2.5.3Verifying Proper ASME Tank Condition Prior to Loading
For the safe and efficient operation of the ASME tank-setting trailer, propane personnel should understand the basic components, maintenance, and operation.
In this module you will learn to:
(1) Identify DOT regulations pertaining to transporting ASME tanks
49 CFR § 172.315 (j): Storage containers for liquefied petroleum gas for permanent installation on consumer premises may be shipped by private motor carrier only under the following conditions:
1) Each container is constructed in compliance with the requirements of the ASME Code and must be marked to indicate compliance [data plate or data specification stamping] in the manner specified by the respective Code.
2) Each container is equipped with safety devices in compliance with the requirements as specified in NFPA Pamphlet No. 58
3) The containers shall be so braced or otherwise secured on the vehicle as to prevent relative motion while in transit. Valves or other fittings shall be adequately protected against injury during transportation.
49 CFR § 172.315 (j): Storage containers for liquefied petroleum gas for permanent installation on consumer premises may be shipped by private motor carrier only under the following conditions:
4) Except as provided in paragraph (5), containers shall not be shipped when charged with liquefied petroleum gas to more than 5 percent of their water capacity.
5) Storage containers of less than 1,042 pounds water capacity (125 gallons) may be shipped when charged with liquefied petroleum gas in compliance with DOT filling density.
Be sure that you read, understand, and apply any company policies and procedures for maintaining ASME tanks and other containers used for customer propane storage.
Particular attention should be given to company-specific standards that stipulate requirements for condition of container coating, customer information decals, sealing of container valves when not in service, and inspection of container valves, fittings, regulators, and other container appurtenances.
Check the condition of each tank valve and fitting.
Check to ensure that weather caps are in place on filler valves and relief valves, the vapor equalizing valve. Verify that the metal plug is in place and sealed on the liquid withdrawal valve.
If the tank is a new tank and not vacuum-sealed by the manufacturer, be sure that the container is properly purged of air before it is transported to the customer location. Older tanks that have been open to the atmosphere must be purged as well.
After the condition of the ASME tank has been determined to be satisfactory, the tank and any required installation materials should be readied for loading. Secure installation items such as masonry foundation blocks on the delivery vehicle; they are considered cargo that must be secured as any other cargo transported under DOT regulations.
Verify that any tank over 125 gallons water capacity contains 5% or less propane in liquid form. If more than 5% liquid is present, the excess liquid must be evacuated before the tank can be transported on public roadways.
Figure 8. Evacuating an ASME Tank Using A Portable Compressor