WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16  · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team

Post on 25-Jul-2020

0 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

Transcript

1693-05-02/72WIS 69

New Glarus – Verona County D to Valley Rd

Dane County

Public Involvement MeetingMay 16, 2017

5:30 p.m. to 7:00 p.m.

1

2

Introductions Meeting Purpose Project Background Scope of Work Staging Concepts Project Schedule Open House

WisDOT Project Development Supervisor Bill Strobel, PE

WisDOT Project Manager Mahesh Shrestha, PE

Design Team Brad Groh, PE – JT Engineering, Inc. Mariah Krueger – WisDOT Greg Payne, PE – WisDOT Sam Bieneman – WisDOT John Kehn – WisDOT

3

Reaffirm project concepts and discuss changes

Outline the anticipated project timeline

Examine draft acquisition limits

Engage real estate staff and answer questions about the acquisition process

4

5

8.2-mile corridor

Major Collector Highway

Mill and overlay completed in 2014

6

Safety Pavement Deterioration Roadway Geometry Traffic

7

8

Crashes 2009-2013

1.7x the state average crash rate for 2-lane rural highway

1.7x the number of fatalities on average Some segments up to 4.6x state average crash rate

4.6x crash rate3.1x crash rate

2.9x crash rate

Emergency Overlay from 2014 improved ride Main problem is with the underlying pavement

9

10

Substandard Intersection layout Shoulder and ditch slope Horizontal curves Objects in clear zone Speed rating

Average Daily Traffic (2010 Count) 3500 – 6000 vehicles per day

2039 Forecast (AADT) 6500 – 8450 vehicles per day

11

Environmental Minimize Section 4f Impacts (Park

Land and Historical Site) Minimize Wetland and River Impacts Avoid Impacts to NRHP Eligible

Archaeological Sites General Avoid Relocations Improve Safety Minimize Project Costs

12

Rehabilitate (Likely Mill & Overlay) from southern project limits to the Gehin Road intersection

Reconstruct from Gehin Road intersection to northern project limits

Improve roadway drainage Establish clear zone Enhance safety throughout the corridor

13

14

Rehabilitation Concept Under Development Rural Reconstruction Proposed Typical Section:

15

16

17

18

19

20

21

22

23

Road Closed to Through Traffic In Work Zone Detour Posted For Non-Local Traffic Staging to Enhance Local Connectivity Stage 1 Work focused on area between Belleville and Paoli County PB intersection remains open Stage 2 Work focused on area between Paoli and northern limits Diane Avenue intersection completed and open

24

Environmental Report Submittal Summer 2017 Transportation Project Plat Approval Summer 2017 Begin Right of Way Acquisition Fall 2017 Agency Scoping/Coordination Ongoing Final Plans May 2019 Construction Summer 2020

25

N

WIS 692020

WIS 692017

CTH PB2018

26

27

28

29

Mahesh Shrestha – WisDOT Project ManagerWisDOT – SW Region2101 Wright StreetMadison, WI 53704608-245-2674Mahesh.shrestha@dot.wi.gov

Project Website: http://wisconsindot.gov/Pages/projects/by-region/sw/wis69/default.aspx

top related