                           WEEKLY PROGRESS REPORT 

Property:   St. Andrew 

Today's Date: Friday, May 28, 2021

This report is for the week ending on: Friday, May 28, 2021

Projected Turnover date  TBD

Construction WK Preconstruction 

Inspection Issues n/a

Utility Issues n/a

Permit Issues n/a

Hot Items Executed contracts

Change Orders Sent  None 

Change Orders Approved None 

RFIs Sent  #1

RFIs Pending  None 

Submittals Sent  Concrete Package, Steel Package, Roof Package

Submittals Open  Roof Package 

Scope Completed To Date:

1 Site fencing installed 

2 Portable restrooms placed 

3 Storage container placed 

4 Temp construction power installed 

5 Building surveyed for excavation 

6 Existing utilities marked 

7 Excavator delivered 

Scope to be Completed Next Week:

1 Building excavation 

2 Soil testing started

3 Building survey for building/foundation 

Inspections This Week: 

1 None

Inspections Scheduled for Next Week:

1 3rd Party Inspections 