Building the Future Current Activities this Week : Mass Excavation : Backfilling of on-grade seating is ongoing in Area 1, Area 2 and Area 3. Site Utilities : Storm Sewer installation (Line 6000) is ongoing on east side of France Family Drive. Sanitary Sewer Line E installation has started on east side of France Family Dive. Foundations : Area 2 Concourse Level – E-Line footing installation is ongoing and E-Line wall installation is ongoing. Area 3 Field Level – A-Line footing (to column line 1) and wall installation (to column line 4) is ongoing. Area 3 Field Level – Installation of Drilled Piers are complete. Area 4 Mezzanine Level – D-Line grade beam installation is ongoing and wall forms are being set. Concrete Flatwork : Area 1 Mezzanine – North slab on metal deck at VIP Entry concrete is placed. Area 1 Concourse – Structural Slab is placed from Column lines 33-23. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 6.9.2010 Re: Wizards Stadium Project Update – Week of 6.7.2010 Field Level Area 1 – Shallow Underground plumbing pipe installation has started at Men’s Field Toilet 01.32.02. Mezzanine Level Area 1 – Concrete Slab on Metal Deck at VIP Entry is placed. Field Level Area 3 – A-Line footing and wall installation is ongoing up to Column Line 1.
KC Soccer Stadium construction update from Turner Construction.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Building the Future
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 1,
Area 2 and Area 3.
Site Utilities:
Storm Sewer installation (Line 6000) is ongoing on
east side of France Family Drive.
Sanitary Sewer Line E installation has started on east
side of France Family Dive.
Foundations:
Area 2 Concourse Level – E-Line footing installation is
ongoing and E-Line wall installation is ongoing.
Area 3 Field Level – A-Line footing (to column line 1) and
wall installation (to column line 4) is ongoing.
Area 3 Field Level – Installation of Drilled Piers
are complete.
Area 4 Mezzanine Level – D-Line grade beam installation
is ongoing and wall forms are being set.
Concrete Flatwork:
Area 1 Mezzanine – North slab on metal deck at VIP
Entry concrete is placed.
Area 1 Concourse – Structural Slab is placed from
Column lines 33-23.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 6.9.2010
Re: Wizards Stadium Project
Update – Week of
6.7.2010
Field Level Area 1 – Shallow Underground
plumbing pipe installation has started at
Men’s Field Toilet 01.32.02.
Mezzanine Level Area 1 – Concrete Slab on
Metal Deck at VIP Entry is placed.
Field Level Area 3 – A-Line footing and wall
installation is ongoing up to Column Line 1.
Building the Future
Structural Steel Erection:
Area 1 – Steel Erection in sequence 1-5 is nearly complete
is currently to Column Line 23. Seven raker pieced remain.
Decking/Detailing/Studs/Edge Angle is ongoing in
sequence 1-2, 1-4 and 1-5.
Underground MEP:
Deep Sanitary installation is ongoing in Area 3.
Electrical Secondary is ongoing in Area 2
MEP Rough-in:
Plumbing and Electrical rough-in for concrete decks are
ongoing Suite Level. Shallow plumbing rough-in has
started at Area 1 Field Level.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will continue. Storm Line 5000 and
4000 will begin. Installation of Sanitary Line E will continue.
Deep Underground Plumbing:
Deep Sanitary installation in Area 3 will continue.
Foundations:
Area 2 Concourse Level – Footing and wall installation
will continue.
Area 3 Field Level – A-Line wall placement will continue.
Area 4 Mezzanine Level – Foundation Wall installation will
continue.
Area 1 – Structural Steel Erection at West
Building is nearly complete from Column
Line 33 – 23.
Field Level Area 2 – Backfill of on-grade
seating area between column lines 21-18 is
ongoing.
Concourse Level Area 1 – Concrete
installation taking place from Column Lines
C – 33.
Building the Future
Concrete Flatwork:
Area 1 Suite Level – Concrete placement will begin.
Structural Steel Erection:
Erection of Structural Steel in Sequence 1-3 will
begin.
Decking/Detailing/Studs/Edge Plates will continue in
Sequence 1-5.
Underground MEP:
Deep Sanitary installation will continue in Area 3.
Electrical Secondary will continue in Area 2
MEP Rough-in:
Plumbing and Electrical rough-in for concrete decks will
begin at Press Level. Shallow plumbing rough-in will
continue at Area 1 Field Level. Shallow electrical will