1 Open Season Development of new capacities between France and Luxembourg NW-GRI, September - 21 st , 2010
Apr 01, 2015
1
Open Season Development of new capacities
between France and Luxembourg
NW-GRI, September - 21st, 2010
Context
Increase of entry capacity in Luxembourg from FranceObjectives :
Improve Security of SupplyDiversify sources of supply(PEG North / NCG / Zeebrugge Hub)Increase competitionMeet Luxembourg’s demand development
2
Luxembourg’s market
Entry points:Fluxys : 110.000 Nm3/h (31 GWh/d)EGT : 150.000 Nm3/h (42 GWh/d)GRTgaz : 1.100 Nm3/h (0,3 GWh/d)
Consumption: 15 TWh/an (73 GWh/d in a 205j/year basis)Institut Luxembourgeois de Régulation, octobre 2009
3
CREOS network
4
Steps of development foreseen
2 scénarii :10 GWh/j (35 000 m3/h)
• 15 km DN300, to connect to the regional network in France• Delivery and metering station in Luxembourg
45 GWh/j (160 000 m3/h)• 45 km DN500, to connect to the national network in France• Delivery and metering station in Luxembourg
Network reinforcements are required
Expected delivery time for developed capacities : around 4 yearsStudies to validate the different steps are in progress
5
2 possible Steps of development
6
General approach
Assessment of market needs through an open season processFull coordination of the 2 TSOs involved inspired by the “France-Spain model”
Technical and commercial coordinationJoint allocation office
Promotion through the NW-GRI platform (IG September, 21st and SG November, 26th)
To create a coordination and regional cooperation reference
To work with all involved stakeholders (TSO, Regulators, Ministries, shippers)
7
NW-GRI: September 21st first communication within the GRIPreparation of OS documents (Information Memorandum) and contracts between the 2 TSOsLaunch of the Non-binding phase: GRI Stakeholder Group meeting November 26th (if all necessary information is available)Expected launch of the Binding phase: feb-march 2011; end by mid-2011
Final Information Memorandum, Allocation Rules and Booking contracts to be written before the launching dateShippers meetings
8
Main steps foreseen