Brookline Reconstruction ProjectPioneer Avenue to Starcamp Street

Project Sponsors

City of PittsburghPennsylvania Department of Transportation

Federal Highway Administration

Consultant TeamMichael Baker Jr., Inc. John J. Clark & Associates

Santangelo &Lindsay, Inc.

Brookline Boulevard Reconstruction Project:Here Tonight to:

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

• Present Final Designs• Present Schedule for Construction

• Room Set Up:TablesBoards

Brookline Boulevard Reconstruction Project:Project Limits

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

Pioneer

Starcamp

Brookline Boulevard Reconstruction Project:Project Development Process:

• Design Charrette• Development of Alternatives• Public Meeting #1 (December 2006)• Identify Preferred Alternative• Public Meeting #2 (May 2009)• Final Design• Public Meeting #3 (March 2012)• Construction

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

Brookline Boulevard Reconstruction Project:Project Elements

• New Sidewalks/Crosswalks• Traffic Signals/Pavement Markings• Curb Extensions• ADA Ramps/Audible signals• Street Lighting• Street Trees / Landscaping• Roadway Mill/Pave/Markings

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

Brookline Boulevard Reconstruction Project:Typical Roadway Pan

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

Brookline Boulevard Reconstruction Project:Typical Landscaping Plan

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

Brookline Boulevard Reconstruction Project:Sidewalk Treatments

Brookline Boulevard Reconstruction Project:Lights and Furniture

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

Brookline Boulevard Reconstruction Project:Landscaping Palette

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

Brookline Boulevard Reconstruction Project:Typical Landscaping Plan

Complete Designs June 2012Advertise Construction Aug. 2012Award Contract Sept. 2012Notice To Proceed Dec. 2012Start Construction March 2013

Phase 1A/1EPhase 1B/1DPhase 1C/1FPhase 2A/1CPhase 2B/2DPhase 2EPhase 3

FINISH CONSTRUCTION: November 2013

Brookline Boulevard Reconstruction Project:Project Schedule

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

Brookline Boulevard Reconstruction Project:Construction Phasing

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

Brookline Boulevard Reconstruction Project:Maintaining Traffic/Access

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

Brookline Boulevard Reconstruction Project:

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh

QUESTIONS/COMMENTS

Brookline Reconstruction ProjectPioneer Avenue to Starcamp Street

Project Sponsors

City of PittsburghPennsylvania Department of Transportation

Federal Highway Administration

Consultant TeamMichael Baker Jr., Inc. John J. Clark & Associates

Santangelo &Lindsay, Inc.

Brookline Boulevard Reconstruction Project:Project Schedule

Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh