Introduction Joshua Castillo Construction Management Center for Creative and Performing Arts High School (CAPA High School) Pittsburgh, Pennsylvania.

Post on 14-Jan-2016

213 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

Transcript

IntroductionIntroduction

Joshua CastilloJoshua Castillo

Construction ManagementConstruction Management

Center for Creative and Performing Arts High School

(CAPA High School)Pittsburgh, Pennsylvania

AgendaAgenda

• General Project Information• Existing Building Systems• Foundation Analysis• Site Plan Analysis• “Astrovision” Video Screen Analysis• Conclusions

General Project InformationGeneral Project Information

• Existing Site and Old Building– Downtown Pittsburgh– Adjacent to Allegheny River– Donation of Site and part of

Existing Building– Existing Building Usage

• Bar and Lounge 1st Floor • Jazz Club 2nd and 3rd Floors• CAPA use Floors 4-6• Unoccupied 7th and 8th Floors• Residence on 9th Floor Penthouse

General Project InformationGeneral Project Information

• New CAPA Building– Approximately 120,000 SF,

7 Stories– Full- Functioning High

School Including:• Classrooms and Labs

• Staff and Faculty Offices

• Cafeteria and Gym

• Below Grade Parking Lot

– Focus in Creative and Performing Arts

• 5,500 SF Theater

• 4 Studios

RENDITION OF CAPA BUILDING

Existing Building SystemsExisting Building Systems

• Foundation System– Caissons with spanning Grade Beams– Slab on Grade and CIP Concrete Walls Below Grade

• Framing System– A36 Steel Framing and Details

• Mechanical systems– Complete with 2 AHU, air Distribution Ducts, Diffusers,

Registers, Dampers, and Grilles

• Electrical systems– Dry-Type Distribution Transformers – Low Volt Distribution Switch Boards– Light and Power Panel Boards for Wiring

Existing Building SystemsExisting Building Systems

• Façade Systems– East Side:

• CMU on Entire Side adjacent to Feiser Building

– West Side: • Brick and Aluminum Windows

– South Side:• Same as West other than Building

Connection to Existing

– North Side:• Glass Curtain Wall Spanning Height

• “Astrovision” Video Display Screen

• Brick and Aluminum Windows

Connection to Existing Building

Foundation AnalysisFoundation Analysis

• CAPA Originally Designed with Caissons– Caisson Construction Methods

• Drill Holes• Reinforce Walls to Prevent Collapsing• Pump Water Out• Place Steel Reinforcing• Place Concrete

Foundation AnalysisFoundation Analysis

• Problems with Using Caissons – Difficult to Construct in unstable Soil Conditions

• High Water Table • Steel Casing as Hole Wall supports• Pump Water or use Tremie Method to Place

Concrete

– Variable Construction • Eight Sizes of Caisson Diameters Ranging from

2 ½ ft to 6 ½ ft across the site

Foundation AnalysisFoundation Analysis

• Problems with Using Caissons– Duration of Installation

• Time to Install Steel Casing• Time to Pump Water• Drill, Reinforce Hole Walls, Place Steel

Reinforcing, then Pour Concrete

Foundation AnalysisFoundation Analysis

• Auger Cast Piles (ACP’s) as an Alternative– Auger Cast Pile Construction Method

• Drill Hole• Concrete Placed as Drill Bit is Removed• Steel Reinforcing Placed after Concrete is Placed• ACP’s used in a Cluster require a Pile Cap to tie them

together

1.Drill Bit

2.Pressurized Concrete

3.Auger Cast Pile

Foundation AnalysisFoundation Analysis

• Using ACP’s as an Alternative Foundation– General Benefits of Using ACP’s

• Speed of Installation• Less Material Costs• Bearing Capacity • Overall Reduced Costs

– Problems with Using ACP’s• Susceptible to Variability• More ACP’s Required than Caissons

Foundation AnalysisFoundation Analysis

• Comparing the Two Foundation Systems

Caissons VS Auger Cast Piles

– Structural Bearing Capacity– Cost differences in Material and Construction– Constructability and Length of Time to Install

Foundation AnalysisFoundation Analysis• General Bearing Capacity

QUltimate = QP + QS

= AP(CNC+ ЧLNq + ЧNЧ) + Σ∆L(AS)S• Surface-Friction per Unit Area

S = KS σ Tan∂ where: KS = Ave. Coeff. of Earth Pressure on Pile

Shaft

Steel Lined Caissons KS=1.1Concrete Alone KS=1.5

*ACP’s can have 36% more Surface-Friction Bearing Capacity than Steel lined Caissons

Foundation AnalysisFoundation Analysis

QUltimate = AP(CNC+ ЧLNq + ЧNЧ) + ASFS

Average Unit Surface-Friction

FS= C+ ½ KS(Ч-G) L (tan Ø)

Assumptions: Ø = 12°

C = 6 KN/m^2

Ч = 18 KN/m^3

Foundation AnalysisFoundation Analysis

• Ultimate Bearing Capacity Comparison– Average Length of 50 Feet– 24” Diameter

• Surface-Friction ComparisonCaissons FS = 20.5 KN/m^2

ACP’s FS = 25.85 KN/m^2

Foundation AnalysisFoundation Analysis

• Ultimate Bearing Capacity ComparisonQUltimate = AP(CNC+ ЧLNq + ЧNЧ) + ASFS

Caissons QUlt = QP + QS

= 140.3 + 598.6 =738.9 KN =168 kips

ACP’s QUlt = QP + QS

= 140.3 + 753 = 893.3 KN =200 kips

Foundation AnalysisFoundation Analysis

• Pile Cap Design– Based on # of Piles / Cluster– All Pile Caps used were 49” deep– Four different pile layouts– Four different size pile caps

Foundation AnalysisFoundation Analysis

Foundation AnalysisFoundation Analysis

• Foundation Cost Comparison– System Estimates Using:

• Means Cost Guides• Walker’s Building Estimating• General Contractor Consulting

Foundation AnalysisFoundation Analysis

• Means Cost Guide Results

  Total Cost

Caissons System $900,000

Auger Cast Pile System $500,000

Difference $400,000

Foundation AnalysisFoundation Analysis

• Duration of Foundation Construction– Foundation System Duration Estimates Using:

• Means Cost Guides• General Contractor Consulting

Foundation AnalysisFoundation Analysis

• Means Cost Guide Duration Results

  Total Duration

Caissons 60 work days

Auger Cast Piles 40 work days

Difference 20 work days/ 4 Weeks

Site Plan ModificationSite Plan Modification

• A Discrepancy Affecting the Site Layout– Location of Existing Sanitary Sewer Line

• Located 5 Feet closer to Building than shown on Drawings

• Changes that were Made– Redesign of shoring system– Hand Excavation

Site Plan ModificationSite Plan Modification• Location of Foundation Problem

– West Side Caissons are too Close to Sewer Line

Site Plan ModificationSite Plan Modification• 1st Possibility

– Reduce Width of Entire Vault Area 1-2 ft – Leave Caissons/Piles at the edge

Site Plan ModificationSite Plan Modification

• Effects of Reducing Vault Area Width– Positive Effects

• Less Congestion for Foundation Installation• No Change in Building Superstructure

– Negative Effects• Vault Area Will be More Congested• Vault is Pre-cast Concrete

Site Plan ModificationSite Plan Modification

• 2nd Possibility – Move West Side Caissons/Piles East 5 ft

Site Plan ModificationSite Plan Modification

• Effects of Partial Foundation Relocation– Positive Effects

• Less Congestion for Foundation Installation• Building Superstructure Stays the Same

– Negative Effects• Located in the Central Axis of the Vault Area• Creates 1 to 1 Cantilever on Grade Beams

Site Plan ModificationSite Plan Modification

• Solution– Move West Side Foundation Piers 5ft East– Move Entire Vault Area 10 ft South

““Astrovision” Video Display Screen AnalysisAstrovision” Video Display Screen Analysis

• What is it?– 22ft X 37ft Video

Screen– 112 Individual Modules

““Astrovision” Video Display Screen AnalysisAstrovision” Video Display Screen Analysis

• Problem With Screen Design– No Outlet to Disperse Heat Generated

• Could Cause Damage to the Screen• Could Cause Excess Heat in Building

• Possible Solution– Add Louvers to Disperse Heat

““Astrovision” Video Display Screen AnalysisAstrovision” Video Display Screen Analysis

• Effects of Adding Louvers– Screen is Able to be Cooled

• Eliminates Potential Damage to Itself• Better Chance of Lasting Expected Lifetime• Eliminates Excess Heat Exposure of Building

– Reduced Screen Size to Account for Louvers• Loss of 3 Lines of Screen Modules (21 Modules)

““Astrovision” Video Display Screen AnalysisAstrovision” Video Display Screen Analysis

• Effects of Adding Louvers– Reduced Screen Size

• Loss in Aesthetical Quality of Screen

• Overall Cost of Screen is Reduced

– Added Cost of Louvers

““Astrovision” Video Display Screen AnalysisAstrovision” Video Display Screen Analysis

• Change in Cost With Louvers

  Total Cost

21 Screen Modules $200,000

Louvers $10,000

Difference $190,000

ConclusionsConclusions• Foundation Analysis

PROS– ACP’s have Better Surface-Friction making their Bearing Capacity higher than

Steel Lined Caissons in the right soil conditions. – Using ACP’s Would Save Money and TimeCONS– More potential for Displacement – Increased Chance of Variability in the Shafts

• Site Plan Modification– Resizing the Vault Area Would Not be a Practical solution– Relocating the Foundation Caissons Reduces the Structural Integrity of the Vault

Area– Move Entire Vault Area away from Potential Traffic Loads

• Screen Redesign with Louvers – Saves Money in Initial and Repair Costs– Loss in Aesthetical Quality

Summary of Costs  

   

Caisson Foundation System………………………………………………… $901,442

ACP Foundation System……………………………………………………. $445,701

Savings………………………….. $455,741

   

Original "Astrovision" Design……………………………………………….. $1,500,000

Reduced Size "Astrovision" With Louvers………………………………… $1,299,800 

Savings………………………… $200,200

Total Cost Savings ………………… $655,941

Duration of Foundation Systems  

Caisson Foundation System………………………………………………… 63 Work Days

ACP Foundation System……………………………………………………. 43 Work Days

Total Time Savings………………… 20 Work Days

• AE Faculty

• Mascaro Construction– Tom Weber– Marc Delrossi – Project Engineer

• Family and Friends

Questions?Questions?

top related