7/28/2019 2_Retaining Wall Ashton Lawler.pdf
1/87
1
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
2/87
2
Retaining Wall 101Retaining Wall 101
D. Ashton LawlerD. Ashton LawlerStructure and Bridge DivisionStructure and Bridge Division
Virginia Department of TransportationVirginia Department of Transportation
1401 E. Broad Street1401 E. Broad Street
Richmond, Virginia 23219Richmond, Virginia 23219
Phone (804)786Phone (804)786--23552355
ee--mail:mail: [email protected]@vdot.virginia.gov
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
3/87
3
Learning GoalsLearning Goals
Get reacquainted with basic retainingGet reacquainted with basic retaining
wall designwall design
Brief look at Conventional C.I.P. WallsBrief look at Conventional C.I.P. Walls
Introduction to MSE WallsIntroduction to MSE Walls Learn how to develop plans for MSELearn how to develop plans for MSE
WallsWalls
Check out what not to doCheck out what not to do
Get some good referencesGet some good references
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
4/87
4
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
5/87
5Foundation Analysis and Design
J oseph E. Bowles
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
6/87
6Foundation Analysis and DesignJ oseph E. Bowles
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
7/87
7
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
8/87
8
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
9/87
9
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
10/87
10
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
11/87
11
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
12/87
12
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
13/87
13
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
14/87
14
Typical Section
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
15/87
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
16/87
16
Three Basic Components of anMSE wall:
Reinforcing Elements
Select Backfill
Precast Facing Panels
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
17/87
17
Courtesy of The Reinforced Earth Company
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
18/87
18
Courtesy of The Neel Company
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
19/87
19
Why do we use these wall systems?
1. Economical2. Versatile
3. Tolerate settlement well
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
20/87
20
Relationship between joint width andRelationship between joint width andlimiting differential settlementslimiting differential settlements
Joint WidthJoint Width Limiting Differential SettlementsLimiting Differential Settlements
1/100 *1/100 *
1/2001/200
1/3001/300
*When significant differential settlements are anticipated*When significant differential settlements are anticipated(greater than 1/100) slip joints must be provided.(greater than 1/100) slip joints must be provided.
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
21/87
21
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
22/87
22
VDOT Approach to MSE Wall Design
External Stability - The Departments (orour Consultants) responsibility.
Internal Stability The WallManufacturers (and the Contractors)responsibility.
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
23/87
23
External Stability1. Bearing Capacity
2. Settlement
3. Overturning Resistance
4. Sliding Resistance
5. Global Stability
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
24/87
24
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
25/87
25
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
26/87
26
Internal Stability1. Pullout Failure of Reinforcement.
2. Breakage of Reinforcement.
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
27/87
27
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
28/87
28
Plan Preparation
Requirements
For Mechanically-Stabilized Earth
(MSE) Walls
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
29/87
29
Refer to
Requirements for Preparation ofAlternate Retaining Wall Plans
[Notes To Designer]
Lets look at each of the notes individually.
What appears on these slides is anabbreviated description of each Note.
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
30/87
30
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
31/87
31
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
32/87
32
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
33/87
33
v = = Contact pressure generatedby the wall loading
L - 2e
e
R
..2 SF
q
eL
R
vult
=
L
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
34/87
34
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
35/87
35
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
36/87
36
This is what happens if you dont follow these
guidelines /
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
37/87
37
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
38/87
38
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
39/87
39
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
40/87
40
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
41/87
41
0
5
10
15
20
25
09/30/85 10/30/85 11/29/85 12/29/85 01/28/86 02/27/86 03/29/86 04/28/86 05/28/86
Date
Frequent Rains
Begin Wall
Wall Completed
Washout
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
42/87
42
0
2
4
6
8
10
12
14
16
1820
51 52 53
Station No.
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
43/87
43
0
2
4
6
8
10
12
51 52 53
Station No.
Base of Wall
Top of Wall
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
44/87
44
11"
1.5
1
18"
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
45/87
45
2' - Live Load Surcharge
4' Berm
1.5
1 2.3'
3.25 ksf
Height = 17'
SFOT = 3.3
SFsliding = 2.0
SFbearing = 2.5
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
46/87
46
2' - Live Load Surcharge
4' Berm
1.5
1 2.3'
Good Compaction Low Compaction
= 120 cf; c = 500 sf; = 32.50
= 110 cf; c = 0 sf; = 30.00
SF = 2.5 SF = 1.7
3.25 ksf
Safet Factor for Bearing Capacity
Height = 17'
SFOT = 3.3
SFsliding = 2.0
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
47/87
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
48/87
48
2' - Live Load Surcharge
4' Berm
1.5
1 2.3'
3.25 ksf
Height = 17'SFOT = 3.3
SFsliding = 2.0
SFbearing = 2.5
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
49/87
49
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
50/87
50
2' - Live Load Surcharge
Good Compaction Low Compaction
= 120 cf; c = 500 sf; = 32.50
= 110 cf; c = 0 sf; = 30.00
SF = 2.5 SF = 1.7
SF = 1.9 SF = 0.8
WITHOUT BERM
WITH BERMSafet Factor for Bearing Capacity
Height = 17'
SFOT = 3.3
SFsliding = 2.0
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
51/87
51
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
52/87
52
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
53/87
53
2' - Live Load Surcharge
SF = 2.5 SF = 1.7 SF = 1.0
SF = 1.9 SF = 0.8 SF = 0.4
Low Compaction
=110 pcf; c =0 psf; =30.00
=120 pcf; c =500 psf; =32.50
WITHOUT BERM
Poor Compaction & Embankment Material
=85 pcf; c =100 psf; =20.00
Safet Factor for Bearing Capacity
WITH BERMGood Compaction
Height = 17'
SFOT = 3.3
SFsliding = 2.0
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
54/87
54
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
55/87
55
FHWA OFFICE OF BRIDGEFHWA OFFICE OF BRIDGE
TECHNOLOGYTECHNOLOGY
www.fhwa.dot.gov/bridge/index.htmwww.fhwa.dot.gov/bridge/index.htm
Click onClick on GeotechnicalGeotechnical
MSEW Version 3 0 SoftwareMSEW Version 3 0 Software
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
56/87
56
MSEW Version 3.0 SoftwareMSEW Version 3.0 Software
ADAMA Engineering, Inc.ADAMA Engineering, Inc.Web:Web: www.geoprograms.comwww.geoprograms.com
Email:Email: [email protected]@geoprograms.comPhone: (302) 368Phone: (302) 368--31973197
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
57/87
57
Questions?
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
58/87
58
Requirements for Preparation ofRequirements for Preparation of
Alternate Retaining Wall PlansAlternate Retaining Wall Plans
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
59/87
59
1. Review road plans and cross-sections to estimate approximate wall location,height and length of reinforced soil mass.
a) Check that the entire wall (including the reinforced mass) is located withinthe Departments right-of-way (R/W). If the wall is outside the R/W limits,determine if it is feasible to acquire additional R/W or underground
easement.b) Check if any utilities or obstructions located within the reinforced soil
mass can be adequately accommodated within the requirements andlimitations of the proposed systems allowed for construction.
2. Review the geotechnical information [geotechnical reports, boring logs (geologysheets), laboratory test data, etc.] and estimate the location of the proposedbearing stratum.
3. Perform bearing capacity calculations to determine the maximum allowable soilbearing capacity at the estimated bearing stratum.The maximum allowable soil
bearing pressure must be stated on the plans.
4. Determine the anticipated loading condition (level backfill, level backfill with trafficsurcharge, sloping backfill, or sloping backfill with traffic surcharge, etc.).
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
60/87
60
5 Calculate the maximum bearing pressure that the wall will impose on the soil. If
the maximum bearing pressure imposed by the wall is less than the maximumallowable soil bearing capacity calculated in Step 3, the bearing pressurerequirements are satisfied.
6 Perform settlement calculations to determine total and differential settlements. Inaddition to the magnitude of settlement, an estimate of the time-rate of settlement
shall be performed. Wick drains, surcharge loading, or some other method ofground improvement may be required to limit post wall construction settlementsto an acceptable amount. Check the angular distortions to determine if theyappear to be within allowable limits according to AASHTO. Depending on theamount of anticipated settlement, the designer shall implement one of thefollowing actions:
Settlement 2 inches. No action required.
Settlement up to 4 inches and longitudinaldifferential settlement less than 1%
No action required.
Settlement up to 4 inches and longitudinaldifferential settlement greater than 1%
Slip joints to be placed at appropriateintervals in order to limit the longitudinal
differential settlement to less than 1%Settlement 4 inches. Requires approval from State Structure
and Bridge Engineer.
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
61/87
61
Estimated settlements along the wall shall be shown in the plans. Method of payment (ifany) for additional square footage of wall created by the settlements should be addressedin the contract documents.
Evaluate whether a waiting period for installing coping, parapet, barrier, moment slab,
piles, paving etc. is required after wall completion.
7 Calculate factors of safety with respect to overturning, sliding, and global stabilityfor the applicable loading conditions. If the factors of safety are greater thanrequired, the overall stability requirements are satisfied.
8 Evaluate the site for potentially deleterious environmental factors such ascorrosive groundwater, seepage forces, stray currents, etc. which may adverselyaffect the wall.
If all of the external stability issues described above (bearing pressure, settlement,overturning, sliding and global stability requirements) are satisfied, alternate walls
may be used at this location. If any of the above is not satisfied, ground modificationor a different type of retaining wall may be required.
9 If an alternate wall is feasible determine the wall geometry (stationing and
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
62/87
62
9 If an alternate wall is feasible, determine the wall geometry (stationing andoffsets).
10 Determine the top-of-wall elevations at intervals not exceeding 50 ft. This can beaccomplished using roadway information such as road plans, profiles, cross-sections, and the like. The top of wall shall be either the top of coping or the topof the moment slab (whichever is applicable).
11 Determine the bottom-of-wall elevations at the same locations (stations) that thetop-of-wall elevations were found in Step 10. Check that there is adequateembedment at the toe of the wall in accordance with AASHTO and that theembedment satisfies global stability requirements. The bottom of wall shall betaken to be the top of the leveling pad.
12 Check that the top and bottom elevations of the wall determined in Steps 10 and11 are within the limits assumed in Step 1. If not, recalculate the bearingcapacity, settlement, and the factors of safety with respect to overturning, sliding,and global stability to be sure that the external stability of the wall is adequate.
13 Draw the Elevation View (or Three-Line Drawing) showing the top of wall,bottom of wall, and the approximate finished grade adjoining the front face of thewall. Show the locations of all pipes and utilities that will be penetrating the wallor behind the panels, so the selected alternate wall company can design forthose conditions.
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
63/87
63
14 Draw the Plan View. Show stationing, offsets, boring locations, and all pipes and
utilities in the vicinity of the wall.
15 If required, rustication treatment and details shall be included on the drawings.
16 Draw Typical Sections for all significantly different wall sections. For eachsection, show the limits of payment, the required slope in front of the wall, the
required slope of the backfill, and all special loading conditions. The limits ofPayment shall be shown to extend from the top of the wall (top of coping ormoment slab) to the bottom of the wall (top of the leveling pad).
17 Calculate the surface area of the wall based on top and bottom wall elevations
and show this quantity on the plans (Square Feet, Plan Quantity Item). Whenrequired, the traffic barrier/parapet shall be listed as a separate payment item
(Linear Feet, Plan Quantity Item).
18 The plans shall clearly indicate whether some method of ground improvement isrequired and the manner in which the Contractor will be paid for this work. If
overexcavation and replacement is required, these items shall be listed asseparate payment items [Undercut Excavation, (Cubic Yards)] and [SelectMaterial Type I, Minimum CBR of 30 (tons)]. The estimated limits of undercutand backfilling shall be indicated on the Elevation View and the Typical Sections.
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
64/87
64
19 List the approved wall companies with their addresses and telephone numbers
on the plans so the Contractor can contact them to request bids. Some projectshave geometric constraints (e.g., walls that wrap around bridge abutments) thatpreclude the use of some wall systems. Wall systems that cannot conform to thegeometrics of the project shall not be included on the plans as an allowable wallsystem.
20 Include the boring logs (Geology Sheets) in the plans.
21 Place appropriate General Notes on the Plans.
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
65/87
65
General Notes for Alternate RetainingGeneral Notes for Alternate Retaining
Wall PlansWall Plans
These are suggested wordings for notes that are regularly or occasionallyneeded. Where these notes are fully applicable, there may be no need to change
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
66/87
66
their wording. They should be changed, however, or other notes added,
wherever they are not adequate.
Notes should line up with the GENERAL NOTE on the Alternate Retaining WallPlan.
Notes in the single parentheses indicate alternate wordings to be selected by the
designer. Notes in the double parentheses((italics))
are explanations andinstructions to the designer. Skip a line between paragraphs.
Specifications:
Construction: Virginia Department of TransportationRoad and Bridge Specifications, 2002.
Design: AASHTO Standard Specifications for Highway Bridges, 1996; 1997and 1998 Interim Specifications; and VDOT Modifications.(Structure(s) is (are) designed for Seismic Performance Category B).((Use note only when designing for Seismic Performance Category B.Do not show note when designing for Seismic Performance Category
A.))
Standards: Virginia Department of TransportationRoad and Bridge Standards, 2001.
These plans are incomplete unless accompanied by the SupplementalSpecifications and Special Provisions included in the contract documents.
The minimum design life of MSE wall shall be (75-year) (100-year).
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
67/87
67
The maximum allowable foundation bearing pressure shall be _____ tons/sq. ft.
((Add table if allowable bearing pressure varies along wall alignment.))
The anticipated MSE wall total settlement is ____ inches and differentialsettlement is _____. ((Add table if settlement varies along wall alignment.))
Vertical slip joints shall be placed in the wall at intervals not to exceed ____ ft.between Stations __________ and _________.
Prior to wall construction, the foundation shall be compacted with a smoothwheel vibratory roller. The drums of the roller should be ballasted and each passof the roller should overlap one half the width of the previous pass. The rollershall make at least ten passes over the proposed wall foundation zone. Nodensity test will be required. Any foundation soils found to be unsuitable shall beremoved and replaced with select material Type I minimum CBR of 30. ((Usenote where marginal foundation conditions exist or zones of unsuitable materialmaybe encountered.))
The minimum required depth of undercut shall be _____ ft. between Stations_________ and _________. ((Add table if undercut depth varies along wallalignment.))
Remove unsuitable or unstable foundation material below the bottom of the wall
and replace with select material prior to wall construction. Compact thefoundation area according to the VDOT Specifications.
The estimated required depth of unsuitable material to be removed is shown onthe plans. The lateral limits of excavation are dependent on the depth at aparticular location below the wall. Additional localized excavation may berequired depending on the site conditions at the time of construction.
Rustication treatment shall be ______________. Forms and liners shall beapproved by the Engineer.
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
68/87
68
Concrete surface coating shall be _______, similar to Federal Standard Color
No. _______.
Minimum panel design thickness is _____ inches. Thickness of concrete mustincrease to accommodate any architectural surface finish that may be specified.
An impervious membrane shall be placed below the pavement and just abovethe first row of reinforcement to intercept any flows containing deicing chemicals.The membrane shall be sloped to drain away from the facing to an intercepting
longitudinal drain outletted beyond the reinforced zone. ((Used when theextensive use of deicing chemical may cause accelerated corrosion problems)).
A geotextile shall be used as a separator between the mechanically stabilizedearth mass and the subbase. ((Used where the potential for the subbasemigration into an oversized selected material may occur)).
Epoxy coated reinforcement steel shall be used in (copings) (facing panels)(parapets) (moment slabs) (traffic barriers) and __________. ((Epoxy coatedsteel is required in area of heavy salt or chemical spray)).
(Coping) (Parapet) (Barrier) (Moment slab) (Piles) (Paving) shall not be placeduntil _____ days after wall completion have elapsed.
The selected wall supplier will submit a detailed design and shop drawings for
approval.
Provide drainage details such as perforated pipe underdrain and/or drainageblanket based upon field conditions. For wall installation at stream crossing,provide adequate drainage so the difference between streambed and saturatedbackfill is not greater than what is considered in the design.
All panel types and other related elements shall be detailed on shop drawings.
This worksheet checks the external stability (i.e. eccentrici ty, slid ing, and bearing pressure)
of MSE walls based on the strength limit state requirements in AASHTO LRFD 4th Edition
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
69/87
69
Version 2-1, 2/08
Project Name: Test
Project Number: 123456
Designer: KL
INPUT (Yellow Colored Cells)
Total Wall Height, H (ft) 30.00
Reinforcement Length, L (ft) 21.00
Backslope Height, h (ft) 0.00Backslope Run, r (ft) 100.00
Wall Embedment, Df(ft) 2
* For level backslope, enter zero for backslope height.
(pcf) ' (deg.) c' (psf)Reinforced Soil 125.00 34.00 0.00
Retained Soil 125.00 30.00 0.00
Foundation Soil 125.00 30.00 0.00
100Depth of Groundwater Below Grade in Front of MSE Wall, Dw(ft)
g q
(2007)
Soil Parameters:
Wall Geometry:H
h
Reinforced
Soil
L
Retained
Soil
Foundation Soil
Df
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
70/87
70
Traffic Live Load, LS (psf) 250.00 (See Tables below for guidelines)
Load Factors:
Different combinations of maximum and minimum values of load factors, p, is considered as follows:
Group EV LSV LSH EH
Strength I-a 1 1.75 1.75 1.5
Strength I-b 1.35 1.75 1.75 1.5
Resistance Factors at Strength Limit States:
Resistance factor for sliding resistance of foundation, is = 0.9
(See AASHTO Table 10.5.5.2.2-1)
Resistance factor for bearing resistance, b = 0.45(See AASHTO Table 10.5.5.2.2-1)
Vehicular Live Load
External Stability Results Summary:
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
71/87
71
Eccentricity:
Group e (ft)Result
Strength I-a 4.40 OK
Strength I-b 3.26 OK
Sliding
Group Rr (kips/ft)Htotal
(kips/ft)Result
Strength I-a 40.92 32.50 OKStrength I-b 55.24 32.50 OK
Bearing Resistance
Group qR (ksf/ft)
qmax
(ksf/ft) Result
Strength I-a 10.33 6.71 OK
Strength I-b 11.52 7.70 OK
* Performance Ratio 1 means factored resistance factored load OK
Performance Ratio < 1 means factored resistance < factored load NG
y y
Performance Ratio*
1.261.70
5.25
5.25
1.19
Performance Ratio*1.54
1.49
Allowable max.e, emax(ft)
Performance Ratio*
1.61
CALCULATIONS
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
72/87
72
Back Slope Angle (deg,) = 0.00
Broken Slope Equivalent Angle (deg.) eq = 0.00 (Art. 3.11.5.8.1)
Active Lateral Pressure Coeff. for Ext. Stability* Ka = 0.333
Additional Height from Backslope h (ft) = 0.00
Total Design Height for External Stability H+h (ft) = 30.00
*For equation of Ka, see Articles 3.11.5.3 & 11.10.5.2
(A) Unfactored Loads
Horizontal Components
PEH = 0.5KaH2cos(eq) = 18.75 k/ft
P(LS)H = Ka(LS)Hcos(eq) = 2.50 k/ft
Vertical Components
PEV1 = HL = 78.75 k/ft
PEV2 = 0.5hL = 0.00 k/ft
P(LS)V1 = (LS)L = 5.25 k/ft
P(EH)V = 0.5KaH2sin(eq) = 0.00 k/ft
P(LS)V2 =Ka(LS)Hsin(eq) = 0.00 k/ft
CALCULATIONS
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
73/87
73
where:
EH is lateral earth pressure acting at eq from horizontal
EV1 and EV2 are vertical earth pressures
LSH is lateral live load acting at eq from horizontal
H
h
EV1
LS
EHLSH
Toe
eq
Equivalent
Backslope
(H+h)/3(H+h)/2
EV2
L
Summary of Unfactored Horizontal Loads
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
74/87
74
Items
Horizontal
Loads
(kips/ft)
Moment
Arm about
Toe (ft)
Moment
about Toe
(k-ft/ft)
PEH 18.75 10.00 187.50
PLSH 2.50 15.00 37.50
Items
Vertical
Loads
(kips/ft)
Moment
Arm about
Toe (ft)
Moment
about Toe
(k-ft/ft)
PEV1 78.75 10.50 826.88
PEV2 0.00 0.00 0.00
P(LS)V1 5.25 10.50 55.13P(EH)V 0.00 21.00 0.00
P(LS)V2 0.00 21.00 0.00
y
and Overturning Moments
Summary of Unfactored Vertical Loads and
Resisting Moments
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
75/87
75
(B) Load Factors
The following strength limit states are not considered in the analysis:
In theory, structures should be evaluated for each of the strength limit states. However, depending
on the particular loading conditions and performance characteristics of a structure, only certain
controlling strength states need to be evaluated for MSE wall.
Strength II: for Owner specified special design vehicles and/or evaluation permit vehicles, without
wind. Not applicable for typical MSE wall unless special vehicle loading is specified.
Consequently, only Strength I loading applies to MSE wall analysis.
Strength III: for structure exposed to wind of velocity of exceeding 55 mph. Not applicable to MSE
wall because wall is not subjected to other than standard wind loading.Strength IV: load combination relating to very high dead load to live load force effect ratio ratios.
Not applicable to MSE wall.
Strength V: load combination relating to normal vehicular use of the bridge with wind velocity of 55
mph. Not applicable to MSE wall because wind load is not a design factor.
(C) Factored Loads
GroupPEH PLSH Total
Factored Horizontal Loads
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
76/87
76
Group
(kips/ft) (kips/ft) (kips/ft)Unfactored Hori. Load, H 18.75 2.50 21.25
Strength I-a 28.13 4.38 32.50
Strength I-b 28.13 4.38 32.50
Group
PEV1
(kips/ft)
PEV2
(kips/ft)
PLSV1
(kips/ft)
PEHV
(kips/ft)
PLSV2
(kips/ft)
Total
(kips/ft)Unfactored Vert. Load, V 78.75 0.00 5.25 0.00 0.00 84.00
Strength I-a 78.75 0.00 9.19 0.00 0.00 87.94
Strength I-b 106.31 0.00 9.19 0.00 0.00 115.50
Group PEH(kips/ft)
PLSH(kips/ft)
Total(kips/ft)
Unfactored Moment from
Horizontal Load, Mh 187.50 37.50 225.00
Strength I-a 281.25 65.63 346.88
Strength I-b 281.25 65.63 346.88
GroupPEV1
(kips/ft)
PEV2(kips/ft)
PLSV1(kips/ft)
PEHV(kips/ft)
PLSV2(kips/ft)
Total
(kips/ft)
Unfactored Moment from
Vertical Load, Mv 826.88 0.00 55.13 0.00 0.00 882.00
Strength I-a 826.88 0.00 96.47 0.00 0.00 923.34
Strength I-b 1116.28 0.00 96.47 0.00 0.00 1212.75
Factored Moments from Horizontal Loads
Factored Vertical Loads
Factored Moments from Vertical Loads
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
77/87
77
(D) Eccentricity Check
Eccentricity, e = L/2 - Xo where: L/2 = 10.5 ft
Allowable max. e, emax = L/4 for MSE wall on soils (see Article 10.6.3.3)
emax = 5.25 ft.
GroupMv, dead load
(k-ft/ft)
MH, total(k-ft/ft)
Vdead load(kips)
Xo (ft) e (ft) Result
Strength I-a 826.88 346.88 78.75 6.10 4.40 OK
Strength I-b 1116.28 346.88 106.31 7.24 3.26 OKNote: OK if e emax; NG if e > emax.
deadload
totalHdeadloadV
oV
MMX
,,
=
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
78/87
78
(E) Base Sliding Check
Assumptions: 1. Passive earth resistance from soils in front of wall is ignored.
Factored Resistance against Base Sliding Failure on Cohesionless Soils, Rr = x V tan'
Factored Resistance against Base Sliding Failure on Cohesive Soils, Rr = x Su
where: is resistance factor for sliding resistance of foundation on soil
(from Table 10.5.5.2.2-1)
V is total vertical loads, excluding traffic live load.' is the lesser ofr of reinforced fill andfof the foundation soil.
Su is undrained shear strength.
Group/Item V (kips/ft) tan' Su (ksf) Rr (kips/ft)Htotal
(kips/ft)Result
Strength I-a 78.75 0.58 0.00 40.92 32.50 OK
Strength I-b 106.31 0.58 0.00 55.24 32.50 OK
Note: OK if Rr Htotal; NG if Rr < Htotal.
2. For clay foundation soils and a layer of compacted granular
material is placed between the MSE mass and foundation soil, refer
to Article 10.6.3.4 for sliding resistance calculations.
(F) Bearing Pressure Check
Equivalent footing width, B' = B - 2e'
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
79/87
79
Applied Bearing Pressure, qmax = (Vtotal)/B'
Eccentricity to calculate equivalent footing width:
e' =(B/2) - X'o
where: 10.5 ft.
Factored Bearing Resistance =qR =b x qnwhere: b = Resistance Factor for Bearing Resistance
qn = Nominal Bearing Resistance (calculated in Bearing Resistance Worksheet)
Group/ItemMv,total(k-ft/ft)
MH,total(k-ft/ft)
Vtotal(ki s/ft)
X'o (ft) e' (ft) B' (ft)
Strength I-a 923.34 346.88 87.94 6.56 3.94 13.11
Strength I-b 1212.75 346.88 115.50 7.50 3.00 14.99
Group/Item qmax (ksf/ft) qR (ksf/ft) Result
Strength I-a 6.71 10.33 OK
Strength I-b 7.70 11.52 OK
Note: OK if qmax qR; NG if qmax >qR.
Note: The values of e' for calculating equivalent footing width and bearing pressure are different
from the e for eccentricity check.
B/2 = L/2 =
total
totalHtotalV
o
V
MMX
,,'
=
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
80/87
80
Version 2-1, 2/08
Project Name: Test
Project Number: 123456
Designer: KL
INPUT (Yellow Colored Cells)
30.00
21.00
0.00
100.00
* For level backslope, enter zero for backslope height.
Calculated backslope angle, (deg) = 0.00
This worksheet checks the internal stabil ity of steel strip MSE walls based on the strength l imit
state requirements in AASHTO LRFD 4th Edi tion ( 2007)
Wall Height, H (ft)
Reinforcement Length, L (ft)
Backslope Height, h (ft)
Wall Geometry:
(Orange Cells are Input Imported from
MSE Ext. Stabili ty Worksheet
Backslope Run, r (ft)
H
h
Reinforced
Soil
L
Retained
Soil
Foundation Soil
r
z
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
81/87
81
(pcf) ' (deg.) c' (psf)125.00 34.00 0.00
125.00 30.00 0.00125.00 30.00 0.00
Traffic Live Load, LS (psf) 250.00
Panel and Strip Properties
MSE Wall Design Life (yr.) = 75 (From Contract Document)Effective Panel Width, (ft) = 4.92 (From MSE wall plans)
Width of Strip, b (in) = 2 (From MSE wall plans)
Nominal long-term strip design strength, Tal (kips/strip) = 7.2 (From MSE wall vendor)
Nominal long-term connection design strength, Tcon (kips/conn) = 8.4 (From MSE wall vendor)
Soil Parameters:
Vehicular Live
Reinforced Soil
Retained SoilFoundation Soil
Calculations
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
82/87
82
A. Factored Tensile Resistance of Strip Reinforcement and Connect ion
Resistance factor for strip tension, = 0.75 for static loading (Per AASHTO Table 11.5.6-1)
Factored tensile resistance of strip,Tal = 5.4 kip/strip
Resistance factor for connection, = 0.75 for static loading (Per AASHTO Table 11.5.6-1)Factored tensile resistance of connection, Tcon = 6.3 kip/strip
B. Factored Load on Strip Reinforcement
The factored horizontal stress, H, at each strip level
= p(vkr+H)
where: p = the load factor for vertical earth pressure EV from Table 3.4.1-2
p, EV = 1.00 (min)
1.35 (max)
The load factor that produces the largest strip tensile force is p, EV = 1.35. Therefore,
only p, EV = 1.35 is considered in the following calculations.
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
83/87
83
kr = reinforced fill horizontal pressure coefficientkr = (kr/ka)x ka
ka, active lateral pressure coefficient = (C11.10.6.2.1)
= 0.28
kr/ka , coefficient multipler, refers to Figure 11.10.6.2.1-3
v =rZ + 0.5Lr(tan) + LS
Z is depth of reinforced fill at strip layer measured from top of MSE wall.
Factored load on strip reinforcement, Tmax =H x Sv x (width of 2 panels/#of strips in 2-panel)
where: Sv = tributary height of strip reinforcement.
v = pressure from soil self weight within and immediately above the reinforced wall backfill, and
any surcharge loads present (ksf)
H = horizontal stress at the reinforcement level resulting from any applicable concentrated
horizontal surcharge load as specificed in Article 11.10.10.1 (ksf), such as "true" MSE
abutment.H is not consiidered in this spreadsheet.
2
'45tan
2 f
C. Strip Reinforcement Tensile Strength and Connection Checks
Number of strip reinforcement layers, N = 8 (From MSE wall shop plans)
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
84/87
84
Reinf.
Layer
Depth, Z
(ft)
Total
Vert.
Pressure,
v (ksf)
Hori.
Pressure
Coeff. kr
Factored
Hori.
Pressure,
H (ksf)
#of
Strips Per
2 Panels
Tributary
Height, Sv(ft)
Factored
Load on
Strip for
Rupture,
Tmax(kips)
Factored
Tensile
Resist. of
Strip,
Tal(kips)
Strip
Tensile
Strength
Check
Connection
Rupture
Check
1 1.25 0.41 0.47 0.26 6.00 2.50 1.06 5.40 OK OK
2 3.75 0.72 0.45 0.44 6.00 2.50 1.81 5.40 OK OK
3 6.25 1.03 0.44 0.61 6.00 2.50 2.49 5.40 OK OK
4 8.75 1.34 0.42 0.76 6.00 2.50 3.11 5.40 OK OK
5 11.25 1.66 0.40 0.90 6.00 2.50 3.68 5.40 OK OK6 13.75 1.97 0.38 1.02 6.00 2.50 4.18 5.40 OK OK
7 16.25 2.28 0.37 1.13 6.00 2.50 4.62 5.40 OK OK
8 18.75 2.59 0.35 1.22 6.00 12.50 24.99 5.40 NG NG
9
10
1112
13
14
15
16
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
85/87
85
D. Strip Pullout Resistance
Width of active zone for pullout calculation = 0.3xH1
H1 = 30.00 ft.
0.3H1 = 9.00 ft.
30.96 Deg.
Only the effective pullout length (Le) which
extends beyond the theoretical failure
surface is considered in pullout resistance
calculations.
tan3.013.0tan1
+= HHH
L
0.3H1
La Le
Zone of max. stress
or potential failuresurface
H1
H1/2
H1/2
H
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
86/87
86
Nominal Pullout Resistance, Pr (kips/strip) =F*vCbLe
where:
F* = Pullout friction factor at top of wall = 2.0
= Scale effect correction factor = 1.0
v = Unfactored vertical stress at the strip level (ksf)
C = Overall strip surface area geometry factor = 2 for strip reinforcementb = Width of strip (ft)
Le = Length of strip in resistant zone (ft)
Pullout Resistance Factor, = 0.9
Factored Pullout Resistance =Pr (kips/strip)
Vertical pressure, v = rZp.where Zp is depth of soil at strip layer at beginning of resistance zone (See AASHTO Fig. 11.10.6.2.1-2)
For strip reinforcement pullout resistance computation, traffic live load (LS) is neglected in computing the
vertical stress and pullout resistance at strip level (See AASHTO Fig. 11.106.2.1-1 and -2).
Factored tensile load on strip, Tmax, is calculated in Section C and is used to compare with the factored
pullout resistance..
E St i P ll t Ch k
7/28/2019 2_Retaining Wall Ashton Lawler.pdf
87/87
87
E. Strip Pullout Checks
Reinf.
Layer
Depth, Z
(ft)
Zp(ft)
Total
Vert.
Pressure,
v (ksf)
Length of
Strip
Beyond
Failure
Surface,
Le (ft)
Pullout
Resist.
Factor, F*
Nominal
Pullout
Resist. Pr(kip)
Factored
Pullout
Resist.,
Pr (kips)
Factored
Load on
Strip for
Pullout,
Tmax
(kips)
Strip
Pullout
Check(PrTmax)
Strip
Pullout
Check(Le3')
1 1.25 1.25 0.16 12.00 1.92 1.20 1.08 0.41 OK OK
2 3.75 3.75 0.47 12.00 1.75 3.28 2.96 1.18 OK OK
3 6.25 6.25 0.78 12.00 1.59 4.96 4.46 1.89 OK OK
4 8.75 8.75 1.09 12.00 1.42 6.21 5.59 2.54 OK OK
5 11.25 11.25 1.41 12.00 1.25 7.06 6.35 3.12 OK OK
6 13.75 13.75 1.72 12.00 1.09 7.48 6.74 3.65 OK OK7 16.25 16.25 2.03 12.75 0.92 7.97 7.17 4.11 OK OK
8 18.75 18.75 2.34 14.25 0.76 8.43 7.59 22.58 NG OK
9
10
11
12
1314
15
16