GSA Expo 2009 Major Acquisition Overview Katherine Autry International Space Station Procurement Office NASA.
Post on 22-Dec-2015
219 Views
Preview:
Transcript
GSA Expo 2009
Major Acquisition Overview
Katherine AutryInternational Space StationProcurement OfficeNASA
Agenda
• Introduction• Define Major Acquisitions• Steps for Successful
Management• Roles and Responsibilities• Conclusion
Vision for Space Exploration
• Complete the ISS• Safely fly the Space Shuttle until 2010• Develop and fly the Orion Vehicle
no later than 2014 • Return to the Moon by 2020• Extend human presence across the Solar system and beyond• Implement a sustained and affordable human and robotic program• Develop innovative
support technologies, knowledge, and Infrastructures
• Promote commercial and international participation
Commercial Resupply Contracts (CRS)
End-to-end resupply services to deliver cargo to the ISS including vehicle and cargo integration (12/23/2008 – 12/31/2015)
OrbitalSciences
CygnusTaurus II
Space Exploration
Technologies
Dragon Falcon 9
• Define “major acquisition”
• Identify successful management steps
• Define Roles and Responsibilities: Who are the key players?
Major AcquisitionsLearning Objectives
“Major System Acquisition”(NASA-Style)
• Category 1 – Nuclear power – Human space flight– Project LCC greater than $1 Billion
• Category 2 – LCC between $250M and $1B– High priority projects, LCC < $250M
• Category 3– Remaining projects
Definition of “Major Acquisition” is relative, depending on agency mission and budget.
Definition of “Major Acquisition” is relative, depending on agency mission and budget.
Unique Aspects –Major System Acquisition
Performance based solicitations:• Describe mission capability in
generic terms (no specific systems)• Identify schedule/cost/capability
objectives, known constraints• Require use of Earned Value
Management System• Do not mandate or reference
Government specs/standards
Specific contract phasing coincides with major program/project phases:
– Concept exploration – Demonstration– Full-scale development– Full production
Beyond this broad guidance, the FAR is silent other than to require agency heads to develop their own procedures.
Orion - Phased Acquisition Using Progressive Competition (FAR Part 34, NASA FAR Supplement 1852.217-72)
• Down-selection strategy, phased acquisition• Single solicitation is issued for all phases of the program• Initial phase contracts are awarded • Contractors for subsequent phases are chosen through “down-selection” from the preceding phase
Orion Phased Down-select Procedure
• Progressively fewer contracts are awarded in each phase until a single contractor is chosen for the final phase
Learning Objectives
Define “major acquisition”
• Identify successful
management steps• Define Roles and Responsibilities
Key Decision Points
FORMULATION IMPLEMENTATION
Major Reviews
1 2 3 4 5
OperationsPre-Program Acquisition Program Acquisition
Program System Requirements/ Definition Reviews
Preliminary Design Review
Critical Design Review
Systems Integration Review
Flight Readiness Review
Operational Readiness Review
Post Launch Assessment Review
Program Status Review
ASP
ASMPSM
Pre-Program Acquisition
Program Acquisition Operations Closeout/Decommission
Acquisition Strategy and Planning is integral to Program Management and is owned by key decision makers.
Acquisition Strategy and Planning is integral to Program Management and is owned by key decision makers.
Program Evaluation
JICB
Acquisition Steps to Ensure Agency Commitment to Programs/ProjectsAcquisition Steps to Ensure Agency Commitment to Programs/Projects
• Focus on Life Cycle Costs• Requirements• Concept of operations
• Share information with industry ASAP
• Issue guidance on industry communication (Down select process)
• Manage organizational conflicts of interest
• Use Technical Resources Proposal Volume
Additional Lessons Learned
Learning Objectives
Define “major acquisition” Identify successful management steps
• Define Roles and Responsibilities: Who are the key players?
Unique Roles and Responsibilities
• FAR Part 34: • Program Manager is responsible for development of acquisition strategy
for major systems acquisitions• Agency head must reaffirm mission objective and ongoing need, approve
any contracts for full production
Courtesy Cal Tech
Conclusion
http://imedia.ksc.nasa.gov/index1.html Interactive Simulations
Http://www.nasa.gov/multimedia/index.html Multimedia NASA missions
http://www.nasaimages.org/ NASA images and video
Major Acquisition Approaches
Contract Orion CRS (x2)
FAR Reference Part 34, Major Systems Acquisitions
Part 12, Commercial Acquisitions
NASA FAR Suppl. Special Contracting Methods
Acquisition of Commercial Items
Mission Scope* ExplorationLEO, Moon, Mars, and…
Transportation ServiceLEO (ISS resupply)
Contract TypeCPAF, CPIF, FPIF
(multi-phase)IDIQ
FFP IDIQ (milestone driven)
*LEO = Low Earth Orbit