BATA –July 13, 2016 San Project 5b: Amendment ... bridge update.pdf · BATA Oversight Committee –July 13, 2016 Richmond San Rafael Bridge Access Improvement Project Item 5b: ...

Post on 27-May-2018

214 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

Transcript

1

BATA Oversight Committee – July 13, 2016Richmond San Rafael Bridge Access Improvement Project

Item 5b:   Project Update and Contract Amendment  On Call Construction Management Services – Parsons Brinckerhoff, Inc.

I‐580 Richmond‐SanRafael Bridge Access Improvement

Project Update ‐ July 2016

2

Project Elements1. Package A ‐ Eastbound 3rd Lane: Sir Francis Drake Blvd. to 

Marine St. (PPU Lane) and Contra Costa County Bike/Pedestrian Connection

2. Package B – Upper Deck Bike/Pedestrian Path and Marin County Bike/Pedestrian Connection

3

Project Status1. Project Study Report 

completed 2. Caltrans signed CE/CE –

May 20163. Project Report –

submitted to Caltrans for approval

4. Final design of 3rd lane –Completed July 2016

5. Utility relocation agreements 

6. Easement acquisitions

4

CE/CE Supporting Studies

5

Budget Allocations ‐ $73.6 m

PA/ED$4.1 

Final Design$4.7 

CM$5.6 

3rd Lane Construction (Pkg A)$27.2 

Upper Deck Bike/Ped Path Construction (Pkg B)

$7.2 

Movable Barrier (Pkg B)$9.0 

CT Oversight$1.9  Misc. Expenses

$0.7 

Emergency Response Equipment$0.2 

Unallocated$10.3 

MMWD (Pkg A)

PG&E ‐Marin (Pkg B)

Chevron 

AT&T PG&E ‐ Contra Costa (Pkg A)

EBMUD 

Utility Relocations$2.7 

Budget items in $ millions

6

Project Report

Environmental Document

Right of Way Certification

Advertise and Award*

Construction

Contra Costa Path Construction

Schedule – PPU Lane

Open 3rd Lane to Traffic – Sept ‘17

* Contract Award requires execution of utility relocation agreements which could delay beginning construction 2 to 3 months

7

Risks to Schedule – PPU Lane1. Executing agreements with Chevron2. Executing agreements with EBMUD 

and PG&E3. Obtaining Right of Way certification 

from Caltrans4. Obtaining encroachment permit from 

Caltrans and permit amendment from BCDC

8

Utilities Relocation Along Stenmark Drive

9

Schedule – Bike Ped Path

Project Report

Environmental Document

Right of Way Certification

Advertise and Award

Construction

Open Bike/PedPath– Mar ‘18

10

Risks to Bid Schedule –Bike Ped Path

1. Executing agreements with PG&E for utility relocation

2. Obtaining easements from the private property owners along Francisco Blvd

3. Risk of having to go through condemnation process

11

PG&E Relocation on Francisco Blvd

12

Thank You

Questions?

13

top related