    FUTURE FOR ALL FOUNDATION (FFAF)

    STRATEGIC PLAN

    2009 - 2011

    Contact:

    Mr. Auberon Jeleel OdoomExecutive FundraiserFuture for All FoundationP. O. Box GP 20950, AccraGhana-W/Africa

    Phone: (233) 24 238 1376 / (233) 20 815 1523E-mail:[email protected]

  • 8/14/2019 Workable Strategic Plan Document

    2/31

    1

    Growth through Soccer

    A not-for-profit organisation committed to improving the lives of under privileged and street

    children living in the Ablekuma North District with the talent to be professional footballers. We

    achieve this by providing support for their formal education and football coaching

    o Accountability: Act with integrity and maintain the highest standards of ethicso Volunteerism : We promote a spirit of volunteerism and volunteer leadershipo Education : We believe in formal education as the bedrock of being a career footballero Respect : We value the contribution of everybodyo Professionalism: We strive to do the right things and things right

    Mission Statement

    Vision Statement

    Core Values

  • 8/14/2019 Workable Strategic Plan Document

    3/31

    2

    1)To assist and support the youth who are less privileged but are talented to beprofessional footballers

    2)To support the parents of the less privileged but talented youth with the education oftheir children so the children can be literate enough to comprehend the issues

    relating to football

    3)To make footballers literate with respect to the games regulation and administration

    L ong-T erm Objectives

  • 8/14/2019 Workable Strategic Plan Document

    4/31

    3

    SWOT ANALYSIS

    STRENGTH (Internal) WEAKNESS (Internal)

    S1: Experienced Football Administration Volunteers

    S2: Well Networked and Committed Volunteers

    S3: Knowledge of Local Community

    S4: Support from Parents of the Underprivileged

    S5: Flexibility and Adaptability. Little Bureaucracy

    W1: Lack of Funding and Unreliable Cashflow

    W2: Lack of Legal Recognition with Ministry of Social

    Welfare and District Assembly

    W3: Lack of Database for Record Keeping

    W4: Poor monitoring system

    OPPORTUNITIES (External) THREATS (External)

    O1: Tax Exemption On Imported Donations In Kind

    O2: Trust Bill- Legitimacy Of Operations

    O3: Public Interest in funding Grassroots football development

    O4: An Improving and Enabling Environment for football

    Related NGOs

    O5: Partnership With District Assembly

    O6: Existence of a Local Juvenile Club (Talent Stars) as a

    Project

    T1: New Regulation The Trust Bill

    T2: Opposition from Supposed Player Managers

    T3: Inadequate Support from Donors.

    Environmental Scanning

  • 8/14/2019 Workable Strategic Plan Document

    5/31

    4

    SWOT/PEST GRID

    S W O T

    P o Lack of LegalRecognition With

    Ministry of Social

    Welfare & District

    Assembly

    o Trust Bill-

    Legitimacy of

    Operations

    o Partnership With

    District Assembly

    o Tax ExemptionOn Imported

    Donations In Kind

    o New

    Regulation

    The Trust Bill

    E o Lack of Funding andUnreliable Cashflow

    o Public Interest infunding Grassroots

    football

    development

    o InadequateSupport From

    Donors

    S o Well Networked Volunteerso Support from Parents of the

    Underprivileged

    o Experienced FootballAdministration Volunteers

    o Knowledge of Local

    Communityo Flexibility and Adaptability:

    Little Bureaucracy

    o An Improving andEnabling

    Environment for

    Football- RelatedNGOs

    o Existence of a

    Local JuvenileClub (Talent Stars)

    as a Project

    o Opposition

    from

    Supposed

    PlayerManagers

    T o Lack of Database forRecord Keeping

    o Poor monitoringsystem

  • 8/14/2019 Workable Strategic Plan Document

    6/31

    5

    THE STAKEHOLDER ANALYSIS MATRIX

    Stakeholder Expectat ions What IfExpectat ions Not Met

    Level OfSignificance

    1, 2 & 31-low, 3-high

    Local Community Cooperation Reputation risk 3

    Media Information on activities / work Limited Impact 2

    Parents of the Youth Fulfill Agreement Loss of Credibility 2

    The Youth Sponsorships Dissatisfaction 3

    Registrar Generals Department Compliance with State Regulations Sanctions 2

    Department of Social Welfare Compliance with State Regulations Sanctions 3

    Accra Metropolitan Assembly Legitimacy of Existence & work Sanctions 1

    Donors Abide by Agreement Withdrawal of Support 3Board Members Achievement of Objectives,

    Accountability and Credibility

    Withdrawal of Service 2

    Volunteers Transparency and Work to be done Withdrawal of Service 3

    Affiliation Bodies Honour Obligations Membership Withdrawal 1

    Employees Compensation and Wellbeing Staff dissatisfaction andHigh attrition rate

    3

    o Human Resource-Volunteerismo Fundingo Regulatory Issueso Financial Management

    Key Issues

  • 8/14/2019 Workable Strategic Plan Document

    7/31

    6

    GROWTH STRATEGIES (BEST CASE SCENARIO) DETAILS OF STRATEGY

    S1 O4 Strategy:

    S1 : Experienced Football Administration Volunteers

    O4 : An improving and enabling environment for football

    related NGOs

    To Use the experienced Football Administration Volunteers to

    take advantage of the improving and enabling environment for

    football Related NGOs

    S2 O4 Strategy:

    S2: Well Networked and Committed Volunteers

    O5: Partnership With District Assembly

    To use our well networked and committed Volunteers to lobby a

    Partnership With the District Assembly

    S2 O3 Strategy:

    S2: Well Networked and Committed Volunteers

    O3: Public Interest in funding Grassroots Football Development

    To use our well networked and committed Volunteers to take

    advantage of the Public Interest in funding Grassroots Football

    Development (Raising funds)

    S4 O5 Strategy :

    S4: Support from Parents of the Underprivileged

    O5: Partnership with District Assembly

    To take advantage of the Support from the Parents of the

    Underprivileged to lobby the District Assembly in undertaking

    Joint Programmes

    S2 O6 Strategy :

    S2: Well Networked and Committed Volunteers

    O6: Existence of a Local Juvenile Club (Talent Stars) as a

    Project

    Capitalise on the Well Networked and Committed Volunteers To

    Raise Funds to Pilot a Project with the Local Juvenile Club

    (Talent Stars)

    Strategy Formulation

  • 8/14/2019 Workable Strategic Plan Document

    8/31

    7

    STABILITY STRATEGIES DETAILS OF STRATEGY

    W1 O3 Strategy :

    W1: Lack of funding and Unreliable Cashflow

    O3: Public Interest In Funding Grassroots Football Development

    To take advantage of The Public Interest In Funding Grassroots

    Football Development to Raise Funds and Improve Cashflow

    W2 O2 Strategy :

    W2: Lack of Legal Recognition with Ministry Of Social Welfare

    and District Assembly

    O2: Trust Bill- Legitimacy Of Operations

    To adhere to the Provisions of the Trust Bill to obtain Legal

    Recognition with the Ministry Of Social Welfare and the District

    Assembly

    S4 T2 Strategy :

    S4: Support from Parents of the Underprivileged

    T2: Opposition From Supposed Player Managers

    To capitalize on the Support from Parents of the Underprivileged

    to Neutralize the Impact of Supposed Player Managers

    S2 T3 Strategy :

    S2: Well Networked and Committed Volunteers

    T3: Inadequate Support from Donors.

    To use the well Networked and Committed Volunteers to Solicit

    Support from Donors

    DEFENSIVE STRATEGIES (WORST CASE SCENARIO) DETAILS OF STRATEGY

    W1 T2 Strategy :

    W1: Lack of Funding and Unreliable CashflowT2: Opposition from Supposed Player Managers To Increase funding and reliability of Cashflow to support thefootballers so as to reduce the Impact of the Supposed Player

    Managers

    W2 T2 Strategy :

    W2: Lack of Legal Recognition With Ministry of Social

    Welfare and District Assembly

    T2: Opposition From Supposed Player Managers

    Register with the Ministry of Social Welfare and the District

    Assembly to legalise role being played

  • 8/14/2019 Workable Strategic Plan Document

    9/31

    8

    STRATEGY : Capitalize On The Well Networked And Committed Volunteers To Raise Funds To Pilot A Project With

    The Local Juvenile Club (Talent Stars)

    OBJECTIVES (2009-2011)

    (Theme :Project Funding )

    1. To Officially Adopt Talent Stars By February 28, 2009 To Pilot First Programme

    2. To Raise Funding/Sponsorship To Implement The Talent Stars Project By End of December 2009

    STRATEGY : To Adhere To The Provisions Of The Trust Bill To Obtain Legal Recognition With The Ministry Of Social

    Welfare And The District Assembly

    OBJECTIVES (2009-2011)

    (Theme : Regulatory Issues)

    1. To Position FFAF as A Recognized NGO in Grassroots Football Development in Ghana By End of December, 2010

    Strategic Objectives

  • 8/14/2019 Workable Strategic Plan Document

    10/31

    9

    STRATEGY : To Take Advantage Of The Public Interest in Funding Grassroots Football Development To Raise

    Funding and Improve Cashflow

    OBJECTIVES (2009-2011)

    (Theme : Publicity And Funding )

    1.To Position FFAF as an Effective and Efficient NGO In Grassroot Football Development In Ghana By End Of 2011

    2.To Raise Funding for Other Programmes By End Of 2011

  • 8/14/2019 Workable Strategic Plan Document

    11/31

    10

    STRATEGIC OBJECTIVE 1: To Raise Funding/Sponsorship To Implement The Talent Stars Project By End Of December 2009

    DELIVERABLES/OUTPUTS

    1. Needs Analysis for The Talent Stars Project Confirmed By End Of February 2009

    2.Funding Proposal For Donors/Sponsors Prepared By End of March 2009

    3. Funding/Sponsorship For Talent Stars Project Raised By June 30, 2009

    STRATEGIC OBJECTIVE 2 : To Position FFAF As An Effective And Efficient NGO In Grassroot Football Development InGhana By End Of 2011

    DELIVERABLES/OUTPUTS

    4. Website Of FFAF Developed And Hosted By December 30, 2009

    5. Official Lunching Of FFAF Including Website Undertaken By End Of January 2010 In Ghana

    Outputs of Strategy Objectives

  • 8/14/2019 Workable Strategic Plan Document

    12/31

    11

    OUTPUT 1: Needs Analysis for The Talent Stars Project Confirmed By End Of February 2009

    ACTIVITIES

    1.

    Meet with Owners of Talent Stars to Confirm the Needs Assessment of the Club Between January 15, 2009 and January

    18, 2009

    2.Meet with at least 70% Of The Playing Body of the Club to Confirm their Needs between January 20, 2009 and January30, 2009

    3.

    Meet With Parents of at least 70% of the Youth Players to Confirm the Needs Assessment of their Wards Between

    February 04, 2009 and February 25, 2009

    OUTPUT 2 : Funding Proposal For Donors/Sponsors Prepared By End of March 2009

    ACTIVITIES

    4.Put together a Budget for Funding Sponsors Between March 02, 2009 And March 09, 2009

    5. Prepare funding proposal Incorporating Budget Details By March 27, 2009

    Activities of Outputs

  • 8/14/2019 Workable Strategic Plan Document

    13/31

    12

    OUTPUT 3: Funding/Sponsorship for Talent Stars Project Raised By June 30, 2009

    ACTIVITIES

    6. Make a list Of Prospective Funders/Sponsors with interest in football Development By April 01, 2009

    7. Distribute Funding Proposals To Prospective Sponsors/Funders as Listed By April 07, 2009

    8. Follow up With Prospective Funders/Sponsors for Responses Between April 15,2009 And April 30, 2009

    9. Meet with interested Sponsors to further discuss details of Proposal/Implementation between May 03 and May 30, 2009

    10. Follow up and Confirm Implementation Plans as agreed with Sponsors Between June 01, 2009 and June 20,2009

    11. Receive Cheques And Other Sponsorship Packages Between June 23, 2009 and June 30, 2009

    OUTPUT 4: Website of FFAF Developed and Hosted By December 30, 2009

    ACTIVITIES

    12. Send Sponsorship Proposal to Web Development Companies or Get A Web Developer Volunteer by End Of April, 2009

    13. Follow Up To Get Confirmed Interest By May 30, 2009

    14. Discuss Web Concept With Developer Between June 01, 2009 and June 10, 2009

    15. Receive And Validate Prototype of Concept By July 30,2009

    16. Provide Content for Final Development By August 15, 2009

    17. Host Site On Web By October 30, 2009

  • 8/14/2019 Workable Strategic Plan Document

    14/31

    13

    OUTPUT 5 : Official Lunching of FFAF including Website Undertaken By End of January 2010 in Ghana

    ACTIVITIES

    18.Hold Consultative Meetings With Key Stakeholders On Funding/ Lunching Activities Between June 01, 2009 and

    September 30, 2009

    19. Follow Up and Confirm launching Activities By November 30, 2009

    20. Distribute Invitations By December 15, 2009

  • 8/14/2019 Workable Strategic Plan Document

    15/31

    14

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Jerseys Sets 8 600.00 4,800.00

    Football Boots Pairs 120 50.00 6,000.00Gym Boots Pairs 125 30.00 3,750.00

    Shin Guards Pairs 120 15.00 1,800.00Footballs 40 35.00 1,400.00Track Suits Pairs 5 30.00 150.00

    T-Shirts For Officials 10 10.00 100.00Bibs Sets 8 45.00 360.00Cones Sets 3 200.00 600.00

    Goalkeeper Gloves Pairs 9 40.00 360.00

    Hose Sets 8 150.00 1,200.00Goal Net Sets 2 200.00 400.00Warming Up Jerseys Sets 2 90.00 180.00Field Development 1 3,000.00 3,000.00

    FIFA Approved Whistles Pieces 3 30.00 90.00

    SUB- TOTAL EQUIPMENT REQUIREMENT 24,190.00

    Summary of Inputs

    ACTIVITY 1: Meet With Owners of Talent Stars to Confirm the Needs Assessment of the Club Between January 15, 2009

    and January 18, 2009

  • 8/14/2019 Workable Strategic Plan Document

    16/31

    15

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Feeding of 72 Players@ GH2.50 per match Matches 80 180.00 14,400.00

    Feeding of 5 Officials @ GH2.50 per match Matches 80 12.50 1,000.00T&T for 72 players @ GH5.00 per match Matches 80 360.00 28,800.00

    Winning bonus for 5 officials @ GH10.00 Matches 80 50.00 4,000.00

    Referees fee per match Matches 80 15.00 1,200.00

    Washing of jerseys per match 80 15.00 1,200.00

    Hiring of vehicle for away matches Matches 40 50.00 2,000.00

    Security for home matches Matches 40 15.00 600.00

    Miscellaneous Matches 80 50.00 4,000.00

    SUB-TOTAL MATCH EXPENSES57,200.00

    Grand Total 81,330.00

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Training Allowance (Annual) Per Player 120 360.00 43,200.00

    ACTIVITY 2 : Meet With at Least 70% of The Playing Body Of The Club To Confirm Their Needs Between January 20, 2009To January 30, 2009

  • 8/14/2019 Workable Strategic Plan Document

    17/31

    16

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    School Fees Support Per Player 120 360.00 43,200.00

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Stationery(A4 Paper) 1 4 4

    Budget Co-ordinator 2 - -

    Total 4

    ACTIVITY 3: Meet With Parents Of At Least 70% Of The Youth Players to Confirm The Needs Assessment Of Their Wards

    Between February 04, 2009 to February 25, 2009

    ACTIVITY 4 : Put Together A Budget For Funding Sponsors Between March 02, 2009 And March 09, 2009

  • 8/14/2019 Workable Strategic Plan Document

    18/31

    17

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Stationery 1 4 4Consultant 1 - -

    Total 4

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Volunteer 2 - -

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Volunteers 10 - -T&T 10 5 50

    Total 50

    ACTIVITY 5 : Prepare Funding Proposal Incorporating Budget Details By March 27, 2009

    ACTIVITY 6 : Make A List Of Prospective Funders/Sponsors With Interest In Football Development By April 01, 2009

    ACTIVITY 7 : Distribute Funding Proposals To Prospective Sponsors/Funders As Listed By April 07, 2009

  • 8/14/2019 Workable Strategic Plan Document

    19/31

    18

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Volunteers 10T&T 10 5 50

    Total 50

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Volunteers 5 - -T&T 5 5 25

    Total 25

    ACTIVITY 8: Follow Up With Prospective Funders/Sponsors For Responses Between April 15, 2009 And April 30, 2009

    ACTIVITY 9: Meet with Interested Sponsors/Funders to further Discuss Details of Proposal/ImplementationBetween May 03, 2009 and May 30, 2009

  • 8/14/2019 Workable Strategic Plan Document

    20/31

    19

    QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Volunteers 5 - -T&T 5 5 25

    Total 25

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST(GHC)

    Volunteers 10 - -T&T 10 5 50

    Total 50

    ACTIVITY 10: Follow Up and Confirm Implementation Plans As Agreed With Sponsors between June 01, 2009

    and June 20,2009

    ACTIVITY 11 : Receive Cheques And Other Sponsorship Packages Between June 23, 2009 And June 30, 2009

  • 8/14/2019 Workable Strategic Plan Document

    21/31

    20

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Volunteers -

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Volunteers -

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    FFAF Director 1 - -Dinner 2 10 20

    Total 20

    ACTIVITY 12: Send Sponsorship Proposal To Website Development Companies Or Get A Web DeveloperVolunteer by End of April, 2009

    ACTIVITY 13 : Follow Up To Get Confirmed Interest By May 30, 2009

    ACTIVITY 14: Discuss Web Concept with Developer between June 01, 2009 and June 10, 2009

  • 8/14/2019 Workable Strategic Plan Document

    22/31

    21

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)Volunteers -

    RESOURCE REQUIRED QUANTITY UNIT COST (USD) TOTAL COST

    (USD)

    FFAF Director -

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Hosting Cost 1 200 200.00Computer 1 1,300 1,300.00

    Internet Connectivity 1 50 50.00

    Total 1,550.00

    ACTIVITY 15: Receive and Validate Prototype of Concept by July 30, 2009

    ACTIVITY 16: Provide Content for Final Development by August 15, 2009

    ACTIVITY 17: Host Site on Web by October 30, 2009

  • 8/14/2019 Workable Strategic Plan Document

    23/31

    22

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Volunteers 10 -T&T 10 10 100

    Total 100

    RESOURCE REQUIRED QUANTITY UNIT COST (GHC) TOTAL COST

    (GHC)

    Volunteers 10 -T&T 10 5 50

    Total 50

    ACTIVITY 18 : Follow Up And Confirm Lunching Activities By November 30, 2009

    ACTIVITY 19: Distribute Invitations by December 15, 2009

  • 8/14/2019 Workable Strategic Plan Document

    24/31

    23

    ACTIVITY RESOURCE

    REQUIRED

    (GHC)

    GHC:USD

    EXH. RATE

    RESOURCE

    REQUIRED (USD)

    SOURCE OF FUNDING

    (Internal or External)

    Meeting to confirm needs assesment with

    owners of Talent Stars 81,330.00 1.0863 74,868.82 External

    Meeting to confirm needs assesment with

    playing body of Talent Stars 43,200.00 1.0863 39,768.02 External

    Meeting to confirm needs assesment with

    parents of players of Talent Stars 43,200.00 1.0863 39,768.02 External

    Put together a budget for funding sponsors 4.00 1.0863 3.68 Internal

    Prepare funding proposal 4.00 1.0863 3.68 Internal

    Make list of prospective funders/sponsors - 1.0863 -

    SUB-TOTAL 167,738.00 154,412.22

    Resource Inventory

  • 8/14/2019 Workable Strategic Plan Document

    25/31

    24

    ACTIVITY RESOURCE

    REQUIRED

    (GHC)

    GHC:USD

    EXH. RATE

    RESOURCE

    REQUIRED (USD)

    SOURCE OF FUNDING

    (Internal or External)

    Distribute funding proposals to prospectivefunders/sponsors 50.00 1.0863 46.03 Internal

    Follow up with prospective funders/sponsors for

    responses 50.00 1.0863 46.03 Internal

    Meet with interested sponsors/funders to discuss

    details of proposal 25.00 1.0863 23.01 Internal

    Follow up and confirm implementation plans

    with sponsors 25.00 1.0863 23.01 Internal

    Receive cheques and other sponsorship packages 50.00 1.0863 46.03 Internal

    Send sponsorship proposal for website

    development - 1.0863 -

    Follow up to get confirmed interest - 1.0863 -

    Discuss web concept development with

    developer 20.00 1.0863 18.41 Internal

    Receive and validate prototype of concept - 1.0863 -

    Provide content for final development - 1.0863 -

    Hosting of site 1,550.00 1.0863 1,426.86 External

    Follow up and confirm lunching activities 100.00 1.0863 92.06 Internal

    Distribute invitations for lunching 50.00 1.0863 46.03 Internal

    SUB-TOTAL 1,920.00 1,767.47

    GRAND TOTAL 169,658.00 156,179.69

  • 8/14/2019 Workable Strategic Plan Document

    26/31

    25

    No Activity Milestone

    Time Frame Responsibility

    Resource-

    funding

    (USD) Assumption

    Start End Assigned To Supervised By

    1

    Meeting to confirmneeds assessment withowners of Talent Stars

    Meeting dateagreed 15/01/09 18/01/09

    ProgramOfficer

    ExecutiveDirector 74,868.82

    That owners andvolunteers are able toattend.

    2

    Meeting to confirmneeds assessment withplaying body of TalentStars

    Meeting dateagreed 20/0109 30/01/09

    ProgramOfficer

    ExecutiveDirector 39,768.02

    That the playing body andvolunteers are able toattend.

    3

    Meeting to confirmneeds assessment withparents of players ofTalent Stars

    Meeting dateagreed 4/2/2009 25/02/09 Volunteer

    ProgramOfficer 39,768.02

    That parents of theplayers and volunteers areable to attend.

    4Put together a budgetfor funding sponsors

    Budget figuresvalidated 2/3/2009 9/3/2009

    ProgramOfficer

    FinanceManager 3.68

    That volunteers withknowledge of budgetingare available

    5

    Prepare funding

    proposal

    Draft proposal

    completed 10/3/2009 27/3/2009

    Program

    Officer

    Executive

    Director 3.68

    That volunteers withknowledge in proposal

    writing are available

    6Make list of prospectivefunders/sponsors

    Draft listcompleted 20/03/09 1/4/2009

    ProgramOfficer

    BusinessManager -

    That volunteers areavailable

    7

    Distribute fundingproposals to prospectivefunders/sponsors

    Funding proposalcompletedSponsors listcompleted 2/4/2009 7/4/2009 Volunteer

    BusinessManager 46.03

    That volunteers areavailable to do thedistribution

    Implementation Plan

  • 8/14/2019 Workable Strategic Plan Document

    27/31

    26

    No Activity Milestones

    Time

    Frame

    Responsibility

    Resource-

    funding

    (USD) Assumption

    Start End Assigned To Supervised By

    8

    Follow up withprospective

    funders/sponsors forresponses

    Acknowledgement

    of proposalreceived 15/04/09 30/04/09 BusinessManager ExecutiveDirector 46.03

    That funders/sponsors are

    willing to be associatedwith project

    9

    Meet with interestedsponsors/funders todiscuss details ofproposal

    Favourableresponses received 3/5/2009 30/05/09

    BusinessManager

    ExecutiveDirector 23.01

    That funders/sponsors arewilling to be associatedwith project andvolunteers are available

    10

    Follow up and confirmimplementation planswith sponsors

    Implementationplan completed.

    Date for meetingsagreed 1/6/2009 20/06/09

    BusinessManager

    ExecutiveDirector 23.01

    That funders/sponsorshave agreed to beassociated with project.

    11

    Receive cheques andother sponsorshippackages

    Cheques signed.

    Sponsorshipapproved 23/06/09 30/06/09

    FinanceManger

    ExecutiveDirector 46.03

    That funding amounts andsponsorship packageshave been agreed andconcluded.

    12

    Send sponsorshipproposal for websitedevelopment Proposal completed 15/04/09 30/04/09 volunteer

    BusinessManager -

    That volunteers areavailable to writeproposal

    13Follow up to getconfirmed interests

    Acknowledgmentof receipt ofproposals 5/5/2009 30/05/09 volunteer

    BusinessManager -

    That volunteers are ableto follow up

    14

    Discuss web content

    development withdeveloper Date of meetingconfirmed. 1/6/2009 10/6/2009 BusinessManager ExecutiveDirector 18.41

    That a web content

    developer has agreed tosponsor

  • 8/14/2019 Workable Strategic Plan Document

    28/31

    27

    No Activity Milestones

    Time

    Frame

    Responsibility

    Resource-

    funding

    (USD) Assumption

    Start End Assigned To Supervised By

    15

    Receive and validate

    prototype of concept

    Design Completed.

    Prototype developed 15/07/09 30/07/09

    Business

    Manager

    Executive

    Director - That prototype is ready

    16Provide content for finaldevelopment

    Content collated anddelivered 3/8/2009 15/08/09

    BusinessManager

    ExecutiveDirector -

    That prototype is readyand been approved

    17 Hosting of site

    Web designcompleted.

    Hosting companycontacted and costagreed.

    Hosting date agreed. 15/10/2009 30/10/09BusinessManager

    ExecutiveDirector 1,426.86

    That funding/sponsorshiphas been secured

    18

    Follow up and confirm

    lunching activities

    Input for lunchingreceived fromvolunteers/sponsors

    Lunching activitiesdetermined.

    Funding/Sponsorshipconfirmed

    Payments made forvarious bookings

    1/11/2009 30/11/09 Volunteer

    Business

    Manager 92.06

    That lunching activities

    has been planned

    19Distribute invitations forlunching

    Invitation cardsprinted

    Names of invitesprinted on cards 1/12/2009 15/12/09 Volunteer

    BusinessManager 46.03

    That lunchingactivities/programme hasbeen approved andconfirmed

  • 8/14/2019 Workable Strategic Plan Document

    29/31

    28

    BlankPage,

    Replacew

    ithGanttC

    hart

  • 8/14/2019 Workable Strategic Plan Document

    30/31

    29

    No ACTIVITY MILESTONES OBJECTIVELYVERIFIABLE

    INDICATORS(OVI)

    MEANS OF

    VERIFICATION

    (MOV)1 Meeting to confirm needs assessment with

    owners of Talent Stars Meeting date agreed

    Letter of confirmation Correspondence file at

    secretariat

    2 Meeting to confirm needs assessment with

    playing body of Talent Stars Meeting date agreed

    Minutes of meeting Minutes file at

    secretariat3 Meeting to confirm needs assessment with

    parents of players of Talent Stars Meeting date agreed

    Minutes of meeting Minutes file at

    secretariat

    4Put together a budget for funding sponsors Budget figures validated

    Budget document Budget file of Finance

    Assistant at secretariat

    5 Prepare funding proposal Draft proposal completed Draft proposal document Business Managers file

    6 Make list of prospective funders/sponsors Draft list completed Sponsors list Business Managers file

    7Distribute funding proposals to prospective

    funders/sponsors

    Funding proposal completed

    Sponsors list completed

    Approved Proposal document Business Managers file

    8

    Follow up with prospective funders/sponsors

    for responses

    Acknowledgement of proposal

    received

    Acknowledgement letter Sponsors file at

    secretariat

    9

    Meet with interested sponsors/funders todiscuss details of proposal Favourable responses received

    Call report on meeting Sponsors file atsecretariat

    10

    Follow up and confirm implementation plans

    with sponsors

    Implementation plan completed.

    Date for meetings agreed

    Implementation document Sponsorship file at

    secretariat

    Monitoring and Evaluation

  • 8/14/2019 Workable Strategic Plan Document

    31/31

    30

    No ACTIVITY MILESTONES OBJECTIVELYVERIFIABLE

    INDICATORS(OVI)

    MEANS OF

    VERIFICATION

    (MOV)

    11

    Receive cheques and other sponsorshippackages

    Cheques signed. Sponsorshipapproved

    Acknowledgementreceipts/letters

    Correspondence file atsecretariat

    12 Send sponsorship proposal for websitedevelopment Proposal completed Proposal document Proposals file atsecretariat

    13 Follow up to get confirmed interests

    Acknowledgment of receipt of

    proposals

    Acknowledgement

    receipts/letters

    Sponsorship file at

    secretariat

    14

    Discuss web content development with

    developer Date of meeting confirmed.

    Minutes of meeting Business Managers file

    at secretariat

    15 Receive and validate prototype of concept

    Design Completed.

    Prototype developed

    Soft copy of prototype on DVD Business manager at

    secretariat

    16 Provide content for final development Content collated and delivered

    Soft copy of content on DVD Business manager at

    secretariat

    17 Hosting of site

    Web design completed.

    Hosting company contacted and cost

    agreed.

    Hosting date agreed.

    Soft copy of completed designon DVD

    Call report on meeting

    Business manager atsecretariat

    18 Follow up and confirm lunching activities

    Input for lunching received from

    volunteers/sponsors

    Lunching activities determined.

    Funding/Sponsorship confirmed

    Payments made for various bookings

    Input list

    List of activities/programme

    Funding confirmation letters

    Receipts/confirmation/booking

    letters

    Business Managers

    Lunching file atSecretariat

    19 Distribute invitations for lunching

    Invitation cards printed

    Names of invites printed on cards

    Invoice

    List of invites

    Business Managers

    Lunching file at

    Secretariat