EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Wolfram KORTEN, JRA-02 AGATA Status of the AGATA project Recent developments Milestones and deliverables for 2006 Plans for 2007/08 Main features of AGATA Efficiency: 40% (M =1) 25% (M =30) today’s arrays ~10% (gain ~4) 5% (gain ~1000) Peak/Total: 55% (M =1) 45% (M =30) today ~55% 40% Angular Resolution: ~1º FWHM (1 MeV, v/c=50%) ~ 6 keV !!! today ~40 keV Rates: 3 MHz (M =1) 300 kHz (M 180 large volume 36-fold segmented Ge crystals in 60 triple-clusters • Digital electronics and sophisticated Pulse Shape Analysis algorithms
20

Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

Jan 13, 2016

Download

Documents

Andrew Dorsey
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Status of the AGATA project

• Recent developments• Milestones and deliverables for 2006• Plans for 2007/08

Main features of AGATA

Efficiency: 40% (M =1) 25% (M =30)today’s arrays ~10% (gain ~4) 5% (gain ~1000)

Peak/Total: 55% (M=1) 45%

(M=30)today ~55% 40%

Angular Resolution: ~1º FWHM (1 MeV, v/c=50%) ~ 6 keV !!!today ~40 keV

Rates: 3 MHz (M=1) 300 kHz (M

=30)today 1 MHz 20 kHz

• 180 large volume 36-fold segmented Ge crystals in 60 triple-clusters • Digital electronics and sophisticated Pulse Shape Analysis algorithms • Operation of Ge detectors in position sensitive mode -ray tracking

Page 2: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Ingredients of -ray Tracking

Pulse Shape Analysisto decompose

recorded waves

Highly segmented

HPGe detectors

·

·

··

Identified interaction

points(x,y,z,E,t)i

Reconstruction of “tracks”

e.g. by evaluation of permutations

of interaction points

Digital electronicsto record and

process segment signals

1

2 3

4

Spectroscopic studies

Page 3: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

AGATA symmetric prototypes

Page 4: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Acceptance tests on prototypes

0,00

0,50

1,00

1,50

2,00

2,50

Reihe1

Reihe2

FWHM at 1.3MeV

FWHM at 60keV

Mean(1.3MeV)=1.99keV

Mean(60keV)=1.14keV

IKP Cologne 001 Core FWHM: at 1.3MeV : 2.10keVat 122keV : 1.20keV

Page 5: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Acceptance tests on prototypes

0,00

0,50

1,00

1,50

2,00

2,50

Reihe1

Reihe2

FWHM at 1.3MeV

FWHM at 60keV

Mean(1.3MeV)=1.98keV

Mean(60keV)=1.07keV

Core FWHM: at 1.3MeV : 2.08keVat 122keV : 1.19keV

GSI 002

Page 6: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Acceptance tests on prototypes

0,00

0,50

1,00

1,50

2,00

2,50

Reihe1

Reihe2

FWHM at 1.3MeV

FWHM at 60keV

Mean(1.3MeV)=2.01keV

Mean(60keV)=1.03keV

Core FWHM: at 1.3MeV : 2.13keVat 122keV : 1.10keV

INFN Padova 003

Page 7: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

First AGATA triple module

Univ. Cologne August 2005

Goal: Validation of pulse-shape analysis codes under realistic experimental conditions

Page 8: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Planning for AGATA detectors in 2006

• Three symmetric detectors are being mounted in test cryostats for characterisation (3D scanning):

cryostat 1: scanning in Liverpool ongoing cryostat 2: delivery to Orsay in April cryostat 3: delivery to GSI in June• Two first asymmetric Ge crystals do not meet

specifications and were returned to Canberra-Eurisys for repair.

• First detector from “new batch” expected in April.• If problems have been solved by Canberra-Eurysis,

first asymmetric triple ready by the end of 2006

Page 9: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Electronics and DAQ developments

Up to 180detectors

Synchronous

Buffered

Analogue

Detectorpreamp.

Digitisers

TrackingControl,Storage…

EventBuilder

Clock100 MHzT-Stamp

PreprocessingPSACore +36 seg.

Ancillary 1.

Ancillary 2.

Handling of ancillary detectors1. interface to GTS via mezzanine 2. merge time-stamped data into event builder3. prompt local trigger available from digitisers

Ancillary 3.

GL Trigger

Page 10: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Digitiser module 36+1 channels, 100 MhZ, 14 bits

(Strasbourg - Daresbury – Liverpool)

• Mounted close to the Detector 5-10 m

• Power Dissipation around400W

• Water Cooling

Prototype Segment Board2 boxes per crystal

Page 11: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Pre-processing modules (E,T, hits, …) (Orsay – Daresbury)

1 ATCA crate for 2 clusters(6 Ge crystals, 222 channels)

ATCA standard :“full mesh” communicationwith Gbit Ethernet or PCIexpress switches

166 8 1012144

1,5U

8U

4,5U

21’’

11 9 7 5 313

14U

2115

1 2 3 4 5 6 7 8 9 10 11 12 13 1514 16

3 X 2 Carriers1 cluster

3 X 2 Carriers1 cluster

Segment preprocessing mezzanine for 6 channels

Page 12: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Global Trigger System (GTS) (Padova – Legnaro)

GTS Pre-Proc. mezzanineOne per detector

(also for ancillaries)Trigger processor layoutFor up to 12 detectors

Page 13: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Status of electronics and DAQ prototypes

• Digitisers Q1 2006• Pre-processing mezzanines Q1 2006• ATCA carrier card Q1 2006• GTS mezzanine 1 (Virtex2) Q2 2005• “ mezzanine 2 (Virtex4) Q2 2006

• All prototypes tested by Summer 2006• Full processing chain, including

prototype of DAQ tested by Autumn 2006• Any needed reprocessing Autumn 2006• Production and start delivery Q4 2006• Test of a triple-cluster Q1-Q2 2007

• Ready for Demonstrator by fall 2007

Page 14: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Pulse shape analysis developments

• Determine the number of interactions– Neural Net Algorithm (IPN Orsay)

• Recognizes ~86% of single hits• Close to 100% of double hits with distance > ~10 mm

Use specific PSA algorithm depending on number of interactions

• Several PSA algorithms under development:– Wavelet based grid search (GSI)– Matrix inversion algorithm (IPN Orsay)

• Only code to treat full crystal “at once”• Very good results for simple events (1-3mm, typical time 1ms)• Still problematic for multiple adjacent interactions

– Particle Swarm search (TU München)• So far only single hits per segment• Hit in single segment: ~300 s, mean distance 1.7 mm (front), 3.5 mm (back)• Hits in two segments: <3 ms, distance 3 – 4.6 mm

PSA has been solved for certain event classes,e.g. single and multiple hits in the detector, but not in the same segment

5 mm average position resolution for 600keV -rays

• Implementation and testing in “real” hardware is ongoing

Page 15: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Status of Pulse shape analysis

M. Schlarb et al. (TUM, 2006)

• Example of the mean distance (in mm) of reconstructed position from real position

• in front segment• simulated signals• Similar results from

other PSA codes

Page 16: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Procedure of Gamma tracking

~ 100 keV ~1 MeV ~ 10 MeV -ray energy

Isolated hits Angle/Energy Pattern of hits

Photoelectric Compton Scattering Pair Production

Probability of E1st = E– 2 mc2

interaction depth

E' E

1E

m0c2 1 cos

Page 17: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Algorithm development and optimisation

Simulation of interactionsof M photons in Agata(with Agata Geant4 code)

Simulation of PSA: packing, smearing,energy threshold

Tracking code

(ei,xi,yi,zi)

(e’k,e’k x’k,x’k y’k,y’k z’k,z’k)

(Ej,j,j) : incident photon energies and emission directions

(and scattering directions for polarisation measurements)

Data analysis

Page 18: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

• Efficient forward tracking algorithms are ready:

• Effect of neutrons has been investigatedph reduced by ~1%/neutron

• Codes have been optimised for speed andspecifications for the demonstrator have been met :0.1 – 3.5 ms/evt for M=1 -30 (on 1 Opteron 1.7 GHz CPU)

• FT code currently being implemented into the DAQ

Status of gamma-ray tracking

E=1MeV, Mult=1 (30)

Mgt (Padova)

FT (Orsay)

Efficiency (%) 43 (28) 37 (24)

P/T (%) 58 (49) 67 (51)

Page 19: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Status of the AGATA project

• Recent developments– General discussion at the next AGATA week: Liverpool, June

6-9– Characterising the first prototype Ge detectors– Testing the first electronics and DAQ prototype boards

• Milestones and deliverables for 2006– Ge detector prototype characterized (06/06)

• o.k., but will use symmetric detector due to delay in delivery– Pulse-shape analysis algorithms optimised (06/06)

• Benchmark will be achieved, but will be ongoing– Gamma-ray tracking algorithms optimised (06/06)

• Benchmark will be achieved, but will be ongoing– Electronics and DAQ prototypes (06/06)

• Prototype local level processing electronics and specific data acquisition hardware: Delivery on schedule

• Ready for Demonstrator by fall 2007

Page 20: Wolfram KORTEN, JRA-02 AGATAEURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006 Status of the AGATA project Recent developments Milestones and deliverables.

EURONS PCC-Meeting, Mainz (Germany), 6.-7. April 2006Wolfram KORTEN, JRA-02 AGATA

Planning (EURONS and beyond)

• Demonstrator commissioning at LNL: second half of 2007

• First physics campaign at LNL in 2008further campaigns (from 2009) at GANIL, GSI, ILL, …

• LoI for construction phase signed in 2005to allow bids for new funds from 2006 (D, …)

• MoU for AGATA construction ready in 2007• Start construction in 2008 1 in possible in 2011• Support in FP7 as an independent RI (I3-TNA, CNI, …)