Top Banner
Wood Thilsted Partners © Wood Thilsted Partners Ltd Company Registered in England No 09853253 Wood Thilsted Partners Limited Luke Fussell, Senior Engineer Developing the best Offshore Wind Farm
17

Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Jan 22, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 09853253

Wood Thilsted Partners Limited

Luke Fussell, Senior Engineer

Developing the best Offshore Wind Farm

Page 2: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 098532532

Introduction: Luke Fussell

A bit about me:• Senior Engineer at Wood Thilsted Partners• MEng, Mechanical Engineering from

University of Bath (2006)Career Highlights:• Just started at WT• Previously Deputy Head of Office at LICenergy

UK (3.5 years)• Prior to that, spent 8+ years at Atkins in

various departments, including Oil & Gas, plus 18 month secondment to Vestas

• Recently Owner’s Engineer for 2 French offshore wind farms currently in development (EPCI Contracts)

Page 3: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 09853253 3

Wood Thilsted Partners is an engineering company specialised in geotechnical and foundation engineering for offshore wind farms.

Wood Thilsted Partner advises in all phases of wind farm developments; from due diligence of green field developments through to construction and O&M phases.

The company was established November 2015 by former two senior engineers from Ørsted (formerly Dong Energy) and has by today grown to 34 employees. Wood Thilsted is working for a wide range of clients across the offshore wind industry in Europe, North America and South East Asia.

Page 4: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 09853253 4

Our company

Page 5: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 09853253

”First of all, I would like to let you know that I am deeply impressed with the work you have done– I think COWI and Ramboll should be scared to their bones when they get to know about your performance!”

Marc Siedel, Dr. ingSenior Key Expert Support Structures for Offshore Wind TurbinesSiemens Wind Power

5

”Benni and I wish to thank you for the great job you did at He Dreiht. We won the bid and would not have been able to do so without your help and expertise. It was a tough call for EnBW and I hope that this bold move without any subsidiaries (yes it really is 0€ per kWh) pays off. ”

Fawad Mohammadi, Dr.Manager, Foundations offshore windEnBW AG

Our clients

Page 6: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 098532536

Developing the best Offshore Wind Farm

Page 7: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 098532537

Designing the best Offshore Wind Farm

• Huge number of inter-linked factors that go into designing an offshore wind farm

• Focus of this presentation is on optimisation of the wind-farm LAYOUT(Hint: It doesn’t all need to be in straight lines)

Page 8: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 098532538

Designing the best Offshore Wind Farm

“Wind farm optimisation is a highly profitable exercise that can make a difference between a project going ahead or not”

Page 9: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 098532539

Designing the best Offshore Wind Farm

So what is it? What does it mean?

• Site optimisation is effectively a FEED study for the layout

• At the heart is a full-life cycle cost modelwhich can include:• Site bathymetry and geology,• different turbines,• array cable layouts and voltages, • and can be adjusted to minimise ground risks

Page 10: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 0985325310

Geotechnical Investigations and Foundations

SiteConditions Unknown

Foundation concept selection

Wind Farm Layout fixedWTG already selected

Certified Design Basis detailed design

SITE

INV

ESTI

GA

TIO

N

Geophysical survey 10% Geotechnical

survey

10% Laboratory testing

100% Geotechnical survey

100% Laboratory testing

Foundation specific cyclic

testing

Pre-investment

decision

ENG

INEE

RIN

G P

HA

SES Due diligence & Desk

studyGround Modelling

Ground Risk Assessment and Mitigation Strategy

Geotechnical laboratory testing

ENDSufficient

investigation

Consultation:DeveloperFinanciersFabricatorContractor

STARTDesk Study

Update geotechnical

report and risk register

Are residual risks acceptable

to project?

Undertake survey / study

Evaluate survey / study and

update ground model

No

Yes

Design Evaluation

Plan study / investigation to

mitigate risk

Optimisationof layout

Site Assessmentoptimisation

Design optimisation

Construction support

Certification

Effective strategies for site investigations and ground modelling to effectively minimize construction risks and optimize DEVEX and CAPEX for the project

Page 11: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 0985325311

Designing the best Offshore Wind Farm

Example Site - Geotechnical Zones for support structure design

Blue area has worst ground conditions. Foundations here are more expensive

Page 12: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 0985325312

Designing the best Offshore Wind Farm

Inter Array Cable (IAC) Architecture selected is “split-string”

Split-string for IAC architecture

IAC routed parallel to sand waves

A detailed study of site bathymetry and sediment transport was undertaken – a Geomorphology study. This informed the likely long-term change in ground levels

Page 13: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 0985325313

Example Site - Layout optimization and wind turbine selectionComparison of Energy Yield for different turbines and different site constraints. These studies provide input to the economic model.

4 MW turbines

6 MW turbines

sandwaves/sand bank

Protected area for

birds

Project capacity (MW)

Projectrate of

Return(IRR)

Page 14: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 0985325314

Site Design Example - Seabed contacts from geophysical survey

Contacts recorded from sub-bottom profiling, magnetometer and side-scan sonar

Page 15: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 0985325315

Geotechnical Investigations and Foundations

SiteConditions Unknown

Foundation concept selection

Wind Farm Layout fixedWTG already selected

Certified Design Basis detailed design

SITE

INV

ESTI

GA

TIO

N

Geophysical survey 10% Geotechnical

survey

10% Laboratory testing

100% Geotechnical survey

100% Laboratory testing

Foundation specific cyclic

testing

Pre-investment

decision

ENG

INEE

RIN

G P

HA

SES Due diligence & Desk

studyGround Modelling

Ground Risk Assessment and Mitigation Strategy

Geotechnical laboratory testing

ENDSufficient

investigation

Consultation:DeveloperFinanciersFabricatorContractor

STARTDesk Study

Update geotechnical

report and risk register

Are residual risks acceptable

to project?

Undertake survey / study

Evaluate survey / study and

update ground model

No

Yes

Design Evaluation

Plan study / investigation to

mitigate risk

Optimisationof layout

Site Assessmentoptimisation

Design optimisation

Construction support

Certification

Effective strategies for site investigations and ground modelling to effectively minimize construction risks and optimize DEVEX and CAPEX for the project

Page 16: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 0985325316

Summary

• Wind farm optimisation can be a highly profitable exercise

• Life Cycle cost modelling is a key part of this work

• Plan ahead for success; start small and work upwards, using results as you go

• Consider as many variables as you can

• Happy optimising! ☺

Page 17: Wood Thilsted Partners Limited - Asia Wind · 2019. 5. 1. · 13. Ex a mp l e S i te - Lay o u t o pt i m i z at i o n an d w i n d t u r bi n e s e l e c t i o n. Co m p a ri so

Wo

od

Th

ilste

d P

artn

ers

© Wood Thilsted Partners Ltd Company Registered in England No 09853253

Contact details:

Luke Fussell, Senior Engineer

[email protected]

+44 7799 413035