    Phase II

    Second Review

    Analysis for development of deferment

    construction project

    Under the guidance of:

    Mr. M. Balasubramanian

    Assistant Professor (O.G)

    Dept. of Civil Engg.

    SRM University

    By

    Chalapati Sreenath

    Roll no: 1521210028

  • 8/12/2019 1521210028 project

    2/16

    INTRODUCTION construction companies are facing today. Delays will

    result in several negative effects like lawsuits

    between house owners and contractors, exaggerated

    prices Delays are unique one in every of the largest

    issues, loss of productivity and revenue, and contract

    termination.

    Schedule delay is a commonly occurring in

    construction projects. In this study identification &analysis of delays in construction projects. Conduct

    schedule delay analysis & reschedule to overcome

    delay.

  • 8/12/2019 1521210028 project

    3/16

    OBJECTIVE

    The study is to determine how different degrees ofuncertainty impact the construction project.

    To identify the causes of delay for construction

    projects in Indian context.

    Conducting the questionnaire survey on various

    parameters and finding reasons for schedule delay in

    construction projects. Analytics the results.

    Implement new schedule to overcome deferment inconstruction project.

  • 8/12/2019 1521210028 project

    4/16

    SCOPE

    Develop a new prototype model and validate the

    functionality, usefulness & practicality through

    implementing in construction projects.

    Comparison with other models.

    Introduce the new deferment analytics model forconstruction projects.

  • 8/12/2019 1521210028 project

    5/16

    METHODOLOGY

    Introduction

    Literature Review

    Prepare Questionnaire & Conduct Survey

    Analysis Survey Results

    Identifying Parameters of Schedule Delay

    Conducting Schedule Delay Analysis

    Reschedule for Delayed Project

    Analysis and Recommendations

  • 8/12/2019 1521210028 project

    6/16

    SCHEDULE PHASE II

    S.No Description From To Status

    1 Continue the questionnaire

    survey in construction site

    December February 95%

    2 Finalize the tools using for

    project

    January February 95%

    3 Selecting Delayed

    construction site

    January February 95%

    4 Analyze the results February March 10%

    5 Compare results and

    recommendations

    February March Not yet

  • 8/12/2019 1521210028 project

    7/16

    Factors Considering For

    Construction Delay

    i. Labour

    ii. Materialsiii. Design

    iv. Contractor

    v. Consultantvi. Equipment

    vii. External

  • 8/12/2019 1521210028 project

    8/16

    QUESTIONNAIRE SURVEY

    The main objective of the study is

    To identify the causes of delay for residential

    construction projects in Indian context

    To suggest the methodology to work out theimportance by different techniques.

    To rank causes of delay by RII (Relative importance

    index) method and IMPI (Importance Index) method.Frequency of occurrence Degree of severity

    Always OftenSome

    timesRarely Extreme Great Moderate Little

  • 8/12/2019 1521210028 project

    9/16

    DATA ANALYSIS APPROACHES

    Frequency Index (F.I.) (%) = a (n/N) * 100/4

    Severity Index (S.I.) (%)= a (n/N) * 100/4

    Importance Index (IMP.I.)(%) = [F.I.(%)* S.I. (%)]/100

    Rank correlation coefficient Relative importance weight

    Mean score

    Frequency Index

    Relative importance index

  • 8/12/2019 1521210028 project

    10/16

    Results in spss

  • 8/12/2019 1521210028 project

    11/16

    Mean, Median, Mode

  • 8/12/2019 1521210028 project

    12/16

    Suggestions by Respondents

    Methods to reduce of delays

    Perfect planning to Execute the work.

    Avoid wastages during construction.

    Allocate skilled labours as required Reducing wastage of reworks

    Schedule to be maintain in works

    prior approvals should taken for projects by govt

    Financial planning

    Selection of quality maintain contractor

    Selection of skilled workmen's

  • 8/12/2019 1521210028 project

    13/16

    Factors affecting delays

    Progress is affected but without any delay Increase in project cost

    Hiring new professionals

    Increase in overhead expences

    Delays in payment

    Procurement delay

    Productivity Degradation

    Quality Degradation

    Logistic Delay

    Poor safety Conditions

    Dispute among professionals

  • 8/12/2019 1521210028 project

    14/16

    REFERENCES CHIDAMBARAM RAMANATHAN, et al. 2012,

    Construction delay causing risks on time and cost- a critical

    review. Australian journal of construction economics and building,12(1)37-57.

    JYH-BING YANG et al. 2010, Causes of delay in the planning

    and design phases for construction projects. Journal ofArchitectural engineering, 16(2), 80-83.

    HAMIDREZA AFSHARI,SHAHRZAD KHOSRAVI,ABBAS

    GHORBANALI,MAHDI BORZABADI,MAHBOD Valipour-

    2010- Identification Of Causes Of Non- Excusable Delays OfConstruction Projects

    ARDITI, PATTANLITCHAMROON T. 2009, Selecting a

    delay analysis method in resolving construction claims.International journal of project management,24(2), 145-155

  • 8/12/2019 1521210028 project

    15/16

    REFERENCE CONTD

    STEEN LICHTENBERG 2005, How to avoid overruns and

    delays successfully nine basic rules and an associated

    operable procedure.Icec internet journal

    ENG.DAVID KAGIRI and GITURO Wainaina-Time And

    Cost Overruns In Projects In Kenya:A Case Study Of

    Electricity Generating Company Limited.

  • 8/12/2019 1521210028 project

    16/16