THE SUMMER OF CHANGE 2013. Things are happening ….. WEEK ONE.

Post on 17-Dec-2015

215 Views

Category:

Documents

2 Downloads

Preview:

Click to see full reader

Transcript

THE THE SUMMER SUMMER

OF OF CHANGECHANGE

20132013

Things are happening Things are happening …..…..

WEEK ONEWEEK ONE

Language Unit - The way it Language Unit - The way it was…..was…..

Unisex toilets

Meeting Room & Therapy

Room

Inner corridor and entrance

corridor

Entrance doors and corridor kitchenette

Unisex Toilet AreaUnisex Toilet Area

Old PTA Cupboard Old PTA Cupboard now knocked now knocked through into old through into old toilet area – to be toilet area – to be made into meeting made into meeting roomroom

After one week………

Window knocked Window knocked through from old through from old PTA cupboard into PTA cupboard into corridor next to old corridor next to old therapy roomstherapy rooms

Old meeting room, Old meeting room, now to be turned now to be turned into Inclusion Office into Inclusion Office

Meeting room and Meeting room and new corridor being new corridor being constructed in old constructed in old KS2 classroom areaKS2 classroom area

KS1 Classroom – now has KS1 Classroom – now has windows into corridorwindows into corridor

View into KS1 View into KS1 classroom from classroom from corridorcorridor

OUTSIDE AREASOUTSIDE AREAS

Enclosed outside area for Chickens

New Sensory Garden / Quiet area

EYFS Inside AreaEYFS Inside Area

Unisex toilets being taken out, to be

refitted with new cubicles

Nursery classroom with new opening

into small learning room

Inner corridor being opened

up

WEEK TWOWEEK TWO

KS2 classroom with new corridor KS2 classroom with new corridor and meeting room constructed.and meeting room constructed.

Old PTA Cupboard Old PTA Cupboard now knocked now knocked through into old through into old toilet area, toilet area, partitioned off and partitioned off and made into meeting made into meeting room.room.

Language Unit

New Inclusion New Inclusion Office area, with Office area, with old kitchen, office old kitchen, office and toilet stripped and toilet stripped out. These to be out. These to be made into small made into small teaching room, teaching room, meeting room and meeting room and kitchenettekitchenette

All other areas of the Language Unit All other areas of the Language Unit refurbishment are progressing well. However, it refurbishment are progressing well. However, it was not possible to take photos this week as we was not possible to take photos this week as we did not want to disturb the workmen in these did not want to disturb the workmen in these rooms.rooms.

EYFS Inside AreaEYFS Inside Area

Looking from Nursery towards Looking from Nursery towards the Office, and visa versathe Office, and visa versa

Inner corridor Inner corridor being opened being opened upup

Reception 1 classroom Reception 1 classroom being re-decorated. Old being re-decorated. Old carpet and parquet carpet and parquet flooring has been flooring has been removed.removed.

Old Reception 1 Old Reception 1 classroom being classroom being restructured back to restructured back to its original form to its original form to match current match current Reception 1 and 2. Reception 1 and 2. This room will This room will become the new become the new D&T roomD&T room

Nursery area, with Nursery area, with opening from small opening from small learning room into learning room into main class; new main class; new radiators in whole radiators in whole area and kitchen area and kitchen stripped out.stripped out.

EYFS Outside AreaEYFS Outside Area

New guttering, New guttering, fascias and fascias and soffits being soffits being installed.installed.

Old canopy has Old canopy has been removed, been removed, awaiting awaiting installation of installation of new one. new one.

ALLOTMENT AREAALLOTMENT AREA

SENSORY GARDEN / QUIET SENSORY GARDEN / QUIET AREAAREA

Trellis, raised Trellis, raised plant beds and plant beds and entry bridges entry bridges installed. installed.

Hole dug in Hole dug in preparation for preparation for water featurewater feature

WEEK THREEWEEK THREE

Language Unit

Unisex toilet area. Walls being covered with hygienic cladding.

Sink being installed in KS1 classroom. Walls have first coat of paint.

Work being carried out in KS2 classroom

Old office area being plaster boarded.

Old adult toilet area being refurbished into kitchenette.

Outside are of old PTA cupboard. Now to have window installed into new meeting room.

EYFS Area

Practical Room with sinks installed and

walls painted.

New units being fitted into kitchen area.

Old Reception 2 classroom, now with newly painted white

walls and ceiling, with two walls being depicted in blue.

Outside Areas

EYFS playground with rubber surface removed. Holes being dug for canopy structure.

Sensory Garden / Quiet Area

Water feature, pergolas and blackboards

now installed.

WEEK FOURWEEK FOUR

Language Unit

Adult toilet and Unisex toilets with utilities being installed.

KS1 classroom. Decorated, sink installed and vinyl flooring laid.

Inclusion Room. Decorated and IT data being installed.

Entrance Lobby. Plastered awaiting decoration.

Inner Corridor being decorated.

EYFS Area

Nursery Classroom. Entrance to small learning room plastered. Remainder of room

decorated.

Nursery Entrance Lobby and inner corridor being decorated.

Practical Room. Windows between room and corridor installed.

Rec 1 Classroom. Flooring being laid, prior to screeding.

EYFS Playground Area

Canopy structure posts being installed.

Sensory Garden / Quiet Area

Almost complete.

Water feature, bridges, pergolas,

planting and pathway all finished.

Plaque still to be done.

Seating to be installed during

October half term.

WEEK FIVEWEEK FIVE

Language Unit

• Old Therapy room being decorated

• New classroom doors being fitted

• Unisex toilets being installed

• Kitchenette area being decorated and electrics installed

• Office Area with IT, electrics and phone cables being installed.

• KS2 classroom flooring being laid

EYFS Area

Above: New kitchen being installed

Below: Store room being decorated

Above: Learning room being decorated

Below: Unisex toilets being installed.

EYFS Playground

• New Canopy installed full length of EYFS Area

• New soft play area being marked out.

• New sand and water play area being constructed