Times Union Center

TIMES UNION CENTERRENOVATIONS

Page 2: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Synthesis Architects

Gilbane - Construction Managers

Ryan Biggs l Clark Davis - Structural Engineering

Place Alliance - Landscape Architecture/ Streetscape

Greenman-Pedersen Engineering - MEP Engineering

Project Design Team

Page 3: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Construction Manager - Gilbane

General Construction - Murnane Building Contractors

Mechanical Contractor - DiGesare Mechanical Incorporated

Plumbing Contractor - DiGesare MechanicalIncorporated

Fire Sprinkler - Condor- Fire Sprinkler Company, LLC

Electrical Contractor - Coghlin Electrical Contractors, Inc.

Project Construction Team

Page 4: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Page 5: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Page 6: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Page 7: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Stairs &EscalatorsTo be Removed

Sidewalks and Entry to be Redesigned

Page 8: 2016-06-23 Presentation for Printing.pdf

Times Union Center

New Escalators

New Elevator

New Entry Stairs and Street Edge

Fountain

Page 9: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Indoor Arena Level : 9,600 SF

Page 10: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Page 11: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Page 12: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Stairs, Floor Area &EscalatorsTo be Removed

Page 13: 2016-06-23 Presentation for Printing.pdf

Times Union Center

New Elevator

Infill Floor Areas

New Escalator

New Broadcast Media Area

Page 14: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Mezzanine Level•Indoor Garden and Circulation: 6,500 SF• Meeting/Reception Area : 2,500 SF•Broadcast and Media Reporters: 3,000 SF•TOTAL AREA 12,000 SF

Page 15: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Stairs, Floor Area &EscalatorsTo be Removed

Page 16: 2016-06-23 Presentation for Printing.pdf

Times Union Center

New Escalators New Elevator

Infill Floor Areas

Page 17: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Concourse Level•Spectator Queuing and Mobile Concessions: 15,000 SF

CONCOURSE CONCOURSE

Page 18: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Northeast Plaza Entry• Covered Pre-function Area: 4,500 SF• Walkway Renovations: 6,500 SF• TOTAL AREA 11,000 SF

Page 19: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Page 20: 2016-06-23 Presentation for Printing.pdf

Times Union Center

Page 21: 2016-06-23 Presentation for Printing.pdf

Times Union Center

c

New Roof AreaWith Skylight

Page 22: 2016-06-23 Presentation for Printing.pdf

Times Union Center

OPERATIONAL and SAFETY DESIGN HIGHLIGHTS

Operations

•Snow removal from inside the arena will be eliminated,•Pigeons and other birds will no longer be a problem .•Extreme temperature difference in the arena itself will be eliminated. •Existing ticketing and circulation patterns are maintained or improved.

Safety

•Safety is greatly improved by enhancing the egress paths from the arena.•Our design add a fire-sprinkler system and fire alarm system into the atrium.•Exit and emergency lighting and a smoke evacuation system are incorporated, none of which are currently present in the atrium space.

•The atrium can now be closed in the evenings and post event to secure the space from crime, vagrancy and vandalism. However, we envision the atrium to be open to

the public during the day for lunch, informal gathering, etc.

Constructability

•The design minimizes disruption to the Arena’s operation, by maintaining much of the existing structure. The design enhances the structural elements, rather than demolishing them, which will significantly reduce construction time and will allow phasing of the work.