Top Banner
Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013
26

Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

Jan 17, 2016

Download

Documents

Martha Wade
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

Work Plan Development

Aschalew AberraHighway Utility Engineer, INDOT

December 19, 2013

Page 2: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

2

Outline Learning objectives –why work

plan? Top five reasons why a work plan is

important What are the recent updates?

Target date, signing first or second page, emergency contact, pre-construction & post construction activity, etc.

Work plan development (Process): preparation, review, revision & approval.

Practical exercise

Page 3: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

Why is a work plan Important?1. Because it is the law!

he 105 IAC 13-3-3 (b) (1): A work plan shall be

submitted whether or not any facility relocations are required.

It is not a matter of opinion or an option, it is the LAW.

Utilities are obligated to submit their work plans to accommodate a highway improvement project.

Page 4: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

Why is a work plan Important ?2. Because it focuses on deliverables:

Target out of conflict date.

Pre-construction schedule.

Construction schedule.

Relocation drawing.

Cost estimate

Proof of property interest.

Page 5: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

Why is a work plan Important?3. Because it is a signed

commitment/contract

A work plan is a signed commitment by a utility to accurately relocate its facilities on schedule.

Projects are let based on information obtained from utility work plans.

A utility may be held accountable, for utility related delay claims.

Page 6: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

Why is a work plan Important4. No Surprises during construction:

Work plan is a major tool to avoid surprises during construction.

The utility team shall demonstrate due diligence in reviewing & approving work plans.

Last chance before construction stage!

Page 7: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

Why is a work plan Important?5: Because we use the work plan as an

input:

Utility risk management report.

Gantt chart.

Utility special provision.

Utility coordination certificate.

Page 8: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

A tool for resolution of scheduling and location conflicts

Page 9: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

Preamble 105 IAC-13-2-19: Work plan is defined as a

plan of the utility to carry out facility relocation to accommodate an improvement project.

Use preliminary final project plan (Stage 3/90%).

Prepare and send letter Request Work Plan.

Use the most recent work plan template. Go to the INDOT website.

Page 10: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

When is a work plan due? Sixty (60) days for a minor project; and

One hundred twenty (120) days for a major project.

An additional thirty (30) days will be allowed to furnish the work plan if coordination is required with another utility or utilities.

If a work plan is not received on time: contact the authorized representative and notify the oversight agent.

Page 11: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

11

Work plan revision Non compatible work plans shall be returned

to the utility immediately.

The utility shall submit a revised work plan within 30 days.

If the revised work plan is not compatible, the UC will prepare an alternate work plan.

The utility shall accept/make changes to the alternate plan within 30 days.

Page 12: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

12

Section 1: General Information

Page 13: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

13

General info……cont’d

Page 14: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

14

General info……cont’d

Page 15: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

15

Section 2: Location info.

Page 16: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

16

Section 3 & 4 Property interest & Work in

contract

Page 17: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

17

Section 5: Pre-construction

Page 18: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

18

Section 6: Construction

Page 19: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

19

Section 7, 8, & 9: Attachments

$500,000.00 (Not Reimbursable)

Page 20: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

20

Work Plan Review Ensure each work plan is

compatible with: INDOT permit requirements The project plans The construction schedule Other utility relocation work plans

Ensure the relocation scheme and cost for compensable work is reasonable

Page 21: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

21

Section 10 & 11: Approval

Page 22: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

22

Work Plan Approval Letter Relocation permit to occupy public

right-of-way.

Notice to proceed with preconstruction activities.

In rare cases a notice to proceed with construction activities.

Page 23: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

23

Work plan addendums: Addendums can either be INDOT initiated or

utility initiated.

A utility shall submit a revised work plan with a new cost estimate (if reimbursable).

The utility coordinator shall review the addendum; and send it to the approval of the oversight agent.

If an addendum is issued during construction, a copy shall be sent to the construction engineer.

Page 24: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

24

Work Plan Addendum Letter What is the change of work.

What is the cost.

Who is paying for it.

What is the impact on construction schedule.

Revise exhibits to executed agreements, if reimbursable.

Page 25: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

25Questions?

Questions?

Page 26: Work Plan Development Aschalew Aberra Highway Utility Engineer, INDOT December 19, 2013.

Practical Exercise Group exercise

Identify 3 or 4 items that need to be corrected.