Tam Valley School Modernization - Phase 1 Summer 2011

Tam Valley Bond Election Project ListSafety and CommunicationReplace outdated fire alarm system Replace outdated clock, bell and paging system American Disabilities Act compliance Food service kitchen compliance

Building Systems and RenovationRepair or replace aging electrical system components Upgrade inefficient lighting systems including exterior lighting Upgrade computer wiring and infrastructure Repair or replace aging plumbing system components Repair or replace leaking or deteriorating roofs and skylights Paint interior and exterior of buildings Replace flooring Repair or replace windows, doors, hardware and signage Site ImprovementsConstruct solar ready covered outdoor eating area Restore or resurface deteriorating concrete or blacktop Reconfigure parking lot to improve fire access and traffic flow Upgrade aging electrical and plumbing utility systems

Safety and CommunicationAmerican Disabilities Act compliance

Building Systems and RenovationRepair or replace signage Site ImprovementsConstruct solar ready covered outdoor eating area Restore or resurface deteriorating concrete or blacktop Reconfigure parking lot to improve fire access and traffic flow Upgrade aging electrical and plumbing utility systems

Tam Valley Phase 2 - Summer 2012 Project List

Before AfterWindows, paint, roof, doors, lights, gutter, landscape, retaining walls, electrical service, parking lot, playground striping

Windows, paint, roof, doors, lights, gutter, landscape, retaining walls, electrical service, remove one level of sun screen, maintenance path and asphalt

Before After

Windows, paint, roof, doors, lights, gutter, landscape, ramp, server room HVAC, water fountain and railings

Before After

Windows, paint, roof, doors, lights, gutter, landscape, and landings

Before After1960’s Addition with storefront

Windows, paint, roof, doors, lights, gutter, and remove one level of sun screen

Before After

Windows, paint, roof, doors, lights, gutter, remove one level of sun screen, remove storage shed, new landings at doors

Before After

Windows, paint, roof, doors, lights, gutter, remove one level of sun screen, ramp, railings, new landings at doors

Before After

Windows, paint, lights, asphalt, and ramp surfaces

Before After

Windows, paint, roof, doors, lights, gutter, ramp and railings

Before After

Windows, paint, roof, doors, lights, and gutter

Before After

Windows, paint, roof, doors, lights, gutter, landing at door

Before After1960’s Addition with storefront

Windows, paint, roof, doors, lights, and gutter

Before After

Paint, abrasive action floor covering, and non-wax floor covering

Before After

Paint, abrasive action floor covering, new double door into MPR

Before After

Paint, abrasive action floor covering, and non-wax floor covering

Before After

Paint, non-wax floor covering, cubbies protector to assist seeing impaired

Before After

Windows, door, paint, abrasive action floor covering, and non-wax floor covering

Before After

Paint, abrasive action floor covering, and non-wax floor covering

Before After

Windows, paint, doors, motorized blinds, new fire alarm speaker and bell systems

Before After

New clock and bell system, wireless access points, and wall mounted short throw projectors

Before After

Operable windows, ceiling paint, motorized shades, and touch up paint to cabinets

Before AfterNon operable windows

Removed all wall mounted televisions and replaced with short throw projectors

Before AfterWall mounted televisions

Replaced all slipper rugs with abrasive actions carpets

Before After

Phase 1 - windows, paint, roof, doors, gutter, and landings at doors. Phase 2 in summer 2012 will have a new walkway and ramps

Before After

Phase 1 - windows, paint, roof, doors, gutter, and landings at doors, new bell system. Phase 2 in summer 2012 will have a new walkway and ramps

Before After

Moved ball walls, slurry seal and restriped blacktop

Before After

Paint, roof, doors, lights, gutter, landscape, larger landing under lunch table

Before After

Windows, paint, roof, doors, lights, gutter, slurry seal and striping

Before After

Paint, lights, ramp surfaces, new fire alarm, clock and speaker systems, slurry seal and restriping blacktop

Before After

Paint, lights, water fountain, railing, roofs, gutter, new fire alarm, clock and speaker systems, slurry seal and restriping blacktop

Before After

Paint, lights, roofs, remove railing, new landing, gutter, new fire alarm, clock and speaker systems, slurry seal and restriping blacktop

Before After

Paint, lights, water fountain, railing, roofs, gutter, new fire alarm, clock and speaker systems, slurry seal and restriping blacktop

Before After

Roof, operable skylights, and venting with curb detail

Before After

Replace all scuppers with gutters, all gutters have screen covers

Before AfterScuppers

All new roofs on main building and modular wing

Before AfterPatched roofs

New heater unit and ducts at Admin offices

Before After

New roof, new windows, and new conduit for data, fire, bell and electrical upgrades

Before After

Phase 1 - Paint, lights, door hardware. Phase 2 summer 2012, landscape changes

Before After

Phase 1 - Remove dumpster enclosure, and new sidewalk. Phase 2 - Parking lot renovation

Before After

Windows, paint, roof, doors, lights, gutter, landscape, ramp, stairs, and railings

Before After

Phase 2 – Summer 2012

Phase 1 – Summer 2011