. . . . . . . . . . . . . . . . . . . Manitoba’s Experience with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. Surfacing Materials Engineer
20

with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Jul 13, 2018

Download

Documents

doantu
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

. . . . . . . . . . . . . . . . . . .

Manitoba’s Experience

with Warm Mix Asphalt

Tara Liske, M.Sc. P.Eng.

Surfacing Materials Engineer

Page 2: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

What is WMA?

• Warm Mix Asphalt (WMA)

– A generic term used for various technologies

that allow production and compaction of

asphalt pavements at lower temperatures

Page 3: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Why WMA?

• Construction

– Improve compaction

– Introduce longer paving season

– Allow longer haul distances

– Increase use of RAP

• Environmental Benefits

– Reduced energy consumption (fuel use)

– Reduced emissions (plant, at the paver)

Page 4: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Manitoba’s Goals for WMA

• Obtain hands on experience with WMA technology

• Contractor friendly - little or no modifications to asphalt plant

• WMA to be an acceptable alternative to HMA

Page 5: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%
Page 6: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

WMA Project

Location

PTH 14

length - 12km (7.5 miles)

Page 7: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Project Details

• Tendered as a WMA project

• Rehabilitation project (mill and fill)

– Mill

• 35mm (1-1/2”)

– Fill

• Lower lift: 50mm (2”), 35% RAP

• Top lift: 50mm (2”), virgin mix

Page 8: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Project Details

• No specification changes

– HMA mix design = WMA mix design

– Temperatures

• To reduce variables, add additive at the

plant

Page 9: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Products Used

• Advera (zeolite) – 0.25% weight of total mix (will not vary with RAP)

Page 10: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Products Used

• Sasobit (wax) – 1.5% of total weight of asphalt cement

Page 11: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Products Used

• Evotherm DAT System (chemical) – 0.5% by weight of asphalt cement (with RAP)

– 0.3% by weight of asphalt cement

Page 12: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Project Layout

500 m 3 km 1 km 3 km 1 km 3 km 500m

HMA Advera HMA Sasobit HMA Evotherm HMA

HMA

35%

RAP

Advera

35% RAP

HMA

35%

RAP

Sasobit

35% RAP

HMA

35%

RAP

Evotherm

35% RAP

HMA

35%

RAP

Top Lift

50 mm (2”)

Bottom Lift

50 mm (2”)

(0.3 mi.) (2 mi.) (0.6 mi.) (2 mi.) (0.6 mi.) (2 mi.) (0.3 mi.)

Page 13: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

WMA Project Specifics

• Construction end of May – end of June

• Haul distance – 24 km (15 mi.)

(time ~ 30 minutes)

• Temperatures

– Air Temperature ~12–27ºC (54–81ºF)

Page 14: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

0

20

40

60

80

100

120

140

160

Mixing (plant) Compaction (paver)

Te

mp

era

ture

(C

)

HMA

WMA

Mixture Temperatures

23ºC (73ºF)

25ºC (77ºF)

148ºC (298ºF)

125ºC (257ºF)

135ºC (275ºF)

110ºC (230ºF)

Page 15: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Emissions Testing

• Asphalt Plant Emission Testing

– Stack tests – US EPA test methods

– Confirmed reduction in concentration and

emission rate of carbon monoxide

– Correspondingly a reduction of fuel

consumption

– Other gas components were inconclusive due

to variability

Page 16: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Emissions Testing

• Paving Site Air Quality Testing

– Emissions were well below occupational

exposure limits

• Emissions Testing on Fresh Asphalt

– Emissions were low

Page 18: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Monitoring Plan

• ARC will be monitoring the 150m (500’)

sections annually (crack mapping)

• Manitoba collect annually

– Ride (IRI)

– Rut

– FWD

– 150mm (6”) cores

Page 19: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Future WMA Projects

• 2010 – Evotherm (additive in asphalt cement)

– Long haul (170 km – 106 mi.)

– Extended paving season

• 2011

– Tender as WMA/HMA? Specify WMA? Approved Products List?

– Foamed WMA

– Other products

Page 20: with Warm Mix Asphalt - … - Manit… · with Warm Mix Asphalt Tara Liske, M.Sc. P.Eng. ... HMA Advera HMA Sasobit HMA Evotherm HMA HMA 35% RAP Advera 35% RAP HMABottom Lift 35%

Questions?

Thank You