Tam Valley School Modernization - Phase 1 Summer 2011
44
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Tam Valley School Modernization - Phase 1 Summer 2011.

Tam Valley School Modernization - Phase 1 Summer 2011

Page 2: Tam Valley School Modernization - Phase 1 Summer 2011.

Tam Valley Bond Election Project ListSafety and CommunicationReplace outdated fire alarm system Replace outdated clock, bell and paging system American Disabilities Act compliance Food service kitchen compliance

Building Systems and RenovationRepair or replace aging electrical system components Upgrade inefficient lighting systems including exterior lighting Upgrade computer wiring and infrastructure Repair or replace aging plumbing system components Repair or replace leaking or deteriorating roofs and skylights Paint interior and exterior of buildings Replace flooring Repair or replace windows, doors, hardware and signage Site ImprovementsConstruct solar ready covered outdoor eating area Restore or resurface deteriorating concrete or blacktop Reconfigure parking lot to improve fire access and traffic flow Upgrade aging electrical and plumbing utility systems

Safety and CommunicationAmerican Disabilities Act compliance

Building Systems and RenovationRepair or replace signage Site ImprovementsConstruct solar ready covered outdoor eating area Restore or resurface deteriorating concrete or blacktop Reconfigure parking lot to improve fire access and traffic flow Upgrade aging electrical and plumbing utility systems

Tam Valley Phase 2 - Summer 2012 Project List

Page 3: Tam Valley School Modernization - Phase 1 Summer 2011.

Before AfterWindows, paint, roof, doors, lights, gutter, landscape, retaining walls, electrical service, parking lot, playground striping

Page 4: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, roof, doors, lights, gutter, landscape, retaining walls, electrical service, remove one level of sun screen, maintenance path and asphalt

Before After

Page 5: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, roof, doors, lights, gutter, landscape, ramp, server room HVAC, water fountain and railings

Before After

Page 6: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, roof, doors, lights, gutter, landscape, and landings

Before After1960’s Addition with storefront

Page 7: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, roof, doors, lights, gutter, and remove one level of sun screen

Before After

Page 8: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, roof, doors, lights, gutter, remove one level of sun screen, remove storage shed, new landings at doors

Before After

Page 9: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, roof, doors, lights, gutter, remove one level of sun screen, ramp, railings, new landings at doors

Before After

Page 10: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, lights, asphalt, and ramp surfaces

Before After

Page 11: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, roof, doors, lights, gutter, ramp and railings

Before After

Page 12: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, roof, doors, lights, and gutter

Before After

Page 13: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, roof, doors, lights, gutter, landing at door

Before After1960’s Addition with storefront

Page 14: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, roof, doors, lights, and gutter

Before After

Page 15: Tam Valley School Modernization - Phase 1 Summer 2011.

Paint, abrasive action floor covering, and non-wax floor covering

Before After

Page 16: Tam Valley School Modernization - Phase 1 Summer 2011.

Paint, abrasive action floor covering, new double door into MPR

Before After

Page 17: Tam Valley School Modernization - Phase 1 Summer 2011.

Paint, abrasive action floor covering, and non-wax floor covering

Before After

Page 18: Tam Valley School Modernization - Phase 1 Summer 2011.

Paint, non-wax floor covering, cubbies protector to assist seeing impaired

Before After

Page 19: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, door, paint, abrasive action floor covering, and non-wax floor covering

Before After

Page 20: Tam Valley School Modernization - Phase 1 Summer 2011.

Paint, abrasive action floor covering, and non-wax floor covering

Before After

Page 21: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, doors, motorized blinds, new fire alarm speaker and bell systems

Before After

Page 22: Tam Valley School Modernization - Phase 1 Summer 2011.

New clock and bell system, wireless access points, and wall mounted short throw projectors

Before After

Page 23: Tam Valley School Modernization - Phase 1 Summer 2011.

Operable windows, ceiling paint, motorized shades, and touch up paint to cabinets

Before AfterNon operable windows

Page 24: Tam Valley School Modernization - Phase 1 Summer 2011.

Removed all wall mounted televisions and replaced with short throw projectors

Before AfterWall mounted televisions

Page 25: Tam Valley School Modernization - Phase 1 Summer 2011.

Replaced all slipper rugs with abrasive actions carpets

Before After

Page 26: Tam Valley School Modernization - Phase 1 Summer 2011.

Phase 1 - windows, paint, roof, doors, gutter, and landings at doors. Phase 2 in summer 2012 will have a new walkway and ramps

Before After

Page 27: Tam Valley School Modernization - Phase 1 Summer 2011.

Phase 1 - windows, paint, roof, doors, gutter, and landings at doors, new bell system. Phase 2 in summer 2012 will have a new walkway and ramps

Before After

Page 28: Tam Valley School Modernization - Phase 1 Summer 2011.

Moved ball walls, slurry seal and restriped blacktop

Before After

Page 29: Tam Valley School Modernization - Phase 1 Summer 2011.

Paint, roof, doors, lights, gutter, landscape, larger landing under lunch table

Before After

Page 30: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, roof, doors, lights, gutter, slurry seal and striping

Before After

Page 31: Tam Valley School Modernization - Phase 1 Summer 2011.

Paint, lights, ramp surfaces, new fire alarm, clock and speaker systems, slurry seal and restriping blacktop

Before After

Page 32: Tam Valley School Modernization - Phase 1 Summer 2011.

Paint, lights, water fountain, railing, roofs, gutter, new fire alarm, clock and speaker systems, slurry seal and restriping blacktop

Before After

Page 33: Tam Valley School Modernization - Phase 1 Summer 2011.

Paint, lights, roofs, remove railing, new landing, gutter, new fire alarm, clock and speaker systems, slurry seal and restriping blacktop

Before After

Page 34: Tam Valley School Modernization - Phase 1 Summer 2011.

Paint, lights, water fountain, railing, roofs, gutter, new fire alarm, clock and speaker systems, slurry seal and restriping blacktop

Before After

Page 35: Tam Valley School Modernization - Phase 1 Summer 2011.

Roof, operable skylights, and venting with curb detail

Before After

Page 36: Tam Valley School Modernization - Phase 1 Summer 2011.

Replace all scuppers with gutters, all gutters have screen covers

Before AfterScuppers

Page 37: Tam Valley School Modernization - Phase 1 Summer 2011.

All new roofs on main building and modular wing

Before AfterPatched roofs

Page 38: Tam Valley School Modernization - Phase 1 Summer 2011.

New heater unit and ducts at Admin offices

Before After

Page 39: Tam Valley School Modernization - Phase 1 Summer 2011.

New roof, new windows, and new conduit for data, fire, bell and electrical upgrades

Before After

Page 40: Tam Valley School Modernization - Phase 1 Summer 2011.

Phase 1 - Paint, lights, door hardware. Phase 2 summer 2012, landscape changes

Before After

Page 41: Tam Valley School Modernization - Phase 1 Summer 2011.

Phase 1 - Remove dumpster enclosure, and new sidewalk. Phase 2 - Parking lot renovation

Before After

Page 42: Tam Valley School Modernization - Phase 1 Summer 2011.

Windows, paint, roof, doors, lights, gutter, landscape, ramp, stairs, and railings

Before After

Page 43: Tam Valley School Modernization - Phase 1 Summer 2011.

Phase 2 – Summer 2012

Phase 1 – Summer 2011

Page 44: Tam Valley School Modernization - Phase 1 Summer 2011.