Introduction Joshua Castillo Construction Management Center for Creative and Performing Arts High School (CAPA High School) Pittsburgh, Pennsylvania.
Post on 14-Jan-2016
213 Views
Preview:
Transcript
IntroductionIntroduction
Joshua CastilloJoshua Castillo
Construction ManagementConstruction Management
Center for Creative and Performing Arts High School
(CAPA High School)Pittsburgh, Pennsylvania
AgendaAgenda
• General Project Information• Existing Building Systems• Foundation Analysis• Site Plan Analysis• “Astrovision” Video Screen Analysis• Conclusions
General Project InformationGeneral Project Information
• Existing Site and Old Building– Downtown Pittsburgh– Adjacent to Allegheny River– Donation of Site and part of
Existing Building– Existing Building Usage
• Bar and Lounge 1st Floor • Jazz Club 2nd and 3rd Floors• CAPA use Floors 4-6• Unoccupied 7th and 8th Floors• Residence on 9th Floor Penthouse
General Project InformationGeneral Project Information
• New CAPA Building– Approximately 120,000 SF,
7 Stories– Full- Functioning High
School Including:• Classrooms and Labs
• Staff and Faculty Offices
• Cafeteria and Gym
• Below Grade Parking Lot
– Focus in Creative and Performing Arts
• 5,500 SF Theater
• 4 Studios
RENDITION OF CAPA BUILDING
Existing Building SystemsExisting Building Systems
• Foundation System– Caissons with spanning Grade Beams– Slab on Grade and CIP Concrete Walls Below Grade
• Framing System– A36 Steel Framing and Details
• Mechanical systems– Complete with 2 AHU, air Distribution Ducts, Diffusers,
Registers, Dampers, and Grilles
• Electrical systems– Dry-Type Distribution Transformers – Low Volt Distribution Switch Boards– Light and Power Panel Boards for Wiring
Existing Building SystemsExisting Building Systems
• Façade Systems– East Side:
• CMU on Entire Side adjacent to Feiser Building
– West Side: • Brick and Aluminum Windows
– South Side:• Same as West other than Building
Connection to Existing
– North Side:• Glass Curtain Wall Spanning Height
• “Astrovision” Video Display Screen
• Brick and Aluminum Windows
Connection to Existing Building
Foundation AnalysisFoundation Analysis
• CAPA Originally Designed with Caissons– Caisson Construction Methods
• Drill Holes• Reinforce Walls to Prevent Collapsing• Pump Water Out• Place Steel Reinforcing• Place Concrete
Foundation AnalysisFoundation Analysis
• Problems with Using Caissons – Difficult to Construct in unstable Soil Conditions
• High Water Table • Steel Casing as Hole Wall supports• Pump Water or use Tremie Method to Place
Concrete
– Variable Construction • Eight Sizes of Caisson Diameters Ranging from
2 ½ ft to 6 ½ ft across the site
Foundation AnalysisFoundation Analysis
• Problems with Using Caissons– Duration of Installation
• Time to Install Steel Casing• Time to Pump Water• Drill, Reinforce Hole Walls, Place Steel
Reinforcing, then Pour Concrete
Foundation AnalysisFoundation Analysis
• Auger Cast Piles (ACP’s) as an Alternative– Auger Cast Pile Construction Method
• Drill Hole• Concrete Placed as Drill Bit is Removed• Steel Reinforcing Placed after Concrete is Placed• ACP’s used in a Cluster require a Pile Cap to tie them
together
1.Drill Bit
2.Pressurized Concrete
3.Auger Cast Pile
Foundation AnalysisFoundation Analysis
• Using ACP’s as an Alternative Foundation– General Benefits of Using ACP’s
• Speed of Installation• Less Material Costs• Bearing Capacity • Overall Reduced Costs
– Problems with Using ACP’s• Susceptible to Variability• More ACP’s Required than Caissons
Foundation AnalysisFoundation Analysis
• Comparing the Two Foundation Systems
Caissons VS Auger Cast Piles
– Structural Bearing Capacity– Cost differences in Material and Construction– Constructability and Length of Time to Install
Foundation AnalysisFoundation Analysis• General Bearing Capacity
QUltimate = QP + QS
= AP(CNC+ ЧLNq + ЧNЧ) + Σ∆L(AS)S• Surface-Friction per Unit Area
S = KS σ Tan∂ where: KS = Ave. Coeff. of Earth Pressure on Pile
Shaft
Steel Lined Caissons KS=1.1Concrete Alone KS=1.5
*ACP’s can have 36% more Surface-Friction Bearing Capacity than Steel lined Caissons
Foundation AnalysisFoundation Analysis
QUltimate = AP(CNC+ ЧLNq + ЧNЧ) + ASFS
Average Unit Surface-Friction
FS= C+ ½ KS(Ч-G) L (tan Ø)
Assumptions: Ø = 12°
C = 6 KN/m^2
Ч = 18 KN/m^3
Foundation AnalysisFoundation Analysis
• Ultimate Bearing Capacity Comparison– Average Length of 50 Feet– 24” Diameter
• Surface-Friction ComparisonCaissons FS = 20.5 KN/m^2
ACP’s FS = 25.85 KN/m^2
Foundation AnalysisFoundation Analysis
• Ultimate Bearing Capacity ComparisonQUltimate = AP(CNC+ ЧLNq + ЧNЧ) + ASFS
Caissons QUlt = QP + QS
= 140.3 + 598.6 =738.9 KN =168 kips
ACP’s QUlt = QP + QS
= 140.3 + 753 = 893.3 KN =200 kips
Foundation AnalysisFoundation Analysis
• Pile Cap Design– Based on # of Piles / Cluster– All Pile Caps used were 49” deep– Four different pile layouts– Four different size pile caps
Foundation AnalysisFoundation Analysis
Foundation AnalysisFoundation Analysis
• Foundation Cost Comparison– System Estimates Using:
• Means Cost Guides• Walker’s Building Estimating• General Contractor Consulting
Foundation AnalysisFoundation Analysis
• Means Cost Guide Results
Total Cost
Caissons System $900,000
Auger Cast Pile System $500,000
Difference $400,000
Foundation AnalysisFoundation Analysis
• Duration of Foundation Construction– Foundation System Duration Estimates Using:
• Means Cost Guides• General Contractor Consulting
Foundation AnalysisFoundation Analysis
• Means Cost Guide Duration Results
Total Duration
Caissons 60 work days
Auger Cast Piles 40 work days
Difference 20 work days/ 4 Weeks
Site Plan ModificationSite Plan Modification
• A Discrepancy Affecting the Site Layout– Location of Existing Sanitary Sewer Line
• Located 5 Feet closer to Building than shown on Drawings
• Changes that were Made– Redesign of shoring system– Hand Excavation
Site Plan ModificationSite Plan Modification• Location of Foundation Problem
– West Side Caissons are too Close to Sewer Line
Site Plan ModificationSite Plan Modification• 1st Possibility
– Reduce Width of Entire Vault Area 1-2 ft – Leave Caissons/Piles at the edge
Site Plan ModificationSite Plan Modification
• Effects of Reducing Vault Area Width– Positive Effects
• Less Congestion for Foundation Installation• No Change in Building Superstructure
– Negative Effects• Vault Area Will be More Congested• Vault is Pre-cast Concrete
Site Plan ModificationSite Plan Modification
• 2nd Possibility – Move West Side Caissons/Piles East 5 ft
Site Plan ModificationSite Plan Modification
• Effects of Partial Foundation Relocation– Positive Effects
• Less Congestion for Foundation Installation• Building Superstructure Stays the Same
– Negative Effects• Located in the Central Axis of the Vault Area• Creates 1 to 1 Cantilever on Grade Beams
Site Plan ModificationSite Plan Modification
• Solution– Move West Side Foundation Piers 5ft East– Move Entire Vault Area 10 ft South
““Astrovision” Video Display Screen AnalysisAstrovision” Video Display Screen Analysis
• What is it?– 22ft X 37ft Video
Screen– 112 Individual Modules
““Astrovision” Video Display Screen AnalysisAstrovision” Video Display Screen Analysis
• Problem With Screen Design– No Outlet to Disperse Heat Generated
• Could Cause Damage to the Screen• Could Cause Excess Heat in Building
• Possible Solution– Add Louvers to Disperse Heat
““Astrovision” Video Display Screen AnalysisAstrovision” Video Display Screen Analysis
• Effects of Adding Louvers– Screen is Able to be Cooled
• Eliminates Potential Damage to Itself• Better Chance of Lasting Expected Lifetime• Eliminates Excess Heat Exposure of Building
– Reduced Screen Size to Account for Louvers• Loss of 3 Lines of Screen Modules (21 Modules)
““Astrovision” Video Display Screen AnalysisAstrovision” Video Display Screen Analysis
• Effects of Adding Louvers– Reduced Screen Size
• Loss in Aesthetical Quality of Screen
• Overall Cost of Screen is Reduced
– Added Cost of Louvers
““Astrovision” Video Display Screen AnalysisAstrovision” Video Display Screen Analysis
• Change in Cost With Louvers
Total Cost
21 Screen Modules $200,000
Louvers $10,000
Difference $190,000
ConclusionsConclusions• Foundation Analysis
PROS– ACP’s have Better Surface-Friction making their Bearing Capacity higher than
Steel Lined Caissons in the right soil conditions. – Using ACP’s Would Save Money and TimeCONS– More potential for Displacement – Increased Chance of Variability in the Shafts
• Site Plan Modification– Resizing the Vault Area Would Not be a Practical solution– Relocating the Foundation Caissons Reduces the Structural Integrity of the Vault
Area– Move Entire Vault Area away from Potential Traffic Loads
• Screen Redesign with Louvers – Saves Money in Initial and Repair Costs– Loss in Aesthetical Quality
Summary of Costs
Caisson Foundation System………………………………………………… $901,442
ACP Foundation System……………………………………………………. $445,701
Savings………………………….. $455,741
Original "Astrovision" Design……………………………………………….. $1,500,000
Reduced Size "Astrovision" With Louvers………………………………… $1,299,800
Savings………………………… $200,200
Total Cost Savings ………………… $655,941
Duration of Foundation Systems
Caisson Foundation System………………………………………………… 63 Work Days
ACP Foundation System……………………………………………………. 43 Work Days
Total Time Savings………………… 20 Work Days
• AE Faculty
• Mascaro Construction– Tom Weber– Marc Delrossi – Project Engineer
• Family and Friends
Questions?Questions?
top related