Working Group/Observational Data (Satellite Data) Fall 2017 COPC Co-Chairs: Mr. Vincent Tabor, NOAA/NESDIS Mr. Jeffrey Ator, NOAA/NCEP Exec. Secretary: Mr. Anthony Ramirez, OFCM
17
Embed
Working Group/Observational Data (Satellite Data) Fall ...
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
WG/ODFall 2017 COPC
Co-Chairs: Mr. Vincent Tabor, NOAA/NESDIS Mr. Jeffrey Ator,
NOAA/NCEP Exec. Secretary: Mr. Anthony Ramirez, OFCM
2
SMAP 557th NESDIS Data incorporated into SMOP data
Closure
Implementation
Megha-Tropique SAPHIR Level 1a and 1b radiances* (*understood to be
data of opportunity only)
FNMOC/ 557th
Implementation
ScatSat FNMOC NESDIS N/A Access Approval (data not yet acquired -
TBD)
SMOPS 557th NESDIS July 2017 via DAPE and PDA
Closure
3
MODIS AMSU/AIRS (343- channel)
Closure
Sentinel-3A NESDIS NAVO November 2017 via DAPE
Implementation
4
IceCube FNMOC NESDIS N/A Access Approval (data not acquired –
ESPC
System owner pushed request back to CSAB)
Tropics FNMOC NESDIS N/A Access Approval (data not acquired –
ESPC
System owner pushed request back to CSAB)
CYGNSS Level 1b and level 2 Ocean Surface Wind Data
FNMOC NESDIS N/A Access Approval (data not yet acquired -
TBD)
Satellite Data Requests (unfunded no current NESDIS
requirements)
Phases: Access Approval, Change Approval, Implementation,
Closure
5
GOES-16 (16-ch, including vis, IR, and WV)
FNMOC 557 WW TBD Formal request to AF/A3W in draft
METEOSAT-11 (same channels and resolution as MET-10)
FNMOC 557 WW TBD Formal request to AF/A3W in draft
Atmospheric Motion Vectors (AMV) Software and Support
FNMOC NESDIS- STAR
Satellite Data Requests Phases: Access Approval, Change Approval,
Implementation, Closure
6
NESDIS/DAPE and FNMOC staffs made the switch to the new DART
distribution server at FNMOC. This new server is expected to be a
more relevant, timely, and effective way for data transfers.
NESDIS requested Sentinel-3A Sea Surface Height Anomaly data for
use in Ocean Heat Content (OHC) system. These data are now being
delivered to the DAPE. DAPE need to now set up transfers of these
data to PDA. NAVO is looking at pushing these data directly to
PDA.
Firewall form to allow them to pushed these data to PDA has been
made available to NESDIS network staff Network staff is waiting for
JPSS freeze to be lifted so that
necessary changes can be made. Transfer data rate testing
NESDIS has approved Work Request (WR) to conduct transfer data rate
testing with NAVO and other OPC and plan to start testing
soon.
These tests should give WG/OD a baseline for MFG tests in the
future.
Recent Activities
DAPE Gateway Statistics April 2017 to September 2017
Apr May Jun Jul Aug Sep From 557th WW 29.5 30.4 29.7 30.7 15.6 0.2
From FNMOC 346.8 324.9 315.9 350.8 332.8 344.6 From NAVOCEANO 0.1
0.1 0.1 0.1 0.1 0.1
Apr May Jun Jul Aug Sep To 557th WW 4231.1 4406.6 4265.3 4423.3
4430.4 4286.0 To FNMOC 6534.1 6807.0 6591.7 6833.0 6855.9 6600.9 To
NAVOCEANO 891.7 908.1 879.0 911.0 927.1 882.9
0.0
50.0
100.0
150.0
200.0
250.0
300.0
350.0
400.0
From 557th WW
To 557th WW
Sheet1
Jan-10
Feb-10
Mar-10
Apr-10
May-10
Jun-10
Jul-10
Aug-10
GB
GB
GB
GB
GB
GB
GB
GB
891.7
908.1
879.0
911.0
927.1
882.9
From 557th WW Apr May Jun Jul Aug Sep 29.5 30.4 29.7 30.7 15.6 0.2
From FNMOC Apr May Jun Jul Aug Sep 346.8 324.89999999999998
315.89999999999998 350.8 332.8 344.6 From NAVOCEANO Apr May Jun Jul
Aug Sep 0.1 0.1 0.1 0.1 0.1 0.1 #REF! Apr May Jun Jul Aug Sep 1 To
557th WW Apr May Jun Jul Aug Sep 4231.1000000000004
4406.6000000000004 4265.3 4423.3 4430.3999999999996 4286 To FNMOC
Apr May Jun Jul Aug Sep 6534.1 6807 6591.7 6833 6855.9 6600.9 To
NAVOCEANO Apr May Jun Jul Aug Sep 891.7 908.1 879 911 927.1
882.9
Sheet3
8
CIP Activated on September 13, 2017 Activated for product
generation and validation
Fail-over (Mini Test) Planned for December 2017 No product
transferred during this test OSPO will test the firewalls OSPO will
test College Park ability to access internet
during fail-over CIP staff is now planning how to operate and make
some
CIP products available to CBU via the CIP
ESPC CIP Fail-over
Note – CIP is Critical Infrastructure Protection (i.e. COOP site)
for ESPC that functions as a transparent backup for the most
critical ESPC data services.
9
CBU was activated on October 4, 2017 JPSS/S-NPP only Users needed
to get S-NPP from CBU during the
activation Pull users needed to make a switch to point to the
CBU Push users should not have to make a change
CBU Activation
Jason-2 Jason-2 geodetic orbit achieved on July 12, 2017. NAVO
commenced operational delivery of Jason-2 geodetic SSHa
products on August 15, 2017. The Jason-2 geodetic data is
degraded/less accurate but does add value.
These non-repeat observations will overlap with other altimetry
satellites; therefore the overall SSHa coverage will be less.
Jason-2 went into safe-hold mode due to gyro issues from 14 Sept -
11 Oct 2017. NAVO resumed wind/wave and SSH deliveries on 13 Oct
2017. The Jason-2 team is working to improve data
availability.
10
Sentinel-3A NAVO commenced operational delivery of Sentinel 3a wind
wave products
to FNMOC on June 12, 2017. To address delivery of the SSHA data to
NOAA Ocean Heat Content
system, two methods are being pursued. A Configuration Change
Request (CCR) was submitted by NESDIS to modify
the DAPE Gateway to grab the Sentinel-3A SSHa files and send them
to PDA. NAVO is also setting up a PDA account/connection to deliver
the SSHA
products directly.
11
GOES-16 GOES-R became GOES-16 when it reached geostationary orbit
(day 14) Satellite currently positioned at 89.3° W longitude for
checkout and
validation (expected duration 1 year) GOES-16 to be moved to 75.2°
W (see transition presentation GOES-13
turned off December 14, 2017 and placed in storage January 2, 2018)
Concerns include data availability and planning continues to
transition
legacy GOES-13 AMV to new DMV BUFR product (new meta data, tables
and parameters). Time is needed to transition and implement data
assimilation changes with the new algorithms. Data currently being
acquired and evaluated from NOAA STAR for risk
reduction purposes Transition to OPS and PDA scheduled for mid
November
12
13
Meteosat-8
Meteosat-8 arrived at 41.5° E on 21 September 2016 Meteosat-8
became primary IODC mission on 1 February 2017 NOAA receives these
data from
EUMETCast terrestrial-based multicast service (NESDIS STAR) Secure
terrestrial point-to-point protocols (EUM MMDS → PDA) WMO GTS
circuits (EUM → GTS → WSH RTH)
EUMESAT Ocean and Sea Ice Satellite Application Facility (OSI SAF)
is making Met-8 SST data available at the JPL Physical Oceanography
DAAC which NAVO has acquired
OPCs have coordinated access methods and exchange protocols
14
Mission Partner (Federated) Gateway
WG/OD standing by to assist as required by gathering representative
proxy data to test the operational effectiveness of the gateway –
reference COPC action item
Product Distribution and Access (PDA) Release 3 (JPSS-1 and other
fixes/improvements) went into ops in October DDS data transition to
PDA is complete (critical weather slowed progress) PDA has gone
down outside of 8 x 5 and push users has lost data. OPCs
may want to considered being pull user for control DDS-CIP
transition; kick-off meeting to sync certain
KPP-like/critical
products occurred recently Hope to finish project by Q2/FY18
Other Activities
DOD Follow-on Efforts
Gap-Fillers Prior to WSF Operationally Responsive Space Mission 6
(ORS-6) Tech Demo
Ocean Wind Vector Radiometer; Launch: 4QFY18 Operationally
Responsive Space Mission 8 (ORS-8) Ops Prototype
Early Morning Polar; processing architecture TDB; Launch:
FY21
Weather System Follow-On (WSF) Polar E-O/IR (WSF-E); Launch: FY24
Geostationary (WSF-G); Relocate Residual GOES to IO region
(~FY20) mitigates anticipated end of life of Meteosat-8 in 2019
Polar Microwave (WSF-M); Launch: FY23
DMSP sustainment continues
COSMIC 2A and 2B
Per joint NOAA and Taiwan Ministry of Science and Technology
memorandum The two agencies concluded they would not pursue
development of a second
set of six Constellation Observing System for Meteorology,
Ionosphere, and Climate (COSMIC) 2 satellites -- COSMIC-2B
Cancelled
COSMIC-2A (initial set of 6 satellites) has been built and is
scheduled for launch as part of the U.S. Air Force’s Space Test
Program 2 mission, launching on a SpaceX Falcon Heavy in early
2018.
Air Force will supplement NOAA data capture with MARK-IVB
17
Slide Number 2
Slide Number 3
Slide Number 4
Slide Number 5
Slide Number 6
Slide Number 8
Slide Number 9