- Recommendations status - PRR Review report: actions - Conclusion EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Guillaume Prévôt APC, Paris Status on PRR recommendations and actions
5

- Recommendations status - PRR Review report: actions - Conclusion EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Guillaume Prévôt APC, Paris Status.

Dec 29, 2015

Download

Documents

Joleen Wade
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: - Recommendations status - PRR Review report: actions - Conclusion EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Guillaume Prévôt APC, Paris Status.

- Recommendations status

- PRR Review report: actions

- Conclusion

E U S O - B A L L O O N D E S I G N R E V I E W, 1 8 . 1 2 . 2 0 1 2 , C N E S T O U L O U S E

Guillaume PrévôtAPC, Paris

Status on PRR recommendations and actions

Page 2: - Recommendations status - PRR Review report: actions - Conclusion EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Guillaume Prévôt APC, Paris Status.

Recommendations

3 recommendations:

- Project organization

- First flight as soon as possible

- Schedule control

Project organization

“ Defining the CNES organization, introducing an electrical architect, identifying all the activities relative to the harness, clarify the participations to the AIT, the instrument GSE responsibilities.”

- Action 1.1: The team has provided the updated organization.- Action 1.2: The team has provided the updated development plan to CNES.

CDR – 18.12.2012

Status on PRR actions 2

Page 3: - Recommendations status - PRR Review report: actions - Conclusion EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Guillaume Prévôt APC, Paris Status.

Recommendations

First flight as soon as possible

“In consequence, the review panel supports the Euso-Balloon Project in its demand to obtain the first flight as soon as possible considering the project schedule and the opportunities of the CNES Balloon campaigns. A first launch before mid 2014 is recommended.”

Schedule control

“In consequence, the review panel supports the Euso-Balloon Project in its demand to obtain the first flight as soon as possible considering the project schedule and the opportunities of the CNES Balloon campaigns. A first launch before mid 2014 is recommended.”

- Action 3.1.1: The 3 laboratories have done a proposition for a new project manager and it has been accepted by CNES.

- Action 3.4.1: The team has provided the updated instrument planning to CNES.

CDR – 18.12.2012

Status on PRR actions 3

Page 4: - Recommendations status - PRR Review report: actions - Conclusion EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Guillaume Prévôt APC, Paris Status.

PRR Review report: actions

41 actions have been taken with answers from the project team expected for the design review.

- Updates of: - The Technical Specifications document (EUSO-TS-INST-206-LAL_V2.0)- The Instrument Definition document (EUSO-DF-INST-204-LAL_V2.0)- The Organization Note (EUSO-ON-INST-201-LAL_V2_6)- The Compliance Matrix (EUSO-PA-INST-203-LAL_V2.0)- The Risk Analysis document (EUSO-RI-INST-404-IRAP V1.1)- The Development Plan (EUSO-DP-INST-207-LAL_V2.0)

- Writing of: - A Thermal Analysis document (EUSO-TA-INST-409-IRAP V1.0)- A Mission Analysis document (CNES)- ICD documentation (EUSO-IC-INST-407-IRAP_V1.0 (electronics) and

EUSO-MI-INST-408-IRAP_V1.0 (mechanics)) - A AIT Plan document (EUSO-AI-INST-251-LAL_V1.0)- A calibration Note (EUSO-CN-INST-003-APC_V1.0)

CDR – 18.12.2012

Status on PRR actions 4

Page 5: - Recommendations status - PRR Review report: actions - Conclusion EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Guillaume Prévôt APC, Paris Status.

PRR Review report: actions

39 actions have been closed by the team.

2 actions are open (about cleanliness strain).

- FB-14 and OLM-14 are open and they will be dealt with on a specific note delivered at the AIT Key Point.

CDR – 18.12.2012

Status on PRR actions 5