Page 1: 6 th Street Water Main And Street Reconstruction 2013.

6th Street Water Main And Street

Reconstruction

2013

Page 2: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street ReconstructionContacts

City of Jesup – Chris Even, Public Works

Dick Quackenbush, Mayor

LeAnn Even, City Clerk

AECOM – Mark Durbahn, Engineer

Questions or concerns, please call city hall at 827-1522.

Page 3: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street ReconstructionWhat’s Included

Remove and replace existing 6th Street surface from Hawley Street to Prospect Street with new 8” concrete.

Widen 6th Street from 27 feet to 40 feet from Hawley Street to Prospect Street.

Install new 8” water main on 6th Street from Hawley Street to Church Street.

Install new storm sewer intakes at 6th Street and Hawley Street intersection

Page 4: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street ReconstructionWhat’s Included

Connect water customers to new larger mains on 6th Street from Hawley Street to 235 6th Street and on Hawley Street from 5th Street to 7th Street.

Install new sidewalks and driveway approaches.

Install sump pump connections to subdrain for each residence.

Page 5: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street ReconstructionWhat’s Included

Relocate utility poles on east side of 6th Street further away from the street

Remove four trees in city parking on west side of 6th Street.

Temporarily relocate mail boxes. Hydro-seed disturbed areas

Page 6: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street Reconstruction

Provided by AECOM

Page 7: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street Reconstruction

Provided by AECOM

Page 8: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street Reconstruction

Provided by AECOM

Page 9: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street Reconstruction

Provided by AECOM

Page 10: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street Reconstruction

Provided by AECOM

Page 11: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street Reconstruction

Provided by AECOM

Page 12: 6 th Street Water Main And Street Reconstruction 2013.

6th Street ReconstructionSchedule

February 26 – Bid Opening March 5 – Award Contract April/May – Anticipated Start Date May 22 – 1st Day to Close Prospect

Street August 9 – Substantial Completion

Date September 30 – Final Completion

Date

Page 13: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street ReconstructionDetour

South to North: 6th Street to Douglas Street to Main Street to County V62

North to South: County V62 to Main Street to Douglas Street to 6th Street

Page 14: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street ReconstructionAccess

6th Street Water Main Construction

6th Street closed to through traffic, open to local traffic

Driveways temporarily unavailable

6th Street Road Construction: 6th Street closed to all traffic Alleys available Temporary drive constructed

west side from Hawley to 534 6th St.

Page 15: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street ReconstructionAccess

Sidewalk & Driveway Construction

6th Street closed to through traffic, open to local traffic

Temporary drive removed Parking available on street

Page 16: 6 th Street Water Main And Street Reconstruction 2013.

2013 6th Street ReconstructionSubdrain Connections

What’s Allowed:– Sump pumps, buried drainage tiles

What’s Not Allowed:– Downspouts, surface drain

Provided by AECOM

Page 17: 6 th Street Water Main And Street Reconstruction 2013.

6th Street ReconstructionTemporary Easements

5 to 15 feet across front yard All improvements within city right of

way Water service connection, sidewalk

and driveway construction, ingress/egress

Terminate upon completion of project

Page 18: 6 th Street Water Main And Street Reconstruction 2013.

6th Street Reconstruction

Questions or Comments?

Page 19: 6 th Street Water Main And Street Reconstruction 2013.

6th Street ReconstructionChris Even

City Hall Phone: 319-827-1522 Cell Phone: 319-404-3893 Email: [email protected]

Also keep up to date on the city’s website:

www.jesupiowa.com– Look under the “News” Tab