ATN 2001, London - 18 Sep 01 1EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
PETAL II and II ExtensionPETAL II and II ExtensionMaastricht Multi-stack Maastricht Multi-stack
ImplementationImplementationLessons LearntLessons Learnt
Prepared by Gustaaf Janssens/Konrad KoebeMaastricht UAC
ATN 2001, London - 18 Sep 01 2EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
TOPICSTOPICS What Do We Mean by Multi-Stack? Why Multi-Stack ? What Are Multi-Stack Design Considerations ? MUAC Ground Architecture MUAC Schedule Achievements How Do We Test ? What Are Our Lessons Learnt ? Next Steps Conclusions
ATN 2001, London - 18 Sep 01 3EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
What Do We Mean by Multi-Stack ?What Do We Mean by Multi-Stack ? Accommodating Existing Specifications for
AGDL NEAN Extension (Prototype VDL4) FANS-1/A ATN SARPs
Aim Communicate With Any Avionics Equipment Using
One Of The Specifications
ATN 2001, London - 18 Sep 01 4EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
Why Multi-Stack ?Why Multi-Stack ? PETAL-II Project Needs for MUAC
Operations - Hide AGDL Technology for User Operational Requirements Validation Independent From
AGDL Technology Quick Implementation
Project Has to Compete With Daily Life Activities at an Operational Centre
Take Advantage of Existing Operational Avionics Equipment
Encourage ATN SARPs based Air and Ground Implementations
ATN 2001, London - 18 Sep 01 5EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
Design Constraints (1)Design Constraints (1) Fit In MUAC Existing Ground Structure
HMI, FDPS, Gateways Add Functionality in HMI and FDPS, Add AGDL Gateway
HMI Add to Normal Controller Presentation and Interface
FDPS Based on ATN SARPs Ground End User Applications
Definitions AGDL Gateway
Single Access Point for FDPS Access Points for Underlying AGDL Technologies
ATN 2001, London - 18 Sep 01 6EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
Design Constraints (2)Design Constraints (2)
Evolutionary Development Next Step Building on Results of Predecessor
ATN 2001, London - 18 Sep 01 7EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
Maastricht Multi-stack GROUND End System (1)Maastricht Multi-stack GROUND End System (1)
Controller
HMIController
HMIController
HMIController
HMI
Flight Data Processing SystemATM Services
NEAN GWY
NEAN
9705BER
P2GW (PETAL 2 GATEWAY)
FANS-1/A GWY
SITA
ProATN ES9705PER
VDL2-ATNProATNROUTER
ATN 2001, London - 18 Sep 01 8EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
Maastricht Multi-stack GROUND End System (2)Maastricht Multi-stack GROUND End System (2)
ControllerHMI
ControllerHMI
ControllerHMI
ControllerHMI
Flight Data Processing System- Flight plan / address association- ATN SARPs (ICAO 9705) CM, ADS, CPDLC- All datalink service logic and dialogue control
P2FEP
NFEP- Aircraft address/state- ASE emulation CM, CPDLC, ADS- Conv. to NEAN specs.
FAFEP- Aircraft address/state- ASE emulation CM, CPDLC, ADS- Conv. To FANS specs
ALLA- P2PI- Aircraft address/state- BER-PER Conversion.
ProATN - ASEs: CM, CPDLC, ADS - ATN Router
FANS-1/A Gateway
NEANServer
9705BER
9705PER
P2GW
ATN 2001, London - 18 Sep 01 9EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
Design Constraints (3)Design Constraints (3) P2GW
Holds and Manages Addressing Data Buffers FDPS from Unexpected
communications MADAP Msg= {Msg ID, Infra
ID+24bits+FID+Reg.Mark+9705-BER-Msg} Hides Communication and Network Specifics from
FDPS
ATN 2001, London - 18 Sep 01 10EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
Design Constraints (4) Design Constraints (4) AGDL Applications implemented
CM, ADS, CPDLC FDPS AGDL Services Using these Applications
CM: DLIC AcceptanceCM: DLIC Acceptance ADS: ADS demand (FLIPCY), ADS periodic (CAP)ADS: ADS demand (FLIPCY), ADS periodic (CAP) CPDLC: (ACL, ACM, AMC)CPDLC: (ACL, ACM, AMC)
FDPS Functionality Used for AGDLFDPS Functionality Used for AGDL Manages Flight plan Operational StatusManages Flight plan Operational Status
DLIC acceptance and ADS, CPDLC requestsDLIC acceptance and ADS, CPDLC requests Terminates CPDLC, ADSTerminates CPDLC, ADS
ATN 2001, London - 18 Sep 01 11EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
Design Constraints (5) Design Constraints (5) Controller AuthorisationController Authorisation
Only Controlling Sector handles CPDLCOnly Controlling Sector handles CPDLC FDP Controls Sequence ExtractionFDP Controls Sequence Extraction
Next internal or external sector (NDA) identitiesNext internal or external sector (NDA) identities Controls Automatic Flight Plan ActionControls Automatic Flight Plan Action
CMContact at OLDI ABI eventCMContact at OLDI ABI event CPDLC (NDA) at OLDI ACT eventCPDLC (NDA) at OLDI ACT event
Extracts Information for Controller HMIExtracts Information for Controller HMI radar picture and tabular displayradar picture and tabular display
Provides Authorised Input Sequences and Provides Authorised Input Sequences and Guidance on Controller HMIGuidance on Controller HMI
ATN 2001, London - 18 Sep 01 12EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
ATN 2001, London - 18 Sep 01 13EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
MUAC Schedule Achievements (1)MUAC Schedule Achievements (1) NEAN IN 4/98 FANS 1/A 2/99 P2GW - BAC1/11 using
ATIF/SATCOM, P-II message set. 5/00 MC-P2GW-BAC1/11 Flight using ATIF/SATCOM,
P-IIe message set. 9/00 Application Testing: FDPS-Avionics 11/00 FDPS, P2GW Ready 3/01
ATN 2001, London - 18 Sep 01 14EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
MUAC Schedule Achievements (2)MUAC Schedule Achievements (2) FANS1/A ONLINE: P-IIe Message set 4/01 NEAN OUT 4/01 CERTification Testing Support 5/01 Non Revenue Flights 6/01 MUAC-RUAC Shadow Flight 7/01 Revenue Flight 8/01
ATN 2001, London - 18 Sep 01 15EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
MUAC Technical Achievements (1)MUAC Technical Achievements (1) ICAO 9705 Compliant FDPS Implementation Usage of ATN, FANS1/A and Prototype VDL4 First Fully Certified ATN avionics CPDLC Flights May1998-June2001 = 8455
(FANS/NEAN) Test Infrastructure Test Methodology
ATN 2001, London - 18 Sep 01 16EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
How Do We Test (1) ?How Do We Test (1) ? Test Approach
Local Tests HMI, FDPS, P2GW
End-to-End Application Tests: FDPS- Other ATC Centre - Avionics
• grounded avionics• airborne avionics
Operational Observation Overview of Our Test Configurations
ATN 2001, London - 18 Sep 01 17EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
P2GW EMUL
FAME
AGDG-FANSFDPS EMUL
AFAME
PSF
AGDG ATN
NON REV
ATN 2001, London - 18 Sep 01 18EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
PIIe Operational ObservationPIIe Operational Observation
VDL M2
B767
P2GW
MAASTRICHT UAC Control Centre
PROATNR
PROATNEnd
SystemFDPS
LANLAN
CPDLC ServicesVIAATN/VDL Mode 2
ATN 2001, London - 18 Sep 01 19EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
What Are Our Lessons Learnt (1) ?What Are Our Lessons Learnt (1) ? Step by Step Implementation
NEAN Validation of Technical Concept and Architecture
FANS 1/A Validation of ‘Multi Stack’ Concept
• HMI, FDPS Independent From AGDL Technology
ATN SARPs Validation of SARPs Compliant Implementation Additional Operational Messages and Stack Functions
Lessons More Testing Effort due to Regression Testing ?
ATN 2001, London - 18 Sep 01 20EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
What Are Our Lessons Learnt (2) ?What Are Our Lessons Learnt (2) ?
ATN SARPs Implementation Tests Early Feedback = Early Application Error Detection
and Correction BAC1-11 Test Flights ATIF-ground Testing End-to-End Application testing
No Application Errors Detected During CERT, Non-Revenue and Revenue Flights
ATN 2001, London - 18 Sep 01 21EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
What Are Our Lessons Learnt (3) ?What Are Our Lessons Learnt (3) ? Local Tests as Much as Possible
Avionics Emulators Test Automation Protocol Test facilities
External Testing is Expensive Test Setup Test Execution Time Consuming
Good Test Objectives and Strategies
ATN 2001, London - 18 Sep 01 22EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
What Are Our Lessons Learnt (4) ?What Are Our Lessons Learnt (4) ? Future Requirements for Test Tools and Strategies
Reference Test Tools Required Available For All Implementers Common Development A lot of Tools exist. Usable to further develop ?
Reference Test Objectives and Strategies Separate Test Network Required
Connect Test Systems Intra Centre Test Avionics Tests
ATN 2001, London - 18 Sep 01 23EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
Next Steps (1)Next Steps (1) Complete PETAL-IIe
System Safety Assessment Document Lessons Learned Consolidate Documentation Evaluate Test Automation (GEODE)
New Project (P2L = PETAL To LINK2000+)(in approval and initiation phase)
ATN 2001, London - 18 Sep 01 24EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
Next Steps (2)Next Steps (2) P2L Objectives
Maintain a State of the Art Implementation of the Existing AGDL Implementation.
Ensure Safety of all Operational Systems Increase the Number of aircraft applying AGDL
Services (FANS, ATN) Support the LINK 2000+ Project
Enabler for aircraft to equip. Enabler for other Centres Enabler for COMS Enabler for Test and Validation tools - Common
Development and Support.
ATN 2001, London - 18 Sep 01 25EUROCONTROL MAASTRICT UACEUROCONTROL MAASTRICT UAC
CONCLUSIONCONCLUSION
MULTI STACK CONCEPT WORKS ! SERVE MORE AIRCRAFT CONNECT TO NEIGHBOUR ATC CENTRES
THANK YOU PARTNERS FOR THE COOPERATION !