` Head of Project : Report No.: 14 Review PD ED (Oprations) Eng Imran Mehmood Review Mr. Mahmud Ali Dillip  Action Signature Designation A.K.M Rafiqul Islam Name SPL- THE SPRING WEEKLY REPORT WEEK 5/14 PROJECT: The Spring PROJECT NO.: STS - 014 1 of 18 Revison 02
12

5 Weekly Construction Report- 05

Jun 03, 2018

Download

Documents

arctushar
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 5 Weekly Construction Report- 05

8/12/2019 5 Weekly Construction Report- 05

http://slidepdf.com/reader/full/5-weekly-construction-report-05 1/12

`

Head of Project :

Report No.: 14

ReviewPD

ED (Oprations)

Eng Imran Mehmood

ReviewMr. Mahmud Ali Dillip

 Action SignatureDesignation

A.K.M Rafiqul Islam

Name

SPL- THE SPRING

WEEKLY REPORT

WEEK 5/14

PROJECT:

The SpringPROJECT NO.:

STS - 0141 of 18 Revison 02

Page 2: 5 Weekly Construction Report- 05

8/12/2019 5 Weekly Construction Report- 05

http://slidepdf.com/reader/full/5-weekly-construction-report-05 2/12

CONTRACTOR'S WORKMENSHIP

Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed

Contractor 01: Md.Jahangir (Civil)

Foreman 1 1 0 0 0

Site clarck 1 1 1 1 1

Steel fixture 40 40 39 38 41

Raj masson 20 20 15 15 17

Contractor 02: Md. Harun (Elec.)

1 1 1 1 1 1 0 Site Engr.

1 1 1 1 1 1 1 Foreman

1 1 1 1 1 1 0 Helpers 0 2 2 2 2

1 1 1 1 1 1 1

Contractor 03: Md. Shahidul

Foreman

Helpers

Total Personal 4 4 4 4 4 4 2

WORKMANSHIP/LABOURS OF SHANTA PROPERTIES

1 1 1 1 1 1 0 Contractor 04: Shree Shamlal

Electrician 2 2 2 2 2 2 1 Wood masson 5 5 5 5 5

1 1 1 1 1 1 0

1 1 1 1 1 1 1

1 1 1 1 1 1 0

1 1 1 1 1 1 1

1 1 1 1 1 1 1

1 1 1 1 1 1 1 Contractor 05: Mr. Mamun(san.)

Breaker M/C Opt. 1 1 1 1 1 1 1 ForemanHelper 2 2 2 2 0

Contractor 06:

Total 10 10 10 10 10 10 6

Watchmen (G4S) 4 4 4 4 4 4 4

Store Assistants

Misc. Labours (Casual) 10 10 9 9 9 10 10

Peon/Cooker 2 2 2 2 2 2 2

Total 16 16 15 15 15 16 16

HEALTH AND SAFETY ISSUES

PROJECT: The Spring PROJECT NO.:

DATE:

Name of Person

STS - 014

 Actioned

Designation

DPM

 APM

CONSULTANTS/AUTHORITIES VISITED ON SITE

Md. Polash Mahamood

Irshadur Rahman

Reported

Reviewed

REMARKS

31.01.14

Sr. DGM( HR & ADMIN)

Action required Date

 A.K.M Rafiqul Islam

31.01.2014

HR & ADMIN ISSUE

WEEK NO.

REMARKS

5

Welder-2

Roof Hoist Opt.

Sanitary & Plumbing Supervisor 

DATE

PLANNING & COORDINATION DEPARTMENT ISSUE

MANPOWER ISSUES

Signature

Store Keeper 

INDIRECT WORKERS OF SHANTA PROP

Store Keeper 

PE (Electrical.)H.M Abdul Quddus

Md. Amanat Ullah

 DPM

Discipline / Description

ARC Archit.

Position/CompanyName

Site Engineer 

Quality Dept.

Md. Nurul Huda

A.K.M Rafiqul Islam

Project Engr.

MANAGEMENT STAFF OF SHANTA PROPERTIES

Discipline / Description

Welder-1

Troyel M/c Opt.

Project A/C

DATE

Page 3: 5 Weekly Construction Report- 05

8/12/2019 5 Weekly Construction Report- 05

http://slidepdf.com/reader/full/5-weekly-construction-report-05 3/12

PROJECT: The Spring PROJECT NO.:

DATE:

STS - 014

31.01.2014

 

WEEK NO. 5

Cladding sample work

Roof Machine room & O.H.W.T & gym area Drawing

Roof Machine room & O.H.W.T & gym structural Draw. 01.02.14

Thai window catchment & sliding modification drawing.

Gr. Floor Details finishing Drawing.

Rooftop finishing Drawing.

Boundary wall finishing drawing.

Common area finishing drawing.

Basement ventilation drawing. P & C Approval re

False slab catchment exhaust drawing P & C Approval re

Toilet exhaust drawing. P & C Approval re

Grill & Cladding work mock approval. 25.01.14 29.01.14 Ar. Mr. Shafayat Observation & Appr

P & C

P & C

CONSULTANT

 P & C

sample making com25.01.14

 APM

 Asif Hasan Ahmed

Action required

Reviewed

Designation

 Actioned ED (P&C)

Date Signature

 A.K.M Rafiqul Islam Reported 31.01.2014

Name of Person

P&C appv. Req.

RECEIVED ON

REQUIRED ON

P&C appv. Req.

P & C

P & C

Md. Polash Mahamood

DPM

REQUIRED FOR CONSULTANT REQUESTED ON REQUIRED ON CONSULTANT

Grill Sample work .

REQUESTED ON COMMENTS &

 P & C

25.01.14

RECEIVED DESIGN REQUESTED ON

DESIGN PACKAGE REQUIRED REQUESTED ON

CONSULTANT

COMMENTS &

sample making com

REQUIRED ON CONSULTANT

COMMENTS &

 REQUIRED FOR APPROVAL

03.02.2014

03.02.2014 P & C

COMMENTS &

PROCUREMENT DEPARTMENT ISSUE

Page 4: 5 Weekly Construction Report- 05

8/12/2019 5 Weekly Construction Report- 05

http://slidepdf.com/reader/full/5-weekly-construction-report-05 4/12

PROJECT: The Spring PROJECT NO.:

DATE:

STS - 014

31.01.2014

 

WEEK NO. 5

Cu.m NDE

13000 Nos SPL-CWH

400 Bags Lafarge surma cement Ltd

864 Cft Momtaj Traders.

Sylhet Sand 201 Cft Momtaj Traders.

Stone Chips (3/4'' down) 0 Cft Trimatra Construction.

Stone Chips (1/2'' down) 378 Cft Trimatra Construction.

MPR Date MPR No. Unit Quantity

Designation

 Actioned Head of SCM

(24-30).01.14

(24-30).01.14

MATERIAL DESCRIPTION

Md. Polash Mahamood Reviewed APM

 A.K.M Rafiqul Islam Reported DPM

(24-30).01.14

Date

Local Sand

Zahir Ahmed

NON CONFORMANCE REPORTS

REASONS FOR RECEIVING NCR

Name of Person

31.01.2014

Action required

NCR NUMBER COMMENTS & ACTIOCLOSE DATE

(24-30).01.14

REQUIRED MATERIALS/EQUIPMENT ON SITE

Ready Mix Concerete

Auto Bricks (24-30).01.14

Cement (24-30).01.14

Origin / ManufacturRequired Date

RECEIV. DATE

Signature

QUALITY ASSURANCE ISSUE

4 of 18

Page 5: 5 Weekly Construction Report- 05

8/12/2019 5 Weekly Construction Report- 05

http://slidepdf.com/reader/full/5-weekly-construction-report-05 5/12

PROJECT: The Spring PROJECT NO.:

DATE:

STS - 014

31.01.2014

 

WEEK NO. 5

Mr. Bhuyan (Q.c dept.) 25.01.14 29.01.14 For Brick work ,Lintel, f

Mr. Alok (Q.c dept.) 25.01.14 29.01.14 slab, Grill checking win

 Actioned

Name of Person Action required Designation

DPM

Md. Polash Mahamood Reviewed APM

DPM

Signature

 A.K.M Rafiqul Islam

Date

Md. Abdun Nur Bhuiyan

COMMENTS & AC

REQUEST FOR INSPECTIONS

GENERAL COMMENTS FOR QA/QC ISSUE

REQUEST SUBMITTED FOR

RFI NUMBER COMMENTS & AC

31.01.2014

SUBMITTED ON INSPECTED ON

COMMENTS INSPECTED ON SUBMITTED ON

Reported

NAME OF THE CHECK LIST INSPECTED ON COMMENTS & AC

CHECK LISTS HANDOVER

SUBMITTED ON RFI NUMBER

RFI NUMBER

Page 6: 5 Weekly Construction Report- 05

8/12/2019 5 Weekly Construction Report- 05

http://slidepdf.com/reader/full/5-weekly-construction-report-05 6/12

PROJECT: The Spring PROJECT NO.:

DATE:

STS - 014

31.01.2014

 

WEEK NO. 5

% COMPL.

30%

Brick work 22%

11%

75% On going.

Lift / Column casting (L-10)

Civil sub-contractor .

Basement C.C work. 11.04.2013 15.11.2014

Sheikh Aftab Ahmed Actioned COO

Name of Person Action required Designation Date Signature

31.01.2014 A.K.M Rafiqul Islam Reported

Plaster work ceiling (7th floor) 04.02.14 Civil sub-contractor .

DPM

OVERALL PROGRESS

Md. Polash Mahamood Reviewed APM

LOOK-AHEAD ACTIVITIES FOR COMING WEEK

30.11.2014

01.02.14

01.02.14

Plaster work 11.08.2013

ACTION BY

Brick work (2nd floor , 3rd floor & 4th floor).

DUE DATE

01.02.14

DESCRIPTION

Civil sub-contractor .

01.02.14

30.08.2014

Slab Shuttering work south side (L-10)

Basement c.c work (B-1).

Civil sub-contractor .

Civil sub-contractor .

On going.

COMMENTS & ACTIONSTART DATE

26.11.2013 27.02.2014 On going.

11.02.2013

WORK PACKAGE FINISH DATE

WORK IN PROGRESS

Super structure work (L-10)

PROGRESS REPORT

48%40%

-8%

-100%

-80%

-60%

-40%

-20%

0%

20%

40%

60%

80%

100%

Planned Slipage

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

 Plann

Actua

6 of 18 R

Page 7: 5 Weekly Construction Report- 05

8/12/2019 5 Weekly Construction Report- 05

http://slidepdf.com/reader/full/5-weekly-construction-report-05 7/12

Page 8: 5 Weekly Construction Report- 05

8/12/2019 5 Weekly Construction Report- 05

http://slidepdf.com/reader/full/5-weekly-construction-report-05 8/12

Fri

0

1

40

19

2

5

0

8 of 18 Revison 02

Page 9: 5 Weekly Construction Report- 05

8/12/2019 5 Weekly Construction Report- 05

http://slidepdf.com/reader/full/5-weekly-construction-report-05 9/12

9 of 18 Reviso

Page 10: 5 Weekly Construction Report- 05

8/12/2019 5 Weekly Construction Report- 05

http://slidepdf.com/reader/full/5-weekly-construction-report-05 10/12

10 of 18 Revison 02

Page 11: 5 Weekly Construction Report- 05

8/12/2019 5 Weekly Construction Report- 05

http://slidepdf.com/reader/full/5-weekly-construction-report-05 11/12

 

11 of 18

Page 12: 5 Weekly Construction Report- 05

8/12/2019 5 Weekly Construction Report- 05

http://slidepdf.com/reader/full/5-weekly-construction-report-05 12/12