesia

ABSTRACT

Lemah Ireng Bridge, section VI, Semarang – Solo toll road is a monumental structure for PT. Trans Marga Jateng

Tbk., Publics Work Departement, Province of Central Java, Indonesia. The bridge has span of : 85 m – 130 m – 85 m and

25 m width, more than 35 m height above the land surface. The upper structure of the bridge is box girder and the

sub-structure is bored piles foundation. The bridge consists of two piers (P-1 and P-2) and two abutments (Abut-1 and

Abut-2). The Construction staging of Lemah Ireng bridge is a balanced cantilever method. The pier P-1 is located on valey

with a slope steep and the foundation structure laids on the clay shale, so to ensure the structure stabilities needs

geotechnical studies. This paper presents the historical case failure of the slope above the Pier P-1, results of Inclinometer

measurement and analysis of slope stability uses Plaxis version 8.50.

KEYWORDS: Lemah Ireng Bridge, Clay shale, Slope Failure, Inclinometer, Slope Stability

INTRODUCTION

Toll road construction is verry important activity to provide a good transportation public and to solve the traffics

 jam in the national road from Semarang to Solo and the traffic jam in the national road relies the surrounding cities in the

Central Java province. Toll road Semarang – Solo is constructed in two phases. Phase I is Semarang - Bawen section and

the second phase is Bawen - Solo section.

The main road alinnement passes at the villages, hilleys, forresters and agricultures areas. Based on the

topography, the bridge should be bulit along from station 22+125 to station 22+840, that is Lemah Ireng bridge.

The structure of the bridge consists of two piers (Piers P1 and P2) and two abutments (Abutment A1 and A2). The Lemah

Ireng Bridge has tree spans of 85 m – 130 m – 85 m and 25 m witdh. The upper structure of the bridge is box girder and the

sub structure is bored piles foundation. The Construction staging of Lemah Ireng bridge is a balanced cantilever method.

(see Figure 1)

Lemah Ireng bridge has a span 300 meters length and high from ground level more than 30 meters is a

monumental project for PT. Trans Marga Jateng Tbk., Publics Work Department, Province of Central Java. That's because

the amount of building bridges, in this project new and high technology used and the amount of the cost allocated, so that

development requires expertise, supervision measured and well planned in order to get the maximum out according to plan. 

International Journal of Civil, Structural,

Environmental and Infrastructure Engineering

Research and Development (IJCSEIERD)

ISSN(P): 2249-6866; ISSN(E): 2249-7978

Vol. 5, Issue 2, Apr 2015, 69-80

© TJPRC Pvt. Ltd.

Page 2: 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

8/9/2019 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

http://slidepdf.com/reader/full/9-civil-ijcseierd-prevention-of-failure-at-edy-purwanto-indonesia 2/12

70  Edy Purwanto

Impact Factor (JCC): 5.7179 Index Copernicus Value (ICV): 3.0

Lemah Ireng bridge stands up on clay-shale. Clay-shale is a type of ground rock hard if not disturbed,

but otherwise the clay-shale when peeled, ground clay-shale contact with water and exposed to sunlight, the soil properties

of clay-shale will change. Physically clay-shale changes into mud and soil strength decreased significantly.

The slip failure occurred on the natural slope above Pier P-1 when the plat-form of Pier P-1 was constructed.

This failure caused by rain-fall infiltre enter the clay shale and it cause decline the shear strength of soil and be side that,

the soil work was realised in rain season,

Slope collapse occurred is located on top of Pier P-1 includes a fairly wide area and a large land mass, so that it

feared would disturb the implementation of the foundation work and influance the bored pile foundation stability Pier P-1

that lies beneath ( see Figure 2 )

Based on the situation and the condition in the field, the designer gave instruction to instale Inclinometer

instrument to mesure the soil mouvement. A new slope should be built in this place to prevent the landslide and ensuit this

structure to give a guarantee construction of bored piles foundation. he success of foundation construction on clay shale

relies on proper planning, design, construction control and site supervision. The construction methods employed at site also

have significant effect to ensure the successfully.

This paper presents the historical case failure of the slope above the Pier P-1, results of Inclinometer

measurement and analysis of slope stability with Paxis version 8.50.

Fiigure 1: Structure of Lemah Ireng Bridge Sta. 22+625

Page 3: 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

8/9/2019 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

http://slidepdf.com/reader/full/9-civil-ijcseierd-prevention-of-failure-at-edy-purwanto-indonesia 3/12

Prevention of Failure to Give a Guarantee Construction of Bored Piles 71Foundation at Lemah Ireng Brigde, Semarang – Solo Toll Road, Indonesia

www.tjprc.org  [email protected]

Figure 2: Slope Failure Lacated at Above Pier P-1 Sta. 22+625

METHODOLOGY

General parameter of bridge: the structural concrete for all members of the bridges shall comply with the

following : Ec = 33234 Mpa, Deck = f’c= 40 Mpa., Pilecap and Abutment = f’c= 35 Mpa, Pile = f’c=30 MPA and Strength

at jacking = f’c= 35Mpa. Where f’c is the specifiied compressive strength of concrete at 28 days. Pier P-1 structure of

Lemah Ireng bridge supports the maximum bridge load because this structure located at the longest bridge span. This

structure laids on the steep valey with the natural slope steep and stands up on clay-shale.

Slope collapse occurred on the slopes located on the top position Pier P-1 stand . The collapse occurred at the time

of preparation work plat form for Pier P-1 Sta . 22 + 625 is in progress and the work takes place in the rainy season. To

assess more comprehensively on the slope collapse then the first step to do is to do a soil investigation at the site of the

collapse.

Soil investigation has realized specially at slope failure location and around Pier P-1 Sta 22 + 625. The objective

is to get a information about soil layers, condition and characteristics of subsoil, soil type and water level. The Figure 3

shows a schematic profile of sub-soil and Table 1 presents the result of laboratory tests of the soil properties.

Figure 3: Subsoil Profile of the Site

Page 4: 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

8/9/2019 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

http://slidepdf.com/reader/full/9-civil-ijcseierd-prevention-of-failure-at-edy-purwanto-indonesia 4/12

72  Edy Purwanto

Impact Factor (JCC): 5.7179 Index Copernicus Value (ICV): 3.0

Table 1: Properties of the Clay-Shale

No. Clayshale

w

Natural

(%)

w

Saturated

(%)

GS

Compressive

Strength

(kg/cm2)

Cohesion

(kg/cm2)

Friction

Angle

( o )

Composition

Ca

(%)

Na

(%)

1. Tuffa 32,70 100 2,67 - 6,40 22 - -2.

Grey and

weathering 9,79 125,21 2,82 45,234 11,28 37,01 0,88 0,70

3.Dark andfresh 11,69 61,96 2,91 73,754 17,83 38,40 3,94 0,74

Source: PT. Selimut Bumi Adhi Cipta, 2012

The auther side, the condition in the field indicate that the ground moves downwards make a slit width of 1.00

meters along the northern slope. A sliding slope forms a gap and is accompanied by get out water significantly from the

gap. It indicates that the landslide which occurred caused by a rain water infiltrates into the ground and caused by a soil

cutting on the foot of the slope. The sliding slope include a fairly wide area and the movement of soil is predicted will

push the bored pile Pier P-1.

It will disturbs the smooth implementation of bored pile foundation work and raises fears would destabilize the

individual bored pile foundation before the time of execution of bored pile foundation united by a pile cap. Before the

bored pile foundation work carried out then this slope sliding problems should be studied comprehensively and find the

best solution first. The landslide covers a large area avalanche and to know more details of the landslide installed several

pieces of apparatus Inclinometer around the area until the establishment of the location of Pier P-1 Lemah Ireng bridge.

We predict this event disturbs the bored piles construction and the stability of the single bored pile, so it should be looked

for a good solution before the bored piles are constructed. To find out how much area that suffered catastrophic landslide

and will endanger the foundations, in the field needs some tools Inclinometer installed around the landslide area until thelocation of Pier P-1. Be expected with this recording and monitoring will be knowed the area of landslide and looked for

the good method to solve the problems occurs. The next will provide a guarantee of the stability of the foundation

structure at Pier P-1 .

INCLINOMETER MEASUREMENT

An Inclinometer or Clinometer is an instrument for measuring angles of slope (or tilt), elevation or depression of

an object with respect to gravity. Inclinometer measure both inclines (positive slopes, as seen by an observer looking

upwards) and declines (negative slopes, as seen by an observer looking downward) using three different units of measure :

degrees, percent and topo.

To indiquate a movement of soil in around of the slope location and location of the Pier-P1 structure, was

installed several inclinometers to measure the landslide or soil lateral mouvement. The observation with the inclinometers

take time more than 30 days and 25 m depth from the surface land existing. Layout of the Inclinometers is presented in

Figure 3 below.

Page 5: 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

8/9/2019 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

http://slidepdf.com/reader/full/9-civil-ijcseierd-prevention-of-failure-at-edy-purwanto-indonesia 5/12

Prevention of Failure to Give a Guarantee Construction of Bored Piles 73Foundation at Lemah Ireng Brigde, Semarang – Solo Toll Road, Indonesia

www.tjprc.org  [email protected]

Figure 4: Layout of the Inclinometer at Pier-P1 Sta. 22+625

The results of the mesurement with five inclinometers installed shows at Figure 5.

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

-0.060 -0.040 -0.020 0.000 0.020 0.040 0.060

Base Reading 15/03/12

3/4/2012

4/4/2012

5/4/2012

7/4/2012

9/4/2012

DISPLACEMENT VAL UE FACE A/B

GRAPHIC DISPLACEMENT IN-01

FACE A/B

A (Lereng)

D (Kanan)C (Kiri)

B ( !"an )

 

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

- 0.020 - 0.015 - 0.010 - 0.005 0.000 0.005 0.010 0.015 0.020

Base Reading 16/03/2012

19/03/12

20/03/12

21/03/12

22/03/12

24/03/12

26/03/12

27/03/12

28/03/12

29/03/12

30/03/12

31/03/12

02/04/12

DISPLACEMENT VALUE FACE C/D

GRAPHIC DISPLACEMENTIN 02

FACE C/D

A ( #a$an )

D ( Kanan)( Kiri ) C

B (!"an)

 

Page 6: 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

8/9/2019 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

http://slidepdf.com/reader/full/9-civil-ijcseierd-prevention-of-failure-at-edy-purwanto-indonesia 6/12

74  Edy Purwanto

Impact Factor (JCC): 5.7179 Index Copernicus Value (ICV): 3.0

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

-0.040 -0.030 -0.020 -0.010 0.000 0.010 0.020 0.030 0.040

Base Reading 28/03/12

29/03/12

30/03/12

31/03/12

2/4/2012

DISPLACEMENT VALUE FACE A/B

GRAPHIC DISPLACEMENT IN-03

FACE A/B

A ( %!ngai )

DC ( &iri sa'a)

B ( !"an)

    D    E    P    T    H    (   m   e    t   e   r    )

 

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

-0.100 -0.050 0.000 0.050 0.100

Base Reading 15/03/12

16/03/2012

19/03/12

20/03/12

21/03/12

22/03/12

24/03/12

DISPLACEMENT VAL UE FACE A/B

GRAPHIC DISPLACEMENT IN-0

FACE A/B

 

0.0 

0.5 

1.0 

1.5 

2.0 

2.5 

3.0 

3.5 

4.0 

4.5 

5.0 

5.5 

6.0 

6.5 

7.0 

7.5 

8.0 

8.5 

9.0 

9.5 

10.0 

10.5 

11.0 

11.5 

12.0 

12.5 

13.0 

13.5 

14.0 

14.5 

15.0 

15.5 

16.0 

16.5 

17.0 

17.5 

18.0 

18.5 

19.0 

19.5 

20.0 

20.5 

21.0 

21.5 

22.0 

22.5 

23.0 

23.5 

24.0 

24.5 

25.0 

25.5 

26.0 

26.5 

27.0 

27.5 

28.0 

28.5 

29.0 

29.5 

30.0 

30.5 

31.0 

31.5 

32.0 

32.5 

33.0 

33.5 34.0 

34.5 

35.0 

35.5 

36.0 

36.5 

37.0 

37.5 

38.0 

38.5 

39.0 

39.5 

40.0 

40.5 

41.0 

41.5 

42.0 

42.5 

43.0 

43.5 

44.0 

44.5 

45.0 

45.5 

46.0 

46.5 

47.0 

47.5 

48.0 

48.5 

49.0 

49.5 

50.0 

-0.050 -0.040 -0.030 -0.020 -0.010 0.000 0.010 0.020 0.030 0.040 0.050

    D    E    P    T    H    (   m   e   t   e   r    )

DISPLACEMENT VALUE FACE A/B ( meter )

GRAPHIC DISPLACEMENT IN - 08

FACE A/BDATE READING : 21 / 04 / 2012

BASE READING 04/04/2012

DATE READING 16/04/2012

DATE READING 17/04/2012

DATE READING 18/04/2012

DATE READING 19/04/2012

DATE READING 20/04/2012

DATE READING 21/04/2012

 

Figure 5: Results of Mesurement Inclinometers at Sta. 22+625

Figure 5 shows the results of several tools inclinometer measurement. Inclinometer number 01 indicate that

there are soil mouvement from the surface land untill 28 m depth from the top surface. The value of the soil mouvement isabout from 10 cm to 15 cm. Inclinometer no.02 shows the mouvement of the soil in two directions ranges from 5 – 10 cm

Page 7: 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

8/9/2019 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

http://slidepdf.com/reader/full/9-civil-ijcseierd-prevention-of-failure-at-edy-purwanto-indonesia 7/12

Prevention of Failure to Give a Guarantee Construction of Bored Piles 75Foundation at Lemah Ireng Brigde, Semarang – Solo Toll Road, Indonesia

www.tjprc.org  [email protected]

from the land surface to 25 m depth. Inclinometer no.3 shows the soil mouvement in two directions with ranges 20 cm

from top surface to 5 m depth and the soil mouvement change direction to 10-12 cm till the end of the Inclinometer.

Inclinometer no.04 address the mouvement of soil vers 1m at the top of surface and return to value of 0-5 cm displacement

untill the 30 m depth. Inclinometer no. 08 shows the soil mouvement from the top vers 10 cm and decline automatically atthe end. In general, the measurement of all Inclinometer shows a soil maximum mouvement at the top surface land and

tends decline untill the end of the Inclinometer. Beside that, in the field, there are differences elevation approximately 25 m

between the original surface land (before slipe failure happen) and after slipe failure happened.This prouves that the slip

failure happened is caused by reduced shear strength of the soil significantly.

SLOPE STABILITY

Pier P-1 structure laids on the steep natural valey and stands up on clay-shale. The slip failure occured when the

plat-form of Pier P-1 structure was realised. To take over this problem happened in the field and give a guarrantee

succesfully bored pile foundation construction needs geotechnical engineering

Results of the investigation in the field indiquate that the slope failure was identified caused by infiltration of rain

fall into to the soil and it cause reduction of shear strength of soil. From observation in the field the rain-fall water get out

at the plat-form of Pier P-1 structure area. Based on that conditions and the topography existing was proposed a new slope

built in four steps with 1,50 m berm width and the slope is made 1 V : 2 H. To analizys the slope stability use Plaxis

program version 8.50. The parameters of soil is presented in Table 2. below.

Table 2: Soil Properties

Parameter Symbol Tuffa Clayshale

Weight volumeunsaturated 17,50 16,00 kN/m3

Weight volume

saturated  18,50 18,50 kN/m

Modulus elastisitas 9200 9200 kN/m2 

Poisson ratio 0,33 0,33 -

Cohesion 64 50 kN/m2 

Frictian angle 22 20

Dilatance ψ  0 0 -

Source : PT Waskita Karya, 2012

The results of the Plaxis program version 8.50 is presented in Figures 5,6,7,8,9,10 and 11 as below.

Figure 6: Topography Model of Slope Stability Analyzis Proposed

Page 8: 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

8/9/2019 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

http://slidepdf.com/reader/full/9-civil-ijcseierd-prevention-of-failure-at-edy-purwanto-indonesia 8/12

76  Edy Purwanto

Impact Factor (JCC): 5.7179 Index Copernicus Value (ICV): 3.0

Figure 7: Deformed Mesh

Figure 8: Total Displacements

Figure 9: Direction of Soil Displacements

Page 9: 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

8/9/2019 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

http://slidepdf.com/reader/full/9-civil-ijcseierd-prevention-of-failure-at-edy-purwanto-indonesia 9/12

Prevention of Failure to Give a Guarantee Construction of Bored Piles 77Foundation at Lemah Ireng Brigde, Semarang – Solo Toll Road, Indonesia

www.tjprc.org  [email protected]

Figure 10: Effective Stress

Figure 11: Maximum Potential of Slope Failure

Figure 12: Safety Factors

Page 10: 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

8/9/2019 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

http://slidepdf.com/reader/full/9-civil-ijcseierd-prevention-of-failure-at-edy-purwanto-indonesia 10/12

78  Edy Purwanto

Impact Factor (JCC): 5.7179 Index Copernicus Value (ICV): 3.0

The result of the Plaxis program shows the deformed mash in Figure 7. The Figure 8 shows total displacements

543,78.10-3

m and the direction of soil displacements is showed in Figure 9, Maximun potential of slope failure is presented

in Figure 10 and the Effective stress is -454,86 kN/m2 presented in Figure 11. Finally, the Figure 12 shows the safety factor

obtained. The safety factor is 2,60 more than 1,30 recomended in the field, so the slope is stable. From the slope stabilityanalysis used Plaxis version 8.50 got a good solution to prevent slope failure with a new slope built in four steps with 1,50

m berm width and the slope is made 1 V : 2 H.

CONCLUSIONS

The geotechnic review is important for a civil engineering consultant, consultant supervisi and contractor to have

some fundamental geotechnical knowledge to prevent failure occurs. To prevent the slope failure, a new slope should be

built in four steps with 1,50 m berm width and the slope is made 1 V : 2 H is recommanded. This new slope structure can

ultimately facilitate the work in the field

ACKNOWLEDGEMENTS

The authors wish to acknowledge the contributions and cooperations of PT. Trans marga Jateng and PT. Waskita

Karya on this research and the contruction in the field.

REFERENCES

1.  Abramson W.T. et all. (1996). Slope Stability and Stabilization Methods, John Wiley & Sons, Inc. New York.

2. 

Das B.M. (1984). Fundamentals of Soil Dynamic, Elservier Science Publishing Co.Inc. New York, USA.

3.  Das, B.M. (1999). Principles of Foundation Engineering 4th Edition, Brooks/Cole Publishing Company.

4. 

Duncan, J.M., and Buchignani, A.L.(1975).  An Engineering Manual for Stability Studies, Civil Engineering

270B, University of California, Barkeley, CA.

5.  Paulus P. Rahardjo. (2005.). Manual Pondasi Tiang, Edisi- 3, GEC – Geotechnical Engineering Center, Bandung.

6. 

Dainty Zahrina Putri. (2013).  Analisis Stabilitas Lereng dengan Perkuatan Geotekstil Menggunakan Software

Plaxis, Studi Kasus pada Lereng Sta. 2+225, Proyek Jalan Tol Semarang-Solo, Tugas Akhir S1, Yogyakarta.

7.  PT. Global Perfex Synergi & ASS. (2012.).  Justifikasi Teknik Pekerjaan Timbunan Abutment dan Badan Jalan

 Lokal serta Fondasi Tiang Bor pada Overpass Sta.22+125 s/d Sta. 22+840, Bawen. Semarang, Semaran.

8. 

PT. Global Perfex Synergi & ASS. (2012).  Justifikasi Teknik Pekerjaan Dinding Penahan Tanah (Retainning

Wall) pada Abutment A2, Sta.22+125, Bawen. Semarang, Semarang.

9.  PT. Global Perfex Synergi. (2012).  Justifikasi Teknik Fondasi Tiang Bor pada Overpass Sta.22+850, Bawen,

Semarang.

10.  PT. Global Perfex Synergi. (2012).  Justifikasi Teknik Fondasi Tiang Bor pada Overpass Sta.21+800, Bawen,

Semarang.

11.  PT. Selimut Bumi Adhi Cipta. (2012).  Hasil uji Laboratotium tanah Batuan, Pembangunan Jalan Tol Semarang

 – Bawen, Paket VI , Semarang.

Page 11: 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

8/9/2019 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

http://slidepdf.com/reader/full/9-civil-ijcseierd-prevention-of-failure-at-edy-purwanto-indonesia 11/12

Prevention of Failure to Give a Guarantee Construction of Bored Piles 79Foundation at Lemah Ireng Brigde, Semarang – Solo Toll Road, Indonesia

www.tjprc.org  [email protected]

12.  PT. Waskita Karya Tbk. (2011). Laporan Soil Investigation Bor Mesin/Bor Log, Semarang.

13. 

PT. Waskita Karya Tbk. (2012).  Laporan Pelaksanaan Pengeboran fondasi tiang bor , Semarang.

14.  PT. Wiecon Consultant. (2012). Sub-structure and Superstructure for Lemah Ireng Bridge, Final report,

Semarang.

15. 

PT.Wirama Karya Consultant. (2004). Pekerjaan Pembangunan Jalan Tol Semarang – Solo, Semarang, Jawa

Tengah.

AUTHORS DETAIL

The Author is graduated in French 1996, Geotechnic expert, Director of Geotechnic Study Center and a Lecturer

at Department. of Civil Engineering, Faculty of Civil Engineering and Planning, Islamic University of Indonesia

Page 12: 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

8/9/2019 9. Civil - IJCSEIERD -Prevention of Failure at - EDY PURWANTO - Indonesia

http://slidepdf.com/reader/full/9-civil-ijcseierd-prevention-of-failure-at-edy-purwanto-indonesia 12/12