FINAL TEAM V-MAZ BUILDING PRESENTATION TEAM MEMBERS ZOG POPINARA MORRIS SCHNEPS ALIMERV PROCTOR VINCENT SCANCARELLO ARCH 2330 | Building Technology III Fall 2016 Prof. Paul King
FINAL TEAM V-MAZ BUILDING PRESENTATION
TEAM MEMBERS
ZOGPOPINARA
MORRIS SCHNEPS
ALIMERVPROCTOR
VINCENTSCANCARELLO
ARCH 2330 | Building Technology III
Fall 2016Prof. Paul King
PROJECT SELECTION & ANALYSIS
ZP
PROJECT SELECTION & ANALYSIS
PROJECT SELECTION& ANALYSIS
ZP
The structural grid is not shown but you get a clear understanding how everything is aligned, however for the selections highlighted in the figure to the right, one cannot know for sure if those are columns or if they act as mullions.
Note that the area shaded in red should contain a expansion joint because that certain area of the building extends to the higher floors while other areas do not. This becomes more clear in the floor plans and sections.
PROJECT SELECTION& ANALYSIS
ZP
Floor to floor are about 12 feet which are perfect for a design but can cause problems when thinking about a split level as you see here highlighted in red.
The area highlighted in yellow shows the vertical circulation. Its important to note that you do have the right amount of egress stairs but they are not enclosed properly.
Also vertical and horizontal mechanical shafts are not included in section drawings, however they exist in the floor plan. (Locker room floor)
PROJECT SELECTION& ANALYSIS
ZP
Problems with Egress Stairs. 1. Stairs are not enclosed properly. 2. Door directions are all wrong except in the first floor plan where they lead you out of the building. 3. There are no doors leading you out of the building in the bottom stair therefor, its not considered an egress if you cant exit out of the stairs (CASE). 4. Some stairs lead directly to rooms/office space. 5. Stairs do not contain doors wherever you see a red question mark. 6. Not clear if area highlighted in green is an elevator or a vertical shaft.
PROJECT SELECTION& ANALYSIS
ZP
Problems with Circulation
In the floor plan you can see the pool is located in the first floor as soon as you enter. That can be a problem for the circulation and also for design purpose. Would someone want to go to the locker room floor, change then come back up to swim.
Pool is also too small according to code, an Olympic sized swimming pool should contain minimum dimensions of
STRUCTURALPROPOSAL
ZP
Spans between grid line A-B and 1-2 are 8’, to show the cantilevered split level.
B-C span 32’ C-D span 36’ (for pool and skylight, also nothing supported above) D-E span 28’.
2-3 spans 18’ and the rest of the grid lines all span 20’.
STRUCTURALPROPOSAL
ZP
Typical Floor Plan contains a central courtyard you can look down in the pool. Its missing a garden which is now moved on the roof of the first floor.
Also you can see the placing of the Rockwall climbing has changed to help circulation through and around.
STRUCTURALPROPOSAL
ZP
Basement to first floor = 12’
1st floor to second floor= 14’
2nd Floor to 3rd Floor= 16’
2.5-3.5 = 14’
3rd Floor to 4th Floor= 14’
STRUCTURALPROPOSAL
MS
The basement has a double height area for the pool,therefore columns must be placed on the perimeter.
STRUCTURALPROPOSAL
MS
Basement to 1st floor = 12’ 1st floor to 2nd floor= 12’ 2nd Floor to 3rd Floor= 12’ 2.5-3.5 = 12’ 3rd Floor to 4th Floor= 12’
STRUCTURALPROPOSAL
VS
A to B = 8’ 1” B to C = 32’ 0”C to D = 32’ 0”D to E = 24’ 6”E to F = 7’ 6”
1 to 2 = 8’ 0”2 to 3 = 12’ 0”3 to 4 = 20’ 0”4 to 5 = 20’ 0”5 to 6 = 20’ 0”6 to 7 = 20’ 0”
STRUCTURALPROPOSAL
VS
Floor to Floor Heights
Basement – First = 12’ 0”First – Second = 14’ 0” Second – Third = 14’ 0” Third – Fourth = 14’ 0” Fourth – Roof = 14’ 0” Roof – Parapet = 4’ 0”
STRUCTURALPROPOSAL
AP
MECHANICAL PROPOSAL
MS
Lighting FixturesAir ReturnAir SupplySprinklers
MECHANICAL PROPOSAL
VS
Reflected Ceiling Plan Including..
-24” x 24” Acoustic Hung Ceiling Tiles
-24” x 24” Air Supply Vents
-24” x 24” Air Return Vents
-24” x 24” Lights
-Sprinklers
ZP
MECHANICAL PROPOSAL
EGRESS PROPOSAL
Show a typical floor plan and a section from your Revit drawings. The section should be cut where it will clearly shows the vertical stairs. You may require more than one.
If your team has all used the same solution then you only need to show one slide, that can be shared by the team. If different team members proposed different solutions then each team member shows their own slide.
Floor plan: Highlight (use color-yellow) the location of the stairs and elevators and the egress corridors. Indicate (use color-red) 1 hour rated corridors &the 2 hour rated stair enclosures. Be certain that all doors open in the direction of egress.
Section: Highlight (use color-yellow) the stairs. Indicate the horizontal routes and vertical routes for egress.
Credit Initials
EGRESS PROPOSAL
MSFirst Floor Level PlanLevel 1 to 2.5 Section Basement to Level 4 Section
EGRESS PROPOSAL
VSFirst Floor PlanStair SectionElevator Section
COMPOSITE MATERIALS PROPOSAL
VS
North
East
West
South
INDIVIDUAL DETAILS PRESENTATIONARCH 2330 | Building Technology III
Fall 2016Prof. Paul King
MORRIS SCHNEPS
MS
CURTAINWALLDETAIL
MS
STRUCTURE
MS
WATERPROOFING
MS
FIRESTOPPING
MS
THERMAL
MS
COMPOSITE
INDIVIDUAL DETAILS PRESENTATIONARCH 2330 | Building Technology III
Fall 2016Prof. Paul King
ZOG POPINARA
ZP
FAÇADE DEVELOPMENT AND DETAILS
ZP
FAÇADE DEVELOPMENT AND DETAILS
INDIVIDUAL DETAILS PRESENTATIONARCH 2330 | Building Technology III
Fall 2016Prof. Paul King
VINCENT SCANCARELLO
CURTAIN WALL DETAILS
VS
Materials Shown
EXTERIOR WALL DETAILS
VS
Materials Shown
FIRST FLOOR PLAN
VS