January 31, 2018 Duke Street Reconstruction Project SR 147, Sec 110 & SR 11, Sec 113 Northumberland Borough Northumberland County ~ PennDOT District 3-0
23

Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Oct 16, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

January 31, 2018

Duke Street Reconstruction Project

SR 147, Sec 110 & SR 11, Sec 113

Northumberland Borough

Northumberland County ~ PennDOT District 3-0

Page 2: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Agenda

• Purpose and Need of Project– Ted Deptula, P.E., PennDOT Assistant Construction Engineer

• Construction 2017 Review

• 2018 Construction and Detours– Joe Whitcomb, New Enterprise Project Manager

– Mindy Foresman, PennDOT Project Manager

• Conclusion

• Open House– Duke Street

– Front Street

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 2

Page 3: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Why Now?

3

3

Page 4: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Project Scope of Work

• Roadway Reconstruction

• Drainage

• ADA Ramps, Curb, & Sidewalk

• Intersection Improvements

• Utilities

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 4

Page 5: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Duke Street Reconstruction Project

• Construction Status

– Work started June 5, 2017

– Contractor = New Enterprise Stone and Lime Co., Inc.

– Cost = $13.7M

– Contract completion date is June 2, 2020

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 5

Page 6: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

147

14711

11

Project Limits & Schedule

• 2017 Construction

– Phase 1-3• Duke Street

• 2018 Construction

– Phase 4-9

• Duke Street

– Phase 14 & 15

• Front Street

• 2019 Construction

– Phase 10 – 13

• Water Street

• King Street

• 2020 Construction

– Clean up

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

LOCATION MAP

6

Page 7: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Traffic Phasing

• Maintain access to businesses and residents

• Maintain bicycle/pedestrian traffic

• Pineknotter Days – Week of July 4th each year

• Detour traffic using borough streets

• Restrict non-local truck traffic (>36’)

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 7

Page 8: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

No Parking Area During Detour

Phases 4 through 9

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 8

No Parking Areas:

Existing Condition

Proposed Detour Condition

Parking Lane

Travel Lane

LEGEND

Travel Lane

Page 9: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Existing Condition Proposed Detour Condition

Local Detour Condition

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 9

King, Queen and Orange Streets

Page 10: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

2017 Review

• Duke Street Reconstructed– 5th to 8th Streets

• Utilities – Duke, Front and Water Streets

• Temporary Wearing Course

• Car and Truck Detours

• Trees

10

Page 11: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

TO M

ILTON

PA 147

PA 147

TO SU

NBU

RY

2Roadway 2012Reconstruction

Completed 2017

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

Completed Roadway Work Area

LEGEND

PA 147

TO SU

NBU

RY

PA 147

TO M

ILTON

11

11

2017 Completed Work

Page 12: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

PROJ ECT LOCATIONCOLUMBIA

WEST

MILTON

WINFIELD

MILTON

NEW

LEWISBURG

NORTHUMBERLAND

MONTANDON

Truck Detour &Alternate Routes

SR 147

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

Work Area

Detour (SR 147)

LEGEND

12

Truck

Detour

Page 13: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

2018 Construction Season

Joe Whitcomb, New Enterprise Project Manager

Mindy Foresman, PennDOT Project Manager

• Scope

– Duke Street, Depot to 5th Street

– Front Street, W&L to Sheetz Avenue

• Work shifts

• Detours

13

Page 14: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

CVS Pharmacy

Crouser & Son Tire Services

Joseph W EplerFuneral Home

Amato's Pizza & FamilyCitizens BankSunoco Gas Station

Bobby Orr Signs

Boyer MachineKeystone Communications Services

Cadillac Car Wash

Star Garden

TO SU

NBU

RY

PA 147

TO MILTON

PA 147

Roadway ReconstructionTraffic Control Plan

Phase 4

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

Roadway Work Area

Detour North (SR 147)

LEGEND

Detour South (SR 147)

Partial Sidewalk Replacement on Culvert

14

Duke Street Project

Page 15: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Roadway Reconstruction Traffic Control Plan

Phase 5

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

Suncom Industries

Joseph W Epler Funeral Home

Boyer MachineKeystone Communications Services

Mason JarNorry MotorsNorry PharmacySubway Restaurants

Keystone ForgingCompany, Inc.

Puff Tobacco ProductsValero

Amato's Pizza & FamilyCitizens BankSunoco Gas Station

NorthumberlandChristian School

CVS Pharmacy

Youngs Sporting Goods

Groninger Insurance AgencyConrail Freight Car Wash FacilitySusquehanna Flower Co.Axonic Inkworks Custom Tattoo Studio

Crouser & Son Tire Services

Northumberland Police DepartmentNorthumberland Borough Office

SUN HomeHealth & Hospice

Star Garden

Cadillac Car Wash

TRAFFIC SIGNALTEMPORARY

TO MILTON

PA 147

PA 147TO SUNBURY

PHASE 5 WORK AREA

DETOUR NORTH (SR 147)

LEGEND

DETOUR SOUTH (SR 147)

PHASE 14B/15B WORK AREA

15

Duke Street Project

Page 16: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Youngs Sporting Goods

Mason JarNorry MotorsNorry PharmacySubway Restaurants

Suncom Industries

Puff Tobacco ProductsValero

SUN HomeHealth & Hospice

Keystone ForgingCompany, Inc.

Groninger Insurance AgencyConrail Freight Car Wash FacilitySusquehanna Flower Co.Axonic Inkworks Custom Tattoo Studio

Joseph W Epler Funeral Home

Crouser & Son Tire Services

Northumberland Police DepartmentNorthumberland Borough Office

Star Garden

Amato's Pizza & FamilyCitizens BankSunoco Gas Station

Cadillac Car Wash

CVS Pharmacy

TO M

ILTON

PA 147

TRAFFIC SIGNAL

TO SUNBURY

TEMPORARY

PA 147

Roadway Reconstruction Traffic Control Plan

Phase 6

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

WORK AREA

DETOUR NORTH (SR 147)

LEGEND

DETOUR SOUTH (SR 147)

16

16

Duke Street Project

Page 17: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Keystone ForgingCompany, Inc.

Joseph W Epler Funeral Home

Mason JarNorry MotorsNorry PharmacySubway Restaurants

Amato's Pizza & FamilyCitizens BankSunoco Gas Station

SUN HomeHealth & Hospice

Puff Tobacco ProductsValero

Suncom Industries

Northumberland Police DepartmentNorthumberland Borough Office

Mike's Service StationGroninger Insurance AgencyConrail Freight Car Wash FacilitySusquehanna Flower Co.Axonic Inkworks Custom Tattoo Studio

Star Garden

Youngs Sporting Goods

TRAFFIC SIGNALTEMPORARY

TO M

ILTON

PA 147

TO SUNBURY

PA 147

Roadway Reconstruction Traffic Control Plan

Phase 7-9

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

PHASE 9 WORK AREA

DETOUR NORTH (SR 147)

LEGEND

DETOUR SOUTH (SR 147)

PHASE 8 WORK AREA

PHASE 7 WORK AREA

17

17

Duke Street Project

Page 18: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Verizon

Priestley SavidgeHouse Wedding

Subaru ServiceSubaru PartsW&L Subaru

Two Scissors Hair Salon

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

LEGEND

Phase 14B

Phase 15B

Roadway Reconstruction Traffic Control PlanFront Street (SR 11)Phase 14B & 15B

18

Front Street

Page 19: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

LEGEND

Phase 14A

Phase 15A

Roadway Reconstruction Traffic Control PlanFront Street (SR 11)Phase 14A & 15A

Verizon

Priestley SavidgeHouse Wedding

Subaru ServiceSubaru PartsW&L Subaru

Two Scissors Hair Salon

19

19

Front Street

Page 20: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Duke Street Reconstruction Project

• Conclusion

– Duke Street, Front Street, Water Street & King Street

– 2017• Duke Street, 5th to 8th Streets

– 2018• Duke Street, Depot Avenue to 5th Streets

• Front Street, W&L to Sheetz Avenue

– 2019• Water Street and King Street

– 2020• Project completion

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 20

Page 21: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Duke Street Reconstruction Project

• Communication

– Website: www.penndot.gov/dukestreet

– E-mail: [email protected]

– 24-Hour Hotline: 855-336-8698

– Community Roundtables

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 21

Page 22: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Duke Street Reconstruction

• Miscellaneous Details

– Railroad Underpass

– Winter of 2018-19

22

Page 23: Duke Street Reconstruction Project - PennDOT Home · Duke Street Reconstruction Project •Construction Status –Work started June 5, 2017 –Contractor = New Enterprise Stone and

Thank you!

DUKE STREET RECONSTRUCTION PROJECT

www.penndot.gov/dukestreet

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County 23