YANBU II POWER & WATER PROJECT METHOD STATEMENT FOR U/G PIPING INSTALLATION & LAMINATION OF GRP Document No. : YT-PF-Z-16-00202 Revision : B
YANBU II POWER & WATER PROJECT
METHOD STATEMENT FOR U/G PIPING INSTALLATION & LAMINATION OF GRP
Document No. : YT-PF-Z-16-00202Revision : BDate of Issue : 06 Mar 2012
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 2 of 46
Rev No. : B
B For Review 06 Mar 2012 Danish khan I G Yeo S K Hong
A For Review 10 Feb 2012 Danish khan I G Yeo S K Hong
Rev. Description Date Prepared By Checked By Approved By
REVISION INDEX
Rev Date Description
B 06 Mar 2012 For Review
A 10 Feb 2012 For Review
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 3 of 46
Rev No. : B
CONTENTS
SECTION DESCRIPTION PAGE NO
1.0 INTRODUCTION............................................................................................5
2.0 OBJECTIVE....................................................................................................5
3.0 REFERENCE DOCUMENTS..........................................................................5
4.0 DEFINITIONS AND ABBREVIATIONS..........................................................6
5.0 RESPONSIBILITIES.......................................................................................6
5.1. Site Manager...................................................................................................6
5.2. Discipline Manager.........................................................................................6
5.3. Site QC Manager............................................................................................75.4. GRP Pipe Erection Manager……………………………………… ….…………..7
5.5. Site HSE Manager..........................................................................................85.6 Site Supervisor ……………………………………………………………………...8
6.0 PROCEDURES...............................................................................................9
6.1. DELIVERY, HANDLING AND STORAGE.......................................................9
6.2. INSTALLATION.............................................................................................157.0 MATERIALS……………………………………………………………………….25
8.0 EQUIPMENTS………………………………………………….………………….26
9.0 INSPECTION AND TEST ………………………………….…………………….27
10.0 SAFETY PRECAUTIONS……………………………………………….………..39
11.0 RISK ASSESSMENTS ………………………………………………………..40
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 4 of 46
Rev No. : B
ATTACHED DOCUMENT
1. RISK ASSESSMENT TABLE
2. REFERENCE DRAWING
- PLOT PLAN
- UNDERGROUND PIPING ARRANGEMENT DRAWING
3. TYPICAL EXCAVATION PLAN
4. RIGGING PLAN
5. TYPICAL SCAFFOLDING PLAN
6. SEQUENCE OF ACTIVITY AT SITE
7. TEMPORARY DEWATERING PLAN
8. INSPECTION TEST PLAN
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 5 of 46
Rev No. : B
INTRODUCTION
This Procedure defines the work method for Installation of GRP Piping for YANBU II POWER & WATER PROJECT at Yanbu in the Kingdom of Saudi Arabia.
1.0 OBJECTIVE
The purpose of this procedure is to set out the requirements and methods for Installation of GRP Piping. This procedure shall be in compliance with the contract and technical specification implemented on the YANBU II POWER & WATER PROJECT at Yanbu in the Kingdom of Saudi Arabia.
2.0 REFERENCE DOCUMENTS
This document is based on the Project Specification, Standard and Contractor’s corporate and Project procedures and fundamentally incorporates the requirements as noted in the following Project Documents.
Specification & Standard
Section 02625
- Glass Fiber Reinforced Plastic Pipe (GRP) (For Seawater Pipe)
Section 02623
For Service other than Sea Water system
ITP for Piping Work
Section 02200 : Earthwork
Section 02610 : Pipe & Pipe Fittings
Section 02713 : Water Distribution Systems
Section 15103 : Valves & Expansion joints for sea water service
Section 15643 : Condenser & Accessories
Section 15913 : Flow meters (Seawater system)
Contractor’s Project documents
YT-PF-Z-16-00026 Method statement for Earth work
YT-PF-Z-16-00005 Site HSE Plan
YT-PF-Z-16-00020 Permit to Work Procedure
YT-PF-Z-16-00036 Method statement for excavation of underground structure
YT-PF-Z-16-00208 Method statement for Pressure test of Piping
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 6 of 46
Rev No. : B
3.0 DEFINITIONS AND ABBREVIATIONS
- Client: Power and Water Utility Company for Jubail and Yanbu (MARAFIQ)
- PMC: Jacobs
- Contractor: Hanwha Engineering and Construction (HENC) and Hanwha Saudi Contracting (HSC)
- Sub-Contractor: Contractor’s Design & Engineering, Fabrication and Erection contractor
4.0 RESPONSIBILITIES
4.1. Site Manager
He shall be responsible for implement the company safety plan overall, and follows;
- To ensure efficient execution of works in accordance with project specifications.
- To arrange necessary equipments from other sites through top management.
- To arrange necessary manpower required for planned work with along term view.
- To manage weekly internal coordination meeting for effective monitoring.
- To encourage the work force for good site keeping.
- To trace the troubles which hurdle the progress of the project and shooting the same with necessary coordination as fast as possible to avoid time loss.
4.2. Discipline Manager
He shall be responsible;
- To organize the available resources in the site effectively
- To report to the Site manager or higher management about the resources requirement
- To encourage the work force for the safe and productive working culture
- To deal with the site supervisor for executing earth work in correct procedure at site.
- To coordinate with equipment controller for routine maintenance as well in case of breakdown issues in order to avoid the time delay in the progress of the project.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 7 of 46
Rev No. : B
4.3. Site QC Manager
He shall be responsible for the overall Quality control of all the construction activities at site, and follows;
- for managing all the necessary inspections, inclusive of witnessing, recording and reporting the results.
- To ensure that all inspections are executed efficiently and expeditiously in order to comply with the master construction schedule.
- To ensure the preparation of Inspection & Test Plan as per Project specification requirement
- To obtain the approval for the same
- To follow up with Planning section/ construction section for method statement for critical activity
- To execute and monitor the approved Inspection and Test Plan & Procedures for effective results of the product
- To initiate the identification of training & recommending the same to the higher management for the team.
- To initiate the approval of 3rd party Lab approval and coordination for the same as and when required
4.4. GRP Pipe Erection Manager
He shall be responsible for the GRP piping from material handling, Unloading &
material storage
He shall prepare work execution plan for erection, hydro test & backfilling
Preparation of all documents related to GRP piping work.
Preparation of Test packages according to P & ID, Piping Instrument Diagram,
piping ISO drawings and Sketches
Working with project personnel, resolve technical problems which require
engineering expertise
To ensure that all materials and equipments are within the correct specification
prior to installation.
Review and correction of hydro test packages for correct system names type of
test and other relevant data.
Responsibility to monitor the daily activities on site and evaluate workers.
Performance to insure that the progress of works is in line with the schedule..
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 8 of 46
Rev No. : B
4.5. Site HSE Manager
He shall be responsible for the overall safety of personnel materials and equipment during the construction and pre-commissioning of a Project, and follows;
- To ensure all the operations at the site are conducted to the minimum safety standards, and that they are maintained throughout construction.
- To coordinate and preside over regular site safety meetings, to attain and maintain effective communications, between Sub Contractor, Contractor and Company’s personnel.
- To establish policies and procedures for the Sub-contractor Site personnel
- Monitors the removal of physical, biological and chemical hazards, and training of employees on safety policies, procedures, and regulations. Verifies compliance with health and safety regulations and ensures all necessary records are maintained and prepared according to established guidelines. Manages the participation in Occupational Safety and Health Administration (OSHA) inspections, providing inspectors with appropriate documents and identifying safety measures. Ensures projects are completed on time and within budget. Acts as advisor to health and safety administration team regarding projects, tasks, and operations. Requires a bachelor's degree and at least 10 years of experience in the field or in a related area. Familiar with standard concepts, practices, and procedures within a particular field. Relies on extensive experience and judgment to plan and accomplish goals. Performs a variety of complex tasks. A certain degree of creativity and latitude is required.
- Site HSE Manager will be fluent conversant in the relative safety regulations of the Company and the statutory requirements of the Kingdom of Saudi Arabia.
5.6 Site Supervisor:
Periodic visits to the job site throughout the duration of pipe installation to advise the contractor
on the proper and applicable handling, storage, laying, jointing and site testing procedures
necessary to achieve a satisfactory pipe installation..
It is the responsibility of the Contractor to make available the pipe installation manual to his
installation crew, and to ensure that they are familiar with, and understand the procedures
described therein
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 9 of 46
Rev No. : B
It is the responsibility of the Contractor to strictly follow and implement the installation
procedures published in this installation manual, as well as any additional advise given by our
field representative.
The manufacturer shall not be liable for any failures related to installation arising from failure of
the Contractor to follow and implement our written installation instructions and any additional
advise or recommendation made by our field representative
5.0 PROCEDURES
5.1. DELIVERY, HANDLING AND STORAGE
• Prior to unloading of pipes from trailers, all items shall be inspected for any visual/transportation damages.
• Single pipes must be unloaded and handled separately (one at a time). Use pliable straps, slings or ropes to lift single pipes.
• Do not use steel cables or chains to lift or transport the pipe.
• Care shall be taken to prevent pipes from rolling or falling from flat bed trailer and this shall be attained by using proper supports.
• If at any time during handling or installation of the pipe, any damage such as cracks, de-lamination or fracture occurs, the pipe should be repaired before the section is installed. Contact BFRPL for inspection of damage and for recommendation for repair method or the replacement.
• The rubber gaskets received along with the pipes and fittings shall be stored in shelter with original packing until it is used at site.
• The gaskets must be protected from exposures to grease or oils, which are petroleum derivatives, and from solvents and other deleterious substances.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 10 of 46
Rev No. : B
Handling of nested pipes:
Handling Loading & Un-loading of GRP Materials:
Transport and storage
1. Loading Pipes, fittings and prefabricated parts (spools) have to be
transported by suitable trucks. These trucks must have flat floors. Check for
and remove any projections or nails etc. before each load.Materials must be
secured for example by using wedges and wooden supports.These supports
must have a minimum width of 10 cm, avoiding sharp edges.Usually the
materials are tied in place, using pliable nylon or canvas slings. Chains or
steel cables may not be used under any circumstances.
The support distances must not exceed 2.5 m. The width of the supports must be a
minimum of 10cm. When pipes are inserted (one inside the other), the support distance
shall not exceed 2 m.Flanges must be secured against sliding. Flanges may only be
loaded on their sealing face if they are sufficiently protected against damage.
The best way for fittings to be transported is in crates or onto pallets. Direct contact
between products during transport must be avoided.
Pipe ends and machined parts must be protected, for example, by means of straw mats
covered by polyethylene sheet or polyethylene netting. Pipes and spools should be
lifted by using nylon or canvas hoisting belts with a minimum width of 10 cm and must
be lifted at two points, using the largest diameter of the prefabricated part (spool), in
such a way that the weight is well-balanced.Any part of the truck has to be protected by
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 11 of 46
Rev No. : B
wood or rubber wherever in contact with the products.We recommend the use of trucks
which can be loaded from the sides. If pipes are handled by a forklift truck, the forks
must be covered with rubber or plastic
DO NOT LIFT THE PIPE BY PASSING A ROPE THROUGH THE SECTION END TO END.
2- Transporting Pipe
If it is necessary to transport pipes at the job site, it is best to use the original shipping
dunning when loading the truck. If this material is no longer available, support all pipe
sections on flat timbers spaced on a maximum of 10 feet centers with a maximum
overhang of 5 feet. Chock the pipes to maintain stability and separation. Insure no pipes
contact other pipes, so vibrations during transport will not cause abrasion (Figure 2.1.a).
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 12 of 46
Rev No. : B
Strap pipe to the vehicle over the support points using pliable straps or rope – never use
steel cables or chains without adequate padding to protect the pipe from abrasion.
Bulges, flat areas or other abrupt changes of curvature are not permitted. Transport of
pipes outside of these limitations may result in damage to the pipes.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 13 of 46
Rev No. : B
3. Pipe Unloading
The unloading of material is the responsibility of the client, unless agreed otherwise.
Because of the relative lightness of glass fiber reinforced plastics (approximately a
quarter compared to steel) handlers may be tempted to handle it roughly, or unload it by
letting it drop of its own accord. This may cause serious damage to the material and
therefore FPI material should be handled with care.
Do not use chains, steel cables or clamps during lifting. Nylon or canvas hoisting belts
with a minimum width of 10 cm must be used. Standard pipe lengths must be picked up
at two supporting points. Ensure that hoisting belts are always put round the widest part.
We strongly recommend that the pipes are unloaded one at a time when hoist belt used.
Each consignment is carefully loaded and must be inspected on site in order to ensure
that no damage has occurred during transportation. This will avoid disputes with regards
to responsibilities.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 14 of 46
Rev No. : B
4. Storage of material
In order to avoid damage to the stacked pipes, the following rules are important:a) Do not lay the pipes directly on the ground, onto rails or concrete floors.
Provide a flat surface.
b) Ensure suitable supports are used for example wooden beams, measuring
10 x 5 cm to avoid damage to machined pipe ends, stacking should be
undertaken with care.
c) The machined ends must be protected for example by polyethylene covered
straw mats or polyethylene netting.
d) The socket and spigot ends must not touch each other.
e) The pipes can be stacked economically by alternating the spigot and the
socket, as illustrated below. In order to avoid bending of the pipes, the
beams should be laid directly above each other in a vertical line. Supports
should be spaced at a max. of 3 meter intervals and about 1 metre from
each end. The width of the supports should be at least 10 cm. The
maximum allowable stack height is 1.5 meters. However, for diameters of
800 mm and above, a maximum of 2 pipes may be stacked one on top of
the other. If the product is stacked too high for long storage periods (6-12
months) and subjected to high temperatures, the supports may cause
flattening. It is recommended that the product (in particular machined parts)
is stored under tarpaulins or (white) polyethylene sheeting. Pipe stacks
should have side supports or blocks to prevent rolling or slipping of the
stack during stormy weather.
f) If any damage during transportation or installation is noticed such as
scratches, cracks or pits, Future Pipe Industries should be contacted for any
repair or replacement. Never use any damaged material.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 15 of 46
Rev No. : B
6.2 INSTALLATION
EXCAVATION
A. Excavate all material of whatever nature encountered to the lines and grades as shown.
1). Excavation includes removal and disposal of pavements and other obstructions on ground surface, underground structures and utilities indicated to be demolished and removed, and all other materials encountered.
Please go through the method of statement of excavation of earth work YT-PF-Z-16-00026 for more technical details.
B. Dewatering : Refer Method of Statement for Dewatering YT-PF-Z-16-00011
HOT WEATHER WORK
The gel time decreases as the air temperature increases. In certain situation, this
property is beneficial in particular in hot climates. When working in direct sunlight
above 40°C, the work area should be shaded with a sun screen to allow uniform
working time and curing of the lay-up around the pipe
EXTERIOR LAY-UP
GRP Vendor’s (FPI) Authorized person will be witnessing the first 2 joints to ensure
the work in accordance with standard.
A. Grind the outer surface of the pipe
B. as per the required minimum bond length mentioned in the provided field recipe.
Extend the sanding of the bond length 20 mm more than the required length to
ensure complete bonding of the lamination material is achieved over the minimum
specified bond area.
B. The maximum time between the grinding operation & lamination process is two
hours. In case of delay in starting the lamination operation, the entire sanding
operation has to be redone.
C. After the component resin/hardener is thoroughly mixed one can start the fit
procedure.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 16 of 46
Rev No. : B
D. The cross section of the pipe has to be protected against penetrating liquid using a
resin or adhesive layer.
E. After the pipe sections are positioned they should be wetted over a length of
approx. 5 cm on both sides of the “weld” using resin/hardener, mixtures, after which
the fit layer can be made.
F. Wrap 5 layers of 270 gr/m² 5 cm width for dia 25 through 350 mm and for dia 400
through 2000mm 5 layers 270 gr/m² 10 cm width have woven roving around the
“weld” taking care that every following layer applied over a totally impregnated
previous one. For this impregnation use a brush or roller. The woven rovings are
wrapped around under tension. The resin/hardener Mixture will be pressed through the
woven roving.
G. Be sure to cure the fit layer over the entire circumference. After curing the fitted part
can be moved. In large diameter the fit layer thickness should be increased if the
part has to be moved.
H. Before continuing, grind again to guarantee a good adhesion between fit layer and
laminate.
I. After the fit layer has hardened re grind the entire tapered section of the pipe & fill it
with pieces of 360 gm woven roving & resin mix until the entire tapered portion is
filled in level with the outside diameter of the pipe. Allow the laminate to cure at
ambient temperature. This is done to avoid excessive exothermal heat that may
interfere during the final welding operation.
J. When the above laminate has hardened sufficiently the exterior part of the laminated
area as well as the total required bond area should be sanded well for the final
welding process.
K. Laminate resin and hardener should be mixed in a bucket in suitable quantities by
preference mechanically e.g. using a propeller mounted on a drilling machine or
manually using a spatula for approx 1 min. The woven roving must be wrapped with
an overlap of 50%; this means that 2 layers per winding are generated. The abraded
and cleaned surface should be wetted with resin mix, using a brush or lamb’s wool
roller.
L. Then layers of woven roving should be wrapped around wetted surface. Each
applied layer must be thoroughly impregnated. The woven roving requires to be
tensioned, so the resin presses out of the underlying layers. For the impregnation of
the applied woven roving use a roller or brush.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 17 of 46
Rev No. : B
M. For diameters up to 150 mm the butt and wrap joint is totally built up from woven
roving’s 270 gr/m²; for dia m 25 through 50 mm the width will be 5 cm, for dia m 80
through 150 mm the width will be 10 cm.
N. For diameter range 200 mm through 350 mm the butt and wrap joint is totally built
up from woven roving 360 gr/m² 10 cm width. The thickness of the lamination must
be maintained at 0.75 x the bond area at either end of the joint. For detail of bond
area & thickness, please see the required lamination recipe.
O. For diameters 400 mm and above the woven roving shall be changed after 12
layers of 360 gr/m² 10/16 cm width into 580 gr/m² 10/16 cm width, which will be
applied in 4 layers alternated with 2 layers of 360 gm layers. The first 12 layers (6
double) should always be woven layers of 360 gm.
P. For diameter range 700 mm through 2000 mm lamination has to be started using
woven roving of 360 gr/m² 16 cm widths.
Q. When the required wall thickness is obtained a final layer of 2 layers of woven
roving for diam > 350 mm 360 gr/m² 16 cm width should be applied. R. After the 2
final layers of 360 gr/m² 16 cm width woven roving have been applied, the laminate
should be finished with 2 layers of reinforced non-woven wrapped over the laminate.
S. The superfluous resin should be removed using a rubber scraper plate after which
the laminate should be cured at room temperature.
Note:
For larger diameters it may not be possible to complete the entire lamination process
in one go. Therefore the lamination process has to be interrupted in case gelation
occurs. The laminate should be allowed to cure at room temperature & later re
grinded to continue the rest of the welding process until the required thickness has
been achieved. The exact quantity of the material of the butt strap joint shall be
issued by FPI Engineering department for each diameter and pressure.
FURTHER RECOMMENDATIONS
A. Adjacent pipes should not have different self deflections causing joint steps, but
where a pipe butts up against a fitting of different thickness, a slight difference in
roundness may occur with the pipe being deflected more than the fitting. It is
possible to correct this slight out-of roundness on the pipe by using a jacking prop
with wooden load spreaders at each end.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 18 of 46
Rev No. : B
B. Where different thicknesses of adjacent parts are encountered (e.g. pipe to
reducer, pipe to elbow, or pipe to tee), the parts should be aligned concentricity
and any step greater than 6 mm removed by applying a 15 deg. tapered build up
to the pipe surface with glass mat and resin. This should be applied all round the
pipe and rolled out as normal. Steps less than 6 mm can be tapered off with
resin/cabosil putty or filled with woven roving. The lay up joint can then be applied
in the normal manner.
C. It is important that when pipe surfaces to be laid up are cleaned with solvent, the
solvent must be freshly drawn and clean. The cloths should also be clean, made
out of white cotton. The solvent used for this cleaning operating can subsequently
be used for cleaning rollers, tools, gloves, etc.
Notes of Caution
1). Do not use resin that is gelling (beginning to thicken). The lay-up cannot obtain
full bond strength with gelling resin.
2). Insure all solvent used to clean the pipe has completely evaporated before
applying the layup. The lay-up loses its bond if it is applied on a surface with
solvent on it.
3). Never allow solvent to run on uncured resin.
4). If the lay-up is not properly bonded to the pipe, remove the lay-up and wash the
area with solvent, being careful not to run solvent into uncured lay-up areas.
5). During a period of rapidly changing temperature, pipes may move due to
expansion or contraction. This movement could reduce the bond strength of the
initial lay-up plies, if the plies have not cured prior to the movement. If this
phenomenon is experienced, the pipes must be restrained against movement
while the lay-up joint is being fabricated.
6). When working on the bottom side of the joint, a faster gel time is desired. This
can be accomplished by (1) increasing the amount of catalyst (2½% maximum)
and / or (2) using the heat of a previous lay-up. Remember never place a lay-up
over another lay-up, if the first one is not comfortable to touch with the bare hand.
7). In the event that a lay-up joint is not completed on the day it is started or if a layer
of the lay up is allowed to cool for several hours, the following procedure should
be followed. :
a. Remove the glossy surface of the lay-up by grinding the lay-up area covered by
resin.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 19 of 46
Rev No. : B
b. Wipe the ground area with clean solvent to remove collected dust and allow the
solvent evaporate completely.
c. Continue to apply the remaining layers of the lay-up as previously described.
Note:
If the top layer of mat is removed when grinding, it will be necessary to apply an
additional piece of mat when the final layer of the lay-up is applied.
INTERNAL SEALING JOINT
GRP Vendor’s (FPI) Authorized person will be witnessing the first 2 joints to
ensure the work in accordance with standard.
Grind the area to be bonded preferably just prior to the welding process.
A. Ensure that any gaps between the pipes are filled well with Cabosil/resin mixture
or glass roving’s.
B. Apply the given nos. of 270 gm woven roving with the resin mixture until the
required thickness has been achieved. In cases where gelling occurs discontinue
the lamination process & allow to cure at room temperature. Re grind the areas
after the curing process is completed & continue the lamination process until
required thickness has been achieved.
C. Finish the interior layer with one layers of C glass & resin mixture.
D. See lamination recipe for detailed bond area & layers. Slightly different
procedures and safety measures must be observed when making internal lay-up
joints. Make sure proper ventilation is available when working in close
environments. Wear safety masks & goggles always when in contact with
chemicals.
CURING & FINISHING:
The resin/catalyst system is as illustrated in Table 1; the curing curve shown in
Figure 1 was obtained in ambient temperature of 20oC and relative humidity of 75%.
Adjustments are required to suit local temperature and humidity; good judgment
should be exercised.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 20 of 46
Rev No. : B
Table 1
After well mixing the above and before start the lamination process add 150 g
catalyst to each 1 Kg of the above mixture.
PRECAUTIONS and EQUIPMENT
The resin, catalyst, booster and accelerator used in performing the lamination are
flammable and can cause harm if not used properly. Data sheets of each material
should be obtained from supplier and read carefully prior to commencing work. The
following list shows equipment that must be supplied by the installation or lamination
contractor:
- Rotary disc sander.
- Carborundum sanding disc 16 grit.
- Polyethylene pots for mixing resin with 1 gallon capacity.
- 1 Pint graduated cylinder for measuring catalyst.
- Paint rollers 5 cm diameter and 15 to 20 cm long.
- Wooden spatulas for mixing resin & catalyst.
- Masking tape.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 21 of 46
Rev No. : B
- Goggles.
- Rubber gloves.
- Grooved rollers 7.5 cm long.
- Dust Masks
QUALITY ASSURANCE
A. Source Quality Control: The following tests shall be carried out during the
manufacturing period:
1). Determination of glass/resin composition as per ASTM D2584.
2). Determination of the Barcol hardness of the laminate as per ASTM D2583.
3). Determination of the laminate strength of tensile bars extended in the
longitudinal direction of the pipe as per ASTM D638.
4). Determination of pipe stiffness using a 300 mm long pipe sample, carried out in
accordance with ASTM D2412.
B. Codes and Standards: The design, material, fabrication, inspection, and testing of
all materials furnished shall be, unless otherwise specified, in accordance with the
latest revisions of the applicable codes and standards of the following United States
regulatory agencies and standards organizations in force on date of Award of
Contract. In the event of conflict between this Document and any codes or standards,
the Contractor shall refer this matter to the MARAFIQ for resolution.
American Society for Testing and Materials (ASTM)
American Society of Mechanical Engineers (ASME)
American Welding Society (AWS)
American Water Works Association (AWWA)
International Standard Organization (ISO)
National Fire Protection Association (NFPA)
Steel Structures Painting Council (SSPC)
American Iron and Steel Institute (AISI)
Hydronics Institute (HI)
Underwriters' Laboratories, Inc. (UL)
Pipe Fabricators Institute (PPI)
American National Standards Institute (ANSI)
C. Material meeting other standards, which ensure quality and safety equal to or
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 22 of 46
Rev No. : B
higher than United States standards, regulations, and codes, will also be acceptable,
subject to the approval of MARAFIQ. In these instances, the Contractor shall be
required to demonstrate the equivalency of the standard(s), and shall furnish the
MARAFIQ with one copy of the standard(s), used for the design and fabrication of the
equipment.
D. The Contractor shall be responsible for the quality of pipe in accordance with the
material, fabrication, qualification testing, and acceptance requirements of the ASTM
Standards and, specifically, the ASME Boiler and Pressure Vessel Code, Section III,
Division I, Code Case N-155-2 (1792-2) except as amended herein. Piping supplied
shall only be from material manufacturers and material suppliers as defined by the
code case.
E. GRP Pipe Applicable Documents: In addition to documents listed in 1.5 B, the
following documents and references shall be used when applicable as a source for
GRP pipe data to fulfill the requirements of this document.
1.) Raw Materials:
ASTM D 2393 and D 445
Viscosity of Resin
ASTM D 2343
Tensile Properties of Glass Fibers
2.) General GRP Pipe Specifications:
ASME B31.1 power piping
ASTM D 2996
RTR Filament Wound Pipe
ASME Code Case 1792-2 (N-155-2)
Nuclear RTRP Standards
PS 15-69
GRP Products
ASTM D 3139
Elastomeric Joints
3.) Pipe Design Standards:
ASME Code Case 1792-2 (N-155-2)
Nuclear Pipe Standards
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 23 of 46
Rev No. : B
ASTM D 2353
Method for Calculating Internal Pressure Stress
ASCE Proceeding 37
M & R No. 37 Chapter 9
ANSI B16.1 and B16.5
Standard Dimensions for Cast Iron and Steel Flanges
ASTM D 2992
Hydrostatic Design Basis
ASTM D 3567
Dimensioning of RTR Pipe and Fittings
4.) Tests for Material Properties of Finished Product:
ASTM D 2583
Barcol Hardness of Product
ASTM D 638
Tensile Properties
ASTM D 790
Flexural Properties
ASTM D 695
Compressive Properties of Rigid Plastic
ASTM D 1599
Short-Time Rupture Strength of Pipe
ASTM D 2105
Longitudinal Tensile Properties of RTRP
ASTM D 2412
External Loading Properties by Parallel-Plate
Loading
ASTM D 2563 Level III
Classifying Visual Defects in GRP Laminate Parts
AWWA C 207
Steel Pipe Flanges for Waterworks Service
(4 in. to 144 in.)
F. Factory Tests (GRP Pipe):
1.) General:
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 24 of 46
Rev No. : B
(a) The manufacturer shall test the material for random sections of pipe or fittings
at a rate that ensures at least one test lot for every 250 meters of pipe which is
produced. The manufacturer shall obtain coupon test samples from nozzle cut-
outs, miter cuts or from a section of pipe which has not had its thickness increase
by the dwell turn at the ends of the pipe section.
(b) Factory tests for GRP pipe shall include but not be limited to tests designated
in this section.
2.) Destructive Tests: The following random destructive tests shall be performed:
(a) Tensile Strength and Tensile Modulus: These properties may be verified by
following test methods utilizing strain gages as specified by ASTM D 638. The
shape of the sample coupon must be adjusted to accommodate the
orientation of the continuous glass filaments.
(b) Flexural Modulus: The flexural modulus of the glassfiber component may be
determined by measuring a sample coupon with strain gages in accordance
with ASTM D 790. The shape of the coupon must be adjusted to
accommodate the orientation of the continuous glass filaments. For
components of a diameter of less than 2 meters, parallel plate loading tests
shall be performed in accordance with ASTM D 2412.
(c) Elastomeric Joint Testing: The Contractor shall document joint integrity from
tests of previously installed and operating fiberglass piping systems or by
means of other testing that the proposed joint is of sufficient strength to
survive the anticipated service conditions without leakage or fracture.
(d) Testing Resin/Glassfiber Overlay Joints: The integrity and strength of a
resin/glassfiber overlay joint shall be analytically evaluated to ascertain that the
strength of the overlay joint is at least equal to or greater than the axial strength
of the GRP pipe. Visual inspection of the overlay joint will be performed to
ascertain its reliability.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 25 of 46
Rev No. : B
QUALITY CONTROL
The following quality control checks can be done on the completed lamination.
- Visual:
There is no specific standard for conducting visual testing. Basically the lamination
should not have irregularities in shape and appearance.
- Dimensional:
The thickness and width of each joint is given in the process sheets. Those are the
minimum values.
PERSONNEL
Lamination works to be done by skilled operators, trained and qualified by Future Pipe.
Qualification certificates for laminate application.
6.0 MATERIALS
The following material shall be prepared;
- Fiberglass joint kit which includes:
- Fiberglass Woven Roving with specific dimensions as per diameter.
- Vinyl Ester Resin (promoted, not catalyzed)
- Top tape for the top coat of the joint
- Catalyst /Hardener
- Cabosil powder
- Styrene
- Inhibitors
Site Material Storage
- Resin – Shall be stored in shelter.
- Catalyst- shall be stored in a properly regulated store temperature of 20°C to25°C.
- Fiberglass kits woven roving – shall be stored in a close room to avoid dust, dump
and direct sunlight.
- Styrene – shall be stored in shelter.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 26 of 46
Rev No. : B
7.0 EQUIPMENTS
The following equipment shall be prepared;
- Rotary disc sander
- Carborundum sanding disc,60 grit
- Table : 1 per work crew, big enough to accommodate largest strip of mat or woven roving.
- 10 Liters polyethylene pots for mixing resin.
- Paint rollers, 5 Cm diameter and 15 Cm. To 20 Cm. Long
- Solvent e.g. methylene Chloride.
- Masking tape
- Safety Goggles
- Rubber Gloves
- Heavy, Kraft paper, large enough to cover work table
- Grooved rollers 7.5 cm long for consolidation.
- Portable Shed
- Crawler Crane : 1 set
- Hydro Crane : 1 set
- Trailer : 1 set
- Generator : 3 sets
- Compressor : 1 set
- Engine welding machine : 2 sets
- Fans : 2 sets
- Pumps
8.0 INSPECTION AND TEST
- Materials and finished components shall be subjected to inspections and tests
according to applicable Codes and Standards and stipulations of Owner‟s
specification.
- Supplier shall submit the Quality Assurance Plan for Purchaser / Owners‟ approval.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 27 of 46
Rev No. : B
- Purchaser / Owner retains the right to appoint inspectors who have the authority to follow the progress of the work and the manner in which it is being done, to inspect materials in manufacture or at the point of delivery, to reject defective materials either at the source of supply or point of delivery at any time, or to suspend work which is not being done properly or is not in accordance with the plans and specifications.
- Owner‟s / Purchaser‟s inspector shall have free access to the work and to all parts of the Vendor's plant engaged in work on equipment and materials to be supplied, at all times while work is being performed on this contract.
- Failure of the Purchaser /Owner to witness any test shall not delay either such test or the proper fulfillment of the specifications and guarantees. The Vendor shall not be relieved from any obligation under the Specifications by virtue of the Purchaser /Owner's attendance at, or failure to attend any such tests, or by virtue of lack of notification of rejection of the results of such tests.
- Marking
Each pipe/fitting and spool shall be permanently marked with following information:
a) Manufacturer‟s name or initials and identification code
b) Normal size
c) Pressure rating and temperature rating
d) Number and date of selected code
e) Resin and reinforcement type
Upon satisfactory completion of inspection and testing on pipes, fittings and
spools, the organizations responsible for design, construction and inspection shall
furnish copies of the certificate to the Purchaser, stating the design, construction
and testing complies with this specification and selected code.
- Quality assurance / documentation
QA shall be according to requirements in selected codes and manufacturer‟s QA-
manual approved by Purchaser / Owner.
Detailed design drawings shall be prepared by the Vendor and submitted for
Purchaser approval prior to start of manufacturing.
All important construction details must be shown in details-drawings.
- Certification
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 28 of 46
Rev No. : B
The Manufacturer shall provide quality control test reports. Manufacture shall
submit a certified record of inspection and testing together with a statement of
compliance with the requirements. These shall also include the relevant
certificates for metallic parts, if any. Additionally, requirements of Owner in regards
certification stipulated in his specification shall be met.
- The installed pipe lines shall be hydro-tested
-
Personal Protective Equipment (PPE)
- Coveralls
- Hard hat
- Safety boots
- Gloves(rubber and cotton)
- Safety glass
- Paper mask
- Respirator with cartridge (RC202) filters (for internal lamination works)
- Full body harness(working at height)
- Face shield to use during the grinding works.
- Access to suitable fire extinguishers tor internal and external work faces.
- Eye wash tools on vicinity of the working area (during the lamination work)
Hazard Identification and Risk Assessment Worksheet
Equipment mobilization Crane, Boom truck, System including pump, Trailer Truck,
Hand tools, Lamination Kits and Accessories
Control Measures
- Crane must have current 3rd party inspection.
- Crane operators and drivers must have current SAG license and TUV certificate.
- Appropriate documents to be sent along with the equipment.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 29 of 46
Rev No. : B
- Documented pre-deployment maintenance check of the equipment by mechanic.
- Crane load chart and operating manual available.
- Hand signals posted on the crane.
- Must pass MET- Inspection.
- Monthly equipment inspection & color coding.
- Conduct daily inspection using equipment daily inspection checklist.
- Through inspection of all equipment shall be carried out by a competent person
designated by ESD-Equipment Service Department prior to delivery of the
equipment to the project.
- Fire extinguisher shall be provided on every equipment with internal combustion
engine, 20lbs.
- Obtain necessary work permit from MET
- As built underground drawing and plot plan from MET showing buried facilities
and limitation shall be provided.
Working in a confined space (for excavation 1.2 m and deeper)
- Obtain necessary work permit from MET No confined space entry starts without a
dedicated trained entry attendant physically available at the entry point. The entry
attendant remains outside the space to constantly monitor (by visual or auditory
communication) authorized entrants working inside the space.
- Ensure gas testing is performed in every level prior to entry.
- Ensure rescue equipments are available.
- Entry attendant shall maintain al log to fully account personnel inside the space.
- The space must be evacuated in emergency inside/outside space or hazardous
atmosphere is detected.
Scaffolding Erection over the GRP field joints.
- Selecting right scaffold for job.
- Assigning personal and training.
- Scaffold inspection and tagging
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 30 of 46
Rev No. : B
- Scaffolding materials proper maintenance and storage.
- Compliance with PPE requirements use eye/face protection, hand gloves, hard
hats and safety shoes.
- All tools/rigging devices to be used will be checked/inspected and color-coded by
competent inspectors.
-
Pipe Installation.
- Obtain necessary work permit from MET.
- Sequence of work shall be discussed during daily toolbox meeting before work
commence.
- Lifting plan to be discussed by rigging supervisor along side with crane operator,
riggers, assist crew, etc.
- Only competent person shall perform all rigging works.
- Lifting gears/tackles shall be inspected prior to use.
- Use proper length and size of slings and ensure lifting tackles in good condition.
- Softeners to be used to protect sling from sharp edges.
- Two tag lines shall be used to control the load.
- Crane shall be properly set-up and appropriate timber pads to be used.
- Physical barricade to install and maintain with entry and exit points.
- “Danger lifting on progress, keep out” signboards to be posted.
- No erection allowed during harsh weather e.g. wig exceeding 20mph, thick fog,
heavy sandstorm, rain.etc.
Fit-up and Lamination of joints
2.0 Lamination joint on GRP piping has two stages:
a) Grinding the pipe surfaces (internal, external).
b) Application of the layers.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 31 of 46
Rev No. : B
c) Witness and approval of Fit-up should be done by the QC Inspector prior to
lamination.
A. External Lamination
1. Fit Layer
a. Measure the fit layer bond length from the end of each pipe.
b. Grind the above area to remove the topcoat and surface layer of the pipes until the pipes
glass fiber are exposed.
c. Clean this area by dry clean cloth or paintbrush and ensure that it is fully dry.
d. Fill the gap if any between the two pipes with cab-o-seal putty.
e. Mix the resin and hardener as per the quantities specified in the recipe to maintain the
right ration.
f. Impregnate the roughened area with above mixture.
g. Apply woven roving glass 270 using a 50% overlap between each two consecutive
windings so that wrapping the full surface will end up with two layers of glass.
h. Impregnate the above layers with the resin/hardener mixture.
i. Repeat the above two steps till the required number of layers is applied.
j. Wait till the lamination is cured under ambient temperature. The curing time of the fit
layer ranges between 1 to 2 hours depending on the sunlight.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 32 of 46
Rev No. : B
2. Main Laminate
a. Measure the bond length on each pipe from the middle of the fit layer.
b. Grind the above area to remove the topcoat and surface of the pipe until the pipe glass
fiber are exposed.
c. Clean this area by dry clean cloth or paintbrush and ensure that it is fully dry.
d. Mix the resin and hardener as per the quantities specified in the recipe to maintain the
right ration.
e. Impregnate the above layer with the resin/hardener mixture.
f. Apply woven roving glass 270 using 50% overlap between each two consecutive
windings so that wrapping the full surface will end up with two layers of glass.
g. Impregnate the above layer with the resin/hardener mixture.
h. Repeat the above two steps till the required number of layers is applied.
i. Depending on the pipe diameter and pressure class, the type of glass and the number of
layers are specified in the lamination recipe. If only glass 270 should be used, skip all the
below steps except the last one to end up the lamination with two layers of top tape
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 33 of 46
Rev No. : B
otherwise move the next step.
j. Apply woven roving glass 360 using 50% overlap between each two consecutive
windings so that wrapping the full surface will end up with two layers of glass.
k. Impregnate the above layer with the resin/hardener mixture.
l. Repeat the above two steps till the required number of layers is applied. A maximum of
12 layers should be applied at this stage as “initial winding”.
m. If more should be applied, move to the following steps. Otherwise skip all the below
steps except the last one to end up the lamination with two layers of Top Tape.
n. Apply the specified number of layers of woven roving 580 and 360 alternatively. Each
type of glass should be applied in four consecutive layers before changing to the other
type. Every two layers should be impregnated before applying the second two layers of
the same type.
o. Apply two “sealing layers” of woven roving glass 360.
p. Impregnate the above layers with the resin/hardener mixture.
q. Wind two layers of top tape glass around the laminate to extract the excess quantity of
resin and to provide smooth surface.
r. The lamination is cured under ambient temperature. Make sure that the joint is
undistributed until it cures. The curing time varies between 4 to 8 hours depending on
the sunlight exposure and temperature.
B. Internal Lamination (Applicable only for 900mm & above in condition that the access
to the joint internal area is safe and possible).
The following steps are to be done inside the pipes:
1. Measure a length of 50 mm from the end of each pipe.
2. Grind the above area to remove the internal liner of the pipe.
3. Cut several pieces of woven roving glass 270/100 with equal length.
4. Mix the right quantity of resin and hardener.
5. Wet the surface area of internal layer with mixture.
6. Stack several pieces of woven roving on a flat surface and impregnate with the
resin mixture.
7. Place the above impregnate woven roving on the joint.
8. Evenly press the surface to flush air traps and blisters using steel roller.
9. Repeat the above three steps until the required thickness is reached.
10. Cover the above laminate with two layers of C glass surface veil material (surface
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 34 of 46
Rev No. : B
mat) to provide a smooth resin-rich laminate surface.
11. The lamination is cured under ambient temperature.
For internal lamination, the plies edges shall be penetrated into the previously made grooves at both side of the lamination width to maintain smooth flow of the product during operation
PRECAUTIONS
a. The prepared bond surface area should be free from grease, oil, dust, moisture, water, etc. Clean the
surface using a clean and dry cloth or a dust brush.
b. Do not move the joint before the laminate is cured.
c. Lamination should be stopped in case resin starts gelling. To continue the laminate,
surface should be abraded.
d. Safety precaution for internal lamination as follows:
Internal lamination shall be done immediately after completing the external lamination to
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 35 of 46
Rev No. : B
limit the entry distance to a standard pipe length. When this is not possible, i.e., where
the entry distance is longer than 20 meters the following safety measures shall apply:
1. If required, the client safety personnel to measure concentration of any toxic gas
and oxygen inside the pipe before giving clearance to enter the line.
2. Use personal protective equipment before entering the pipe.
3. If required, use a rechargeable lamp or hand torch for enough light inside the
pipeline. Usually, the daylight is sufficient at the 1st joint near the open end.
4. Ensure that no blockage at the access of the open pipe end.
5. Use exhaust fan or blower to ensure fume free and to avoid accumulated fumes.
6. Ensure that there is no water present in the line/sections, other wise use
dewatering pump and sand bags to prevent flow of water to the joint to be
laminated.
7. If required, a watchman should be standing outside the pipe and in frequent
verbal contact with the technician working inside the pipeline.
8. If the internal joint to be carried out is more than five standard pipe away, a rope
will be tightened from the waist of the technician for easy pull out inside the pipe
and to ensure his safety in case something gets wrong inside the pipe.
9. The chemicals are potentially flammable, NO SMOKING inside the pipe is
allowed and in all areas where lay ups are being made.
10. If required, technicians will wear fume mask to protect from fumes and chemical
smell.
11. A safety guards shall be mounted on the grinders.
12. Follow any safety rules as strictly enforced of the end users and the client.
REPAIR PROCEDURE
a. If any lamination joint is found to be leaking cut the joint out and replace it with a pipe
piece. Connect this piece by two laminations following the same procedure described
above.The same shall be done if the leak occurs on the pipe wall due to impact damage.
If possible, the leaking lamination can be removed by grinding it off the pipe
completely and re-laminate by a new one following the same procedure described
above.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 36 of 46
Rev No. : B
b. In case of a superficial damage on the pipe, the following steps to be followed. A
superficial damage is a scratch within the resin rich outer layer of the pipe.
1. Abrade the damaged area by using emery paper.
2. Use a brush to clean the area from dust.
3. Mix the resin according to the recipe.
4. If it is necessary apply 1 or 2 layers of C-glass.
5. Apply the mixed resin on the damaged surface.
QUALITY CONTROL FOR THE GRP LAMINATION JOINTS.
1. PTS WILL PROVIDE QUALIFIED QA/QC INSPECTORS TO VERIFY THE JOINT
SPECIFICATION AS PER THE AMIANTIT PROCESS.
2. VISUAL INSPECTION FOR THE LAMINATED JOINTS FOR EXTERNAL AND
INTERNAL WORKS
3. CHECKING THE LAMINATION THICKNESS USING THE PI TAPE ALSO THE
LAMINATION WIDTH
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 37 of 46
Rev No. : B
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 38 of 46
Rev No. : B
4. BARCOL HARDNESS TO CHECK THE LAMINATION HARDNESS SHOULD
NOT BE LESS THAN 30.
.......CAUTION............1-Do not use resin if it is near to gel.
2-Never allow solvent to run on un-cured resin (the layers looses bonding strength if solvent
got mixed with it.)
3- During rapidly changing in temperature periods, pipes may move due to expansion /
contraction, This could effect the bonding strength of the initial lamination plies, if the same
are not cured prior to the movement. In such cases, the pipe shall be restrained against
movement while the jointing is under progress
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 39 of 46
Rev No. : B
10.0 SAFETY PRECAUTIONS
The chemical components required for the butt-strap joints present certain safety and health
hazards if not handled well. Following are the recommendation:
HAZARDS;-
Resin:- Liquid resin contains styrene which is flammable. Its vapors may cause irritation of
eyes, nose and throat. Excessive inhalation may cause dizziness, drowsiness or loss of
consciousness.
Catalyst:- Methyl ethyl ketone per oxide is a strong oxidizing agent and is a fire and
explosion hazard. It is irritant to eyes, skin and mucous membranes, and is known as
sensitizer. It shall always be stored in original containers & only small quantity shall be
taken to the work place as per site activities/ requirement.
Styrene:- ( For tools cleaning) The principal hazard is loss of consciousness in case of
excessive in halation of vapors .Exposure to high vapor concentration may cause cardiac
irregularities.
PRECAUTIONARY MEASURES:-
Work in adequate ventilation. Wear dust / vapor mask while mainly working inside the
pipes. All crew members shall use protective / safety glasses and rubber gloves.
Long sleeved shirts, long pants and hats of some kinds (depend on client safety
requirement) are recommended.
“NO SMOKING “sign in all lamination material storage and working area shall be displayed.
All materials and chemicals shall be away from heat source, sparks and open flames.
FIRST- AID PROCEDURE:-
IN CASE OF:-
Inhalation: Remove the victim to fresh air.
Eyes: - Flush exposed eye large amount of flowing water. In case of severity, immediately
obtain medical aid from nearest hospital.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 40 of 46
Rev No. : B
Skin: - Wash skin with soap using enough volume of water.
11.0 Risk AssessmentsThe Sub-contractor safety officer and site management will meet the terms of Health
and Safety regulations equally across all FRP installation work activities. All sub-
contractors employees to carry out a suitable and sufficient assessment of all risks to
workers and any others who might be affected by their work activities. This is for the
purpose of identifying the measures he needs to take to comply with the requirements
and prohibitions imposed upon him by or under relevant statutory provisions. In essence
this is a requirement to wherever possible remove the risk entirely, or where this is not
practicable reduce and control the risk to the lowest level that is reasonably practicable.
Listed below the FRP materials used for jointing works notifying that the MSDS will be
submitted to HANWHA HSE Managers :-
1) Fiberglass woven roving in strips of the width required.
2) Resin (promoted but not catalyzed) of the same type as the tank wall materials.
3) Styrene.
4) Catalyst.
The Resin, Styrene and Catalyst used in making the lamination joints are flammable
and may be harmful.
Materials:
Common Name : Resin
Hazard:
Styrene monomer vapor may cause irritation of the eyes, skin and mucous membranes
of the upper respiratory tract. Excessive inhalation may cause loss of consciousness.
Repeated skin contact with polyester resin may cause dermatitis.
Precautionary Measures:
Use with adequate ventilation. Avoid inhalation of vapors and preferably use respirators
with filters (chemical usage).
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 41 of 46
Rev No. : B
Spilled resin should be absorbed with inert materials such as sand; Resin that may have
been mixed with peroxide initiators prior to spillage should be mixed with inert filler and
removed to an open area. And allow time to gel and cure.
Fire Hazards:
Liquid polyester resin systems contain styrene which is flammable.
“NO SMOKING” in storage or work areas, store in cool place away from flames, sparks ,
direct sun light steam pipes or other sources of heat.
Fight fire with foam, carbon dioxide, or dry chemical type extinguishers.
Common Name: Styrene
Hazard:
Exposure to excessive styrene vapor concentrations may cause irritation of the eyes,
skin and mucous membranes. Direct contact with the liquid may cause blistering of the
skin.
Precautionary Measures:
Use with adequate ventilation. NO SMOKING in area where materials is stored or used.
Avoid contact with skin and excessive inhalation of vapors. To prevent eye and skin
contact use Rubber gloves and safety glass for the technicians at work.
Fire Hazards:
Styrene is a flammable liquid.
“NO SMOKING” in storage or work areas, store in cool place away from flames, sparks ,
direct sun light steam pipes or other sources of heat.
Fight fire with foam, carbon dioxide, or dry chemical type extinguishers.
Materials:
Common Name: Catalyst
The catalyst is an oxidizing agent and is a fire hazard. It is an irritant to eyes, skin and
mucous membranes and is known sensitizer.
Precautionary Measures:
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 42 of 46
Rev No. : B
Wear protective clothing, rubber gloves and safety glass to prevent eye and skin
contact. Use with adequate ventilation. Avoid breathing vapor.
Store in the original containers, in the smallest quantity, isolated from other chemicals
and away from heat and open flames
. NO SMOKING” in storage or work areas.
General Safety Rules to follows during site lamination & materials handling:
Sub- Contractor Safety Officer will make sure for all Technicians to fulfill the following safety
rules as detailed:-
Safety glasses should be worn at all time and by all personal in the vicinity of the lamination
operation.
The skin of all technicians handling the materials should be protected with
rubber gloves, long sleeve shirts, long pants, paper mask and respirator with
cartridge (RC202) filter for the internal lamination works.
The chemicals are flammable and shock sensitive. Care should be taken that
they are kept away from open flames or sparks and that are stored separately
away from work areas and other flammable materials. They should also protect
from heat and direct sun light.
A “NO SMOKING RULE” should vigorously be enforced in all areas where
lamination is being made.
All sub-contractor technicians will wear a respirator with filter during the lamination
works.
WORK IN CONFINED SPACES Only authorized to suitable trained personnel shall be allowed to enter into
confined spaces (such as FRP pipe line).
No work whatsoever shall be undertaken without first referring to the current
Risk Assessment for the work to be undertaken.
A 'Permit to Enter a Confined Space' is to be issued by the relevant trained
personal or Supervisor or his authorized assistant prior to each and every entry.
Personal Protective Equipment - Gloves, overalls, safety boots, safety helmets,
eye protection etc, and is to be worn as appropriate to the task.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 43 of 46
Rev No. : B
Sub-contractor will provide exhaust fan with a size enough to have good air
circular ventilation inside the FRP pipe line.
HANWHA will provide the gas tester equipment and trained personal to use and
monitor the oxygen percentage in the atmosphere. Records and such training
shall be maintained by sub-contractor safety officer in cooperation with
HANWHA HSE Managers and will be entered to the permit to work.
Sub-contractor will identify qualified personal for confined space stand by men
and to be trained from HANWHA HSE Managers. His responsibilities to monitor
authorized entry to confined space in accordance with the permit to work
conditions, to maintain contact with those inside the confined space ant raise the
alarm and provide initial controlling the event of any emergency.
Records of any such training shall be mentioned by sub-contractor HSE office.
Each Lamination group of technicians (4 Techs.) should have separate suitable
fire extinguisher to use at the time required and be trained to use them.
First aider and paramedic’s response.
Ambulance response and treatment by HENC doctor and or hospital
Proper communication equipments and contact numbers (Emergency contact
numbers attached)
nsure PTW is processed by authorized and
Competent persons.2.1.2 Ensure effective supervision and conduct inspection.
Conduct tool box talk prior to starting work to the force by using the TBT (Tool Box Talks) prompt
card. Confirm they all understood the task, hazards and safety precautions and actions to be
taken in case of emergency.
WORK AT NIGHTAll activities shall be followed as bellow:
Equipment shall be checked in good working condition before using.
Trained workers only shall be allowed to perform each task. Adequate
supervision shall be provided o enforce procedure and to guard against
untrained authorized worker.
Visible access for personnel shall be prepared on the slope surface. All
equipment and material shall be located at least 2 meter away from the
excavation.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 44 of 46
Rev No. : B
Watchman shall be used and control all equipment to warn personnel or other
equipments, motor vehicles to keep safe distance from working equipments.
All vehicles shall have safe distance during excavation works to avoid accident.
Watchman shall also used to warn and prevent colliding with each other.
Back alarm is installed on all equipments to serve as warning signal prior to
backing out the equipments.
All personnel working in night must wear reflective vests.
Flash light shall be provided to the foreman and supervisor/ watchman.
LOADING / UNLOADING Provide warning tape or wood cap in all extruding sharp edges.
Unwanted materials should not be pile at the work area.
The workers who perform the job must be trained.
Barricade and signage should be provided in working area.
Always avoid blocking the access with materials.
Perform good house-keeping in the work area
Don’t lift the load beyond the capacity of the equipment.
All material must be arranged in proper place after finishing your job.
Access must be clear.
Transport materials / loading / unloading movements of vehicle
The vehicle should be inspected by HENC prior to using.
Ensure periodic maintenance of vehicle.
Do not over speed and avoid sudden breaking.
Ensure proper plan to transport and loaded material.
Plant and vehicle to be operated by experienced and licensed operators /
drivers.
Transport to agreed location.
All workers will be ensured to use PPE.
Proper assistance given by the supervisor.
Adherence to lifting and rigging plan.
Licensed driver will be ensured to drive.
Passage of movement will be confirmed to driver.
Crane operator to inspect the area for suitability for staging the crane and space
for extending out rigger.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 45 of 46
Rev No. : B
All the lifting equipment and tackles shall be inspected prior to use. All lifts to be
carried out by competent rigging crew approved by TUV and crane operator,
using proper lifting tackles.
Unloading of the materials should be conducted without standing on the
material.
The entire job should be properly planned and scheduled in advance to inimize
confusion and shortcuts.
Equipment to be in good order and inspected before use by contractor.
Ensure experienced and licensed operators by contractor.
Ensure experienced, competent rigger to control the lifting equipment.
Competent rigger / banks man to attach lifting equipment.
Establish exclusive zone and ensure use of PPE.
Locating of lifting points will be ensured to operator.
Passage of travel will be ensured to operator.
The area under shifting will be cleared without workers and crane to be
relocated at a safe area.
Competent rigger will inspect lifting equipments.
Timber, soft or suitable material shall be used between sling belt and steel
members.
SCAFFOLDING Engage skilled workers for the work.
Inspect all the tools and discard the damaged ones.
Ensure that all workers know use of tool.
Ensure effective supervision and conduct inspection.
Conduct tool box talk prior to starting work to the force by using the TBT (Tool
Box Talks) prompt card. Confirm they all understood the task, hazards and
safety precautions and actions to be taken in case of emergency.
Ensure PTW is processed by authorized and competent persons.
Anchor always to a lanyard.
Provided proper guard rails.
Never ride of scaffold being removed. Make sure that toe boards and handrails
are secure.
Barricade the areas to which objects can fall.
YANBU II POWER & WATER PROJECT
Contract PO No.: 7200 018 725 Method Statement for U/G Piping Installation & Lamination of GRP
Date of Issue: 06 Mar 2012
Doc No. : YT-PF-Z-16-00202Page 46 of 46
Rev No. : B
Don’t permit the workers to enter the barricade area.
All Persons should wear the hard hat and adequate PPE
Provide ladder extension of one meter above landing platform.
Use another person to hold the ladder.
Do not use last 2 top rungs.
Materials should not be pile stocked over the platform.
Good housekeeping should be maintained.
Keep Electrical Cord Wire out of the walk away.
Working platform shall be fully planked and tied properly with to board and guard
rails.
Provide proper size of platform to suit the working area. Only trained and
authorized persons shall work at height.
Follow scaff-tag system to identify the status of scaffolding by the trained and
competent person
EXCAVATION Safe Work Permits and other pertinent documents shall be secured before any
works commence.
Sequence of work shall be discussed during daily toolbox meeting before work
commence.
Equipment and tool inspection must be carried out.
Safety Officer assigned in the area to check safe work plan/excavation permit
prior to actual excavation.
Permit should be placed at the work site.
Excavate in accordance with the approved Work procedure.
Observe proper sloping/benching
Competent Supervisor to oversee actual excavation.
Back-up/reversing alarm of loader, truck, crane, excavation etc. must always in
good condition/operational.
Soft ground / newly backfilled areas must be marked / identified.
Provide adequate and appropriate access for personnel.
Use of full body harness and life line / anchorage point.
Providing physical barricade (scaffold tubes or equivalent).
Install safety warning signs – “Danger Deep Excavation”.