7/30/2019 Wind Farm-Fesaibility Study
1/42
1
PRMG 050:
Projects Feasibility Studies
FEASIBILITYSTUDYOF120MWWINDPARK
PROJECTMEMBERS
HASANIEN,AHMEDKAMAL ID:700081207
HUSSEIN,MOHAMEDHAMDY ID:700081206
MOHAMED,AHMEDSAMYYOUNIS ID:700081205
OSMAN,YASSERAHMED ID:700081186
SHARARA,KHALEDMAGDY ID:700081345
Spring2009 Section1
7/30/2019 Wind Farm-Fesaibility Study
2/42
2
TableofContents1.Introduction........................................................................................................................................................ 3
1.1ReliabilityofRenewables.............................................................................................................................. 5
1.1.1. ElectricityGenerationCosts............................................................................................................ 5
1.1.2. LandAreaRequirements................................................................................................................ 5
1.1.3. Controllability................................................................................................................................. 6
1.1.4. Availability...................................................................................................................................... 6
1.1.5. Security........................................................................................................................................... 7
2.EnergyMarketStudyinEgypt........................................................................................................................... 8
2.1WindEnergyMarketinEgypt........................................................................................................................ 8
2.2Economic,SocialandEnvironmentalImpactasResultofWindEnergyProjectsinEgypt ........................10
3.Wind
Park
Site
..................................................................................................................................................
11
3.1GabalElZytSite............................................................................................................................................ 12
3.2ZafaranaSite............................................................................................................................................... 14
4.TechnicalStudy................................................................................................................................................. 16
4.1WindParkmanufacturingComponents ..................................................................................................... 16
4.2WindParkComponentsContributiontoCost............................................................................................. 19
4.3WindParkComponentsContributiontoCost............................................................................................. 20
4.3.1.
Wind
Turbine
Parameters
............................................................................................................
20
4.3.2. TurbinesLoses.............................................................................................................................. 21
4.3.3. Turbulence ................................................................................................................................... 21
4.3.4. TechnicalSummary....................................................................................................................... 22
4.3.5. Estimationofcosts........................................................................................................................ 22
5.EconomicEvaluation ........................................................................................................................................ 24
6.Cocnlusions........................................................................................................................................................ 28
7.References
........................................................................................................................................................29
8.Appendices ....................................................................................................................................................... 30
7/30/2019 Wind Farm-Fesaibility Study
3/42
3
1. IntroductionWith the rapidly growing demand for electrical power in Egypt and the finite life of
conventionalfossil fuels (oil,gasandcoal)coupledwiththeiradverseeffectsonpollutionof
the environment and global warming, there is a critical need to increase the percentage of
electricpowergenerationinEgyptfromrenewableenergy.
Egyptselectricitydemandisprojectedtoreach120GWin2050.Duetothelimitedfossilfuel
resources, it isexpected that theirpricecontinues torisedramatically in the future.On the
otherhandclimatechangeobligeshumanitytoreactaccordingly.
TheEgyptianelectricitygridispredominantlyfossilfuelfired.Renewableenergy,consistingof
mostlylargescalehydro,isresponsibleforjustunder20%ofgeneration.Apartfromthehydro
facilities, the existing Zafarana wind facilities comprise this category. The remainder, more
than 80% of electricity including those purchased from independent power producers, is
produced
from
conventional
plants.
Due
to
the
abundance
of
natural
gas
in
Egypt,
approximately 90% of the fossil fuel used in the conventional plants is natural gas and the
remaining10%fueloil.
As is the case for most nonhydropowerdominated grids, hydro plants are considered low
costandthereforenotmarginal.Thesamecanbesaidforwindpower.Itisofnotethatunlike
many grids which utilize hydro facilities during peak demand to take advantage of their
responsiveness to varying demand, Egypts hydro facilities provide mainly base capacity
power,withamarginlefttorespondtopeakdemand.Thisisduetothefactthattheirrigation
needsofagriculturalactivitiestakeprecedencewhendeterminingthewaterrelease,whichis
controlled
by
the
Ministry
of
Irrigation.
In
the
context
of
the
baseline
determination,
thiscircumstanceisinagreementwiththeapproachtoexcludehydropower,astheProjectwillin
nowayaffectthepowergeneratedfromhydropowerfacilities.
Theremainingfacilitiesintheoperatingmarginaregasturbine,steamturbineandcombined
cycle conventional units fuelled by natural gas and fuel oil. This is a conservative
representationoftheactualoperatingmargin,giventhatthemostlikelymarginalplantstobe
displaced are low efficiency fuel oil and natural gas facilities, instead of the average of all
thermal power plants. Improving energy efficiency and shifting to cleaner and noncarbon
energysourcesareessentialtoimprovethecountrysenvironmentandhelptomitigateglobal
climatechange.
Withayearlyaveragegrowthofabout6%,Egypt isexpectingto increase its installedenergy
from17 GW in 2002 to50 GW in2020andwith asmaller increase rate to 120 GW in year
2050.Thisincreasewillexhaustthebudgetiftheadditionalelectricityisproducedfromfossil
fuelsonly.Thereforethetargetof55%REshareisverymodestandshouldbeachievable.
7/30/2019 Wind Farm-Fesaibility Study
4/42
4
Table1EnergyProjectionsinEgyptandREFuturetrends
Year 2002 20.1 2020 20.5
EgyptREshare 16% 20% 30% 55%
EgypttotalElectricity 17GW 27GW 50GW 120GW
Egypttotal
RE
share
2.7
GW
5.4
GW
15
GW
66
GW
EgyptHydroshare 15% 2.5GW 10% 2.7GW 6% 3.0GW 2% 3.0GW
EgyptWindshare 1% 0.2GW 8% 2.2GW 12% 6.2GW 17% 20GW
EgyptSolarshare 0% 0GW 2% 0.5GW 12% 5.8GW 36% 43GW
Asthehydroenergycannotbeincreasedafter2020,theremainingREsharemustbecovered
by wind and solar energy; however, wind alone cannot cover the demand because of its
fluctuating character.Thegood wind areas are allaligned inwindmain direction on the
shoresoftheredseawhichmeansthatawindstillwillaffectthemalltogether.
Leading countries in the use of RE, like Germany made the experience, that RE must be
generatedfromdifferentsourcestoensureareliableenergysupply.Thereforethekeyforthe
solution is a mix of different renewables, otherwise serious supply gaps may occur. At the
moment,windenergygenerationisthemosteconomicREafterhydroenergy.However,solar
thermalgenerationhas thegreatadvantage that itcandesalinateseawaterwith thewaste
heat,givingmillionsofmofdesaltedwaterneededinthenearfutureforthedevelopmentof
Egyptatreasonablecosts.
Moreover,planningforthefuturemustalsoconsiderthecostreductionpotentialswhichsolar
thermal
generation
still
has;
one
can
expect
that
solar
thermal
generation
will
be
considerably
cheaperthanbothwindenergyandenergyproductionfromfossilswhosepricesdonotclimb
upastheoilpricedoes.
This paper presents a feasibility study of potential wind energy developments in Egypt by
studying the implementationofawindpark asan environmental friendlypower generation
solution comparing between the current viability of the alternatives of wind park sites
betweenZafaranaandGabalElZytsettingthefactorstodeterminethemostfeasiblesite,also
comparing between 2 of the wind turbines manufacturers Gamesa and Vestas selecting the
most
feasible
alternative
as
well.
However
well
discuss
first
the
obstacles
prevented
us
from
pickingthesolaralternativebeforegoingthroughthemarketandtechnicalstudies.
7/30/2019 Wind Farm-Fesaibility Study
5/42
5
1.1ReliabilityofRenewables
Egypt is theonlyplace in theworldwherebothsolarandwindpotentialsareavailableata
highqualityandinthemeantimerelativelyneartothedemandofelectricity.Itistheoretically
possibletoproducethewholeenergydemandofEgyptfromwindorfromthesun.Butwhich
optionispreferableanswerthisquestion,onemustconsiderapackageofseveraltopics:
Electricity
generation
costs,
Landarearequired,
Controllability,
Availability,and
Securityofelectricitysupply.
1.1.1.ElectricityGenerationCostsCostsaregenerallythemostimportantfactortodecideaboutaninvestment.Inthisparticular
case,namelydealingwithrelativelynewtechnologies,onemustconsiderbesidethecostsat
thepresenttimealsodevelopmentofcostsinfuture,e.g.after20years.Startingwithpresentcostswewilltrytomakeacomparisonbetweenwindenergyandsolar
energy considering the optimal benefits of each. Assuming a square kilometer of desert,
equipped with the most modern and most efficient solar thermal system now available
workinginhybridoperationwithasolarshareof35%itwillyieldperyear:
300GWhelectricityatacostof0.05$/kWhtotaling15.0million$
+
13millionmdesaltedseawaterat0.70$/mtotaling9.1million$
(Combinedgenerationusingwasteheat,noextraenergyneeded)
To produce the same quantities (electricity + desalted water) from a good wind park with
45005000fullloadhoursperyear,followingcostswilloccur:
300GWhelectricityatacostof0.03$/kWhtotaling9.0million$
+
13millionmdesaltedseawaterat1.10$/mtotaling14.3million$
(ProducedbyReverseOsmosisusingelectricpower)
Thetotal
cost
of
both
products
together
gives
24.1
and
23.3
million
$/year
respectively.
Thus
wind power is only 3% cheaper in the present time. However the solar power costs are
expectedtoflattendownwithinthenext20years.
1.1.2.LandAreaRequirementsContinuingwiththeexampleabove,1km isneededtoproduce300GWh/ysolarelectricity
and13millionmofdesaltedseawater.Weadd0.1kmforthedesalinationequipmentthus
totalingto1.1km.Toproducethesameelectricityfromwindwith45005000fullloadhours
7/30/2019 Wind Farm-Fesaibility Study
6/42
6
we can calculate with a wind mill density of maximum 7.5 MW/km. A higher density will
causereductionofproducedelectricity fromthefield.Thiswillgive8.4km.Toproducethe
same water quantity with reverse osmosis (RO)we will need8kWh/m which calculates to
104 GWh.Asupplemental area for producing thiselectricitywill beneeded whichgives2.9
kmthetotalareaneeded is11.3kmwhich is10timesasmuchasforthesolarapplication.
The desert area may be cheap, but looking at this disproportion we have to think about
parameters
like
cable
lengths
needed
and
time
consumed
by
maintenance
personnel
to
reach
allunitsinthefield.
1.1.3.ControllabilityControllability isthecapabilityto followtheupsanddownsofthedemandduring24hours.
SolarHybrid power stations, which are the present object of this comparison, are working
exactlylikefossilfiredpowerstationswiththedifferencethatduringthedaylessfuelisburnt
becauseitispartlysubstitutedbythesunheat.Futureoptionsaresolaronlypowerstations
with thermal storage allowing continuous operation. In both cases the power station is
controllable
in
the
same
manner
like
conventionally
fired
power
stations,
backup
capacity
for
thefluctuatingsolarresourceisintegratedwithintheplant.
Ontheotherhandwindisroughlypredictablebutnotcontrollableandstorageofwindpower
is only possible in rechargeable batteries which are so expensive that they cannot be
considered for largeapplications.For thisreasonwindparksareworkingwithingridswhere
thecontrolislefttothethermalbackuppowerstationsconnectedtothegrid.
1.1.4.AvailabilityAvailability isthecertaintytodeliverelectricitythroughtheyear.Forthereasonsmentioned
under
the
third
topic,
availability
is
achieved
with
hybrid
solar
power
stations
without
anyproblems.InEgyptitisevenadvantageousbecausetheelectricitydemandinsummerisabout
20%higherthaninwinter,whichisfullyconsistentwiththeseasonaltrendofthesolarenergy
resource.Oncloudywinterdaysthehybridsolarpowerstationwillusefossilfuelorheatfrom
thestoragewithoutrestrictionofavailability.TheuniquesolarenergyresourceofEgypt(upto
3000 kWh/m/year) and thermal energy storage allows for aroundtheclock operation
throughthewholeyearlikeabaseloadfossilfuelplant.
Wind,however, issubject toseasonal fluctuations.Goodwindsites liketheGulfofSuezare
highly affected as the site is lengthily extended in main wind direction. This negative effect
may
be
partly
compensated
by
connecting
wind
parks
in
different
areas,
e.g.
Red
Sea
andNorthernCoast,takinginaccountthelessfavorablewindconditionsintheNorthCoast.Even
thenavailability isnotguaranteed,soalwaysfreecapacitiesofthermalpowerstationsmust
bekeptwithinthegridinthebackground(calledshadowpowerstations).Capitalcostsofsuch
power station capacitiesmust be taken inaccountwhen considering a large scalesupplyof
windenergyinthegrid.
7/30/2019 Wind Farm-Fesaibility Study
7/42
7
1.1.5.SecurityInsummer2003severalblackoutsoccurred inUSAandEurope,mainlybecauseoffailuresof
transmissionlineswhichleadtooverloadingandthustrippingofseveralpowerstations.
Thiscanbeavoidedbyincreasingtheavailablethermalpowerstations(includingsolarthermal
power
stations)
connected
to
the
grid,
but
not
by
adding
wind
power.
Wind
power
has
in
generala destabilizingeffect on thegrid,which has to becompensatedbyother resources,
likehydropowerorthermal(solar)powerstations.
Finally Controllability, availability and security of electricity supply are as important for a
modern society as generation costs. Experience in Germany in summer 2003 with long
periodsofwindstill demonstratedthe importanceofthesefactors.Forthisreasonexperts
recommendthatthewindshareshallnotexceed20%inanelectricitygrid.
Production of desalted seawater from waste heat and the future perspective for a
considerable
cost
reduction
of
solar
thermal
power
stations
makes
it
essential
that
they
get
sufficientsupporttodevelopforthefuture,forthoughWindenergy isaverygoodchoice in
thepresent,wheresolarthermalenergyisessentialforthefuture.
7/30/2019 Wind Farm-Fesaibility Study
8/42
8
2. EnergyMarketStudyinEgyptThe electricity sector is facing a number of challenges and constraints in securing the
electricity demand for Egypt in the coming decade. The most pressing issues include the
havingsufficientbaseandpeakloadcapacity,ensuringtheavailabilityofnaturalgasforpower
production(atpricelevelsthatcanbeabsorbedbytheretailelectricitytariff),succeedingwith
the
ambitious
renewable
energy,
as
well
as
other
energy
efficiency
measures
and
continuing
thepathoftariffandsubsidyreform.
2.1. WindEnergyMarketinEgyptEgypt isworkingveryhard to develop its renewable energy (RE) resources, includinghydro,
windandsolar.Hydroelectricpowercapacityhasbeenalmostfullyexploredwithaninstalled
capacityof 2,780 MWandannual energyproductionofabout12,650GWh. Wind andsolar
energyareintheearlystagesofexplorationandutilization.InApril2007,theSupremeCouncil
for Energy adopted an ambitious plan which aims at having 20% of the country's installed
capacity
in
the
form
of
RE
by
2020.
Notably,
over
10%
of
this
i
s
expected
to
come
from
wind
energy, which translates into about 7,200 mega watts (MW)of grid connected wind parks.
Thedevelopmentofthisatsuchalargescaleisbeingdesignedbased,onaprivatesectorled
strategy,ofwhichtheWorldBankisprovidingtechnicalassistance.
TheNewandRenewableEnergyAuthority(NREA),establishedin1983,isthemainagencyfor
promotingandoperatingRE technologies.Atpresent,windandsolarenergyprojectsareat
thecoreofNREA'scurrentandfutureplans.AWindAtlasfortheentirecountrywasissuedin
2005indicatingabout20,000MWofwindpotentialintheGulfofSuezarea.Aseriesoflarge
scalewindenergyprojectswereconstructedwithacurrentoperationalcapacityof225MW
connectedto
the
national
grid.
Egypt
is
also
implementing
its
first
solar
thermal
power
plant
of
140MW(solarshareof20MW)southofCairo,plannedtobeoperationalby2010.
Ministry of Electricity and Energy started by implementing several experimental wind park
projects which concluded the setting up of ambitious program for the construction of large
windparkpowerplantsconnected to thenationalgridwith total installedcapacity reaching
965MWin2011/2012.
Itisnoteworthytomentionthat,in30/6/2008,theinstalledcapacityofthelargestwindpark
intheMiddleEastregionandAfricaislocatedatElZafaranaonGulfofSuezreached305M.W
andis
connected
to
the
national
grid.
Egyptian Electricity Holding Company (EEHC) cooperates with the NREA, responsible of
disseminatingtheuseofnewandrenewableenergyresourcesinEgypt,throughthefollowing:
Generation planning taking into consideration the contribution of the renewableenergy.
7/30/2019 Wind Farm-Fesaibility Study
9/42
9
Network planning to ensure the capability of power transfer from the renewableprojects.
Purchase energy generatedfrom the wind parks at
reasonable price to
encourage the use of
renewableenergy.
Prepare the power purchase
agreements from the wind
parkswithareasonableprice
to encourage the use of
renewableenergy.
Figure1WindEnergyImplementationTrendtill2011/2012inEgypt
The above figure shows the government plans till 2011/2012 for the wind parks
implementations
which
shall
reach
to
956
MW
installed
and
connected
to
the
grid
by
an
annualincrementof20%tothenationalgridbyusingwindenergy,howeverthegovernment
longtermplanswhichsymbolizethecontributionofrenewableenergytoreach20%oftotal
energy generated in 2020(8%hydro&12% wind) gives the wind energy the desired
environmentrequiredbytheinvestortogothroughtheinvestmentsinwindenergyinEgypt.
;SoinordertoachievetheEgyptian2020strategyofthewindenergyimplementationtherate
ofwindparksinstallmentshavetobeaccordingly,about400600MWyearlyimplemented.
Figure2Egypt's2020strategyforwindenergy
7/30/2019 Wind Farm-Fesaibility Study
10/42
10
2.2. Economic,SocialandEnvironmentalImpactasResultofWindEnergyProjectsinEgypt.
TheCrudeoilexports isoneofthenational incomeofEgypt,thereforethefuelsavingcanprovideanincreaseinthenationalincomebyprovidingtheforeigncurrencydueto
oilexportation.
IncreasejobopportunitiesandhelpsolvingtheunemploymentproblemthatpositivelyaffectsthegeneraleconomicsituationinEgypt. New community is going to be established in the vast desert area in Zafarana that
enhance localmigrationofpopulation from theNilevalley to theGulfofSuez.This is
stillaproblemofpopulationdistributioninEgypt.
The Zafarana wind park has very effective and positive environmental impact, theoperationofthe600MWwindparkswillproduce42,000millionkWhallovertheir20
years life time, that in turn will save 10 million tons oil equivalent and will abate the
emissionofthefollowingquantitiesofgreenhousegases:588MiotonCox,2.1Mioton
NOx,8.4
Mio
ton
Sox.
As a result for the above discussed points, we decided to study the feasibility of the
implementationofthe120MWwindparkasanintendedfigurebythegovernmentasithas
beenrecentlytakenastheannualdevelopmentstep inthewindenergycapacity inEgypt
(shown in figure1),and liesbelow theannual forecasteddevelopmentstepaccording to
theambitionsoftheEgyptiangovernment inachieving7200MWbytheyear2020which
hasbeendistributedinfigure2togivethattheannualstepshallbe400MWtill2011/2012.
Thesefiguresgiveustheconfidenceaboutthemarketgapinthewindenergyaccordingto
thefuture
plan
of
the
Egyptian
government
which
the
investor
rely
on
as
asolid
platform
forthedecisiontoinvestinsuchsectorinEgypt,andgivesanindicationtotheviabilityof
theinvestmentenvironmentespeciallywhentheopportunitiesarenotonlycreatedbythe
demand,butalsofromtheambitionoftheEgyptiangovernmentwhichmayfacilitatemore
obstaclestoensureflexibleandsustainablesupplyofwindenergy.
7/30/2019 Wind Farm-Fesaibility Study
11/42
3.Coa
Ene
par
hig
proEas
oft
The
has
Egy
12
alth
tob
avaineg
An
me
tabl
nor
of
Hur
Red
TheDar
littl
and
spe
win
Tabl
W
indPark
stal zone
rgy pote
icularly a
est wind
posed
winernside
eRedSe
coastbet
the mos
pt with a
m/s. Th
oughpart
eatouris
lable
foligiblecoa
overall s
suredatf
e below.
htosout
lZyt are s
ghada in
Sea.
measuregandZaf
moreth
resulting
dandme
dspeeda
e2Overalls
ibullAand
Site
s in Egy
ntial. T
the Gulf
areas
d
park
sitfEgyptcl
.
weenAbu
t favorab
erage win
lands i
ofthisar
icresort,l
wind
st.
mmary
ourmain
The stat
;AbuDa
ituated al
the nort
wind
dist
arana,wh
n18kma
inalmosti
anenergy
ddirectio
ummary199
parameter
pt enjoy
e Red
of Suez is
f the wo
es
are
sitsetothe
Daragan
le wind c
d speeds
s desert
ea isbein
largearea
projects
f the wi
tationsis
ions are
ag,Zafara
ong the G
ernmost
ributionsicharesit
part,are
dentical
densities.
n.
195ofwind
,meanwin
cal
high wi
Sea coa
one of t
rld; so t
ated
in
tcoastalli
dHurgha
ondition
between
area, a
develop
oflanda
at
almo
d climat
givenint
listed fro
naandG
ulf of Sue
part of t
tAbu
ateda
erysimila
eanwind
Thewind
observation
speed(U),
satallfour
11
d
st
e
e
e
e
a
in
7
d
d
re
st
s
e
m
lf
z,
e
r
climatein
s24.5ma.g.
eanenergy
stationsisle
Fig
thisarea
l.atthefour
density(E)a
sthan0.1%.
ure3Overvi
issteady,
mainstatio
nddirection
ewmapfort
ithrespe
s:datareco
(DU).Theoc
heGulfofS
cttoboth
eryrate(R),
currenceof
ezinEgypt
7/30/2019 Wind Farm-Fesaibility Study
12/42
12
ThewindclimateattheGulfofElZytstation,which issituatedattheentrancetotheGulfof
Suezabout160kmtotheSouth,exhibitsthesamegeneralcharacteristicsasdescribedabove.
Here,however,theWeibullAparameter issomewhathigher, leadingtoahighermeanwind
speedand, inparticular toameanenergy densitywhich isabout40%higher thanZafarana
area.LeavingtheGulfofSuezandenteringtheRedSea,thewindclimatechangessignificantly
the
character
over
the
60
km
stretch
between
Gulf
of
ElZyt.
The
mean
wind
speed
at
Hurghada
is only about two thirds and the energy density only about one third of the mean values
measuredatGulfofElZyt.Thewindsarestillsteady.
Figure4WindRosesshowthewindflowdirectionsatGabalElZytandZafaranaSites
Egypt's Red Sea Coast region has two natural
resources,landandstrongwindinenormoussupply.
The
2
sites
which
shall
lie
under
our
study
concern
areZafarana,andGabalElZytsites.
3.1. GabalElZytSiteThisareaislocatedtotheWestoftheHurghadaSuez
roadandextendingabout70kmfromNorthtoSouth
andabout9 to10km to the inland.Theareastarts
about60kmintheNorthofHurghada.
It is a desert area. Only at very limited spots some
very
scattered
desert
vegetation
is
observed.
The
southern part of about 55 km (reaching to about 5
km to the north of the Wadi Dara road) is almost
completelyconsistingofdesertplainsformedbythe
extraordinarywind.Thisareaiscrossedbytwomain
Wadis,theWadiDibbandtheWadiDara.However,
due to the high wind speeds and the large sand
Figure5SatellitemapofGabalElZytarea
7/30/2019 Wind Farm-Fesaibility Study
13/42
13
transport/ sedimentation potential, the wadi beds are not pronounced at most of the wadi
courses.
The northern part of the area shows both, undulated land and gravel desert plains. The
westernsideofthisnorthernareashowshillsupto250mheight.
Thegroundsurface inmostofthearea iscoveredwithcompactangulargravelsandpebbles
formingwhatcanbecalleddesertarmor.Thelevelofthewholeprojectareaabovesealevel
ranges
from
9
m
below
sea
level
in
the
north
eastern
side
to
hills
and
slightly
elevated
mountainsrisingtolevelsof250m inthewest.Ingeneral,thesmallermountainousareasin
theNorthwestwouldbekeptfreefromwindpowerdevelopmentbecauseofdifficultaccess
conditions.
Inadditiontherearesomeoftheareacharacteristicswhichshallbealsotaken intoaccount
especiallyastheymayhavean impactonthecostofthe implementationoftheprojectand
might affect the project capital cost by a percent of raise according to such characteristics
shownasfollows:
Infrastructure:Theprojectareahasnoinfrastructureexceptafewdeserttracks,gravelroads
and
the
crossing
asphalt
road
to
the
Wadi
Dara
settlement.
The
next
settlement
is
atminimumdistancesofabout800mfromtheborderofthearea.
Connection to the Grid: Electricity transmission denotes bottlenecks for a first stagewind power development at this area, as the double circuit 230 kV transmission line
HurghadatoZafaranamustbeavailabletoallowanadditionalfeedfromthegenerated
electricityfromGabalElZyt.
Hub Height: According to the geographical characteristics of thisarea theheightof the turbine hubmustbe 100m to function the
windspeedofthisarea.
Theabove
stated
characteristics
of
the
Gabal
ElZyt
site
would
definitely
affect the investment cost of the wind park; that is because of the Site
preparation and construction measures which exclusively have to be
performedforthissiteas:
ExtraExcavation,backfillingandcompactionworksforroadsandplatformconstructionaswellasforfoundationsandtrenchesto
overcometheareageographicalcharacteristics.
Reinforcementof theZafarana transmission lineswhichshallbedonebytheconstructionofanadditional linesfromZafaranato
thecentral
power
grid
along
the
way
to
Hurghada.
Perform a modification to the tower engineering (Material,Fabrication, and Erection Management) according to the extra
heightofthehubwhichwillleadtoatowerheightof100m.
These counter measures for site preparation and construction would affect the investment
costby25%ofraisethantheregularinvestmentcostofthewindparkdueto10%increasein
thetowerengineering,10% forthereinforcementofthetransmission lines,andan increase
5%duetotheextracivilworks.
Figure6HubHeight
7/30/2019 Wind Farm-Fesaibility Study
14/42
14
3.2. ZafaranaSite
Figure7LocationofZafaranasite
The site is located in Egypt on the western shore of the Bay of Suez approximately 200 km
southeastofCairo,onthe inlandsideofahighwayalongtheSuezGulfcoastline.Thesite is
located
in
a
desert
area
with
favorable
wind
conditions.
There
is
no
human
activity
in
the
vicinity of the site, with the nearest commercial activity being several resort hotels
approximately10kmfromthesite.Thenearestcommunityissome30kmaway.
Due to the established former phases of the wind parks at Zafarana site; this site shows
readinesstothefurtherimplementationsofmorewindparksastheexpertspredictstobethe
largestwindparkintheworld.ThesiteleadsGabalElZytinthematterofinstantreadinessto
have further expansions of the capacity of the site from the power production as the
infrastructureofthesitehasbeenestablishedandalwayssubjectedtomodificationstocope
withtheplansofthesitedevelopments.
Wearent
showing
supremacy
of
Zafarana
site
to
Gabal
ElZyt,
but
it
amatter
of
readiness
for
theprivateinvestorZafaranasitedenotesabusinessopportunitymorethanGabalElZytshows
howeverthepotentialliesintheinvestmentatGabalElZytisveryenormouswheretheenergy
experts, The Egyptian Government, and the world global funding and environmental assure
thatthewindenergyfutureinEgyptshallbedrawnatGabalElZyt.Forthoughallthefeasibility
studiesconsiderGabalElZytasafeasiblesiteforthelargescaleimplementationofwindparks
about10002000MW;thatswhentheextra25%forthesitepreparationandtheconstruction
7/30/2019 Wind Farm-Fesaibility Study
15/42
15
measures vanishes in front of the hugeness of the project scale and the total revenue
expectedorbythegovernmentindecreasingsuchfactormayariseasaninvestmentrisk.
As a matter of fact the government contribution by the infrastructure and the transmission
linesofelectricitytransferbeenimplementedisthekeytoGabalElZytSupremacywhichshall
benotonlycompetingwithZafaranabutalsobeatingitfromtheeconomicalfeasibilitypoint
ofview.
But
for
the
current
time
being,
Zafarana
site
shows
more
profitable
opportunity
more
than
Gabal ElZyt shows for the analysis conducted above and resulted in the difference in 25%
increase in the total investment cost of the wind park construction at Gabal ElZyt. For the
analysisresultsandfortheclearobviousreasonswhichreflectsthecurrentsituationZafarana
siteshowsmorefeasibilityfor120MWwindparkconstruction.
7/30/2019 Wind Farm-Fesaibility Study
16/42
16
4. TechnicalStudy4.1. WindParkComponentsManufacturing
Frame Assembly Once the yaw system is assembled with its yaw motors, column and
hydraulic
group
and
the
rotational
test
is
passed,
this
assembly
is
connected
to
the
rear
frame.
Next, the rail beams and the service crane are installed, and cables are run to the control
cabinet.
Gearbox AssemblyThenacelleassembly isplaced within the lower housing,and thepower
transformerandthemainshaft/gearboxsubsetareassembled.GearboxsubsetFrontframe
Figure8FrameandGearboxAssemblies
GeneratorAssemblyTheprocesscontinueswith thegeneratorassemblyandalignmentand
theelectrical
connection
of
all
the
components
in
the
control
cabinet.
Once
connected,
the
nacelleisgivenacomprehensivefinalverificationcheck,simulatingitswindparkoperation.
Upper housing Assembly Once the nacelle verification test is passed the upper housing is
assembledandthenacelleisreadytobesenttoitscorrespondingwindpark.
7/30/2019 Wind Farm-Fesaibility Study
17/42
17
Figure9GeneratorandUpperhousingAssemblies
Gearbox Consists of three combined stages: 1 planetary stage and two helical stages. The
multiplicationratiois1:100.5for50Hzmachinesand1:120.5for60Hzmachines.
Generator Rated power electric generator. Highly efficient, it has 4 poles and is doublyfed
withawoundrotorandsliprings.Therotationalspeedrangeisfrom900to1900rpm,witha
ratedspeedof1680rpm.Theoutputvoltageis690VAC.
Figure10GearboxandGenerator
7/30/2019 Wind Farm-Fesaibility Study
18/42
18
SteelTowerManufacturingFirstlyReceptionandQualityControlofSteelPlatesthecylinders
formingthewindturbinetoweraremadefromplatedsheetsthatareflamecutandprimed.
Then the sheets are inserted in a machine with three large rollers that shape the rings.
Afterwards the rings are submerged arcwelded, forming sections of different lengths. The
structureisplacedinsidethepaintinganddryingtunnel.Oncethetowerplatingisfinished,it
isthengivenasurfacetreatment,consistingofadoublesteelshotpeeningandthreecoatsof
paint.
This
provides
a
C
5
level
protection.
Once
the
tower
is
dry,
all
the
service
elements
(such
asplatformsandladders)aremountedonit.DependingontheModelandtherequiredheight
(between14and29meters),eachsectionmaybemadeupofbetween4and12rings.
BladesManufacturing
BeamManufacturingUsingglassandcarbonfibermaterialsthathavebeenimpregnatedwith
epoxy resin as a base, several cloth lengths are cut and placed in a mould. They are then
subjected
to
a
curing
process.
After
applying
a
coat
of
paint
which
will
act
as
a
protectivecoating on the blade, glass fiber is used to manufacture the shells, following the same
manufacturingprocessasforthebeam.
AssemblyOncethetwoshellsarefinished,weproceedwiththeirassemblyandgluethebeam
betweenthetwoshells.
CuringTheassemblyispassedthroughthekilnoncemore,formingacompactunit.
Figure11 WindTowermanufacturingStages
7/30/2019 Wind Farm-Fesaibility Study
19/42
19
TrimmingandPolishingThebladeassemblyisremovedfromthemouldandistransferredto
the finishing area, where the leading and trailing edges of the blades are finished and
subjectedtoafinalrevision.
Figure12BladesManufacturingStages
4.2. WindParkComponentsContributiontoCostAs stated above, in the manufacturing
stagesofeachofthecomponents,eachof
these components have their different
sophisticated manufacturing technology
which have an impact on the wind park
cost. For though the given analysis made
in figure 13, shows that the nacelle with
its
components
which
is
mainly
theturbine has the highest contribution to
the cost of the wind park. From this point,
we have to study the alternatives of the turbines manufacturers as to go through the most
feasiblesolutionthroughthisstudyweshouldpickthefactorwiththehighestcontributionto
thecostandperformtheeconomicalanalysisonthealternativetoreachtothemostfeasible
alternative.
Figure13SharesofWindParkComponentsbycost
7/30/2019 Wind Farm-Fesaibility Study
20/42
20
4.3. WindTurbinesAlternativesThetwowindturbinetypesunderconsiderationallowtheimplementationofawindparkof
theenvisagedinstalledcapacitywithintheforeseenarea.Similarsizeoftheturbinesanda
rotordiameterinacloserange(from52m[VestasV52]to58m[GamesaG58])leadstoa
similarbasicparkdesignwhichhasthenbeenoptimizedintermsofparkefficiencyandenergy
production,accordingtotheirdatasheets(Appendices)thetechnicalanalysisshallbe
performed
as
follows
for
the
most
important
technical
aspects
for
an
adequate
evaluation
for
eachalternativebeforetheeconomicaloneandtoassuretheirsuitabilityaswell.
Figure14GamesaG58andVestasV52theturbinesalternativeswhicharebeingconsidered
4.3.1.WindTurbineParameters142xVESTAS:V52,HubHeight55m
Nominalpower:
0.850
MW
Controlsystem:Pitch
Rotordiameter:52m
142xGAMESA:G58;HubHeight55m
Nominalpower:0.850MW
Controlsystem:Pitch
Rotordiameter:58m
ThePowercurveofawindturbineisanimportantparameter,describingtherelationbetween
thewind
speed
on
site
and
the
respective
electrical
energy
output.
Power
curves
and
ct
values
(aparameter for thecalculationof thewakeeffect)of the turbinesunderconsiderationare
givenintheappendices
7/30/2019 Wind Farm-Fesaibility Study
21/42
21
4.3.2.TurbinesLosesAfterpassingtherotorofawindturbine,thewindhasadecreasedspeedduetothekinetic
energytakenawaybytherotorandincreasedturbulencecausedbytherotatingrotorandthe
difference in speed compared to the undisturbed flow. Until the speed difference to
undisturbed flow is not equalized, the result is a lower energy yield for the wind turbines
following in the direction of the flow. These losses are called array or wake losses. The
calculation
of
the
wake
losses
of
the
wind
turbines
causing
the
so
called
shadowing
effect
betweenthewindturbines,wheretheresultsofbothofouralternativeswereasfollowsTable3ArraylossesatZafaranawindpark
4.3.3.TurbulenceTo
ensure
the
close
spacing
of
the
wind
turbines
will
not
affect
(decrease)
the
lifetime
of
the
turbineanditscomponents,aturbulencecalculationisnecessarywhichhasbeencarriedout
byLI.The turbulenceof thewind flow isa factorwhichcausesstressand fatigue toseveral
components of a wind turbine including blades, bearing and gearbox. It consists of the so
calledambientturbulenceappliedtothewindflowbythecoarsenessoftheearth(vegetation,
buildings,rocksetc.)andtheturbulenceaddedbytheotherwindturbinesofawindpark.
Table4Turbulencesubclassesoftheselectedwindturbines
Thewindturbinescheckingtheturbulenceimpactisgenerallyrequired;fortheproposedwind
parklayoutsforZafaranasitehowever,noproblemsintermsofturbulenceintensityaretobe
expected.
7/30/2019 Wind Farm-Fesaibility Study
22/42
22
4.3.4.TechnicalSummaryThehigherenergyyieldcalculatedfortheGamesaG58turbineismainlyrelatedtothelarger
rotordiameteroftheseturbinescomparedtotheVestasV52turbine.
Thefocusingtothegeneratedenergy
yield however is not sufficient.
Investment
costs,
indicated
by
the
ratio specific investment costs ( per
kWh)aremoresignificant,fordetails
refer to the economical part of the
Feasibility Study for the presented
specificdatain$perkWh.
4.3.5.EstimationofcostsThe estimation of costs has been
performed
according
to
the
previous
cases of implementations of wind
parks at Zafarana where Vestas V52
was implemented in Egypt at the
second phase of Zafarana Wind Park
and Gamesa G58 has been and is
beingimplementedforthelastthreephasesandthecurrentlyconstructedone.
The total investment costs are itemized and described in the table below according to the
foreignmaterialcostsaswell as localcostcomponents inorder to increase theuseof local
participationand
local
materials
in
this
project
which
directly
appear
in
the
civil
works
cost
and
theelectricalworksaswell.Alsothecontributionofthelocaltowermanufacturertothetotal
priceoftheturbinesastheturbinespriceisencompassingthewhole142turbineswithitsfull
components(nacelle,rotor,blades,andtowers)
Table5ItemizedCapitalCostsofZafaranaWindPark
Whereaperiodof12monthswasassumedfortheconstructionoftheZafaranaWindPark,as
previouslyhappenedforthelastfourwindparksbeenconstructedinEgypt.
CapitalCosts VestasV52 GamesaG58
Turbines $150,000,000 $147,000,000
WindFarmEPC $1,392,000 $1,392,000
Civil
Works $8,215,000 $8,215,000Installations $670,000 $670,000
ElectricalWorks $9,682,000 $9,682,000
TotalInvestmentCost $169,959,000 $166,959,000
USD
Fi ure15 Ener YieldsofGamesaG58andVestasV52
7/30/2019 Wind Farm-Fesaibility Study
23/42
23
For the Operation and Maintenance Costs, The estimates havebeen modeled based on the
experience of the former phases which have been constructed in Zafarana but for Vestas
alternative thepriceswhereamendedaccording toVestasglobalcurrentpricesaswecould
havereliedontheitformercaseinEgyptasithasbeenyearswhichmayaffecttheaccuracyof
the
results
of
the
study.
Annual
O&M
costs
are
categorized
into
three
main
components
the
operationcostsofbothlaborandequipmentsandwindmonitoringsystems,themaintenance
costsincludingthescheduledpreventivemaintenanceandUnscheduledRepairformboththe
sparepartsandthemaintenanceteammanhour,aswellasthemanagementcostofthewind
park which is a portion related only to the 120MW phase which is a part from the whole
systemofmanagingthewindenergyatZafaranainEgypt.
Table6ItemizedO&MCosts
AnnualO&MCosts VestasV52 GamesaG58
AnnualOperationCosts $1,597,500 $1,562,750
AnnualMaintenance
Costs $3,622,300 $3,438,050
AnnualWindFarmManagement $1,250,200 $1,250,200
TotalAnnualO&MCosts $6,470,000 $6,251,000
USD/yr
7/30/2019 Wind Farm-Fesaibility Study
24/42
24
5. EconomicEvaluationThe main purpose of an economic analysis is to help to design and select projects that
contribute to the welfare of a country. Whereas the financial analysis evaluates the project
fromthepointofviewoftheoperatingcompanyor IndependentPowerProducer (IPP), the
economicanalysisevaluatestheprojectfromthepointofviewofthewholeeconomyofthe
country.
Thepurposeoftheinvestigationistocomparefromamacroeconomicstandpointthebenefits
of the project with the costs it incurs, as is customary in any costbenefit analysis. The
standard of evaluation for costs and benefits is a monetary quantification. To the greatest
possibleextent,theprojectimpactsareevaluatedintermsofeconomicmarketprices.
As inthetechnicalanalysis,twoScenarioshavebeenconsidered intheeconomicanalysisof
theZafaranaWindPark:
ScenarioI142VestasV52turbines
ScenarioII142
Gamesa
G58
turbines
Theeconomicanalysis isconducted intheformofequalizingthevalueofgettingwindparks
introducedtothepowersystemtothe inducedsavings inthepowersystem.Aneconomical
modelhasbeenestablishedusedmanyof theevaluationmethods todetermine theproject
feasibilityacrossthe2alternatives.
Thefollowingprofitabilitycriteriaarepostulatedforthepurposesofthisanalysisrespectively:
NetPresentValue(NPV)Presentvalue isthefinancialmathematicalexpressionusedforthe
sumofthediscountedvaluesofatimeseries.Thenetpresentvalueisthedifferencebetween
thepresentvalueofthebenefitsandthepresentvalueofthecosts.Theprojectisprofitable,if
thenet
present
value
is
positive.
Assensitivityanalysisvariousvaluesoftheinterestratewhereconsideredat20%and25%in
additiontothebasicinterestrate15%.
Internal Rate of Return (IRR) The internal interest is the social discount rate at which the
presentvaluesofcostsandbenefitsareequal.
Benefitscostratio(B/C)Thepresentvaluesofthebenefitsaredividedbythepresentvalues
ofthecosts,andtheprojectisprofitableiftheresultantbenefitscostratioisgreaterthanone.
Theeconomicbenefitsofthewindenergypowergenerationhavebeenconsideredasthecost
ofsavedfueltogeneratethesameamountofenergyusingnaturalgas.AlsotheCO2emissions
which isbeingmitigatedby the implementationof theWindEnergyaccording toa taxation
system of 3$/t CO2 emitted by the same amount of energy production from a natural gas
powerplantinthetermsofmarginemissionsfactortCO2/kWh
Tobesustainable,oneof thebasicrequirements for thewindenergyproject is itsability to
compete against conventional electricity generation technologies. In fact, within a business
7/30/2019 Wind Farm-Fesaibility Study
25/42
25
context electricity is a homogeneous commodity good and wind turbines are valued in the
marketplacealmostexclusivelyasaproducerofelectricityand,aslongasmarketsforgreen
powerandgreenhousegasemissionfreepowerdonotexist,canonlycompeteonprice.
Thus, unlike new technologies in other industries, wind turbines cannot command a higher
pricebasedonqualityfeaturesandstillcaptureamarketshare.
Concerning the environmental impact Wind energy is regarded as environmentally friendly.
Environmental
impacts
associated
with
wind
park
installations,
such
as
noise,
visual
impact,
andlanduse,aremeaninglessinthecaseoftheZafaranaproject.Theprojectisintendedtobe
located inadesertareawithnohumansettles,sparsevegetation,andnoactivities,suchas
airportsortelecommunicationfacilities,thatcouldbeaffectedbythewindturbinesoperation.
Contrasting toothersituations (India, forexample)whererisingcostsof landconstitutesan
importantbarrierforwindturbinesdeployment,theZafaranalocationpresentsnorestrictions
onlanduse.Moreover,thewindparkoperationavoidsemissionsoflocalpollutantsassociated
withconventionalthermalpowerplants,usuallylocatedintheproximityofurbancenters.
TheEconomicalmodelbelowshowsallthecalculationsresults;todeterminethefeasibilityof
the
project
across
its
two
alternatives
including
all
the
market
and
technical
studies
parameterswerethemodelinputs.
TheresultsshowthatselectingGamesaG58 isthemostfeasiblealternativeeventhoughtat
differentinterestratesbytakingintoconsiderationtheworstcasescenariowhereaninflation
mayoccurat25%andaccordingtothebenefittocostratio italsoturnedouttobefeasible
thanVestasV52alternative.
In determining the wind energy benefits, the avoided fuel costs are determined by the fuel
prices and the fuel consumption to generate 120MW by natural gas was considered in
additiontotheCO2emissionsreduction comparedtosamepowergenerationbynaturalgas
at3$/MWh.
7/30/2019 Wind Farm-Fesaibility Study
26/42
26
Table7EconomicalandFinancialEvaluationModelfor120MWWindParkatZafaranaSite
WindFarmPerformance Unit
InstalledCapacity MW
No.ofWindTurbines
FullloadHours hrs/yr
CapacityFactor
TotalPowerProduction GWh/yr
General
EconomicLifetime years
ElectricityValue $/MWh
InterestRate
CapitalCosts VestasV52 GamesaG58
Turbines $150,000,000 $147,000,000
WindFarmEPC $1,392,000 $1,392,000
CivilWorks $8,215,000 $8,215,000
Installations
$670,000 $670,000ElectricalWorks $9,682,000 $9,682,000
TotalInvestmentCost $169,959,000 $166,959,000
AnnualO&MCosts VestasV52 GamesaG58
AnnualOperationCosts $1,597,500 $1,562,750
AnnualMaintenanceCosts $3,622,300 $3,438,050
AnnualWindFarmManagement $1,250,200 $1,250,200
TotalAnnualO&MCosts $6,470,000 $6,251,000
EconomicalEvaluation
NPV,i=15% $115,019,528 $119,474,788
NPV,i=20% $44,349,422 $48,443,801
NPV,i=25% $1,566,578 $5,442,665
IRR 0.2523065% 0.2581560%
TotalCost $435,229,000 $423,250,000 USD
EUAC $10,880,725 $10,581,250
EUAWBenefittoCostRatio 2.458034736 2.527603071
EnvironmentalBenefits:CO2EmissionsReductioncomparedto120MW
electricitygenerationbyNaturalGas at3$/MWh$1,645,200
AnnualFuelSavingsComparedtoNaturalGasconsumptionto
generate120MW
USD/yr
$25,100,000
$26,745,200
40
90
15%
USD
USD/yr
USD
Value
120
142
4570
57%
548.4
7/30/2019 Wind Farm-Fesaibility Study
27/42
27
Figure16VestasV52CashFlowDiagram
Figure17GamesaG58CashFlowDiagram
7/30/2019 Wind Farm-Fesaibility Study
28/42
28
6. ConclusionsTheresultsoftheeconomicanalysisarehighlypositive,showingthatthewindparkinallTwo
Scenarios ishighlyeconomicallyfeasible.Thehighestresult isproducedbytheScenariowith
theGamesaG58.
A scenario analysis has been carried out for the wind park scenario with the highest IRR,
highestB/CRatioandhighestnetbenefits,i.e.,theScenarioII(142GamesaG58turbines).
Changesin(i) Avoidedcapacitycosts,(ii) Fuelprices,(iii) CO2penaltiesand(iv) ElectricitygenerationandtheirimpactontheIRRhavebeenevaluated.
The scenario analysis shows that the variable with the highest impact on the IRR is the
investment costof the wind park followed by the electricitygeneration estimates. Thebest
results are obtained when decreasing investment costs by 15 %, whereas the impact on of
increasingemissionpenaltiesisfromaneconomicpointofviewverylow.
TheeconomicappraisaloftheZafaranaWindParkschemehasbeencarriedoutbycomparing
thecash flowassociatedwithconstructionandoperationofthewindpark. In theappraisal,
the avoided costs of thermal generation are regarded as benefits attributable to Zafarana
WindParkProject.ThedifferencebetweenthecostsoftheZafaranaprojectandthebenefits
oftheavoidednaturalgaspowerandenergyhasbeendeterminedovera40yearoperational
periodduringoneyearofconstruction.
The comparison of the proposed Wind Power Project with an equivalent thermal plant has
been
made
for
2
different
Scenarios
(Vestas
V52
and
Gamesa
G58).
The
results
show
that
all
scenarios are economically feasible, however the best Scenario the wind park with Gamesa
G58windturbines.
7/30/2019 Wind Farm-Fesaibility Study
29/42
29
7. References RenewableEnergyMixForEgypt Adapting and calibration of existing wake models to meet the conditions inside
offshorewindfarms Casestudy2:Zafarana
Wind Power Projects In The CDM: MethodologiesAnd Tools For Baselines, CarbonFinancing
And
Sustainability
Analysis
Zafarana
park
WindEnergyinEgypt FeasibilityStudyForALargeWindFarmAtGulfOfElZyt FeasibilityStudyofWindFarmConstruction WindpowerandtheCDM FinancingLargeScaleWindFarmsinDevelopingCountriesZafaranaWindFarm ZafaranaWindPowerPlantProjectDesignDocument WindAtlasforEgypt
7/30/2019 Wind Farm-Fesaibility Study
30/42
30
8. Appendices VestasV52DataSheet GamesaG58DataSheet
7/30/2019 Wind Farm-Fesaibility Study
31/42
V52-850 kWThe turbine that goes anywhere
7/30/2019 Wind Farm-Fesaibility Study
32/42
Versatile, efficient, dependable and popular
The highly efficient operation and flexible configuration
of the V52 make this turbine an excellent choice for all
kinds of wind conditions. In addition, thanks to its modest
dimensions, the V52 is simple and cost-effective to trans-
port and install. If you add in robust construction,
thoroughly tested components and an enviable track
record, it is easy to see why Vestas has erected more V52s
than any other turbine in its portfolio approximately
1500 turbines, all over the world.
One of the factors that contribute to the success of the V52
is OptiTip, its pitch regulation system. This system features
microprocessors which control the pitching of the blades,
thus ensuring continuous adjustment to maintain optimal
blade angles in relation to the prevailing wind. At the
same time, OptiTip makes it possible to keep sound levels
within the l imits st ipulated by local regulations.
The optimal solution
Another innovative feature of the V52 is the OptiSpeed*
generator. This is a significant advance in wind turbine
technology and makes a major contribution to the effi-
ciency of the V52. In practice, it allows the turbine rotor
speed to vary between 14 and 31 rpm depending on the
conditions at any given time.
While the technology involved may be advanced, its pur-
pose is simple: to maximise output. It does this by tapping
the higher efficiency of slow and variable rotation, storing
excess energy in rotational form and exploiting the full
force of transient gusts. All told, OptiSpeed boosts annual
energy production.
As an added benefit , OptiSpeed also reduces wear and
tear on the gearbox, blades and tower on account of lower
peak loading. Moreover, as turbine sound is a function of
wind speed, the lower rotation speeds made possible by
OptiSpeed naturally reduce sound levels.
Finally, OptiSpeed helps the V52 deliver better quality
power to the grid, with rapid synchronisation, reduced
harmonic distortion and less flicker.
Quite simply, OptiSpeed means more output, better quality
power and less mechanical strain and sound.
Proven Performance
Wind power plants require substantial investments, and the
process can be very complex. To assist in the evaluation and
purchasing process, Vestas has identified four factors that
are critical to wind turbine quality: energy production,
operational availability, power quality and sound level.
We spend months testing and documenting these perform-
ance areas for all Vestas turbines. When we are finally satis-
fied, we ask an independent testing organisation to verifythe results a practice we call Proven Performance. At
Vestas we do not just talk about quality. We prove it.
* Vestas OptiSpeed is not available in the USA and Canada.
7/30/2019 Wind Farm-Fesaibility Study
33/42
1
23 4
5
6
7
8
910
11
12
13
14
15
16
17
18
19
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
Technical specifications
Ultrasonic wind sensor
Service crane
VMP-Top controller
with converter
OptiSpeed generator
Pitch cylinder
Oil and water coolers
Gearbox
Main shaft
Blade bearing
Blade
Rotor lock system
Hydraulic unit
Torque arm
Machine foundation
Mechanical disc brake
Yaw gear
Composite disc coupling
100.0 dB(A) 101.0 dB(A) 102.0 dB(A)
103.0 dB(A) 104.2 dB(A)
Sound 100.0 dB(A)
Speed of revolution (rpm)
Power curve V52-850 kW
Power(kW)
1,000
900
800
700
600
500
400
300
200
100
0
Wind speed (m/s)
0 5 10 15 20 25
Wind/sound
Sound
(dB(A))
104
102
100
98
96
94
92
90
88
86
Wind speed (m/s)
3 4 5 6 7 8 9 10 11 12 13
Speedofrev
olution(rpm)
45
40
35
30
25
20
15
10
5
0
The figure above illustrates the power curves at different sound levels for the
V52-850 kW turbine, which is equipped with OptiSpeed
.
The sound output level can be adjusted by varying the revolution speed of
the turbine as illustrated in the figure above. It clearly shows the soundlevel advantages of lower speeds of revolution because the sound level is
approximately 7 dB(A) lower at 4 m/s than at 8 m/s. For other sound
levels, the benefit can be as much as 10 dB(A). Please note that a decrease
of 3 dB(A) represents a halving of the sound level.
Pitch system
Blade hub
7/30/2019 Wind Farm-Fesaibility Study
34/42
Rotor
Diameter: 52 mArea swept: 2,124 m2
Nominal revolutions: 26 rpmOperational interval: 14.0-31.4 rpm
Number of blades: 3Power regulation: Pitch/OptiSpeed
Air brake: Full blade pitch
Tower
Hub height: 40 m, 44 m, 49 m, 55 m,60 m, 65 m, 74 m, 86 m
Operational data
Cut-in wind speed: 4 m/sNominal wind speed: 16 m/sCut-out wind speed: 25 m/s
Generator
Type: Asynchronous with OptiSpeedNominal output: 850 kWOperational data: 50 Hz/60 Hz
690 V
Gearbox
Type: 1 planet step/2-stepparallel axle gears
Control
Type: Microprocessor-based monitoring of allturbine functions as well as OptiSpeedoutput regulation and OptiTip pitchregulation of the blades.
Weight
Nacelle: 22 tRotor: 10 t
Towers: IEC IA IEC IIA DIBt II DIBt IIIHub height:40 m 40 t 44 m 45 t 49 m 50 t 55 m 55 t 50 t 60 m 70 t 70 t 70 t65 m 75 t 75 t 75 t74 m 95 t 86 m 110 t
t = metric tonnes
DIBt towers are only approved for Germany.
All specifications subject to change without notice.
OptiSpeed allows the rotor speed to vary within a
range of approximately 60 per cent in relation tonominal rpm. Thus with OptiSpeed, the rotor speed
can vary by as much as 30 per cent above and below
synchronous speed. This minimises both unwanted
fluctuations in the output to the grid supply and the
loads on the vital parts of the construction.
Time
1,000
800
600
400
200
0
Power(kW)
Output
Spee
d(rpm)
Time
Generator
30
25
20
15
10
5
0
Pitch
Time
An
gle(degrees)
Wind
Time
Speed(m/s)
30
25
20
15
10
60 Hz
2,050
1,850
1,650
1,450
1,250
1,050
50 Hz
1,900
1,700
1,500
1,300
1,100
900
7/30/2019 Wind Farm-Fesaibility Study
35/42
If you have a viable wind power site, chances are that the
V52 will do well there. That is because at Vestas, we have
devoted the last 25 years to expanding the range of condi-
tions under which wind can be profitably harnessed and
because the V52 represents Vestas at its most versatile.
An all-round performer, this 850 kW wind turbine is ourmost adaptable turbine, well suited for a broad spectrum
of medium and high winds. This is why we have installed
approximately 1500 V52s all over the world.
Several factors contribute to the flexibility of this wind
turbine. Not only is the V52 available with eight different
tower heights, but its modest size and remarkable sound
profile also make it the perfect choice for both populated
and remote locations. As a finishing touch, its compact
dimensions make overland transport simple.
The V52 is also the only kW-class turbine to be fitted with
OptiSpeed, a technology that allows the rotor speed to
vary within a range of approximately 60 per cent in relationto nominal rpm. This means that with OptiSpeed, the
rotor speed can vary by as much as 30 per cent above and
below synchronous speed. OptiSpeed thereby maximises
the aerodynamic efficiency of the rotor in response to
changing wind conditions and provides yet another
instance of how Vestas versatility enhances the delivery of
dependable power.
The turbine that goes anywhere
7/30/2019 Wind Farm-Fesaibility Study
36/42
7/30/2019 Wind Farm-Fesaibility Study
37/42
GAMESA G58-850 KW
7/30/2019 Wind Farm-Fesaibility Study
38/42
Optimum performancefor low winds
- Class IIIB/WZII.
- Pitch and variable speed
technology to maximizeenergy production.
- Production of lighterblades using fiberglassand prepreg method.
- Compliance with the maininternational Grid Codes.
- Aerodynamic design andGamesa NRSTM controlsystem to minimize noiseemissions.
- Gamesa SGIPE: Remotemonitoring and controlsystem with Web access.
- Over 4,600 GamesaG5X-850 kW wind turbinesinstalled.
BENEFITS
7/30/2019 Wind Farm-Fesaibility Study
39/42
7/30/2019 Wind Farm-Fesaibility Study
40/42
- The Generator is a doubly fed machine (DFM), whose speed andpower is controlled through IGBT converters and PWM (Pulse
Width Modulation) electronic control.- Benefits:
Active and reactive power control.
Low harmonic content and minimal losses.
Increased efficiency and production.
Prolonged working life of the turbine.
Control System
Gamesa SGIPE and its new generation Gamesa WindNet (wind
farm control systems), developed by Gamesa, that allow realtimeoperation and remote control of wind turbines, meteorological
mast and electrical substation via satellite-terrestrial network.Modular design with control tools for active and reactive energy,noise, shadows and wake effects. TCP/IP architecture with a Web
interface.
Gamesa SGIPE
SMP Predictive Maintenance System
Drive train with main shaft supported by two spherical bearingsthat transmit the side loads directly to the frame by means of thebearing housing. This prevents the gearbox from receiving
additional loads, reducing malfunctions and facilitating itsservice.
Mechanical design
Aerodynamic primary brake by means of full-feathering blades. Inaddition, a hydraulically-activated mechanical disc brake for
emergencies is mounted on the gearbox high speed shaft.
Brake
The Gamesa G58-850 kW wind turbine generator uses the totallightning protection system, in accordance with standard IEC
61024-1. This system conducts the lightning from both sides ofthe blade tip down to the root joint and from there across thenacelle and tower structure to the grounding system located inthe foundations.
As a result, the blade and sensitive electrical components areprotected from damage.
Lightning protection
Predictive Maintenance System for the early detection of
potential deterioration or malfunctions in the wind turbines maincomponents.
- Benefits:
Reduction in major corrective measures.
Increase in the machines availability and working life.
Preferential terms in negotiations with insurance
companies.
Integration within the control system.
Rotor
Diameter 58 m
Swept area 2,642 m2
Rotational speed Variable 14.6 - 30.8 rpm, towers 55 and 65mVariable 16.2 - 30.8 rpm, torre 44m
Rotational direction Clock Wise (front view)
Weight (incl. Hub) Approx. 12 T
Top head mass Approx. 35 T
Gearbox
Type 1 planetary stage / 2 helical stages
Ratio 50 Hz 1:61.74
Cooling Oil pump with oil cooler
Oil heater 1.5 kW
Tubular Tower
Modular type Height Weight
2 sections 44 m 45 T
3 sections 55 m 62 T
3 sections 60 m 72 T
3 sections 65 m 79 T
3 sections 71 m 86 T
Blades
Number of blades 3
Length 28.3 m
Airfoils NACA 63.XXX + FFA-W3
Material Epoxy reinforced glass fibre
Total blade weight 2,400 kg
Generator 850 kWType Doubly-fed machine
Rated power 850 kW
Voltage 690 V ac
Frequency 50 Hz
Protecction class IP 54
Number of poles 4
Rotational speed 900:1,900 rpm(rated 1,620 rpm)
Rated Stator Current 670 A @ 690 V
Power factor (standard) 0.95 CAP - 0.95 IND at partial loads and1 at nominal power.*
Power factor (optional) 0.95 CAP - 0.95 IND throughoutthe power range.*
* Power factor at generator output terminals, at low voltage side before transformer input terminals.
7/30/2019 Wind Farm-Fesaibility Study
41/42
111213141516171819
1 2 3 4 5 6 7 8 9 10
Power Curve Gamesa G58-850 kW
(for an air density
of 1,225kg/m3)
3 5 6 7 8 9 10 11 12 13 14 15 16 17-21
0
100
200
300
400
500
600
700
800
900
4
Cut-in speed: 3 m/s
Cut-out speed: 21 m/s
PowerkW
Wind speed m/s
Power curve calculation based on NACA 63.XXX and FFA-W3airfoils.
Calculation parameters: 50 Hz grid frequency; tip angle pitch
regulated, 10% turbulence intensity and a variable rotor speedranging from 14.6 - 30.8 rpm.
Gamesas doubly-fed wind turbines and Active Crowbar and oversized converter technologies ensure the compliance with the mostdemanding grid connection requirements.
Low voltage ride-through capability and dynamic regulation of
active and reactive power.
Grid connection
Aerodynamic blade tip and mechanical component design mini-mize noise emissions. In addition, Gamesa has developed theGamesa NRSTM noise control system, which permits programming
the noise emissions according to criteria such as date, time orwind direction. This achieves the goals of local regulation com-
pliance as well as maximum production.
Noise control
Speed (m/s) Power (kW)
3 9.7
4 31.2
5 78.4
6 148.2
7 242.7
8 368.8
9 525.3
10 695.0
11 796.612 835.9
13 846.8
14 849.3
15 849.9
16 850.0
17-21 850.0
1. Service crane
2. Generator
3. Cooling system
4. Top control unit
5. Gearbox
6. Main shaft with twobearing housings
7. Rotor lock system
8. Blade
9. Blade Hub
10. Hub cover
11. Blade bearing
12. Bed frame
13. Hydraulic unit
14. Shock absorbers
15. Yaw ring
16. Brake
17. Tower
18. Yaw gears19. Transmission.
High speed shaft
7/30/2019 Wind Farm-Fesaibility Study
42/42
Gamesa Wind GmbH
Wailandtstrasse 7
63741 Aschaffenburg
Germany
Tel: +49 (0) 6021 15 09 0
Fax: +49 (0) 6021 15 09 199
E-mail: [email protected]
Gamesa Wind Engineering
Vejlsvej 51
8600 Silkeborg
Denmark
Tel: +45 87 229205 / 9204
Fax: +45 87 229201
France
Parc Mail
6 Alle Joliot Curie, btiment B69791 Saint Priest
Tel: +33 (0) 472 79 47 09
Fax: +33 (0) 478 90 05 41
Greece
3, Pampouki Street
154 51 Neo Psichiko
Athens
Tel: +30 21 06753300
Fax: +30 21 06753305
Gamesa Eolica Italia
Via Pio Emanuelli,1
Corpo B, 2 piano
00143 RomeTel: +39 0651531036
Fax: +39 0651530911
Portugal
Edificio D. Joo II
PARQUE DAS NAOES
Av. D. Joo II, lote 1.06.2.37 B
1990-090 Lisbon
Tel: +351 21 898 92 00
Fax: +351 21 898 92 99
United Kingdom
Rowan House Hazell Drive
NEWPORT South Wales NP10 8FY
Tel: +44 1633 654 140
Fax: +44 1633 654 147
Gamesa Wind US
1 Ben Fairless Drive - Ste. 2
Fairless Hills, PA 19030
Tel: +1 215 736 8165Fax: +1 215 736 3985
Gamesa Wind Tianjin
Room 1103, Tower 1
Bright China
Changan Building
7 Jianguomennei Av.
Beijing 100005
China
Tel.: +86 10 65186158
Fax: +86 10 65171337
Polgono Industrial Agustinos, C/A s/n31013 Pamplona, SpainTel: +34 948 309010Fax: +34 948 [email protected]