文文文文 文文文文 2G IP new site intergration guide There are two ways to do the IP new site intergration,one is USB Flash Drive for GBTS Commissioning , the other one is SMT for GBTS Commissioning. For USB Flash Commissioning ,you only need an USB,and put the BTS configuration file in the USB accurately,then you plug the USB to the BTS;For the SMT commissioning ,you need connect to the BTS by a laptop , then you can do the config of the BTS by SMT software. About the two methods ,we recommend the USB commissioning ,if the USB commissioning is not working ,you can use the SMT commissioning. Ste p Work procedure 1 The power for the BTS is OK and the BTS is power on; 2 Check the CWO status with CWO engineer, the port for BTS should be defined in the transmission side; 3 Transmission for the site is OK,ping test from RTN or GPON to the BSC gateway is OK; 4 If the transmission is pingable,go to the site and connect the LAN cable between the transmission FE1 port and GTMU FE0 port. 5 Start the site intergration procedure,you can refer the 《2G IP new site intergration guide》 2022-6-10 文文文文文文,文文文文文文文文 文 1 文, 文 13 文
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
文档名称 文档密级
2G IP new site intergration guide
There are two ways to do the IP new site intergration,one is USB Flash Drive for GBTS
Commissioning , the other one is SMT for GBTS Commissioning.
For USB Flash Commissioning ,you only need an USB,and put the BTS configuration file in the USB
accurately,then you plug the USB to the BTS;For the SMT commissioning ,you need connect to the BTS by a
laptop , then you can do the config of the BTS by SMT software.
About the two methods ,we recommend the USB commissioning ,if the USB commissioning is not
working ,you can use the SMT commissioning.
Step
Work procedure
1 The power for the BTS is OK and the BTS is power on;
2
Check the CWO status with CWO engineer, the port for BTS should be defined in the transmission side;
3Transmission for the site is OK,ping test from RTN or GPON to the BSC gateway is OK;
4If the transmission is pingable,go to the site and connect the LAN cable between the transmission FE1 port and GTMU FE0 port.
5Start the site intergration procedure,you can refer the 《2G IP new
site intergration guide》
一、USB Flash Drive for GBTS Commissioning1.Plug the USB flash drive into the USB port of the computer;
2.Create a folder named BTS3900 GSM in the USB flash drive;
3.Then create a folder named Site0 (the name is the site name ) in the folder BTS3900 GSM;
4.Copy the TransCfg.ini file to the folder ,you can get the TransCfg.ini file from the BSC intergration.