Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including fina ncing (Nobu) Sensor Specs (Nobu)
12

Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Dec 21, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Y. Unno, 2007/2/26

sLHC sensor R&D• Module Plans (Nobu)• Manufacturing plans, including financing (Nobu)• Sensor Specs (Nobu)

Page 2: Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Y. Unno, 2007/2/26

ATLAS06J fabrication• Masks are done• Fabrication is on-g

oing– p-FZ(100)

– p-MCZ(100)

– 3 wafers each

• Delivery– April

• Irradiation– End April

– 70 (or 80) MeV p

Page 3: Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Y. Unno, 2007/2/26

ATLAS07

• 150mm wafer– p-FZ(100)

• n-strip isolation– Individual p-stop

• 4 segments– SS: as is– LS: wire-bond segments

Page 4: Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Y. Unno, 2007/2/26

Stereo?

Page 5: Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Y. Unno, 2007/2/26

Edge stereo connection

Page 6: Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Y. Unno, 2007/2/26

ATLAS07 specification

Page 7: Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Y. Unno, 2007/2/26

ATLAS07• Design

– 2 months+?– by May?

• Fabrication– a few months– depends on quantity

• Financing– Mask cost to be shared– No. wafers=Cost share– Invoices

• Japan: KEK

• Outside Japan: CERN TID

• My big question mark– Readout ASIC?

• Irradiation campaign– CYRIC (70-80 MeV p)

• (April), Aug, Nov,Mar

– PSI (pions)– Neutrons

• Dummy ATLAS07– Al metal only– Who are interested?– How many?– Financing with same mod

el

Page 8: Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Y. Unno, 2007/2/26

ATLASxx plan• 2007 3-5 Design of pre-prototype (Barrels)• 2007 6-9 Fabrication of pre-prototype• 2007 9- Irradiation, Module fabrication a

nd evaluation• 2008 3-6 Design of prototype (Barrels, En

dcaps)• 2008 6-10 Fabrication of prototypes• 2008 10- Irradiation, Module fabrication a

nd evaluation, beamtests• 2010 2 TDR

Page 9: Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Y. Unno, 2007/2/26

Sensor parameters for ASIC

• 1-MeV neq /cm2 • Fluence by particles

Page 10: Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Y. Unno, 2007/2/26

Sensor parameters for ASIC• Constraint from HV

cable rating– 500 V– (1 kV tested)

• Sensor operation– <500 V

• Parameters for ASIC– at 500 V– Preliminary

Page 11: Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Y. Unno, 2007/2/26

Sensor parameters for ASIC

• Preliminary!!!

pFZ initial pFZ 5x1014 pFZ 9x1013 pMCZ Initial pMCZ 5x1014 pMCZ 9x1014

Coupling type to amplifier AC <- <- AC <- <-

Coupling capacitance to amp Total for 2.4, 4.8, 9.6 cm strips

20 pF/cm 48, 96, 192 pF

<- <- 20 pF/cm 48, 96, 192 pF

<- <-

Capacitance of strip to all neighbour strips 1.03 pF/cm <- <- 1.03 pF/cm <- <-

Capacitance of strip to backplane 0.30 pF/cm 0.42 pF/cm 0.48 pF/cm 0.4 pF/cm 030 pF/cm 0.33 pF/cm

Metal strip resistance 15 /cm <- <- 15 /cm <- <-

Bias Resistor 1.5 M <- <- 1.5 M <- <-

Max leakage current per strip for shot noise

2.4, 4.8, 9.6 cm strips

0.5, 1, 2 nA 0.3, 0.6, 1.2 µA 0.5, 1, 2 A 0.5, 1, 2 nA 0.3, 0.6, 1.2 µA 0.5, 1, 2 A

Charge collection efficiency (at 500 V) 1 0.6 0.45 0.6 0.85 0.6

Charge collection time < 10 ns <- <- < 10 ns <- <-

Page 12: Y. Unno, 2007/2/26 sLHC sensor R&D Module Plans (Nobu) Manufacturing plans, including financing (Nobu) Sensor Specs (Nobu)

Y. Unno, 2007/2/26

Module plan• Modules

– have to have– ABCN

• when?

– hybrids• develop along with A

BCN

– fabrication of modules

• time scale uncertain

• Staves– ?