WEEKLY PROGRESS REPORT
Property: St. Andrew
Today's Date: Friday, May 28, 2021
This report is for the week ending on: Friday, May 28, 2021
Projected Turnover date TBD
Construction WK Preconstruction
Inspection Issues n/a
Utility Issues n/a
Permit Issues n/a
Hot Items Executed contracts
Change Orders Sent None
Change Orders Approved None
RFIs Sent #1
RFIs Pending None
Submittals Sent Concrete Package, Steel Package, Roof Package
Submittals Open Roof Package
Scope Completed To Date:
1 Site fencing installed
2 Portable restrooms placed
3 Storage container placed
4 Temp construction power installed
5 Building surveyed for excavation
6 Existing utilities marked
7 Excavator delivered
Scope to be Completed Next Week:
1 Building excavation
2 Soil testing started
3 Building survey for building/foundation
Inspections This Week:
1 None
Inspections Scheduled for Next Week:
1 3rd Party Inspections