Top Banner
© Nuffield Foundation 2011 Nuffield Free- Standing Mathematics Activity Refurbishin g a room © Nuffield Foundation 2011
9

© Nuffield Foundation 2011 Nuffield Free-Standing Mathematics Activity Refurbishing a room © Nuffield Foundation 2011.

Dec 17, 2015

Download

Documents

Jody Goodwin
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: © Nuffield Foundation 2011 Nuffield Free-Standing Mathematics Activity Refurbishing a room © Nuffield Foundation 2011.

© Nuffield Foundation 2011

Nuffield Free-Standing Mathematics Activity

Refurbishing a room

© Nuffield Foundation 2011

Page 2: © Nuffield Foundation 2011 Nuffield Free-Standing Mathematics Activity Refurbishing a room © Nuffield Foundation 2011.

Refurbishing a room

You can answer such questions by using critical path analysis.

This activity will show you how to do this.

Where shall I start? What order shall I do things in? How soon can it be ready?’

Page 3: © Nuffield Foundation 2011 Nuffield Free-Standing Mathematics Activity Refurbishing a room © Nuffield Foundation 2011.

The techniques of critical path analysis were developed in the late 1950s by two American companies, Dupont and Remington Rand.

They were used to plan large-scale projects such as the development of the Polaris Missile.

The algorithm determines the minimum time for a project to be completed and optimises manpower and resources to achieve this minimum completion time.

Critical Path Analysis

Page 4: © Nuffield Foundation 2011 Nuffield Free-Standing Mathematics Activity Refurbishing a room © Nuffield Foundation 2011.

ActivityTime

(hours)Precedingactivities

Decorating and furnishing a spare bedroom

1Remove old furnitureRemove carpetTake down curtains and railRemove wallpaper

0.5

0.52

A

B C

A

B

CD

Prepare wallsPrepare woodworkPaint walls & ceiling 1st coat (& dry)Paint woodwork (and dry)

Lay new carpetPut up curtain rail and hang curtainsArrange new furniture

Paint walls & ceiling 2nd coat (& dry)

EF

GH

I

JKL

M

0.5

1.5

58

52

11

0.5Put up posters

DD

EF

GH I

H IJ

I

Think about…What else needs to be done?Which jobs need to be done before others?How long each job will take?

Page 5: © Nuffield Foundation 2011 Nuffield Free-Standing Mathematics Activity Refurbishing a room © Nuffield Foundation 2011.

K

1

End0

M

0.5

L

1

I5

G5

F

1.5

E

0.5

D

2

C0.5

B

0.51

A

Start

00 0

0 1 1 1.5

0 1.5

3.5 4

3.5 6

1.5 3.5

4 9 9 14

J2 16

14 17

14 17

16 17

17 17

Draw an activity network

Carry out a forward pass to show earliest possible start times

Carry out a reverse pass to show latest possible finish times

Show the time needed for each activity

14

Find a critical path Start A B D E G I J L End

8

H

5 14

Think about…What will the rest of the network look like?

Page 6: © Nuffield Foundation 2011 Nuffield Free-Standing Mathematics Activity Refurbishing a room © Nuffield Foundation 2011.

Critical path analysis

Step 1 List the activities with a time estimate for each.

Step 2 Note which activities must precede others.

Step 3 Draw an activity network, including the time for each activity.

Step 4 Carry out a forward pass to find the earliest possible start times.

Step 5 Carry out a reverse pass to find the latest possible finish times.

Step 6 Identify critical activities and find a critical path.

Page 7: © Nuffield Foundation 2011 Nuffield Free-Standing Mathematics Activity Refurbishing a room © Nuffield Foundation 2011.

Critical activities must start on time if the project is not to be delayed. They are those for which:

A Furniture removal

B Carpet removal

D Wallpaper removal

E Wall preparation

G 1st coat on walls

I 2nd coat on walls

J Carpet laying

L Arranging new furniture

must start at 0 hours

must start at 1 hours

must start at 1.5 hours

must start at 3.5 hours

must start at 4 hours

must start at 9 hours

must start at 14 hours

must start at 16 hours

Latest finish time = earliest start time + duration

Think about…What comes next?

Page 8: © Nuffield Foundation 2011 Nuffield Free-Standing Mathematics Activity Refurbishing a room © Nuffield Foundation 2011.

ActivityEarliest

startLatest finishDuration Float

The other activities have some flexibility in their start time.

C Remove curtain & rail

F Prepare woodwork

H Paint woodwork

K Put up curtain & rail

M Put up posters

0 1.5 1 h

3.5 6 1 h

5 14 1 h

14 17 2 h

14 17 2.5 h

Float = latest finish time – (earliest start time + duration)

0.5

1.5

8

1

0.5

Think about…Which activities have float?

Page 9: © Nuffield Foundation 2011 Nuffield Free-Standing Mathematics Activity Refurbishing a room © Nuffield Foundation 2011.

Reflect on your work

• Summarise the steps in working out a critical path.

• Describe what is meant by ‘float’.

• What effect will the number of helpers involved have on the minimum completion time?

• When on your finished network will there be the need for at least one helper to allow some of the activities to take place simultaneously?

• What practical considerations need to be taken into account when working out the minimum completion time?

Refurbishing a room