Lisa Darling, Executive Director Rick Marsicek, Director of Engineering South Metro Water Supply Authority October 5, 2017 WISE Update and South Metro’s Progress to Sustainable Water Supplies Water Resources Review Committee
Lisa Darling, Executive DirectorRick Marsicek, Director of EngineeringSouth Metro Water Supply Authority
October 5, 2017
WISE Update and South Metro’s Progress to Sustainable Water Supplies
Water Resources Review Committee
Who We Are
2
• 13 Members
• Serve 300,000 people
• Projected to serve 550,000 people by 2050– 80% of Douglas
County– 10% of Arapahoe
County
• Goal: Shift away from nonrenewable sources of water
• Plan based on three pillars1. Partnerships – Leverage relationships with each other, local
governments in the region, and other water providers
2. Investment – In supply and storage projects, individually and
collectively
3. Efficiency – Become a leader in conservation and the efficient
use of water
3
2004: South Metro Water Supply Authority
4
2016 Master Plan Update1999
Metropolitan Study
2003
South Metro Water
Supply Study
2007
Master Plan
2011
Master Plan Update
Shift to Renewable Supply• Early 2000’s: 60% nonrenewable; Many of the region’s
largest water providers were 100% nonrenewable
• By 2020: 22% nonrenewable
• By buildout (2065) it will be down to 15%
• Some entities are already almost
completely renewable on average
5
Tremendous Progress
Conservation and Efficiency
• Reduced per capita water demands across the region by 30%
• The region currently averages about 120 GPCD.
• The region is set up to reuse all of the supplies that are legally able to be reused.
6
0
50
100
150
200
250
2000 2010 2014
Gal
lon
s p
er c
apit
a p
er d
ay (
gpcd
)
Regional Per Capita Water Use (gpcd)
Tremendous Progress
ACWWA/ Cottonwood Joint Water
Purification Facility
WISE Project: Smoky Hill Tank
ECCV Northern Project
Chatfield Reallocation Project
Plum Creek Water
Purification Facility Rueter-Hess Reservoir
WISE Project: Quebec St.
Water Purification Facility
WISE Project: Aurora
Temporary Connection
Progress: Projects
8
WISE:Regional Collaboration
• Centennial Water and Sanitation
• Cottonwood Water and Sanitation
• Dominion Water and Sanitation
• Inverness Water and Sanitation
• Meridian Metropolitan District
• Parker Water and Sanitation District
• Pinery Water and Wastewater
• Rangeview Metropolitan District
• Stonegate Village Metropolitan
• Town of Castle Rock
South Metro WISE Authority
Aurora Water
Denver Water
Denver & Aurora Water
Supplies
Aurora’s PWP Infrastructure
Delivery to Aurora, Denver,
& SMWA
Uses $800 million in existing infrastructure• Cost Recovery for Aurora’s
Investments• Purchase of existing “Western
Pipeline”
Construction of ~$120M of new infrastructure
What is WISE?
• Aurora Water– Offset PWP costs (annual revenue of $10M)
– Continued use of PWP for drought supply
• SMWSA– Renewable supply for SMWSA (100KAF/10yr)
– Allows use of Denver Basin aquifer for drought supply
• Denver Water– Drought and emergency supplies for Denver
Opens the door to regional cooperationTotal Affected Population = 2 million 10
WISE:
Water Supply Benefits
WISE Timeline
12
2007 Began Planning
2013 WISE Water Delivery Agreement Executed
2014 WISE/DW Purchase of ECCV Pipeline
2015-2016 WISE infrastructure construction
June 2017 -- Final Completion of WISE Pipeline Modifications
Summer 2017 -- WISE Water Deliveries began to some WISE Members
Early 2018 – WISE Deliveries will begin to remaining members
WISE AGREEMENTS
13
WISE Infrastructure
WISE PIPELINE
- $34M Purchase
Aurora Water Connection
March 29, 2016
March 29, 2016
August 21, 2016
Smoky Hill Tank
April 1, 2015
August 6, 2015 September 10, 2015
Smoky Hill TankSeptember 28, 2015
October 28, 2015
April 20, 2016July 13, 2016
BEFORE
AFTER
Quebec Street Water Treatment Plant
March 17, 2015
March 15, 2016April 20, 2016
Quebec Street Water Treatment PlantMay 31, 2016
September 22, 2016
May 31, 2016 DW Bypass
February 2016
Pipeline Connections
ECCV Connection
January 18, 2017
Cottonwood Connection
February 1, 2017
Ridgegate Connection
January 31, 2017
Managing 10 Connections
22Partner Ordering Portal
Orders Entered into SCADA System
Summary of WISE Phase I Construction Costs
23
*Does not include investment by each WISE
Member for individual connections
2014 BudgetTotal $ 11.90
Denver Water $ 3.45 ECCV $ 3.45
WISE $ 5.00*
WSRA Grants $ 1.57
Summary of WISE Phase I Construction Costs
24
*Does not include investment by each WISE
Member for individual connections
2014 Budget Final CostTotal $ 11.90 $ 16.06
Denver Water $ 3.45 $ 3.45 ECCV $ 3.45 $ 3.45
WISE $ 5.00* $ 9.16*
WSRA Grants $ 1.57
Summary of WISE Phase I Construction Costs
25
*Does not include investment by each WISE
Member for individual connections
2014 Budget Final CostTotal $ 11.90 $ 16.06
Denver Water $ 3.45 $ 3.45 ECCV $ 3.45 $ 3.45
WISE $ 5.00* $ 9.16*
WSRA Grants $ 1.57 $ 2.49
WISE - SRF Loans
26
• 4 WISE Members received State Revolving Fund Loans totaling $35M to help pay for:
• Pipeline purchase
• Phase I infrastructure
• Future Infrastructure
Thank You !
Future WISE Infrastructure
1. Additional increment of
supply: ~30KAF of additional renewable supplies by 2065
2. Storage (surface and ASR) to
firm existing and new supplies
3. TDS management for new supplies and WISE supplies: Blend water or RO
4. Conservation: Individual member’s efforts and regional
28
Non-Renewable16,900 AF
14%
Renewable72,240 AF
60%
Planned Renewable20,000 AF
17%
Renewable Goal11,307 AF
9%
SMWSA Projected Supplies at Buildout (2065)
Non-Renewable Renewable Planned Renewable Renewable Goal
The Path Forward:
Our 4-Point Plan for the Future
Despite ongoing needs, our region is well on
its way to a secure water future.
29
The Bottom Line
Questions?
30