Top Banner
8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8
76

8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

Dec 27, 2015

Download

Documents

Rachel Elliott
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-1Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Project Management

Chapter 8

Page 2: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-2Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

■The Elements of Project Management

■CPM/PERT

■Probabilistic Activity Times

■Microsoft Project

■Project Crashing and Time-Cost Trade-Off

■Formulating the CPM/PERT Network as a Linear Programming Model

Chapter Topics

Page 3: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-3Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

■ Network representation is useful for project analysis.

■ Networks show how project activities are organized and are used to determine time duration of projects.

■ Network techniques used are:

▪ CPM (Critical Path Method)

▪ PERT (Project Evaluation and Review Technique)

■ Developed independently during late 1950s.

Overview

Page 4: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-4Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Elements of Project Management

■ Management is generally perceived as concerned with planning, organizing, and control of an ongoing process or activity.

■ Project management is concerned with control of an important activity for a relatively short period of time after which management effort ends.

■ Primary elements of project management to be discussed: Project Planning Project Return Project Team Project Control

Page 5: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-5Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Elements of Project ManagementProject Planning

■Objectives

■Project scope

■Contract requirements

■Schedules

■Resources

■Personnel

■Control

■Risk and problem analysis

Page 6: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-6Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Figure 8.1 The project management process

The Project Management Process

Page 7: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-7Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Elements of Project ManagementProject Return

Return on investment (ROI) is a measure used to evaluate projects calculated by dividing the dollar gain minus the dollar cost by the dollar cost. gain from project - cost of projectROI

cost of project

• ROI can be used to rank projects

• Not all project benefits can be measured in dollars

Page 8: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-8Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

■ Project team typically consists of a group of individuals from various areas in an organization and often includes outside consultants.

■ Members of engineering staff often assigned to project work.

■ Project team may include workers.

■ Most important member of project team is the project manager.

■ Project manager is often under great pressure because of uncertainty inherent in project activities and possibility of failure. Potential rewards, however, can be substantial.

■ Project manager must be able to coordinate various skills of team members into a single focused effort.

Elements of Project ManagementThe Project Team

Page 9: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-9Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Elements of Project ManagementScope Statement

■ Document providing common understanding of project.

■ Justification describing the factors giving rise to need for project.

■ Expected results and what constitutes success.

■ List of necessary documents and planning reports.

■ Statement of work (SOW) - a planning document for individuals, team members, groups, departments, subcontractors and suppliers, describing what are required for successful completion on time.

Page 10: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-10Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Elements of Project ManagementWork Breakdown Structure (WBS) (1 of 2)

■ WBS breaks down project into major components (modules).

■ Modules are further broken down into activities and, finally, into individual tasks.

■ Identifies activities, tasks, resource requirements and relationships between modules and activities.

■ Helps avoid duplication of effort.

■ Basis for project development, management , schedule, resources and modifications.

■ Approaches for WBS development:1. Top down process 2. Brainstorm entire project

Page 11: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-11Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Figure 8.2 WBS for computer order-processing system project

Elements of Project ManagementWork Breakdown Structure (2 of 2)

Page 12: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-12Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Elements of Project ManagementResponsibility Assignment Matrix (1 of 2)

■ RAM shows who is responsible for doing the necessary work in the project

■ Project manager assigns work elements to organizational units, departments, groups, individuals or subcontractors.

■ Uses an organizational breakdown structure (OBS).

■ OBS is a table or a chart showing which organizational units are responsible for work items.

■ OBS leads to the responsibility assignment matrix (RAM)

Page 13: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-13Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Elements of Project ManagementResponsibility Assignment Matrix (2 of 2)

Figure 8.3 A responsibility assignment matrix

Page 14: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-14Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Elements of Project ManagementProject Scheduling■ Project schedule evolves from planning documents,

with focus on timely completion.

■ Critical element in project management – source of most conflicts and problems.

■ Schedule development steps:1. Define activities, 2. Sequence

activities,3. Estimate activity times, 4. Develop

schedule.

■ Gantt chart and CPM/PERT techniques can be useful.

■ Computer software packages available, e.g. Microsoft Project.

Page 15: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-15Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Elements of Project ManagementGantt Chart (1 of 2)

■ Popular, traditional technique, also known as a bar chart -developed by Henry Gantt (1914).

■ Direct precursor of CPM/PERT for monitoring work progress.

■ A visual display of project schedule showing activity start and finish times and where extra time is available.

■ Suitable for projects with few activities and precedence relationships.

■ Drawback: precedence relationships are not always discernible which limits chart’s use for smaller projects

Page 16: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-16Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Elements of Project ManagementGantt Chart (2 of 2)

Figure 8.4 A Gantt chart

Page 17: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-17Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Elements of Project ManagementProject Control■ Process of ensuring progress toward successful

completion.

■ Monitoring project to minimize deviations from project plan and schedule.

■ Corrective actions necessary if deviations occur.

■ Key elements of project control Time management Cost management Performance management Earned value analysis (EVA)

Page 18: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-18Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

■ A branch reflects an activity of a project.

■ A node represents the beginning and end of activities, referred to as events.

■ Branches in the network indicate precedence relationships.

■ When an activity is completed at a node, it has been realized.

The Project NetworkCPM/PERT

Figure 8.5 Nodes and branches

Activity-on-Arc (AOA) Network

Page 19: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-19Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

The Project NetworkHouse Building Project DataNumber

Activity Predecessor

Duration

1 Design house and obtain financing

-- 3 months

2 Lay foundation 1 2 months

3 Order and receive materials 1 1 month

4 Build house 2,3 3 months

5 Select paint 2, 3 1 month

6 Select carper 5 1 month

7 Finish work 4, 6 1 month

Page 20: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-20Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

■ Activities can occur at the same time (concurrently).

■ Network aids in planning and scheduling.

■ Time duration of activities shown on branches.

The Project NetworkConcurrent Activities

Figure 8. 6 Concurrent activities for house-building project

Page 21: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-21Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

■ A dummy activity shows a precedence relationship but reflects no passage of time.

■ Two or more activities cannot share the same start and end nodes.

The Project NetworkDummy Activities

Figure 8. 7 A dummy activity

Page 22: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-22Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

The Project NetworkAON Network for House Building Project

Activity-on-Node (AON) Network A node represents an activity, with its label and time shown on the node The branches show the precedence relationships Convention used in Microsoft Project software

Figure 8.8 AON network

Page 23: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-23Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

The Project NetworkPaths Through a Network

Table 8.1Paths through the house-building

network

Path EventsA 1247

B 12567

C 1347

D 13567

Page 24: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-24Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

The critical path is the longest path through the network; the minimum time the network can be completed. From Figure 8.8:

Path A: 1 2 4 7 3 + 2 + 3 + 1 = 9

months

Path B: 1 2 5 6 7 3 + 2 + 1 + 1 + 1= 8

months

Path C: 1 3 4 7 3 + 1 + 3 + 1 = 8

months

Path D: 1 3 5 6 7 3 + 1 + 1 + 1 + 1 = 7

months

The Project NetworkThe Critical Path

Page 25: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-25Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

The Project NetworkActivity Start Times

Figure 8.9 Activity start time

Page 26: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-26Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

The Project NetworkActivity Scheduling in Activity-on-Node Configuration

Figure 8.10 Activity-on-node configuration

Page 27: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-27Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

■ ES is the earliest time an activity can start:

■ EF is the earliest start time plus the activity time:

The Project NetworkActivity Scheduling : Earliest Times

Figure 8.11 Earliest activity start and finish times

EF ES t

{ }ES Maximum EF immediate predecessors

Page 28: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-28Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

■ LS is the latest time an activity can start without delaying critical path time:

The Project NetworkActivity Scheduling : Latest Times

Figure 8.12 Latest activity start and finish times

■ LF is the latest finish time:

LS LF t

{ }LF Minimum LS following activities

Page 29: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-29Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Slack is the amount of time an activity can be delayed without delaying the project: S = LS – ES = LF - EF

Slack Time exists for those activities not on the critical path for which the earliest and latest start times are not equal.

Shared Slack is slack available for a sequence of activities.

The Project NetworkActivity Slack Time (1 of 2)

Table 8.2

*Critical path

Activity

LS ES LF EF Slack, S

*1 0 0 3 3 0

*2 3 3 5 5 0

3 4 3 5 4 1

*4 5 5 8 8 0

5 6 5 7 6 1

6 7 6 8 7 1

*7 8 8 9 9 0

Page 30: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-30Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

The Project NetworkActivity Slack Time (2 of 2)

Figure 8.13 Activity slack

Page 31: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-31Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

■Activity time estimates usually cannot be made with certainty.

■PERT used for probabilistic activity times.

■In PERT, three time estimates are used: most likely time (m), the optimistic time (a), and the pessimistic time (b).

■These provide an estimate of the mean and variance of a beta distribution:

variance:

mean (expected time):

a 4m bt 6

2b - a6

v

Probabilistic Activity Times

Page 32: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-32Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Probabilistic Activity TimesExample (1 of 3)

Figure 8.14 Network for order processing system installation

Page 33: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-33Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Probabilistic Activity TimesExample (2 of 3)

Table 8.3 Activity time estimates for figure 8.14

Page 34: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-34Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Probabilistic Activity TimesExample (3 of 3)

Figure 8.15 Earliest and latest activity times

Page 35: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-35Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

■ Expected project time is the sum of the expected times of the critical path activities.

■ Project variance is the sum of the critical path activities’ variances

■ The expected project time is assumed to be normally distributed (based on central limit theorem).

■ In example, expected project time (tp) and variance (vp) interpreted as the mean () and variance (2) of a normal distribution:m = 25 weeks

2 = 62/9

= 6.9 weeks2

Probabilistic Activity TimesExpected Project Time and Variance

Page 36: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-36Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

■Using the normal distribution, probabilities are determined by computing the number of standard deviations (Z) a value is from the mean.

■The Z value is used to find the corresponding probability in Table A.1, Appendix A.

Probability Analysis of a Project Network (1 of 2)

Page 37: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-37Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Probability Analysis of a Project Network (2 of 2)

Figure 8.16 Normal distribution of network duration

Page 38: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-38Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Probability Analysis of a Project NetworkExample 1 (1 of 2)

Figure 8.17 Probability that the network will be completed in 30 weeks or less

Page 39: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-39Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

What is the probability that the new order processing system will be ready by 30 weeks?

Probability Analysis of a Project NetworkExample 1 (2 of 2)

2

25

6.9

6.9 2.63

30 251.90

2.63

weeks

xZ

Z

Z value of 1.90 corresponds to probability of .4713 in Table A.1, Appendix A. The probability of completing project in 30 weeks or less: (.5000 + .4713) = .9713.

Page 40: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-40Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Probability Analysis of a Project NetworkExample 2 (1 of 2)

Figure 8.18 Probability the network will be completed in 22 weeks or less

Page 41: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-41Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

■ A customer will trade elsewhere if the new ordering system is not working within 22 weeks. What is the probability that she will be retained?

Z = (22 - 25)/2.63 = -1.14

■ Z value of 1.14 (ignore negative) corresponds to probability of .3729 in Table A.1, Appendix A.

■ Probability that customer will be retained is .1271 (.5000-.3729)

Probability Analysis of a Project NetworkExample 2 (2 of 2)

Page 42: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-42Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

CPM/PERT Analysis with QM for Windows & Excel QM (1 of 2)

Exhibit 8.1: QM for Windows solution output for system installation

Page 43: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-43Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

CPM/PERT Analysis with QM for Windows & Excel QM (2 of 2)

Exhibit 8.2: Excel QM solution

Input time estimates

Input activity predecessors

Page 44: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-44Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Microsoft Project handles only AON networks.

Analysis with Microsoft Project (1 of 6)

Exhibit 8.3

Gantt chart tools

Create precedence relationships by typing in predecessor activities, separated by commas, or by clicking on “link” icon

Start date

Activity duration, i.e., “3 mo”

Activity name

Page 45: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-45Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Analysis with Microsoft Project (2 of 6)

Exhibit 8.4

Change timescale

Click on “Entire Project” to fit Gantt chart on screen

Predecessor activities; separated by commas if more than one

Right-click on time line to change scale

Page 46: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-46Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Analysis with Microsoft Project (3 of 6)

Exhibit 8.5

Select “Critical Tasks” to highlight critical path

Critical activities highlighted in red

Page 47: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-47Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Analysis with Microsoft Project (4 of 6)

Exhibit 8.6

Click “Zoom” to make network larger on screen

Page 48: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-48Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Analysis with Microsoft Project (5 of 6)

Exhibit 8.7

Page 49: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-49Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Analysis with Microsoft Project (6 of 6)

Exhibit 8.8

Click on “Network Diagram” to get network

Critical path in red

Page 50: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-50Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

■Project duration can be reduced by assigning more resources to project activities.

■However, doing this increases project cost.

■Decision is based on analysis of trade-off between time and cost.

■Project crashing is a method for shortening project duration by reducing one or more critical activities to a time less than normal activity time.

Project Crashing and Time-Cost Trade-Off Overview

Page 51: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-51Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Project Crashing and Time-Cost Trade-Off Example Problem (1 of 5)

Figure 8.19 The project network for building a house

Page 52: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-52Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Project Crashing and Time-Cost Trade-Off Example Problem (2 of 5)

Figure 8.20 Time-cost relationship for crashing activity 1

Crash cost & crash time have a linear relationship:

$2000$400 /

5

Total Crash Costweek

Total Crash Time weeks

Page 53: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-53Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Table 8.4 Normal activity and crash data for the Fig 8.19 network

Project Crashing and Time-Cost Trade-Off Example Problem (3 of 5)

Page 54: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-54Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Figure 8.21 Network with normal activity times and weekly crashing costs

Project Crashing and Time-Cost Trade-Off Example Problem (4 of 5)

Page 55: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-55Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Figure 8.22 Revised network with activity 1 crashed

Project Crashing and Time-Cost Trade-Off Example Problem (5 of 5)As activities are crashed, the critical path

may change and several paths may become critical.

Page 56: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-56Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Exhibit

8.9

Project Crashing and Time-Cost Trade-Off QM for Windows

Page 57: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-57Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Project Crashing and Time-Cost Trade-Off General Relationship of Time and Cost (1 of 2)■Project crashing costs and indirect costs

have an inverse relationship.

■Crashing costs are highest when the project is shortened.

■Indirect costs increase as the project duration increases.

■The optimal project time is at the minimum point on the total cost curve.

Page 58: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-58Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Project Crashing and Time-Cost Trade-Off General Relationship of Time and Cost (2 of 2)

Figure 8.23The time-cost trade-off

Page 59: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-59Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

General linear programming model with AOA convention

The objective is to minimize the project duration (critical path time).

The CPM/PERT Network Formulating as a Linear Programming Model

minimize

subject to

, for all activities

, 0

earliest event time of node

earliest event time of node

time of activity

ii

j i ij

i j

i

j

ij

Z x

x x t i j

x x

where

x i

x j

t i j

Page 60: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-60Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

The CPM/PERT Network Example Problem Formulation and Data (1 of 2)

Figure 8.24 CPM/PERT network with earliest event times

Page 61: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-61Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Minimize Z = x1 + x2 + x3 + x4 + x5 + x6 + x7

subject to:

x2 - x1 12x3 - x2 8x4 - x2 4x4 - x3 0x5 - x4 4x6 - x4 12x6 - x5 4x7 - x6 4xi, xj 0

The CPM/PERT Network Example Problem Formulation and Data (2 of 2)

Page 62: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-62Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Exhibit 8.10

The CPM/PERT Network Example Problem Solution with Excel (1 of 4)

B6:B12=B7-B6

Decision variables, B6:B12

Page 63: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-63Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Exhibit 8.11

The CPM/PERT Network Example Problem Solution with Excel (2 of 4)

Page 64: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-64Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Exhibit 8.12

The CPM/PERT Network Example Problem Solution with Excel (3 of 4)

Page 65: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-65Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Exhibit 8.13 Sensitivity report for house-building

project

The CPM/PERT Network Example Problem Solution with Excel (4 of 4)

A shadow price of 1 indicates critical path

Page 66: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-66Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Minimize Z = $400y12 + 500y23 + 3000y24 + 200y45 + 7000y46 + 200y56 + 7000y67

subject to:y12 5 y12 + x2 - x1 12 x7 30 y23 3 y23 + x3 - x2 8 xi, yij ≥ 0y24 1 y24 + x4 - x2 4y34 0 y34 + x4 - x3 0y45 3 y45 + x5 - x4 4y46 3 y46 + x6 - x4 12y56 3 y56 + x6 - x5 4y67 1 x67 + x7 - x6 4

xi = earliest event time of node Ixj = earliest event time of node jyij = amount of time by which activity i j is crashed

Project Crashing with Linear ProgrammingExample Problem – Model Formulation

The objective is to minimize the cost of crashing

Page 67: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-67Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Project Crashing with Linear ProgrammingExcel Solution (1 of 3)

Exhibit 8.14

Page 68: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-68Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Project Crashing with Linear ProgrammingExcel Solution (2 of 3)

Exhibit 8.15

Page 69: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-69Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Project Crashing with Linear ProgrammingExcel Solution (3 of 3)

Exhibit 8.16

Page 70: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-70Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Given this AON network and the data on the following slide, determine the expected project completion time and variance, and the probability that the project will be completed in 28 days or less.

Example Problem (1 of 6)

Page 71: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-71Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Example Problem (2 of 6)

Page 72: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-72Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

a 4m bt 6

2b - a

6v

Example Problem (3 of 6)

Step 1: Compute the expected activity times and variances.

Page 73: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-73Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Example Problem (4 of 6)

Step 2: Determine the earliest and latest activity times & slacks

Page 74: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-74Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Example Problem (5 of 6)

Step 3: Identify the critical path and compute expected completion time and variance.

Critical path (activities with no slack): 1 3 5 7 Expected project completion time: tp = 9+5+6+4 =

24 days

Variance: vp = 4 + 4/9 + 4/9 + 1/9 = 5 (days)2

Page 75: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-75Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

Example Problem (6 of 6)

Step 4: Determine the Probability That the Project Will be Completed in 28 days or less (µ = 24, = 5)

Z = (x - )/ = (28 -24)/5 = 1.79

Corresponding probability from Table A.1, Appendix A, is .4633 and P(x 28) = .4633 + .5 = .9633.

Page 76: 8-1 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.

8-76Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall

All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying,

recording, or otherwise, without the prior written permission of the publisher. Printed in the United States of America.

All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying,

recording, or otherwise, without the prior written permission of the publisher. Printed in the United States of America.