Page 1
© Copyright belongs to the authors. All rights reserved. Please contact authors for citation details.
Analysis of the London Underground PPP Failure
Authored by
Trefor Williams
Working Paper Proceedings Engineering Project Organizations Conference South Lake Tahoe, CA
November 4-7, 2010
Proceedings Editors
John E. Taylor, Columbia University
Paul Chinowsky, University of Colorado - Boulder
Page 2
Proceedings-EPOC 2010 Conference
1
ANALYSIS OF THE LONDON UNDERGROUND PPP FAILURE
Trefor P. Williams1
ABSTRACT
The London Underground Public Private Partnership (PPP) allowed for private sector
consortiums to take over infrastructure maintenance and rehabilitation of the London
Underground system. Private financing was arranged to fund the infrastructure rehabilitation
programs and the PPPs also received annual grants from the government. The PPP arrangements
were contracted for a 30 year period beginning in 2004, yet by early 2010 both private
consortiums had failed and control of the infrastructure had returned to the government. This
paper is a literature survey of the many problems that beset the London PPP, as well as current
thinking about PPPs in general. Topics considered include the financing of the PPPs, the PPP
contract, construction management issues that affected rehabilitation projects, and the
contracting relationships between the PPP consortiums and their parent companies.
KEYWORDS
Public Private Partnerships, infrastructure, contracts, financing
INTRODUCTION
The London Underground Public Private Partnership (PPP) has always been
controversial, from the planning stages of the scheme to the final failure of the partnerships and
their ultimate return to the London Underground public agency (U.K. National Audit Office
2004a, UKNAO 2004b, Gosling 2008). A government report on the feasibility of the PPP
indicated that the scheme would give better value for money than a comparable public alternative
(UKNAO 2000). However, Shaoul (2002) questioned the accuracy of the government’s analysis
of the viability of the PPP scheme before it was implemented.
The primary reasons given by the British government for the implementation of the PPP
scheme was the inability of London Underground, as a public agency, to deliver long term
infrastructure improvements. In the period before implementing the PPP, the London
Underground’s budget for infrastructures projects was re-evaluated every year, so damaging cuts
were often made to the budget for infrastructure renewal projects (UKNAO 2004a). The budget
cuts did not allow London Underground to move forward with major long-term rehabilitation
efforts causing deterioration in the Underground infrastructure.
The goals of implementing the PPP contracts were:
• To provide a more stable funding environment with the private sector obtaining long term
funding.
• Give private sector project management an interest in the projects success over a thirty-year
period.
• Allow the London Underground government agency to retain control of operating the
trains.
1 Professor of Civil Engineering, Center for Advanced Infrastructure and Transportation, Rutgers University,
Piscataway, NJ, [email protected]
Page 3
Proceedings-EPOC 2010 Conference
2
• Deliver projects in a more efficient manner than past methods of project delivery used by
London Underground.
The London Underground PPP was a complex arrangement where the government
agency, London Underground, operated the trains, but three PPP consortiums were set up to
maintain, and rehabilitate the underground infrastructure. Figure 1 shows the complex
relationships between government and private entities and the cash flows from the government
agencies to the private sector. The figure shows several interesting items. First, it indicates that
London Underground made annual “Infrastructure Service Charge Payments” to the PPPs of
approximately £1.1 billion. These service charge payments were made monthly and were
adjusted based on three performance measures. The measures were capability, availability and
(Source: United Kingdom. National Audit Office, 2004) Reproduced under the terms of the
Click-Use License.
Figure 1. Structure of the London Underground PPP
Page 4
Proceedings-EPOC 2010 Conference
3
ambiance. Capability is a measure of the ability of the infrastructure to support train service. It is
based on a passengers average journey time. Availability was a measure of the
The service charge was paid by a grant from the U.K. Department of Transport which
was passed to Transport for London, the parent organization of London Underground and then to
London Underground. Second, it was London Undergrounds responsibility to operate the trains
that were paid for out of fare receipts. Finally, it shows that the PPP consortiums, Metronet and
Tube Lines were responsible for the maintenance, replacement and upgrade of trains, and the
Underground’s civil infrastructure.
The PPP consortiums took over control of the underground infrastructure in 2004. The
PPP contracts were intended to run for thirty years with periodic performance reviews every 7.5
years. Various problems occurred in the implementation of the PPPs and by 2008, two of the
three PPPs (both controlled by a consortium called Metronet) went into bankruptcy when they
became unable to meet their spending obligations. Their failure resulted in London Underground
having to buy 95 per cent of Metronet’s outstanding debt obligations from its private sector
lenders in February 2008 rather than repaying this debt over the 30 years of the contract. The
U.K. Department for Transport made a £1.7 billion grant available to help London Underground
buy out the remaining amount of the private debt. Estimated loses to the taxpayer of the
Metronet failure have been as high as £4.1 billion (UKNAO 2009). The final PPP, Tube Lines,
ended in early 2010. “Tube Lines initially wanted £6.8billion (later reduced to £5.75billion) for a
major programme of renewal on the Piccadilly and Northern Lines, and the arbiter has only
granted the company just under £4.4 billion (Wolmar 2009). This shortfall caused the Tubelines
consortium to go bankrupt and London Underground has bought the consortium’s shares for
£310 million. As of the fall of 2010 control of the entire Underground infrastructure has returned
to London Underground. Controversy still exists around the PPPs as London Underground
contends it can provide infrastructure rehabilitation at a lower cost than the consortiums, while
others believe its costs may be up to a third higher (BBC News 2010, U.K. House of Commons
Transport Committee 2010)
The PPP Structure
PPPs can be defined many different ways and can take on various types of structures. A
general definition of PPPs is that they are “an arrangement of roles and relationships in which
two or more public and private entities coordinate in a complementary way to achieve their
separate objectives through the joint pursuit of one or more common objectives” (Lawther,
2002). A definition of complex infrastructure PPPs is “a long-term contract between the public
and private sectors where mutual benefits are sought and where ultimately the private sector
provides operating services or puts private finance at risk (Garvin 2010).” In the case of the
London Underground a complex PPP structure was required. The London Underground PPP can
be categorized as a Design-Build-Finance-Operate (DBFO) PPP project. A private partner in a
DBFO is responsible for the design, construction, maintenance and operation of a facility. The
DBFO private partner finances the project and is granted a long-term right of access. The public
partner makes service payments to the private partners based on performance metrics (Williams
2003)
Three PPPs were formed. One group of bidders, Metronet, won two of the PPP
consortiums. The companies included in Metronet were Bombardier, W.S. Atkins, EDF Energy,
Page 5
Proceedings-EPOC 2010 Conference
4
Thames Water and Balfour Beatty. The third PPP consortium was called Tube Lines and
included Bechtel and Armey as partners.
Figure 2 shows the detailed structure of the Metronet PPP consortiums and their
relationship to public oversight agencies. Funding came from private debt financing and the
annual infrastructure service charge payment from the London Underground. There was an
arbiter who decided on pricing when disputes occurred. The PPP contract was set up so the
arbiter could award additional funding if the work was considered to be what an economic and
efficient supplier in similar circumstances could charge. In other words, the arbiter could adjust
prices upwards if he considered the request to be reasonable and representing good “value for
money.” The arbiter could make additional award decisions only when requested by the PPP
consortiums or the London Underground. The arbiter had no power to impose changes to the
PPP agreement. The arbiter could also adjust prices during a periodic review that was scheduled
to occur every 7.5 years during the PPP contract (PPP Arbiter 2010).
The PPP contract allowed up to £360 million in contingency to be paid to the PPP
consortium for unforeseen changes in the work. Each consortium was responsible for £50 million
in additional costs each year before they could receive additional compensation. It is important to
note from the figure that although the Department for Transport guaranteed the debt to the
private debt providers, it had no direct oversight of the operations of the PPP.
Purpose of the Paper
The failure of the London Underground PPPs raised many questions about the application
of PPPs to construction projects. Questions have arisen concerning the benefits of the London
(Source: United Kingdom. National Audit Office, 2008) Reproduced under the terms of the
Click-Use License.
Figure 2. Detailed Structure of the Metronet PPPs
Page 6
Proceedings-EPOC 2010 Conference
5
PPP arrangements and the actual cost to tax payers. In addition, project management issues arose
during many of the rehabilitation projects that were related to the nature of the PPP contracts.
The purpose of this paper is to analyze available literature about the London
Underground PPP's failure and the literature about PPPs in general to determine what the causes
of the PPP failures were, and in particular what contractual and project management practices
contributed to the PPP's failure. The paper will focus on problems with infrastructure projects
conducted by the PPP.
SOME BACKGROUND LITERATURE ON PUBLIC PRIVATE PARTNERSHIPS
In theory a PPP can provide improved service quality, risk sharing with the private sector,
and cost savings (Bloomfield 2006).. There is some disagreement concerning the effectiveness of
PPPs in achieving these goals. This may be caused to some extent because PPPs have been
applied to many different types of projects, with the projects varying greatly in scope, contract
type and length. Hodge and Greve (2009) state that evaluations of public–private partnerships
thus far point to contradictory results regarding their effectiveness and value-for-money. They
state, “Despite continuing political popularity, greater care is needed to strengthen future
evaluations...” They also analyzed available literature that assessed the value for money
outcomes of various PPPs. They conclude that there is both supporting and opposing outcomes
reported for PPP projects and that there is a need for a more rigorous financial analysis of the
benefits of using PPPs.
Kwak et al. (2009) have determined through a literature survey that the success or failure
of a PPP project is dependent on four groups of factors: the competence of the government, the
selection of an appropriate concessionaire, an appropriate risk allocation between the public and
private sectors, and a sound financial package, The problems with the London Underground
PPPs centered on the allocation of risk between the government and private sector and the ability
of the government agencies to appropriately monitor the private participants.
Many PPPs have been successful. Garvin (2010) discusses the latest techniques used in
Europe and states that for highway transportation projects governments in Europe governments
have developed a large body of experience to deal with the implementation of PPPs. The
increased use of PPPs in the United States is also advocated. Bloomfield (2006) reports on the
success of a waste water treatment PPP in Seattle. The U.K. National Audit Office (2003) has
reported on the performance of Private Finance Initiative (PFI) Projects, a British government
PPP program. These PPPs as being delivered on time far more often than traditional
infrastructure contracting arrangements. They reported that where traditional public
infrastructure provision arrangements are on-time and on-budget 30% and 27% of the time,
British PFI public private partnerships are on-time and on- budget 76% and 78% of the time,
respectively. Possibly, successful PPP projects are not as complex as the London Underground
PPP, are more clearly defined, with distinct life-cycle phases. It was also concluded that the PPP
projects provided the contracting government agencies with more price certainty and that the
facilities constructed had good quality. PFI projects that have had problems usually suffer from
poor project definition and poor management (Major Project Association 2003)
Unlike a highway project where it is typically new construction that is well defined, the
London Underground PPP was in essence “open-ended,” with various projects spread out over a
planned 30-year period. Because there was uncertainty as to what the projects would include this
Page 7
Proceedings-EPOC 2010 Conference
6
contributed to the failure of the PPPs. The London Underground PPP was not created for a single
project unlike many PPPs but was created to conduct many products spread out over time and
location vastly increasing the PPPs’ complexity.
A project similar to the London Underground PPP, the Madrid-Barajas International
Airport project has been discussed by o and Vassallo (2009). The project involved the
extension of an existing subway line with maintenance of the line to be handled by the PPP and
operation of the line handled by the government agency responsible for the subway system. They
conclude that this “nonintegrated” approach, with a separation of the responsibilities for
operation and maintenance is beneficial for urban railway projects. They conclude that from the
point of view of the government, nonintegrated PPPs have the advantage of boosting competition
in the bidding process, and subsequently reduce monopolistic power over an integrated PPP
where the PPP will both operate and maintain the urban railway. For urban rail users, a
nonintegrated approach has the advantage that it does not involve a breakdown in transportation
service. As users strongly penalize transportation changes, this promotes a greater use of public
transportation. A particular difference between the two PPPs is the difference in scope of the
projects, and the fact that the Spanish project was new construction.
Perhaps, the size and complexity of the London Underground PPPs, differing from the
Spanish PPP where a single project for a relatively short section of a subway line, indicates why
problems were encountered with the London Underground PPP. In addition, although the
London Underground was operated in a “nonintegrated” way, there were disputes between the
London Underground and the PPPs concerning line closures for access to tunnels and stations for
construction work.
Some literature relates to the problems inherent in large and complex PPP arrangements
like the London Underground. Vining and Boardman (2008) hypothesize that there is an inherent
conflict in complex PPPs that can cause difficulties between project partners. They state that
there is a divergence of goals between public and private partners with the private sector seeking
to maximize profits and the government agency seeking to minimize current cost, on balance
sheet debts and political costs. Studies have shown that when inter-organizational conflict is
present in it often leads to opportunistic behavior by one or both parties, high contract bargaining
costs, failure to achieve project goals and the breakup of the partnership.
Bloomfield (2006) has suggested that long term PPP contracts need to be approached
with caution and that it has often been recognized that business transactions between government
and private companies are more likely to serve public objectives when competition is robust,
when measurable performance requirements can be specified in advance, when the contractor
can be readily replaced, and when the transactions are transparent. Due to the size of the London
Underground PPP project competition was limited to only a few large consortiums with the
resources to enter into the complex negotiation project. Upon taking over the operation of the
Underground the consortiums could not be readily replaced. The transactions involved in the
London Underground were criticized for lack of transparency with great uncertainty still existing
concerning the consortiums transactions and profits (UKNAO 2009). The very large and
complex nature of the London PPP, the complex negotiations that were necessary to develop the
contracts and the lack of transparency concerning the financial dealings contributed to its failure.
Page 8
Proceedings-EPOC 2010 Conference
7
LONDON UNDERGROUND PPP PROBLEMS
In this section the various problems that plagued the London Underground PPP are
discussed. In particular, issues related to how the PPPs were financed, their contracts and
operational problems that arose during construction problems are discussed.
Failure of Consortium Management and Lack of Governmental Control
British government reports assign most of the blame for the PPP failure to the
consortiums poor internal management (UKNAO 2009). In the case of Metronet, the
management changed frequently and found it difficult to manage the work of its shareholders.
The U.K. National Audit Office report states:
These suppliers had power over some of the scope of work, expected to be paid
for extra work undertaken and had better access to cost information than the
management. The poor quality of information available to management,
particularly on the unit costs of the station and track programmes, meant that
Metronet was unable to monitor costs and could not obtain adequate evidence to
support claims to have performed work economically and efficiently (UKNAO
2009).
In the case of Metronet, its internal structure did not give it access to the required cost and
management data of it component companies as they conducted the rehabilitation projects.
In addition to the problems with consortium management, additional problems existed
with the control the government could exert over the PPP. The arrangements for the London
Underground PPP were dictated in part by the move in the United Kingdom to devolve power
from the central government to local governments. Control of the London Underground was
devolved from the U.K Department of Transport to the Mayor of London and an agency called
Transport for London. This agency was responsible for the London Underground. The
Department of Transport had guaranteed the private loans yet had few ways of controlling the
PPP when problems occurred. The Department of Transport relied on the London Underground
and Transport for London to monitor the projects for financial risk. Yet London Underground
pursued a rigorous interpretation of the contract scope which tended to increase costs. However,
in the case of Metronet, London Underground had difficulty obtaining information and cost data
which would have allowed it to more closely monitor costs and to understand the effect of its
interpretation of the contract scope on project cost increases. In addition, London Underground
lacked the information that would have allowed it to take more of a “partnering” approach with
the consortiums (UKNAO 2009). It can be concluded that Transport for London and London
Underground did not have enough information about project performance to provide oversight
and control over the PPP consortiums activities.
Financing Issues
A controversial part of the PPP arrangement was the use of private debt to finance the
PPPs and if this actually provided cost savings to the government. One critic of the financing
arrangement stated:
Page 9
Proceedings-EPOC 2010 Conference
8
"... You'll often find public quotes saying that the PPP or PFI enables the private
sector to step in and provide infrastructure that the taxpayer cannot afford...
Whether it's deliberate or not, I don't know, but it's a delusion. What you are
doing is delaying paying for something - it's like public borrowing of other kinds,
where the state issues gilt-edged securities but repays them out of future
taxation."(Stephen Glaister, quoted in Professional Engineer, August 13, 2008)
It has been argued that the cost of private borrowing was greater then the cost of issuing public
debt. Some, critical of the PPP arrangement, have argued that rather than borrowing capital at
between 4-5%, which was the going rate for government debt, the PPP companies borrowed
from their shareholders and their banks at a rate of 20%. A public accounts committee report
says this added £450 million to the cost of the PPP contracts, in addition to the £450 million cost
of deciding the contracts, with legal bills (Professional Engineer 2008).
The PPP projects had high debt to equity ratios, with approximately 88.3% debt to 11.7%
equity. Therefore, most of the funding contributed by the PPPs was in the form of private debt
with a relatively small amount of equity risk borne by the PPP consortium members. The small
amount of equity risk provided less of an incentive for the PPPs to perform. In addition, the
government guaranteed 95% of the private debt in the case of bankruptcy by the PPPs (Vining
and Boardman 2008).
The five Metronet participants split the equity requirement of £350 million between
them. This amounted to approximately £250 million after taxes on bankruptcy. This was not a
huge write-off for these large corporations. Furthermore, these firms were major suppliers to the
project. Metronet received £3 billion in service charges from 2003 to 2007, or approximately
60% of all capital expenditures. A large percentage of this was passed on to Bombardier or to
Trans4m, a stand-alone corporation owned by the other four equity partners (Vining and
Boardman 2008). Trans4m was the group of consortium partners that performed the
infrastructure renewal work.
The ways in which the consortiums financing were structured, and the high interest rates
for private finance may have increased project costs. Perhaps the high interest rates the
consortiums accepted from the financiers indicate the risk and uncertainty surrounding the PPP.
Potentially, financing the project through the government using a traditional method like a bond
issue could have reduced borrowing costs. In addition the guarantee of the private debt by the
Department of Transport tended to significantly reduce the consortiums financing risk. Yet, the
contract was structured in such a way that the Department of Transport had little authority to
intervene in the PPP activities.
Contract Incompleteness and Risk Transfer
Soliño and Vassallo (2009) discuss the difference between economically efficient
contracts and incomplete contracts. Contracts have ex-ante and ex-post efficiencies. An
inefficient contract has ex-post inefficiencies because they oblige an exchange to happen
regardless of the ultimate benefit to be achieved by the parties. Ex-ante and ex-post efficiency
are in tension when parties contract under uncertainty. It may turn out, for example, that the
value of the contract performance to the government agency is less than the value of the private
PPP consortium’s cost of performance. A solution to the dual objective of ex-ante and ex-post
Page 10
Proceedings-EPOC 2010 Conference
9
efficiency is setting up a complete contingent contract, which is able to specify obligations in
each potentially possible state of the world and is enforceable according to its terms. Such a
contract ensures that performance occurs when, but only when, it is efficient. However, in
practice many contracts are incomplete. These contracts often do not specify the parties’
obligations in all possible states of the world. One of the major reasons incompleteness occurs
because there is not enough information at the time of signing of the contract.
Contract incompleteness occurred for the London Underground PPPs. London
Underground was aware that the condition of less accessible infrastructure and facilities would
not be known before the award of contracts. “The uncertainty meant that bidders sought
protection from the consequences of adverse conditions exceeding prudent levels of contingency
(UKNAO 2004a).” An example of the contract incompleteness is related to the refurbishment of
stations.
Vining and Boardman (2008) contend that the government and the PPP consortiums
disagreed on the fundamental nature of the contracts. The government believed it had purchased
an output based fixed price contract and the private consortiums behaved like it had agreed to a
series of heterogeneous cost plus projects. In successful PPPs the risk allocation between
partners should be worked out before the contract is signed (Bing 2005). Clearly this was not
accomplished for the London Underground PPP due to its complexity.
The PPP contract stated that the extent station refurbishments could be classified as
modernization, refurbishment or enhanced refurbishment. These terms were not well defined in
the PPP contract, and resulted in disagreements between Metronet and London Underground
over what level of rehabilitation should be conducted at a station (UKNAO 2009). In addition,
the PPP contracts may not have transferred sufficient risk to the private PPPs. Many aspects of
the London Underground PPP contracts reduce the risks the private consortiums must bear. A
House of Commons committee concluded (U.K. House of Commons, Committee of Public
Accounts 2005):
There are caps, caveats and exclusions to project risks borne by the Infracos. The
risk of cost overruns in repairing assets of unknown condition, such as tunnel
walls, is excluded because knowledge of their residual life and associated costs is
incomplete. In the case of assets whose condition has been fully identified against
specific engineering standards, the cost overruns that the Infracos have to bear are
capped, so long as the Infracos can demonstrate that they are acting economically
and efficiently... There is no definition of economic and efficient behavior in the
contracts; an independent arbiter can make a ruling if asked. Exclusions to the
risks borne by the Infracos include passenger demand, lower income with fewer
users and capacity constraints in the face of increased use. These are borne by
London Underground.
This finding indicates that the design for various infrastructure rehabilitation projects could not
be fully specified at the time of the contract signing due to uncertainty in existing conditions.
Therefore, the contract required these risks to be assumed by the government agency. The lack of
definition of what economic and efficient behavior by the private sector infrastructure companies
was which lead to disagreements when funds were requested for additional work. It is essential
with the huge financial stakes a PPP entails that the contract be technically optimal, but also
allow for transparency and clarity (Hodge 2004).
Page 11
Proceedings-EPOC 2010 Conference
10
Contracting Methods for Infrastructure Projects
Metronet and Tube Lines employed different methods of contracting out rehabilitation
projects. Metronet used practices which were sharply criticized because they favored the parent
companies of the consortium. Tube Lines contracting practices were seen as more open and it
was less criticized.
The Tied Supply Chain
The PPP consortium was responsible for letting a large number of projects for major
infrastructure rehabilitation including the refurbishment and modernization of many stations.
These projects involved installing better lighting, décor, elevator access, waiting facilities, public
address and closed-circuit television to enhance safety and the physical environment (Sibley
2009). Other major projects included the upgrade of signaling systems for various underground
lines.
In particular the UKNAO (2009) in its report on the Metronet failure criticized Metronet
for using a “Tied Supply Chain” to deliver the infrastructure contracts and concluded that the
poor management of these arrangements were the primary cause of Metronet’s failure. The
shareholders of the Metronet were also the suppliers of the infrastructure rehabilitation projects
in a tied supply chain, and they adopted governance and management structures which gave
power to the suppliers rather than the management of the Metronet business. Metronet’s
management was unable to extract key information or incentivize suppliers to perform their roles
in line with its own interests (UKNAO 2009). This arrangement gave little incentive to the
suppliers of the infrastructure refurbishment to behave in an efficient manor or to hold down
costs.
Figure 3 shows the structure of the Metronet Tied Supply Chain. The figure shows that an
organization called Trans4m was formed to be the contractor for all civil infrastructure projects.
Trans4m consisted of four of the Metronet PPP consortiums members and was awarded all of the
station and civil works projects let by Metronet. It has been suggested that the participants in the
PPP consortium may have actually had limited losses, even though Metronet went bankrupt,
because of the money which was paid to the parent companies through the “tied supply chain.”
Tube Lines Experience
Tube Lines used a more open process to select contractors to perform rehabilitation
projects. The Tube Lines approach was based on procuring the contractors for individual
contracts through open competition. Tub Lines approach to letting the infrastructure contracts
changed over time as more experience was gained. Initially, a traditional design-bid-build model
was employed. The low bidding contractor typically used subcontractors for most of the work.
Tube Lines found that the use of many subcontractors increased communication time when
problems arose, the station rehabilitations required many design changes and that scope issues
often arose with London Underground. Over time, Tube Lines began acting as a construction
manager with work packages let to the different specialty subcontractors (Sibley 2009). This was
found to be more efficient.
Page 12
Proceedings-EPOC 2010 Conference
11
Tube Lines also experienced some criticism of its contracting practices. A House of
Commons report (U.K. House of Commons Transport Committee 2010) stated “We are
concerned, however, that there may be a temptation for Tube Lines to award projects to its parent
companies for which they do not possess the required expertise. Such practices may have
contributed to delays on the upgrade.”
Approvals and Communications
Many projects had problems with developing appropriate lines of communication
between the public and private partners for approvals and permits. Although there was a single
London Underground contact designated in the PPP contracts, case studies found that for
individual station rehabilitation projects many different approvals were required from several
branches of the London Underground organization (UKNAO 2009). This indicates that various
processes could have been implemented to help control the infrastructure rehabilitation contracts.
Using a configuration management process and clearly establishing lines of communication for
the relationship between private participants and government agencies could have corrected the
problems with approvals.
It has been recommended that more attention be paid to the management of relationships
between private and public participants in a PPP. Smyth and Edkins (2007) advocate a shift from
relational contracting to a relationship management approach that fosters proactive collaboration.
This paradigm shift could have reduced communications delays between the partners.
(Source: United Kingdom. National Audit Office, 2008) Reproduced under the terms of the
Click-Use License.
Figure 3. Metronet “Tied Supply Chain”
Page 13
Proceedings-EPOC 2010 Conference
12
CONCLUSIONS AND DISCUSSION
This survey of literature related to the failure of the London Underground PPPs indicates
it was an extremely complex undertaking with many factors that affected the ultimate outcome of
the partnerships. The literature indicates that there were several primary factors that caused the
failure:
• The consortiums lacked good management data, and were unable to provide government
agencies responsible for oversight with good data about cost performance.
• The PPP contract required many different individual construction projects to be conducted
over a long time period. However, the PPP contract could not fully specify these projects at
the time of contract signing because there were many unknowns about the condition of the
existing infrastructure. The PPP contract at times offered vague wording that led to
disputes and conflicts later.
• The British Department for Transport guaranteed the private debt and had to pay £1.7
billion when Metronet failed, yet it had little say in the oversight of the PPP consortiums.
The guarantee of the private debt greatly reduced the financial risk to the consortiums.
• The tied supply chain method of letting rehabilitation projects did not transfer risk to the
contractors performing the work. Tube Lines later found more success in the rehabilitation
projects by acting as construction manager.
The London Underground PPP had many problems, yet many have reported good results using
PPPs. Many PPP projects are of a more limited scope and involve the construction of a single
new facility. Rather then forming large PPP consortiums to do all of the infrastructure
rehabilitation projects for the London Underground it may have been more appropriate to use a
PPP structure for individual infrastructure rehabilitation projects. This would make the individual
infrastructure projects more competitive because the project is no longer tied only to one large
consortium with a long-term contract. In addition, the project estimates will be more accurate
and timely because they will be done at the time of the project initiation rather than a few years
previously when the consortium contracts were signed. Additionally, overall financial risk will
be reduced because only individual projects are included in the PPP arrangements rather than
large portions of the Underground system with the need for large amounts of debt. The British
government has had considerable success with PPPs using the PFI initiative. It is logical to
assume that the knowledge from that program could be extended to the London Underground
infrastructure work. It is possible to conclude that the London Underground PPPs were not a
failure of the PPP form of contract, rather they were an inappropriate application of PPP because
the undertaking was so complex.
REFERENCES
BBC News (2010) “Tube Maintenance Work Deal Agreed.” <
Bing, L., Akintoye, A., Edwards, P., and Hardcastle, C. (2005). "The allocation of risk in
PPP/PFI construction projects in the UK." International Journal of Project Management,
23, 25-35.
Bloomfield, P. (2006). "The challenging business of long-term public–private partnerships:
reflections on local experience." Public Administration Review, 66(3), 400-411.
Page 14
Proceedings-EPOC 2010 Conference
13
Garvin, M. (2010). "Enabling Development of the Transportation Public-Private Partnership
Market in the United States." Journal of Construction Engineering and Management,
36(4), 402-411.
Gosling, P. (2008) "PFI: Against the public interest." Unison, London, UK
<http://www.unison.org.uk/pfi/docs_list.asp> (March 10, 2010).
Hodge, G. (2004). "The risky business of public–private partnerships." Australian Journal of
Public Administration, 63(4), 37-49.
Hodge, G., and Greve, C. (2009). "PPPs: The Passage of Time Permits a Sober Reflection."
Economic Affairs, 29(1), 33-39.
Kwak, Y., Chih, Y., and Ibbs, C. (2009). "Towards a comprehensive understanding of public
private partnerships for infrastructure development." California Management Review,
51(2), 51-78.
Major Projects Association (2003) “Overview of the MPA’s 21st Annual Conference: PFI/PPP
Projects – are they working?”
<http://www.majorprojects.org/knowledge/pasteventsknowledge.php> (October 10,
2010).
PPP Arbiter (2010) “The Role of the PPP Arbiter.”
<http://www.ppparbiter.org.uk/output/page16.asp> (October 12, 2010).
Professional Engineer (2008). "Mind the gap." 21(14), 27-28.
Shaoul, J. (2002). "A financial appraisal of the London Underground public-private partnership."
Public Money & Management, 22(2), 53-60.
Sibley, K. (2009). "New approach puts Tube station upgrade back on track." Proceedings of the
Institute of Civil Engineers-Civil Engineering, 162(7), 35-41.
Smyth, H., and Edkins, A. (2007). "Relationship management in the management of PFI/PPP
projects in the UK." International Journal of Project Management, 25, 232-240.
Soliño, A., and Vassallo, J. (2009). "Using Public-Private Partnerships to Expand Subways:
Madrid-Barajas International Airport Case Study." Journal of Management in
Engineering, 25(1), 21-28.
United Kingdom: National Audit Office (2009). The failure of Metronet: Department for
Transport. The Stationary Office, London UK.
United Kingdom. National Audit Office (2000). The financial analysis for the London
Underground public private partnership. The Stationary Office, London UK
United Kingdom. National Audit Office (2003) PFI: Construction Performance, The Stationary
Office, London UK.
United Kingdom. National Audit Office. (2004a). London underground: are the public private
partnerships likely to work? The Stationary Office, London UK.
United Kingdom. National Audit Office (2004b). London underground PPP: were they good
deals? The Stationary Office, London UK.
United Kingdom. House of Commons, Committee of Public Accounts. (2005). London
underground public private partnerships (Seventeenth Report of Session 2004-2005).
The Stationary Office, London UK.
United Kingdom. House of Commons, Transport Committee (2010) Update on the London
Underground and the public-private (PPP) partnership agreements (Seventh Report of
Session 2009–10). The Stationary Office, London UK.
Vining, A., and Boardman, A. (2008). "Public--Private Partnerships: Eight Rules for
Governments." Public Works Management & Policy, 13(2), 149.
Page 15
Proceedings-EPOC 2010 Conference
14
Williams, Trefor P. (2003). Moving to Public-Private Partnerships: Learning from Experience
Around the World. New Ways to Manage Series. Washington, DC: IBM Endowment for
the Business of Government.
Wolmar, Chrisitan (2009). “Tube PPP reaches the end of the line.” The Guardian, December 18.
<http://www.guardian.co.uk/commentisfree/2009/dec/18/tube-ppp-upgrade-london-
underground> (July 23, 2010)