Grøn gas gennem metanisering

Post on 31-Jan-2016

51 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

DESCRIPTION

Claus Friis Pedersen clfp@topsoe.dk. Grøn gas gennem metanisering. Vehicle to grid (V2G) is the future!. An integrated energy infrastructure. CH 4 + CO 2 + 4H 2 2CH 4 + 2 H 2 O. The right factors for biogas upgrading. Haldor Topsøe group (2011). Catalyst and engineering for - PowerPoint PPT Presentation

Transcript

Confidential

Claus Friis Pedersen clfp@topsoe.dk

Grøn gas gennem metanisering

Vehicle to grid (V2G) is the future!

An integrated energy infrastructure

CH4 + CO2 + 4H2 2CH4 + 2 H2O

The right factors for biogas upgrading

Livestock, Windturbine capacity and NG consumption per capita

0,00

0,50

1,00

1,50

2,00

2,50

Pigs

Cattle

Wind,kW

NG MTOe

Haldor Topsøe group (2011)Catalyst and engineering for

Fertilizers

Refineries

The environmental sector

Synthetic fuels

Turnover: DKK 4.4 billion

Result: DKK 397 MM

2091 employees

250 employees in R&D

Synthetic Natural Gas (SNG) - Xinjiang Qinghua

50 PJ corresponding to >50% of the total Danish Natural gas consumption

5 PJ gasified biomass SNG plants are projected

0.1 PJ would be a large biogas methanation unit

Transport SNG in pipelines rather than coal on trucks

0%

20%

40%

60%

80%

100%

120%

XinjiangQinghua

Gasifiedbiomass

Biogas

Me

tha

na

tio

n R

ela

tiv

e C

os

t

Fuel Cell and Electrolyser

½O2

H2 H2O

½O2

H2O + 2e- → H2 + O2-

O2-

O2- → 2e- +½O2

H2 + O2- → H2O + 2e-

O2-

½O2 + 2e- → O2-

SOFC SOEC

H2H2O

Exergy Flows

Biogas upgrade value proposition # 1

BiogasCH4 +30-40% CO2

H2Electrolysis

BioGas CH4 40 PJ

”Electro-gas” CH4, 27 PJ

Biogas Upgrade

CO2

Fuel synthesis

Biogas upgrade value proposition # 2

Spot prices 2011

-0.4

-0.2

0

0.2

0.4

0.6

0.8

1

1 1001 2001 3001 4001 5001 6001 7001 8001

kr/

kW

h

Pre studies

Metan samfundet SOEC biogas upgrade

The business case (w. 5% interest)

0

10

20

30

40

50

60

Expensis NG gasprice

Biogasprice

Expensis NG gasprice

Biogasprice

Power Biogas Investment Operational cost Gas sale Heat sale

2020100% Electrolysis

203591% Electrolysis

Mio

DK

K

Plant size:

75 mio Nm3 biogas/year

Pilot test at Foulum – 5 Nm3/h

CH4 + CO2 + 4H2 2CH4 + 2 H2O

Summary

Electrolysis based biogas upgrade has the potential to:

– Store electricity as fuel

– Increase the biogas production

The business case is interesting but many aspects are still uncertain

A pilot scale field trial is planned for 2015