Top Banner

of 42

Wind Farm-Fesaibility Study

Apr 04, 2018

Download

Documents

Mosherif3891
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/30/2019 Wind Farm-Fesaibility Study

    1/42

    1

    PRMG 050:

    Projects Feasibility Studies

    FEASIBILITYSTUDYOF120MWWINDPARK

    PROJECTMEMBERS

    HASANIEN,AHMEDKAMAL ID:700081207

    HUSSEIN,MOHAMEDHAMDY ID:700081206

    MOHAMED,AHMEDSAMYYOUNIS ID:700081205

    OSMAN,YASSERAHMED ID:700081186

    SHARARA,KHALEDMAGDY ID:700081345

    Spring2009 Section1

  • 7/30/2019 Wind Farm-Fesaibility Study

    2/42

    2

    TableofContents1.Introduction........................................................................................................................................................ 3

    1.1ReliabilityofRenewables.............................................................................................................................. 5

    1.1.1. ElectricityGenerationCosts............................................................................................................ 5

    1.1.2. LandAreaRequirements................................................................................................................ 5

    1.1.3. Controllability................................................................................................................................. 6

    1.1.4. Availability...................................................................................................................................... 6

    1.1.5. Security........................................................................................................................................... 7

    2.EnergyMarketStudyinEgypt........................................................................................................................... 8

    2.1WindEnergyMarketinEgypt........................................................................................................................ 8

    2.2Economic,SocialandEnvironmentalImpactasResultofWindEnergyProjectsinEgypt ........................10

    3.Wind

    Park

    Site

    ..................................................................................................................................................

    11

    3.1GabalElZytSite............................................................................................................................................ 12

    3.2ZafaranaSite............................................................................................................................................... 14

    4.TechnicalStudy................................................................................................................................................. 16

    4.1WindParkmanufacturingComponents ..................................................................................................... 16

    4.2WindParkComponentsContributiontoCost............................................................................................. 19

    4.3WindParkComponentsContributiontoCost............................................................................................. 20

    4.3.1.

    Wind

    Turbine

    Parameters

    ............................................................................................................

    20

    4.3.2. TurbinesLoses.............................................................................................................................. 21

    4.3.3. Turbulence ................................................................................................................................... 21

    4.3.4. TechnicalSummary....................................................................................................................... 22

    4.3.5. Estimationofcosts........................................................................................................................ 22

    5.EconomicEvaluation ........................................................................................................................................ 24

    6.Cocnlusions........................................................................................................................................................ 28

    7.References

    ........................................................................................................................................................29

    8.Appendices ....................................................................................................................................................... 30

  • 7/30/2019 Wind Farm-Fesaibility Study

    3/42

    3

    1. IntroductionWith the rapidly growing demand for electrical power in Egypt and the finite life of

    conventionalfossil fuels (oil,gasandcoal)coupledwiththeiradverseeffectsonpollutionof

    the environment and global warming, there is a critical need to increase the percentage of

    electricpowergenerationinEgyptfromrenewableenergy.

    Egyptselectricitydemandisprojectedtoreach120GWin2050.Duetothelimitedfossilfuel

    resources, it isexpected that theirpricecontinues torisedramatically in the future.On the

    otherhandclimatechangeobligeshumanitytoreactaccordingly.

    TheEgyptianelectricitygridispredominantlyfossilfuelfired.Renewableenergy,consistingof

    mostlylargescalehydro,isresponsibleforjustunder20%ofgeneration.Apartfromthehydro

    facilities, the existing Zafarana wind facilities comprise this category. The remainder, more

    than 80% of electricity including those purchased from independent power producers, is

    produced

    from

    conventional

    plants.

    Due

    to

    the

    abundance

    of

    natural

    gas

    in

    Egypt,

    approximately 90% of the fossil fuel used in the conventional plants is natural gas and the

    remaining10%fueloil.

    As is the case for most nonhydropowerdominated grids, hydro plants are considered low

    costandthereforenotmarginal.Thesamecanbesaidforwindpower.Itisofnotethatunlike

    many grids which utilize hydro facilities during peak demand to take advantage of their

    responsiveness to varying demand, Egypts hydro facilities provide mainly base capacity

    power,withamarginlefttorespondtopeakdemand.Thisisduetothefactthattheirrigation

    needsofagriculturalactivitiestakeprecedencewhendeterminingthewaterrelease,whichis

    controlled

    by

    the

    Ministry

    of

    Irrigation.

    In

    the

    context

    of

    the

    baseline

    determination,

    thiscircumstanceisinagreementwiththeapproachtoexcludehydropower,astheProjectwillin

    nowayaffectthepowergeneratedfromhydropowerfacilities.

    Theremainingfacilitiesintheoperatingmarginaregasturbine,steamturbineandcombined

    cycle conventional units fuelled by natural gas and fuel oil. This is a conservative

    representationoftheactualoperatingmargin,giventhatthemostlikelymarginalplantstobe

    displaced are low efficiency fuel oil and natural gas facilities, instead of the average of all

    thermal power plants. Improving energy efficiency and shifting to cleaner and noncarbon

    energysourcesareessentialtoimprovethecountrysenvironmentandhelptomitigateglobal

    climatechange.

    Withayearlyaveragegrowthofabout6%,Egypt isexpectingto increase its installedenergy

    from17 GW in 2002 to50 GW in2020andwith asmaller increase rate to 120 GW in year

    2050.Thisincreasewillexhaustthebudgetiftheadditionalelectricityisproducedfromfossil

    fuelsonly.Thereforethetargetof55%REshareisverymodestandshouldbeachievable.

  • 7/30/2019 Wind Farm-Fesaibility Study

    4/42

    4

    Table1EnergyProjectionsinEgyptandREFuturetrends

    Year 2002 20.1 2020 20.5

    EgyptREshare 16% 20% 30% 55%

    EgypttotalElectricity 17GW 27GW 50GW 120GW

    Egypttotal

    RE

    share

    2.7

    GW

    5.4

    GW

    15

    GW

    66

    GW

    EgyptHydroshare 15% 2.5GW 10% 2.7GW 6% 3.0GW 2% 3.0GW

    EgyptWindshare 1% 0.2GW 8% 2.2GW 12% 6.2GW 17% 20GW

    EgyptSolarshare 0% 0GW 2% 0.5GW 12% 5.8GW 36% 43GW

    Asthehydroenergycannotbeincreasedafter2020,theremainingREsharemustbecovered

    by wind and solar energy; however, wind alone cannot cover the demand because of its

    fluctuating character.Thegood wind areas are allaligned inwindmain direction on the

    shoresoftheredseawhichmeansthatawindstillwillaffectthemalltogether.

    Leading countries in the use of RE, like Germany made the experience, that RE must be

    generatedfromdifferentsourcestoensureareliableenergysupply.Thereforethekeyforthe

    solution is a mix of different renewables, otherwise serious supply gaps may occur. At the

    moment,windenergygenerationisthemosteconomicREafterhydroenergy.However,solar

    thermalgenerationhas thegreatadvantage that itcandesalinateseawaterwith thewaste

    heat,givingmillionsofmofdesaltedwaterneededinthenearfutureforthedevelopmentof

    Egyptatreasonablecosts.

    Moreover,planningforthefuturemustalsoconsiderthecostreductionpotentialswhichsolar

    thermal

    generation

    still

    has;

    one

    can

    expect

    that

    solar

    thermal

    generation

    will

    be

    considerably

    cheaperthanbothwindenergyandenergyproductionfromfossilswhosepricesdonotclimb

    upastheoilpricedoes.

    This paper presents a feasibility study of potential wind energy developments in Egypt by

    studying the implementationofawindpark asan environmental friendlypower generation

    solution comparing between the current viability of the alternatives of wind park sites

    betweenZafaranaandGabalElZytsettingthefactorstodeterminethemostfeasiblesite,also

    comparing between 2 of the wind turbines manufacturers Gamesa and Vestas selecting the

    most

    feasible

    alternative

    as

    well.

    However

    well

    discuss

    first

    the

    obstacles

    prevented

    us

    from

    pickingthesolaralternativebeforegoingthroughthemarketandtechnicalstudies.

  • 7/30/2019 Wind Farm-Fesaibility Study

    5/42

    5

    1.1ReliabilityofRenewables

    Egypt is theonlyplace in theworldwherebothsolarandwindpotentialsareavailableata

    highqualityandinthemeantimerelativelyneartothedemandofelectricity.Itistheoretically

    possibletoproducethewholeenergydemandofEgyptfromwindorfromthesun.Butwhich

    optionispreferableanswerthisquestion,onemustconsiderapackageofseveraltopics:

    Electricity

    generation

    costs,

    Landarearequired,

    Controllability,

    Availability,and

    Securityofelectricitysupply.

    1.1.1.ElectricityGenerationCostsCostsaregenerallythemostimportantfactortodecideaboutaninvestment.Inthisparticular

    case,namelydealingwithrelativelynewtechnologies,onemustconsiderbesidethecostsat

    thepresenttimealsodevelopmentofcostsinfuture,e.g.after20years.Startingwithpresentcostswewilltrytomakeacomparisonbetweenwindenergyandsolar

    energy considering the optimal benefits of each. Assuming a square kilometer of desert,

    equipped with the most modern and most efficient solar thermal system now available

    workinginhybridoperationwithasolarshareof35%itwillyieldperyear:

    300GWhelectricityatacostof0.05$/kWhtotaling15.0million$

    +

    13millionmdesaltedseawaterat0.70$/mtotaling9.1million$

    (Combinedgenerationusingwasteheat,noextraenergyneeded)

    To produce the same quantities (electricity + desalted water) from a good wind park with

    45005000fullloadhoursperyear,followingcostswilloccur:

    300GWhelectricityatacostof0.03$/kWhtotaling9.0million$

    +

    13millionmdesaltedseawaterat1.10$/mtotaling14.3million$

    (ProducedbyReverseOsmosisusingelectricpower)

    Thetotal

    cost

    of

    both

    products

    together

    gives

    24.1

    and

    23.3

    million

    $/year

    respectively.

    Thus

    wind power is only 3% cheaper in the present time. However the solar power costs are

    expectedtoflattendownwithinthenext20years.

    1.1.2.LandAreaRequirementsContinuingwiththeexampleabove,1km isneededtoproduce300GWh/ysolarelectricity

    and13millionmofdesaltedseawater.Weadd0.1kmforthedesalinationequipmentthus

    totalingto1.1km.Toproducethesameelectricityfromwindwith45005000fullloadhours

  • 7/30/2019 Wind Farm-Fesaibility Study

    6/42

    6

    we can calculate with a wind mill density of maximum 7.5 MW/km. A higher density will

    causereductionofproducedelectricity fromthefield.Thiswillgive8.4km.Toproducethe

    same water quantity with reverse osmosis (RO)we will need8kWh/m which calculates to

    104 GWh.Asupplemental area for producing thiselectricitywill beneeded whichgives2.9

    kmthetotalareaneeded is11.3kmwhich is10timesasmuchasforthesolarapplication.

    The desert area may be cheap, but looking at this disproportion we have to think about

    parameters

    like

    cable

    lengths

    needed

    and

    time

    consumed

    by

    maintenance

    personnel

    to

    reach

    allunitsinthefield.

    1.1.3.ControllabilityControllability isthecapabilityto followtheupsanddownsofthedemandduring24hours.

    SolarHybrid power stations, which are the present object of this comparison, are working

    exactlylikefossilfiredpowerstationswiththedifferencethatduringthedaylessfuelisburnt

    becauseitispartlysubstitutedbythesunheat.Futureoptionsaresolaronlypowerstations

    with thermal storage allowing continuous operation. In both cases the power station is

    controllable

    in

    the

    same

    manner

    like

    conventionally

    fired

    power

    stations,

    backup

    capacity

    for

    thefluctuatingsolarresourceisintegratedwithintheplant.

    Ontheotherhandwindisroughlypredictablebutnotcontrollableandstorageofwindpower

    is only possible in rechargeable batteries which are so expensive that they cannot be

    considered for largeapplications.For thisreasonwindparksareworkingwithingridswhere

    thecontrolislefttothethermalbackuppowerstationsconnectedtothegrid.

    1.1.4.AvailabilityAvailability isthecertaintytodeliverelectricitythroughtheyear.Forthereasonsmentioned

    under

    the

    third

    topic,

    availability

    is

    achieved

    with

    hybrid

    solar

    power

    stations

    without

    anyproblems.InEgyptitisevenadvantageousbecausetheelectricitydemandinsummerisabout

    20%higherthaninwinter,whichisfullyconsistentwiththeseasonaltrendofthesolarenergy

    resource.Oncloudywinterdaysthehybridsolarpowerstationwillusefossilfuelorheatfrom

    thestoragewithoutrestrictionofavailability.TheuniquesolarenergyresourceofEgypt(upto

    3000 kWh/m/year) and thermal energy storage allows for aroundtheclock operation

    throughthewholeyearlikeabaseloadfossilfuelplant.

    Wind,however, issubject toseasonal fluctuations.Goodwindsites liketheGulfofSuezare

    highly affected as the site is lengthily extended in main wind direction. This negative effect

    may

    be

    partly

    compensated

    by

    connecting

    wind

    parks

    in

    different

    areas,

    e.g.

    Red

    Sea

    andNorthernCoast,takinginaccountthelessfavorablewindconditionsintheNorthCoast.Even

    thenavailability isnotguaranteed,soalwaysfreecapacitiesofthermalpowerstationsmust

    bekeptwithinthegridinthebackground(calledshadowpowerstations).Capitalcostsofsuch

    power station capacitiesmust be taken inaccountwhen considering a large scalesupplyof

    windenergyinthegrid.

  • 7/30/2019 Wind Farm-Fesaibility Study

    7/42

    7

    1.1.5.SecurityInsummer2003severalblackoutsoccurred inUSAandEurope,mainlybecauseoffailuresof

    transmissionlineswhichleadtooverloadingandthustrippingofseveralpowerstations.

    Thiscanbeavoidedbyincreasingtheavailablethermalpowerstations(includingsolarthermal

    power

    stations)

    connected

    to

    the

    grid,

    but

    not

    by

    adding

    wind

    power.

    Wind

    power

    has

    in

    generala destabilizingeffect on thegrid,which has to becompensatedbyother resources,

    likehydropowerorthermal(solar)powerstations.

    Finally Controllability, availability and security of electricity supply are as important for a

    modern society as generation costs. Experience in Germany in summer 2003 with long

    periodsofwindstill demonstratedthe importanceofthesefactors.Forthisreasonexperts

    recommendthatthewindshareshallnotexceed20%inanelectricitygrid.

    Production of desalted seawater from waste heat and the future perspective for a

    considerable

    cost

    reduction

    of

    solar

    thermal

    power

    stations

    makes

    it

    essential

    that

    they

    get

    sufficientsupporttodevelopforthefuture,forthoughWindenergy isaverygoodchoice in

    thepresent,wheresolarthermalenergyisessentialforthefuture.

  • 7/30/2019 Wind Farm-Fesaibility Study

    8/42

    8

    2. EnergyMarketStudyinEgyptThe electricity sector is facing a number of challenges and constraints in securing the

    electricity demand for Egypt in the coming decade. The most pressing issues include the

    havingsufficientbaseandpeakloadcapacity,ensuringtheavailabilityofnaturalgasforpower

    production(atpricelevelsthatcanbeabsorbedbytheretailelectricitytariff),succeedingwith

    the

    ambitious

    renewable

    energy,

    as

    well

    as

    other

    energy

    efficiency

    measures

    and

    continuing

    thepathoftariffandsubsidyreform.

    2.1. WindEnergyMarketinEgyptEgypt isworkingveryhard to develop its renewable energy (RE) resources, includinghydro,

    windandsolar.Hydroelectricpowercapacityhasbeenalmostfullyexploredwithaninstalled

    capacityof 2,780 MWandannual energyproductionofabout12,650GWh. Wind andsolar

    energyareintheearlystagesofexplorationandutilization.InApril2007,theSupremeCouncil

    for Energy adopted an ambitious plan which aims at having 20% of the country's installed

    capacity

    in

    the

    form

    of

    RE

    by

    2020.

    Notably,

    over

    10%

    of

    this

    i

    s

    expected

    to

    come

    from

    wind

    energy, which translates into about 7,200 mega watts (MW)of grid connected wind parks.

    Thedevelopmentofthisatsuchalargescaleisbeingdesignedbased,onaprivatesectorled

    strategy,ofwhichtheWorldBankisprovidingtechnicalassistance.

    TheNewandRenewableEnergyAuthority(NREA),establishedin1983,isthemainagencyfor

    promotingandoperatingRE technologies.Atpresent,windandsolarenergyprojectsareat

    thecoreofNREA'scurrentandfutureplans.AWindAtlasfortheentirecountrywasissuedin

    2005indicatingabout20,000MWofwindpotentialintheGulfofSuezarea.Aseriesoflarge

    scalewindenergyprojectswereconstructedwithacurrentoperationalcapacityof225MW

    connectedto

    the

    national

    grid.

    Egypt

    is

    also

    implementing

    its

    first

    solar

    thermal

    power

    plant

    of

    140MW(solarshareof20MW)southofCairo,plannedtobeoperationalby2010.

    Ministry of Electricity and Energy started by implementing several experimental wind park

    projects which concluded the setting up of ambitious program for the construction of large

    windparkpowerplantsconnected to thenationalgridwith total installedcapacity reaching

    965MWin2011/2012.

    Itisnoteworthytomentionthat,in30/6/2008,theinstalledcapacityofthelargestwindpark

    intheMiddleEastregionandAfricaislocatedatElZafaranaonGulfofSuezreached305M.W

    andis

    connected

    to

    the

    national

    grid.

    Egyptian Electricity Holding Company (EEHC) cooperates with the NREA, responsible of

    disseminatingtheuseofnewandrenewableenergyresourcesinEgypt,throughthefollowing:

    Generation planning taking into consideration the contribution of the renewableenergy.

  • 7/30/2019 Wind Farm-Fesaibility Study

    9/42

    9

    Network planning to ensure the capability of power transfer from the renewableprojects.

    Purchase energy generatedfrom the wind parks at

    reasonable price to

    encourage the use of

    renewableenergy.

    Prepare the power purchase

    agreements from the wind

    parkswithareasonableprice

    to encourage the use of

    renewableenergy.

    Figure1WindEnergyImplementationTrendtill2011/2012inEgypt

    The above figure shows the government plans till 2011/2012 for the wind parks

    implementations

    which

    shall

    reach

    to

    956

    MW

    installed

    and

    connected

    to

    the

    grid

    by

    an

    annualincrementof20%tothenationalgridbyusingwindenergy,howeverthegovernment

    longtermplanswhichsymbolizethecontributionofrenewableenergytoreach20%oftotal

    energy generated in 2020(8%hydro&12% wind) gives the wind energy the desired

    environmentrequiredbytheinvestortogothroughtheinvestmentsinwindenergyinEgypt.

    ;SoinordertoachievetheEgyptian2020strategyofthewindenergyimplementationtherate

    ofwindparksinstallmentshavetobeaccordingly,about400600MWyearlyimplemented.

    Figure2Egypt's2020strategyforwindenergy

  • 7/30/2019 Wind Farm-Fesaibility Study

    10/42

    10

    2.2. Economic,SocialandEnvironmentalImpactasResultofWindEnergyProjectsinEgypt.

    TheCrudeoilexports isoneofthenational incomeofEgypt,thereforethefuelsavingcanprovideanincreaseinthenationalincomebyprovidingtheforeigncurrencydueto

    oilexportation.

    IncreasejobopportunitiesandhelpsolvingtheunemploymentproblemthatpositivelyaffectsthegeneraleconomicsituationinEgypt. New community is going to be established in the vast desert area in Zafarana that

    enhance localmigrationofpopulation from theNilevalley to theGulfofSuez.This is

    stillaproblemofpopulationdistributioninEgypt.

    The Zafarana wind park has very effective and positive environmental impact, theoperationofthe600MWwindparkswillproduce42,000millionkWhallovertheir20

    years life time, that in turn will save 10 million tons oil equivalent and will abate the

    emissionofthefollowingquantitiesofgreenhousegases:588MiotonCox,2.1Mioton

    NOx,8.4

    Mio

    ton

    Sox.

    As a result for the above discussed points, we decided to study the feasibility of the

    implementationofthe120MWwindparkasanintendedfigurebythegovernmentasithas

    beenrecentlytakenastheannualdevelopmentstep inthewindenergycapacity inEgypt

    (shown in figure1),and liesbelow theannual forecasteddevelopmentstepaccording to

    theambitionsoftheEgyptiangovernment inachieving7200MWbytheyear2020which

    hasbeendistributedinfigure2togivethattheannualstepshallbe400MWtill2011/2012.

    Thesefiguresgiveustheconfidenceaboutthemarketgapinthewindenergyaccordingto

    thefuture

    plan

    of

    the

    Egyptian

    government

    which

    the

    investor

    rely

    on

    as

    asolid

    platform

    forthedecisiontoinvestinsuchsectorinEgypt,andgivesanindicationtotheviabilityof

    theinvestmentenvironmentespeciallywhentheopportunitiesarenotonlycreatedbythe

    demand,butalsofromtheambitionoftheEgyptiangovernmentwhichmayfacilitatemore

    obstaclestoensureflexibleandsustainablesupplyofwindenergy.

  • 7/30/2019 Wind Farm-Fesaibility Study

    11/42

    3.Coa

    Ene

    par

    hig

    proEas

    oft

    The

    has

    Egy

    12

    alth

    tob

    avaineg

    An

    me

    tabl

    nor

    of

    Hur

    Red

    TheDar

    littl

    and

    spe

    win

    Tabl

    W

    indPark

    stal zone

    rgy pote

    icularly a

    est wind

    posed

    winernside

    eRedSe

    coastbet

    the mos

    pt with a

    m/s. Th

    oughpart

    eatouris

    lable

    foligiblecoa

    overall s

    suredatf

    e below.

    htosout

    lZyt are s

    ghada in

    Sea.

    measuregandZaf

    moreth

    resulting

    dandme

    dspeeda

    e2Overalls

    ibullAand

    Site

    s in Egy

    ntial. T

    the Gulf

    areas

    d

    park

    sitfEgyptcl

    .

    weenAbu

    t favorab

    erage win

    lands i

    ofthisar

    icresort,l

    wind

    st.

    mmary

    ourmain

    The stat

    ;AbuDa

    ituated al

    the nort

    wind

    dist

    arana,wh

    n18kma

    inalmosti

    anenergy

    ddirectio

    ummary199

    parameter

    pt enjoy

    e Red

    of Suez is

    f the wo

    es

    are

    sitsetothe

    Daragan

    le wind c

    d speeds

    s desert

    ea isbein

    largearea

    projects

    f the wi

    tationsis

    ions are

    ag,Zafara

    ong the G

    ernmost

    ributionsicharesit

    part,are

    dentical

    densities.

    n.

    195ofwind

    ,meanwin

    cal

    high wi

    Sea coa

    one of t

    rld; so t

    ated

    in

    tcoastalli

    dHurgha

    ondition

    between

    area, a

    develop

    oflanda

    at

    almo

    d climat

    givenint

    listed fro

    naandG

    ulf of Sue

    part of t

    tAbu

    ateda

    erysimila

    eanwind

    Thewind

    observation

    speed(U),

    satallfour

    11

    d

    st

    e

    e

    e

    e

    a

    in

    7

    d

    d

    re

    st

    s

    e

    m

    lf

    z,

    e

    r

    climatein

    s24.5ma.g.

    eanenergy

    stationsisle

    Fig

    thisarea

    l.atthefour

    density(E)a

    sthan0.1%.

    ure3Overvi

    issteady,

    mainstatio

    nddirection

    ewmapfort

    ithrespe

    s:datareco

    (DU).Theoc

    heGulfofS

    cttoboth

    eryrate(R),

    currenceof

    ezinEgypt

  • 7/30/2019 Wind Farm-Fesaibility Study

    12/42

    12

    ThewindclimateattheGulfofElZytstation,which issituatedattheentrancetotheGulfof

    Suezabout160kmtotheSouth,exhibitsthesamegeneralcharacteristicsasdescribedabove.

    Here,however,theWeibullAparameter issomewhathigher, leadingtoahighermeanwind

    speedand, inparticular toameanenergy densitywhich isabout40%higher thanZafarana

    area.LeavingtheGulfofSuezandenteringtheRedSea,thewindclimatechangessignificantly

    the

    character

    over

    the

    60

    km

    stretch

    between

    Gulf

    of

    ElZyt.

    The

    mean

    wind

    speed

    at

    Hurghada

    is only about two thirds and the energy density only about one third of the mean values

    measuredatGulfofElZyt.Thewindsarestillsteady.

    Figure4WindRosesshowthewindflowdirectionsatGabalElZytandZafaranaSites

    Egypt's Red Sea Coast region has two natural

    resources,landandstrongwindinenormoussupply.

    The

    2

    sites

    which

    shall

    lie

    under

    our

    study

    concern

    areZafarana,andGabalElZytsites.

    3.1. GabalElZytSiteThisareaislocatedtotheWestoftheHurghadaSuez

    roadandextendingabout70kmfromNorthtoSouth

    andabout9 to10km to the inland.Theareastarts

    about60kmintheNorthofHurghada.

    It is a desert area. Only at very limited spots some

    very

    scattered

    desert

    vegetation

    is

    observed.

    The

    southern part of about 55 km (reaching to about 5

    km to the north of the Wadi Dara road) is almost

    completelyconsistingofdesertplainsformedbythe

    extraordinarywind.Thisareaiscrossedbytwomain

    Wadis,theWadiDibbandtheWadiDara.However,

    due to the high wind speeds and the large sand

    Figure5SatellitemapofGabalElZytarea

  • 7/30/2019 Wind Farm-Fesaibility Study

    13/42

    13

    transport/ sedimentation potential, the wadi beds are not pronounced at most of the wadi

    courses.

    The northern part of the area shows both, undulated land and gravel desert plains. The

    westernsideofthisnorthernareashowshillsupto250mheight.

    Thegroundsurface inmostofthearea iscoveredwithcompactangulargravelsandpebbles

    formingwhatcanbecalleddesertarmor.Thelevelofthewholeprojectareaabovesealevel

    ranges

    from

    9

    m

    below

    sea

    level

    in

    the

    north

    eastern

    side

    to

    hills

    and

    slightly

    elevated

    mountainsrisingtolevelsof250m inthewest.Ingeneral,thesmallermountainousareasin

    theNorthwestwouldbekeptfreefromwindpowerdevelopmentbecauseofdifficultaccess

    conditions.

    Inadditiontherearesomeoftheareacharacteristicswhichshallbealsotaken intoaccount

    especiallyastheymayhavean impactonthecostofthe implementationoftheprojectand

    might affect the project capital cost by a percent of raise according to such characteristics

    shownasfollows:

    Infrastructure:Theprojectareahasnoinfrastructureexceptafewdeserttracks,gravelroads

    and

    the

    crossing

    asphalt

    road

    to

    the

    Wadi

    Dara

    settlement.

    The

    next

    settlement

    is

    atminimumdistancesofabout800mfromtheborderofthearea.

    Connection to the Grid: Electricity transmission denotes bottlenecks for a first stagewind power development at this area, as the double circuit 230 kV transmission line

    HurghadatoZafaranamustbeavailabletoallowanadditionalfeedfromthegenerated

    electricityfromGabalElZyt.

    Hub Height: According to the geographical characteristics of thisarea theheightof the turbine hubmustbe 100m to function the

    windspeedofthisarea.

    Theabove

    stated

    characteristics

    of

    the

    Gabal

    ElZyt

    site

    would

    definitely

    affect the investment cost of the wind park; that is because of the Site

    preparation and construction measures which exclusively have to be

    performedforthissiteas:

    ExtraExcavation,backfillingandcompactionworksforroadsandplatformconstructionaswellasforfoundationsandtrenchesto

    overcometheareageographicalcharacteristics.

    Reinforcementof theZafarana transmission lineswhichshallbedonebytheconstructionofanadditional linesfromZafaranato

    thecentral

    power

    grid

    along

    the

    way

    to

    Hurghada.

    Perform a modification to the tower engineering (Material,Fabrication, and Erection Management) according to the extra

    heightofthehubwhichwillleadtoatowerheightof100m.

    These counter measures for site preparation and construction would affect the investment

    costby25%ofraisethantheregularinvestmentcostofthewindparkdueto10%increasein

    thetowerengineering,10% forthereinforcementofthetransmission lines,andan increase

    5%duetotheextracivilworks.

    Figure6HubHeight

  • 7/30/2019 Wind Farm-Fesaibility Study

    14/42

    14

    3.2. ZafaranaSite

    Figure7LocationofZafaranasite

    The site is located in Egypt on the western shore of the Bay of Suez approximately 200 km

    southeastofCairo,onthe inlandsideofahighwayalongtheSuezGulfcoastline.Thesite is

    located

    in

    a

    desert

    area

    with

    favorable

    wind

    conditions.

    There

    is

    no

    human

    activity

    in

    the

    vicinity of the site, with the nearest commercial activity being several resort hotels

    approximately10kmfromthesite.Thenearestcommunityissome30kmaway.

    Due to the established former phases of the wind parks at Zafarana site; this site shows

    readinesstothefurtherimplementationsofmorewindparksastheexpertspredictstobethe

    largestwindparkintheworld.ThesiteleadsGabalElZytinthematterofinstantreadinessto

    have further expansions of the capacity of the site from the power production as the

    infrastructureofthesitehasbeenestablishedandalwayssubjectedtomodificationstocope

    withtheplansofthesitedevelopments.

    Wearent

    showing

    supremacy

    of

    Zafarana

    site

    to

    Gabal

    ElZyt,

    but

    it

    amatter

    of

    readiness

    for

    theprivateinvestorZafaranasitedenotesabusinessopportunitymorethanGabalElZytshows

    howeverthepotentialliesintheinvestmentatGabalElZytisveryenormouswheretheenergy

    experts, The Egyptian Government, and the world global funding and environmental assure

    thatthewindenergyfutureinEgyptshallbedrawnatGabalElZyt.Forthoughallthefeasibility

    studiesconsiderGabalElZytasafeasiblesiteforthelargescaleimplementationofwindparks

    about10002000MW;thatswhentheextra25%forthesitepreparationandtheconstruction

  • 7/30/2019 Wind Farm-Fesaibility Study

    15/42

    15

    measures vanishes in front of the hugeness of the project scale and the total revenue

    expectedorbythegovernmentindecreasingsuchfactormayariseasaninvestmentrisk.

    As a matter of fact the government contribution by the infrastructure and the transmission

    linesofelectricitytransferbeenimplementedisthekeytoGabalElZytSupremacywhichshall

    benotonlycompetingwithZafaranabutalsobeatingitfromtheeconomicalfeasibilitypoint

    ofview.

    But

    for

    the

    current

    time

    being,

    Zafarana

    site

    shows

    more

    profitable

    opportunity

    more

    than

    Gabal ElZyt shows for the analysis conducted above and resulted in the difference in 25%

    increase in the total investment cost of the wind park construction at Gabal ElZyt. For the

    analysisresultsandfortheclearobviousreasonswhichreflectsthecurrentsituationZafarana

    siteshowsmorefeasibilityfor120MWwindparkconstruction.

  • 7/30/2019 Wind Farm-Fesaibility Study

    16/42

    16

    4. TechnicalStudy4.1. WindParkComponentsManufacturing

    Frame Assembly Once the yaw system is assembled with its yaw motors, column and

    hydraulic

    group

    and

    the

    rotational

    test

    is

    passed,

    this

    assembly

    is

    connected

    to

    the

    rear

    frame.

    Next, the rail beams and the service crane are installed, and cables are run to the control

    cabinet.

    Gearbox AssemblyThenacelleassembly isplaced within the lower housing,and thepower

    transformerandthemainshaft/gearboxsubsetareassembled.GearboxsubsetFrontframe

    Figure8FrameandGearboxAssemblies

    GeneratorAssemblyTheprocesscontinueswith thegeneratorassemblyandalignmentand

    theelectrical

    connection

    of

    all

    the

    components

    in

    the

    control

    cabinet.

    Once

    connected,

    the

    nacelleisgivenacomprehensivefinalverificationcheck,simulatingitswindparkoperation.

    Upper housing Assembly Once the nacelle verification test is passed the upper housing is

    assembledandthenacelleisreadytobesenttoitscorrespondingwindpark.

  • 7/30/2019 Wind Farm-Fesaibility Study

    17/42

    17

    Figure9GeneratorandUpperhousingAssemblies

    Gearbox Consists of three combined stages: 1 planetary stage and two helical stages. The

    multiplicationratiois1:100.5for50Hzmachinesand1:120.5for60Hzmachines.

    Generator Rated power electric generator. Highly efficient, it has 4 poles and is doublyfed

    withawoundrotorandsliprings.Therotationalspeedrangeisfrom900to1900rpm,witha

    ratedspeedof1680rpm.Theoutputvoltageis690VAC.

    Figure10GearboxandGenerator

  • 7/30/2019 Wind Farm-Fesaibility Study

    18/42

    18

    SteelTowerManufacturingFirstlyReceptionandQualityControlofSteelPlatesthecylinders

    formingthewindturbinetoweraremadefromplatedsheetsthatareflamecutandprimed.

    Then the sheets are inserted in a machine with three large rollers that shape the rings.

    Afterwards the rings are submerged arcwelded, forming sections of different lengths. The

    structureisplacedinsidethepaintinganddryingtunnel.Oncethetowerplatingisfinished,it

    isthengivenasurfacetreatment,consistingofadoublesteelshotpeeningandthreecoatsof

    paint.

    This

    provides

    a

    C

    5

    level

    protection.

    Once

    the

    tower

    is

    dry,

    all

    the

    service

    elements

    (such

    asplatformsandladders)aremountedonit.DependingontheModelandtherequiredheight

    (between14and29meters),eachsectionmaybemadeupofbetween4and12rings.

    BladesManufacturing

    BeamManufacturingUsingglassandcarbonfibermaterialsthathavebeenimpregnatedwith

    epoxy resin as a base, several cloth lengths are cut and placed in a mould. They are then

    subjected

    to

    a

    curing

    process.

    After

    applying

    a

    coat

    of

    paint

    which

    will

    act

    as

    a

    protectivecoating on the blade, glass fiber is used to manufacture the shells, following the same

    manufacturingprocessasforthebeam.

    AssemblyOncethetwoshellsarefinished,weproceedwiththeirassemblyandgluethebeam

    betweenthetwoshells.

    CuringTheassemblyispassedthroughthekilnoncemore,formingacompactunit.

    Figure11 WindTowermanufacturingStages

  • 7/30/2019 Wind Farm-Fesaibility Study

    19/42

    19

    TrimmingandPolishingThebladeassemblyisremovedfromthemouldandistransferredto

    the finishing area, where the leading and trailing edges of the blades are finished and

    subjectedtoafinalrevision.

    Figure12BladesManufacturingStages

    4.2. WindParkComponentsContributiontoCostAs stated above, in the manufacturing

    stagesofeachofthecomponents,eachof

    these components have their different

    sophisticated manufacturing technology

    which have an impact on the wind park

    cost. For though the given analysis made

    in figure 13, shows that the nacelle with

    its

    components

    which

    is

    mainly

    theturbine has the highest contribution to

    the cost of the wind park. From this point,

    we have to study the alternatives of the turbines manufacturers as to go through the most

    feasiblesolutionthroughthisstudyweshouldpickthefactorwiththehighestcontributionto

    thecostandperformtheeconomicalanalysisonthealternativetoreachtothemostfeasible

    alternative.

    Figure13SharesofWindParkComponentsbycost

  • 7/30/2019 Wind Farm-Fesaibility Study

    20/42

    20

    4.3. WindTurbinesAlternativesThetwowindturbinetypesunderconsiderationallowtheimplementationofawindparkof

    theenvisagedinstalledcapacitywithintheforeseenarea.Similarsizeoftheturbinesanda

    rotordiameterinacloserange(from52m[VestasV52]to58m[GamesaG58])leadstoa

    similarbasicparkdesignwhichhasthenbeenoptimizedintermsofparkefficiencyandenergy

    production,accordingtotheirdatasheets(Appendices)thetechnicalanalysisshallbe

    performed

    as

    follows

    for

    the

    most

    important

    technical

    aspects

    for

    an

    adequate

    evaluation

    for

    eachalternativebeforetheeconomicaloneandtoassuretheirsuitabilityaswell.

    Figure14GamesaG58andVestasV52theturbinesalternativeswhicharebeingconsidered

    4.3.1.WindTurbineParameters142xVESTAS:V52,HubHeight55m

    Nominalpower:

    0.850

    MW

    Controlsystem:Pitch

    Rotordiameter:52m

    142xGAMESA:G58;HubHeight55m

    Nominalpower:0.850MW

    Controlsystem:Pitch

    Rotordiameter:58m

    ThePowercurveofawindturbineisanimportantparameter,describingtherelationbetween

    thewind

    speed

    on

    site

    and

    the

    respective

    electrical

    energy

    output.

    Power

    curves

    and

    ct

    values

    (aparameter for thecalculationof thewakeeffect)of the turbinesunderconsiderationare

    givenintheappendices

  • 7/30/2019 Wind Farm-Fesaibility Study

    21/42

    21

    4.3.2.TurbinesLosesAfterpassingtherotorofawindturbine,thewindhasadecreasedspeedduetothekinetic

    energytakenawaybytherotorandincreasedturbulencecausedbytherotatingrotorandthe

    difference in speed compared to the undisturbed flow. Until the speed difference to

    undisturbed flow is not equalized, the result is a lower energy yield for the wind turbines

    following in the direction of the flow. These losses are called array or wake losses. The

    calculation

    of

    the

    wake

    losses

    of

    the

    wind

    turbines

    causing

    the

    so

    called

    shadowing

    effect

    betweenthewindturbines,wheretheresultsofbothofouralternativeswereasfollowsTable3ArraylossesatZafaranawindpark

    4.3.3.TurbulenceTo

    ensure

    the

    close

    spacing

    of

    the

    wind

    turbines

    will

    not

    affect

    (decrease)

    the

    lifetime

    of

    the

    turbineanditscomponents,aturbulencecalculationisnecessarywhichhasbeencarriedout

    byLI.The turbulenceof thewind flow isa factorwhichcausesstressand fatigue toseveral

    components of a wind turbine including blades, bearing and gearbox. It consists of the so

    calledambientturbulenceappliedtothewindflowbythecoarsenessoftheearth(vegetation,

    buildings,rocksetc.)andtheturbulenceaddedbytheotherwindturbinesofawindpark.

    Table4Turbulencesubclassesoftheselectedwindturbines

    Thewindturbinescheckingtheturbulenceimpactisgenerallyrequired;fortheproposedwind

    parklayoutsforZafaranasitehowever,noproblemsintermsofturbulenceintensityaretobe

    expected.

  • 7/30/2019 Wind Farm-Fesaibility Study

    22/42

    22

    4.3.4.TechnicalSummaryThehigherenergyyieldcalculatedfortheGamesaG58turbineismainlyrelatedtothelarger

    rotordiameteroftheseturbinescomparedtotheVestasV52turbine.

    Thefocusingtothegeneratedenergy

    yield however is not sufficient.

    Investment

    costs,

    indicated

    by

    the

    ratio specific investment costs ( per

    kWh)aremoresignificant,fordetails

    refer to the economical part of the

    Feasibility Study for the presented

    specificdatain$perkWh.

    4.3.5.EstimationofcostsThe estimation of costs has been

    performed

    according

    to

    the

    previous

    cases of implementations of wind

    parks at Zafarana where Vestas V52

    was implemented in Egypt at the

    second phase of Zafarana Wind Park

    and Gamesa G58 has been and is

    beingimplementedforthelastthreephasesandthecurrentlyconstructedone.

    The total investment costs are itemized and described in the table below according to the

    foreignmaterialcostsaswell as localcostcomponents inorder to increase theuseof local

    participationand

    local

    materials

    in

    this

    project

    which

    directly

    appear

    in

    the

    civil

    works

    cost

    and

    theelectricalworksaswell.Alsothecontributionofthelocaltowermanufacturertothetotal

    priceoftheturbinesastheturbinespriceisencompassingthewhole142turbineswithitsfull

    components(nacelle,rotor,blades,andtowers)

    Table5ItemizedCapitalCostsofZafaranaWindPark

    Whereaperiodof12monthswasassumedfortheconstructionoftheZafaranaWindPark,as

    previouslyhappenedforthelastfourwindparksbeenconstructedinEgypt.

    CapitalCosts VestasV52 GamesaG58

    Turbines $150,000,000 $147,000,000

    WindFarmEPC $1,392,000 $1,392,000

    Civil

    Works $8,215,000 $8,215,000Installations $670,000 $670,000

    ElectricalWorks $9,682,000 $9,682,000

    TotalInvestmentCost $169,959,000 $166,959,000

    USD

    Fi ure15 Ener YieldsofGamesaG58andVestasV52

  • 7/30/2019 Wind Farm-Fesaibility Study

    23/42

    23

    For the Operation and Maintenance Costs, The estimates havebeen modeled based on the

    experience of the former phases which have been constructed in Zafarana but for Vestas

    alternative thepriceswhereamendedaccording toVestasglobalcurrentpricesaswecould

    havereliedontheitformercaseinEgyptasithasbeenyearswhichmayaffecttheaccuracyof

    the

    results

    of

    the

    study.

    Annual

    O&M

    costs

    are

    categorized

    into

    three

    main

    components

    the

    operationcostsofbothlaborandequipmentsandwindmonitoringsystems,themaintenance

    costsincludingthescheduledpreventivemaintenanceandUnscheduledRepairformboththe

    sparepartsandthemaintenanceteammanhour,aswellasthemanagementcostofthewind

    park which is a portion related only to the 120MW phase which is a part from the whole

    systemofmanagingthewindenergyatZafaranainEgypt.

    Table6ItemizedO&MCosts

    AnnualO&MCosts VestasV52 GamesaG58

    AnnualOperationCosts $1,597,500 $1,562,750

    AnnualMaintenance

    Costs $3,622,300 $3,438,050

    AnnualWindFarmManagement $1,250,200 $1,250,200

    TotalAnnualO&MCosts $6,470,000 $6,251,000

    USD/yr

  • 7/30/2019 Wind Farm-Fesaibility Study

    24/42

    24

    5. EconomicEvaluationThe main purpose of an economic analysis is to help to design and select projects that

    contribute to the welfare of a country. Whereas the financial analysis evaluates the project

    fromthepointofviewoftheoperatingcompanyor IndependentPowerProducer (IPP), the

    economicanalysisevaluatestheprojectfromthepointofviewofthewholeeconomyofthe

    country.

    Thepurposeoftheinvestigationistocomparefromamacroeconomicstandpointthebenefits

    of the project with the costs it incurs, as is customary in any costbenefit analysis. The

    standard of evaluation for costs and benefits is a monetary quantification. To the greatest

    possibleextent,theprojectimpactsareevaluatedintermsofeconomicmarketprices.

    As inthetechnicalanalysis,twoScenarioshavebeenconsidered intheeconomicanalysisof

    theZafaranaWindPark:

    ScenarioI142VestasV52turbines

    ScenarioII142

    Gamesa

    G58

    turbines

    Theeconomicanalysis isconducted intheformofequalizingthevalueofgettingwindparks

    introducedtothepowersystemtothe inducedsavings inthepowersystem.Aneconomical

    modelhasbeenestablishedusedmanyof theevaluationmethods todetermine theproject

    feasibilityacrossthe2alternatives.

    Thefollowingprofitabilitycriteriaarepostulatedforthepurposesofthisanalysisrespectively:

    NetPresentValue(NPV)Presentvalue isthefinancialmathematicalexpressionusedforthe

    sumofthediscountedvaluesofatimeseries.Thenetpresentvalueisthedifferencebetween

    thepresentvalueofthebenefitsandthepresentvalueofthecosts.Theprojectisprofitable,if

    thenet

    present

    value

    is

    positive.

    Assensitivityanalysisvariousvaluesoftheinterestratewhereconsideredat20%and25%in

    additiontothebasicinterestrate15%.

    Internal Rate of Return (IRR) The internal interest is the social discount rate at which the

    presentvaluesofcostsandbenefitsareequal.

    Benefitscostratio(B/C)Thepresentvaluesofthebenefitsaredividedbythepresentvalues

    ofthecosts,andtheprojectisprofitableiftheresultantbenefitscostratioisgreaterthanone.

    Theeconomicbenefitsofthewindenergypowergenerationhavebeenconsideredasthecost

    ofsavedfueltogeneratethesameamountofenergyusingnaturalgas.AlsotheCO2emissions

    which isbeingmitigatedby the implementationof theWindEnergyaccording toa taxation

    system of 3$/t CO2 emitted by the same amount of energy production from a natural gas

    powerplantinthetermsofmarginemissionsfactortCO2/kWh

    Tobesustainable,oneof thebasicrequirements for thewindenergyproject is itsability to

    compete against conventional electricity generation technologies. In fact, within a business

  • 7/30/2019 Wind Farm-Fesaibility Study

    25/42

    25

    context electricity is a homogeneous commodity good and wind turbines are valued in the

    marketplacealmostexclusivelyasaproducerofelectricityand,aslongasmarketsforgreen

    powerandgreenhousegasemissionfreepowerdonotexist,canonlycompeteonprice.

    Thus, unlike new technologies in other industries, wind turbines cannot command a higher

    pricebasedonqualityfeaturesandstillcaptureamarketshare.

    Concerning the environmental impact Wind energy is regarded as environmentally friendly.

    Environmental

    impacts

    associated

    with

    wind

    park

    installations,

    such

    as

    noise,

    visual

    impact,

    andlanduse,aremeaninglessinthecaseoftheZafaranaproject.Theprojectisintendedtobe

    located inadesertareawithnohumansettles,sparsevegetation,andnoactivities,suchas

    airportsortelecommunicationfacilities,thatcouldbeaffectedbythewindturbinesoperation.

    Contrasting toothersituations (India, forexample)whererisingcostsof landconstitutesan

    importantbarrierforwindturbinesdeployment,theZafaranalocationpresentsnorestrictions

    onlanduse.Moreover,thewindparkoperationavoidsemissionsoflocalpollutantsassociated

    withconventionalthermalpowerplants,usuallylocatedintheproximityofurbancenters.

    TheEconomicalmodelbelowshowsallthecalculationsresults;todeterminethefeasibilityof

    the

    project

    across

    its

    two

    alternatives

    including

    all

    the

    market

    and

    technical

    studies

    parameterswerethemodelinputs.

    TheresultsshowthatselectingGamesaG58 isthemostfeasiblealternativeeventhoughtat

    differentinterestratesbytakingintoconsiderationtheworstcasescenariowhereaninflation

    mayoccurat25%andaccordingtothebenefittocostratio italsoturnedouttobefeasible

    thanVestasV52alternative.

    In determining the wind energy benefits, the avoided fuel costs are determined by the fuel

    prices and the fuel consumption to generate 120MW by natural gas was considered in

    additiontotheCO2emissionsreduction comparedtosamepowergenerationbynaturalgas

    at3$/MWh.

  • 7/30/2019 Wind Farm-Fesaibility Study

    26/42

    26

    Table7EconomicalandFinancialEvaluationModelfor120MWWindParkatZafaranaSite

    WindFarmPerformance Unit

    InstalledCapacity MW

    No.ofWindTurbines

    FullloadHours hrs/yr

    CapacityFactor

    TotalPowerProduction GWh/yr

    General

    EconomicLifetime years

    ElectricityValue $/MWh

    InterestRate

    CapitalCosts VestasV52 GamesaG58

    Turbines $150,000,000 $147,000,000

    WindFarmEPC $1,392,000 $1,392,000

    CivilWorks $8,215,000 $8,215,000

    Installations

    $670,000 $670,000ElectricalWorks $9,682,000 $9,682,000

    TotalInvestmentCost $169,959,000 $166,959,000

    AnnualO&MCosts VestasV52 GamesaG58

    AnnualOperationCosts $1,597,500 $1,562,750

    AnnualMaintenanceCosts $3,622,300 $3,438,050

    AnnualWindFarmManagement $1,250,200 $1,250,200

    TotalAnnualO&MCosts $6,470,000 $6,251,000

    EconomicalEvaluation

    NPV,i=15% $115,019,528 $119,474,788

    NPV,i=20% $44,349,422 $48,443,801

    NPV,i=25% $1,566,578 $5,442,665

    IRR 0.2523065% 0.2581560%

    TotalCost $435,229,000 $423,250,000 USD

    EUAC $10,880,725 $10,581,250

    EUAWBenefittoCostRatio 2.458034736 2.527603071

    EnvironmentalBenefits:CO2EmissionsReductioncomparedto120MW

    electricitygenerationbyNaturalGas at3$/MWh$1,645,200

    AnnualFuelSavingsComparedtoNaturalGasconsumptionto

    generate120MW

    USD/yr

    $25,100,000

    $26,745,200

    40

    90

    15%

    USD

    USD/yr

    USD

    Value

    120

    142

    4570

    57%

    548.4

  • 7/30/2019 Wind Farm-Fesaibility Study

    27/42

    27

    Figure16VestasV52CashFlowDiagram

    Figure17GamesaG58CashFlowDiagram

  • 7/30/2019 Wind Farm-Fesaibility Study

    28/42

    28

    6. ConclusionsTheresultsoftheeconomicanalysisarehighlypositive,showingthatthewindparkinallTwo

    Scenarios ishighlyeconomicallyfeasible.Thehighestresult isproducedbytheScenariowith

    theGamesaG58.

    A scenario analysis has been carried out for the wind park scenario with the highest IRR,

    highestB/CRatioandhighestnetbenefits,i.e.,theScenarioII(142GamesaG58turbines).

    Changesin(i) Avoidedcapacitycosts,(ii) Fuelprices,(iii) CO2penaltiesand(iv) ElectricitygenerationandtheirimpactontheIRRhavebeenevaluated.

    The scenario analysis shows that the variable with the highest impact on the IRR is the

    investment costof the wind park followed by the electricitygeneration estimates. Thebest

    results are obtained when decreasing investment costs by 15 %, whereas the impact on of

    increasingemissionpenaltiesisfromaneconomicpointofviewverylow.

    TheeconomicappraisaloftheZafaranaWindParkschemehasbeencarriedoutbycomparing

    thecash flowassociatedwithconstructionandoperationofthewindpark. In theappraisal,

    the avoided costs of thermal generation are regarded as benefits attributable to Zafarana

    WindParkProject.ThedifferencebetweenthecostsoftheZafaranaprojectandthebenefits

    oftheavoidednaturalgaspowerandenergyhasbeendeterminedovera40yearoperational

    periodduringoneyearofconstruction.

    The comparison of the proposed Wind Power Project with an equivalent thermal plant has

    been

    made

    for

    2

    different

    Scenarios

    (Vestas

    V52

    and

    Gamesa

    G58).

    The

    results

    show

    that

    all

    scenarios are economically feasible, however the best Scenario the wind park with Gamesa

    G58windturbines.

  • 7/30/2019 Wind Farm-Fesaibility Study

    29/42

    29

    7. References RenewableEnergyMixForEgypt Adapting and calibration of existing wake models to meet the conditions inside

    offshorewindfarms Casestudy2:Zafarana

    Wind Power Projects In The CDM: MethodologiesAnd Tools For Baselines, CarbonFinancing

    And

    Sustainability

    Analysis

    Zafarana

    park

    WindEnergyinEgypt FeasibilityStudyForALargeWindFarmAtGulfOfElZyt FeasibilityStudyofWindFarmConstruction WindpowerandtheCDM FinancingLargeScaleWindFarmsinDevelopingCountriesZafaranaWindFarm ZafaranaWindPowerPlantProjectDesignDocument WindAtlasforEgypt

  • 7/30/2019 Wind Farm-Fesaibility Study

    30/42

    30

    8. Appendices VestasV52DataSheet GamesaG58DataSheet

  • 7/30/2019 Wind Farm-Fesaibility Study

    31/42

    V52-850 kWThe turbine that goes anywhere

  • 7/30/2019 Wind Farm-Fesaibility Study

    32/42

    Versatile, efficient, dependable and popular

    The highly efficient operation and flexible configuration

    of the V52 make this turbine an excellent choice for all

    kinds of wind conditions. In addition, thanks to its modest

    dimensions, the V52 is simple and cost-effective to trans-

    port and install. If you add in robust construction,

    thoroughly tested components and an enviable track

    record, it is easy to see why Vestas has erected more V52s

    than any other turbine in its portfolio approximately

    1500 turbines, all over the world.

    One of the factors that contribute to the success of the V52

    is OptiTip, its pitch regulation system. This system features

    microprocessors which control the pitching of the blades,

    thus ensuring continuous adjustment to maintain optimal

    blade angles in relation to the prevailing wind. At the

    same time, OptiTip makes it possible to keep sound levels

    within the l imits st ipulated by local regulations.

    The optimal solution

    Another innovative feature of the V52 is the OptiSpeed*

    generator. This is a significant advance in wind turbine

    technology and makes a major contribution to the effi-

    ciency of the V52. In practice, it allows the turbine rotor

    speed to vary between 14 and 31 rpm depending on the

    conditions at any given time.

    While the technology involved may be advanced, its pur-

    pose is simple: to maximise output. It does this by tapping

    the higher efficiency of slow and variable rotation, storing

    excess energy in rotational form and exploiting the full

    force of transient gusts. All told, OptiSpeed boosts annual

    energy production.

    As an added benefit , OptiSpeed also reduces wear and

    tear on the gearbox, blades and tower on account of lower

    peak loading. Moreover, as turbine sound is a function of

    wind speed, the lower rotation speeds made possible by

    OptiSpeed naturally reduce sound levels.

    Finally, OptiSpeed helps the V52 deliver better quality

    power to the grid, with rapid synchronisation, reduced

    harmonic distortion and less flicker.

    Quite simply, OptiSpeed means more output, better quality

    power and less mechanical strain and sound.

    Proven Performance

    Wind power plants require substantial investments, and the

    process can be very complex. To assist in the evaluation and

    purchasing process, Vestas has identified four factors that

    are critical to wind turbine quality: energy production,

    operational availability, power quality and sound level.

    We spend months testing and documenting these perform-

    ance areas for all Vestas turbines. When we are finally satis-

    fied, we ask an independent testing organisation to verifythe results a practice we call Proven Performance. At

    Vestas we do not just talk about quality. We prove it.

    * Vestas OptiSpeed is not available in the USA and Canada.

  • 7/30/2019 Wind Farm-Fesaibility Study

    33/42

    1

    23 4

    5

    6

    7

    8

    910

    11

    12

    13

    14

    15

    16

    17

    18

    19

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    Technical specifications

    Ultrasonic wind sensor

    Service crane

    VMP-Top controller

    with converter

    OptiSpeed generator

    Pitch cylinder

    Oil and water coolers

    Gearbox

    Main shaft

    Blade bearing

    Blade

    Rotor lock system

    Hydraulic unit

    Torque arm

    Machine foundation

    Mechanical disc brake

    Yaw gear

    Composite disc coupling

    100.0 dB(A) 101.0 dB(A) 102.0 dB(A)

    103.0 dB(A) 104.2 dB(A)

    Sound 100.0 dB(A)

    Speed of revolution (rpm)

    Power curve V52-850 kW

    Power(kW)

    1,000

    900

    800

    700

    600

    500

    400

    300

    200

    100

    0

    Wind speed (m/s)

    0 5 10 15 20 25

    Wind/sound

    Sound

    (dB(A))

    104

    102

    100

    98

    96

    94

    92

    90

    88

    86

    Wind speed (m/s)

    3 4 5 6 7 8 9 10 11 12 13

    Speedofrev

    olution(rpm)

    45

    40

    35

    30

    25

    20

    15

    10

    5

    0

    The figure above illustrates the power curves at different sound levels for the

    V52-850 kW turbine, which is equipped with OptiSpeed

    .

    The sound output level can be adjusted by varying the revolution speed of

    the turbine as illustrated in the figure above. It clearly shows the soundlevel advantages of lower speeds of revolution because the sound level is

    approximately 7 dB(A) lower at 4 m/s than at 8 m/s. For other sound

    levels, the benefit can be as much as 10 dB(A). Please note that a decrease

    of 3 dB(A) represents a halving of the sound level.

    Pitch system

    Blade hub

  • 7/30/2019 Wind Farm-Fesaibility Study

    34/42

    Rotor

    Diameter: 52 mArea swept: 2,124 m2

    Nominal revolutions: 26 rpmOperational interval: 14.0-31.4 rpm

    Number of blades: 3Power regulation: Pitch/OptiSpeed

    Air brake: Full blade pitch

    Tower

    Hub height: 40 m, 44 m, 49 m, 55 m,60 m, 65 m, 74 m, 86 m

    Operational data

    Cut-in wind speed: 4 m/sNominal wind speed: 16 m/sCut-out wind speed: 25 m/s

    Generator

    Type: Asynchronous with OptiSpeedNominal output: 850 kWOperational data: 50 Hz/60 Hz

    690 V

    Gearbox

    Type: 1 planet step/2-stepparallel axle gears

    Control

    Type: Microprocessor-based monitoring of allturbine functions as well as OptiSpeedoutput regulation and OptiTip pitchregulation of the blades.

    Weight

    Nacelle: 22 tRotor: 10 t

    Towers: IEC IA IEC IIA DIBt II DIBt IIIHub height:40 m 40 t 44 m 45 t 49 m 50 t 55 m 55 t 50 t 60 m 70 t 70 t 70 t65 m 75 t 75 t 75 t74 m 95 t 86 m 110 t

    t = metric tonnes

    DIBt towers are only approved for Germany.

    All specifications subject to change without notice.

    OptiSpeed allows the rotor speed to vary within a

    range of approximately 60 per cent in relation tonominal rpm. Thus with OptiSpeed, the rotor speed

    can vary by as much as 30 per cent above and below

    synchronous speed. This minimises both unwanted

    fluctuations in the output to the grid supply and the

    loads on the vital parts of the construction.

    Time

    1,000

    800

    600

    400

    200

    0

    Power(kW)

    Output

    Spee

    d(rpm)

    Time

    Generator

    30

    25

    20

    15

    10

    5

    0

    Pitch

    Time

    An

    gle(degrees)

    Wind

    Time

    Speed(m/s)

    30

    25

    20

    15

    10

    60 Hz

    2,050

    1,850

    1,650

    1,450

    1,250

    1,050

    50 Hz

    1,900

    1,700

    1,500

    1,300

    1,100

    900

  • 7/30/2019 Wind Farm-Fesaibility Study

    35/42

    If you have a viable wind power site, chances are that the

    V52 will do well there. That is because at Vestas, we have

    devoted the last 25 years to expanding the range of condi-

    tions under which wind can be profitably harnessed and

    because the V52 represents Vestas at its most versatile.

    An all-round performer, this 850 kW wind turbine is ourmost adaptable turbine, well suited for a broad spectrum

    of medium and high winds. This is why we have installed

    approximately 1500 V52s all over the world.

    Several factors contribute to the flexibility of this wind

    turbine. Not only is the V52 available with eight different

    tower heights, but its modest size and remarkable sound

    profile also make it the perfect choice for both populated

    and remote locations. As a finishing touch, its compact

    dimensions make overland transport simple.

    The V52 is also the only kW-class turbine to be fitted with

    OptiSpeed, a technology that allows the rotor speed to

    vary within a range of approximately 60 per cent in relationto nominal rpm. This means that with OptiSpeed, the

    rotor speed can vary by as much as 30 per cent above and

    below synchronous speed. OptiSpeed thereby maximises

    the aerodynamic efficiency of the rotor in response to

    changing wind conditions and provides yet another

    instance of how Vestas versatility enhances the delivery of

    dependable power.

    The turbine that goes anywhere

  • 7/30/2019 Wind Farm-Fesaibility Study

    36/42

  • 7/30/2019 Wind Farm-Fesaibility Study

    37/42

    GAMESA G58-850 KW

  • 7/30/2019 Wind Farm-Fesaibility Study

    38/42

    Optimum performancefor low winds

    - Class IIIB/WZII.

    - Pitch and variable speed

    technology to maximizeenergy production.

    - Production of lighterblades using fiberglassand prepreg method.

    - Compliance with the maininternational Grid Codes.

    - Aerodynamic design andGamesa NRSTM controlsystem to minimize noiseemissions.

    - Gamesa SGIPE: Remotemonitoring and controlsystem with Web access.

    - Over 4,600 GamesaG5X-850 kW wind turbinesinstalled.

    BENEFITS

  • 7/30/2019 Wind Farm-Fesaibility Study

    39/42

  • 7/30/2019 Wind Farm-Fesaibility Study

    40/42

    - The Generator is a doubly fed machine (DFM), whose speed andpower is controlled through IGBT converters and PWM (Pulse

    Width Modulation) electronic control.- Benefits:

    Active and reactive power control.

    Low harmonic content and minimal losses.

    Increased efficiency and production.

    Prolonged working life of the turbine.

    Control System

    Gamesa SGIPE and its new generation Gamesa WindNet (wind

    farm control systems), developed by Gamesa, that allow realtimeoperation and remote control of wind turbines, meteorological

    mast and electrical substation via satellite-terrestrial network.Modular design with control tools for active and reactive energy,noise, shadows and wake effects. TCP/IP architecture with a Web

    interface.

    Gamesa SGIPE

    SMP Predictive Maintenance System

    Drive train with main shaft supported by two spherical bearingsthat transmit the side loads directly to the frame by means of thebearing housing. This prevents the gearbox from receiving

    additional loads, reducing malfunctions and facilitating itsservice.

    Mechanical design

    Aerodynamic primary brake by means of full-feathering blades. Inaddition, a hydraulically-activated mechanical disc brake for

    emergencies is mounted on the gearbox high speed shaft.

    Brake

    The Gamesa G58-850 kW wind turbine generator uses the totallightning protection system, in accordance with standard IEC

    61024-1. This system conducts the lightning from both sides ofthe blade tip down to the root joint and from there across thenacelle and tower structure to the grounding system located inthe foundations.

    As a result, the blade and sensitive electrical components areprotected from damage.

    Lightning protection

    Predictive Maintenance System for the early detection of

    potential deterioration or malfunctions in the wind turbines maincomponents.

    - Benefits:

    Reduction in major corrective measures.

    Increase in the machines availability and working life.

    Preferential terms in negotiations with insurance

    companies.

    Integration within the control system.

    Rotor

    Diameter 58 m

    Swept area 2,642 m2

    Rotational speed Variable 14.6 - 30.8 rpm, towers 55 and 65mVariable 16.2 - 30.8 rpm, torre 44m

    Rotational direction Clock Wise (front view)

    Weight (incl. Hub) Approx. 12 T

    Top head mass Approx. 35 T

    Gearbox

    Type 1 planetary stage / 2 helical stages

    Ratio 50 Hz 1:61.74

    Cooling Oil pump with oil cooler

    Oil heater 1.5 kW

    Tubular Tower

    Modular type Height Weight

    2 sections 44 m 45 T

    3 sections 55 m 62 T

    3 sections 60 m 72 T

    3 sections 65 m 79 T

    3 sections 71 m 86 T

    Blades

    Number of blades 3

    Length 28.3 m

    Airfoils NACA 63.XXX + FFA-W3

    Material Epoxy reinforced glass fibre

    Total blade weight 2,400 kg

    Generator 850 kWType Doubly-fed machine

    Rated power 850 kW

    Voltage 690 V ac

    Frequency 50 Hz

    Protecction class IP 54

    Number of poles 4

    Rotational speed 900:1,900 rpm(rated 1,620 rpm)

    Rated Stator Current 670 A @ 690 V

    Power factor (standard) 0.95 CAP - 0.95 IND at partial loads and1 at nominal power.*

    Power factor (optional) 0.95 CAP - 0.95 IND throughoutthe power range.*

    * Power factor at generator output terminals, at low voltage side before transformer input terminals.

  • 7/30/2019 Wind Farm-Fesaibility Study

    41/42

    111213141516171819

    1 2 3 4 5 6 7 8 9 10

    Power Curve Gamesa G58-850 kW

    (for an air density

    of 1,225kg/m3)

    3 5 6 7 8 9 10 11 12 13 14 15 16 17-21

    0

    100

    200

    300

    400

    500

    600

    700

    800

    900

    4

    Cut-in speed: 3 m/s

    Cut-out speed: 21 m/s

    PowerkW

    Wind speed m/s

    Power curve calculation based on NACA 63.XXX and FFA-W3airfoils.

    Calculation parameters: 50 Hz grid frequency; tip angle pitch

    regulated, 10% turbulence intensity and a variable rotor speedranging from 14.6 - 30.8 rpm.

    Gamesas doubly-fed wind turbines and Active Crowbar and oversized converter technologies ensure the compliance with the mostdemanding grid connection requirements.

    Low voltage ride-through capability and dynamic regulation of

    active and reactive power.

    Grid connection

    Aerodynamic blade tip and mechanical component design mini-mize noise emissions. In addition, Gamesa has developed theGamesa NRSTM noise control system, which permits programming

    the noise emissions according to criteria such as date, time orwind direction. This achieves the goals of local regulation com-

    pliance as well as maximum production.

    Noise control

    Speed (m/s) Power (kW)

    3 9.7

    4 31.2

    5 78.4

    6 148.2

    7 242.7

    8 368.8

    9 525.3

    10 695.0

    11 796.612 835.9

    13 846.8

    14 849.3

    15 849.9

    16 850.0

    17-21 850.0

    1. Service crane

    2. Generator

    3. Cooling system

    4. Top control unit

    5. Gearbox

    6. Main shaft with twobearing housings

    7. Rotor lock system

    8. Blade

    9. Blade Hub

    10. Hub cover

    11. Blade bearing

    12. Bed frame

    13. Hydraulic unit

    14. Shock absorbers

    15. Yaw ring

    16. Brake

    17. Tower

    18. Yaw gears19. Transmission.

    High speed shaft

  • 7/30/2019 Wind Farm-Fesaibility Study

    42/42

    Gamesa Wind GmbH

    Wailandtstrasse 7

    63741 Aschaffenburg

    Germany

    Tel: +49 (0) 6021 15 09 0

    Fax: +49 (0) 6021 15 09 199

    E-mail: [email protected]

    Gamesa Wind Engineering

    Vejlsvej 51

    8600 Silkeborg

    Denmark

    Tel: +45 87 229205 / 9204

    Fax: +45 87 229201

    France

    Parc Mail

    6 Alle Joliot Curie, btiment B69791 Saint Priest

    Tel: +33 (0) 472 79 47 09

    Fax: +33 (0) 478 90 05 41

    Greece

    3, Pampouki Street

    154 51 Neo Psichiko

    Athens

    Tel: +30 21 06753300

    Fax: +30 21 06753305

    Gamesa Eolica Italia

    Via Pio Emanuelli,1

    Corpo B, 2 piano

    00143 RomeTel: +39 0651531036

    Fax: +39 0651530911

    Portugal

    Edificio D. Joo II

    PARQUE DAS NAOES

    Av. D. Joo II, lote 1.06.2.37 B

    1990-090 Lisbon

    Tel: +351 21 898 92 00

    Fax: +351 21 898 92 99

    United Kingdom

    Rowan House Hazell Drive

    NEWPORT South Wales NP10 8FY

    Tel: +44 1633 654 140

    Fax: +44 1633 654 147

    Gamesa Wind US

    1 Ben Fairless Drive - Ste. 2

    Fairless Hills, PA 19030

    Tel: +1 215 736 8165Fax: +1 215 736 3985

    Gamesa Wind Tianjin

    Room 1103, Tower 1

    Bright China

    Changan Building

    7 Jianguomennei Av.

    Beijing 100005

    China

    Tel.: +86 10 65186158

    Fax: +86 10 65171337

    Polgono Industrial Agustinos, C/A s/n31013 Pamplona, SpainTel: +34 948 309010Fax: +34 948 [email protected]