Innovative Water Recycling

Post on 21-Oct-2014

210 Views

Category:

Documents

1 Downloads

Preview:

Click to see full reader

DESCRIPTION

 

Transcript

Innovative Water Recycling

PERC Water Corporation

o A water infrastructure development company o Headquartered in Costa Mesa, California o Founded in 1998 o Privately held o 22 water recycling facilities o Provide innovative, efficient solutions to water infrastructure

needs o Industry leader in utilization of public-private partnerships

2

PERC Water ASP® Unique Characteristics

o Certainty of cost, schedule and performance o Small footprint:

• Common wall construction • Underground and covered tanks • Buildings above tanks

o Neighbor friendly o Risk management using integrated alternative delivery

methods

3

Neighbor Friendly

4

Small Footprint

5

Public-Private Partnership v. Design-Bid-Build

o Transfer of risk o Performance based

• Power costs • Extended warranties • Employees retained

o Reduced costs o City still sets rates o Risk management using integrated Design-Build-Operate

6

Socio-Economic Benefits of PPP

o Local job creation > multiplier effect on the local economy o Sales tax revenues o Potential revenues derived from the trading or sale of

recycled water o Local control over assets, costs and rate setting o Complete reversion at the end of the PPP term

7

Risk Allocation Table

8

Concessions

o Leverage operational efficiencies o Monetizing existing assets o Receive initial funding o Stabilizing or maintaining rates o Future upgrades & expansion o Implementation of technology & automation

9

Concession – Case Study

10

Central PERC™

11

o Secure login o Ties to SCADA and CMMS systems o Delivers up to the minute facility

information o Graphics to drill down for more detail o Notifications deliver critical messages o Easy accesses to facility references o Operations Manuals o Permits o Safety Information

Portfolio Overview

12

Mountain House, California

Project Type: Design/Build/Operate Capacity: 3.0 MGD (designed for 5.4 MGD) Population Capacity: 35,000 (64,000) Design: 9 months Construction: 16 months

13

City of Goodyear, Arizona

Project Type: Design/Build/Operate Capacity: 4.1 MGD (designed for 8.2 MGD) Population Capacity: 48,000 (96,000) Design: 6 months Construction: 9 months

14

City of Santa Paula, California

Project Type: Design/Build/Operate/Finance Capacity: 4.2 MGD (current rating 3.4 MGD) Population Capacity: 50,000 Design: 6 months Construction: 18 months

15

City of El Mirage, Arizona

Project Type: Design/Build/Operate Capacity: 3.6 MGD Population Capacity: 43,000 Design: 5 months Construction: 14 months

16

City of Surprise, Arizona

Project Type: Design/Build/Operate Capacity: 3.0 MGD Total (SPA 2 – 1.2 MGD, SPA 3 – 1.8 MGD) Population Capacity: 35,000 Design: 6 / 9 months Construction: 14 /16 months

17

Public-Private Partnership Case Study

18

Santa Paula City Data

o 65 miles northwest of Los Angeles o Population approximately 30,000 o “Citrus Capital of the World”

19

The Problem

20

Santa Paula’s Problems

o Out of compliance with the State o Faced over $8 million in fines by the States o Aged facility reached end of useful life (1939) o Insufficient capacity for growth o No certainty of capital costs and operating costs o No certainty of project schedule o No certainty of financing o No reuse of water

21

Santa Paula’s Goals

o Compliance with the State and eliminate fines o Certainty of capital and operating costs o Certainty of financing o Competitive rates o Recycle and reuse wastewater

22

The Solution

Retain PERC Water and Alinda Capital to privately fund, build and own a new water recycling facility

23

Solution: PERC ASP® Water Recycling Facility

o Capacity to treat and recycle 4.2 million gallons per day o Support population of 50,000 o Membrane bio reactor using Koch Membranes o Title 22 unrestricted reuse effluent o Integrated biosolids facility o Integrated recycling education center o Small tank footprint of less than 1 acre o Aesthetically pleasing buildings / no odors

24

Solution: Private Funding

o Financed by Alinda Capital Partners and PERC Water o 100% privately funded with debt & equity o No capital obligations by the City o 30 year concession with fixed fees o Future cap ex included

25

Solution: A Public-Private Partnership

26

Solution: Risk Mitigation for the City

27

Solution: Innovative Design

28

Solution: Small Footprint

29

Solution: Land Efficiency

30

Solution: Fast Track Design / Build Schedule

May 5, 2008: City Council vote to proceed May 6, 2008: Commence engineering July 7, 2008: Break ground December 16, 2009: Complete construction May 13, 2010: Begin full operations (7 months early) December 15, 2010: Required compliance date

31

Santa Paula Water Recycling Facility September 2008

32

Santa Paula Water Recycling Facility December 2008

33

Santa Paula Water Recycling Facility March 2009

34

Santa Paula Water Recycling Facility June 2009

35

Santa Paula Water Recycling Facility August 2009

36

Santa Paula Water Recycling Facility November 2009

37

Santa Paula Water Recycling Facility January 2010

38

Santa Paula Water Recycling Facility Completed May 2010

39

40

41

42

43

44

45

46

47

48

Goals Achieved by the City

o Compliance with the State and eliminate fines Guaranteed to meet State compliance Scheduled completion is seven months early Transferred violation risk to PERC Water/Alinda

o Certainty of capital and operating costs 30 years of guaranteed capital, operating costs and cap ex 30 years of guaranteed power consumption

49

Goals Achieved by the City

o Certainty of financing 100% privately funded and privately owned

o Competitive rates 40% lower than neighboring City Lowest overall rates from procurement process

o Recycle and reuse wastewater Can produce 4,700 acre feet per year of recycled water

50

Recognition

o 2011 National Council of Public-Private Partnerships “Award for Innovation”

o 2011 Design-Build Institute of America – Western Pacific – Top Tier Water Award

o 2010 Environmental Business Journal “Project Merit” Achievement Award

o 2009 Global Water Intelligence Water Deal of the Year “Award of Distinction”

o 2009 Environmental Business Journal “Sustainability & Resource Protection” Achievement Award

51

Rec

52

“In the history of the world, no one has ever washed a rented car.” - Lawrence Summers, Former Harvard University President

53

54

55

56

57

58